Ann 0304 Chap 14

download Ann 0304 Chap 14

of 24

Transcript of Ann 0304 Chap 14

  • 7/27/2019 Ann 0304 Chap 14

    1/24

    CHAPTER XIV

    NEYVELI LIGNITE CORPORATION LIMITED

    14.1. Geological reserves of lignite in the country have been estimated at around 35636

    Million Tonnes. Out of the above 4150 Million Tonnes (MT) spread over 480 sq. km. isin the Neyveli Lignite fields in Cuddalore District of which around 2360 Million Tonnes

    have been proved. Geological reserves of about 1168 MT of lignite have been identifiedin Jayamkondacholapuram of Trichy District of Tamilnadu. In Mannargudi and East ofVeeranam, geological reserves of around 22898 Million Tonnes and 1342.45 Million

    Tonnes of lignite have been estimated respectively.

    14.2. Lignite reserves at Neyveli are exploited by Neyveli Lignite Corporation Ltd.(NLC), which was incorporated as a private limited company in 1956 wholly owned by

    Government of India. With effect from 7th

    March 1986, the Corporation was convertedinto public limited company.

    EXISTING PROJECTS :

    14.3. NLC is an integrated complex consisting of three lignite mines, three thermal

    power stations. The capacity of the various units is as under:

    Mine-I - 10.5 MT/ annum.Mine-IA - 3.0 MT / annumMine-II - 10.5 MT/ annum.

    Thermal Power Station-I (linked to Mine-I) - 600 MWThermal Power Station-I Expansion (linked to Mine-I) - 420 MW

    Thermal Power Station-II (linked to Mine-II) - 1470 MW

    MINEI

    14.4. The first Lignite Mine has been in operation since 1961 using continuous mining

    technology viz., Bucket Wheel Excavators, Mobile Transfer Conveyors and System ofConveyors, which are used for excavation and transportation of lignite and overburden.Spreaders are used for dumping of overburden. The technology and the equipment were

    imported from Germany and German credit was availed for import of Specialized Mining

    Equipment (SME). The capacity of this Mine was 6.5 MT which will meet the fuelrequirement of Thermal Power Station-I. The capacity was increased to 10.5 MT ofLignite/Annum from March 2003 and at present meets the fuel requirement forgenerating power from Thermal Power Station-I and Thermal Power Station-I Expansion.

    THERMAL POWER STATION-I

  • 7/27/2019 Ann 0304 Chap 14

    2/24

    14.5. The Thermal Power Station-I (capacity 600 MW) has six units of 50 MW eachand three units of 100 MW each. The nine units of this power station were commissioned

    between May, 1962 and Sept, 1970. The equipments of this power station were importedfrom the then USSR under Indo-Soviet assistance Programme. The erection was entirely

    carried out by Indian engineers/ workers under the supervision of experts from the USSR.

    Entire power generated from this thermal power station after meeting NLC's requirementis fed into the Tamil Nadu Electricity Board grid, which is the sole beneficiary. As the

    units have served more than its normal life (One lakh unit running hours), Life ExtensionProgramme was taken up between April 1992 and March 1999. The life of this plant has

    been extended by fifteen years.

    MINE-I A

    14.6. The Mine-IA Project The mine (capacity of 3 MTPA) uses continuous mining

    technology viz. Bucket Wheel Excavators, Mobile Transfer Conveyors and system ofconveyors which are used for excavation and transportation of lignite and Overburden.

    The project was sanctioned by Govt. of India in February 1998 at a cost of Rs.1032.81Crs and the Lignite production commenced from 30th March 2003. The project wascompleted without time and cost over run. The lignite excavated from this mine is

    catering to the needs of M/s. ST-CMS, an IPP and to utilize the balance for the bestcommercial advantage of the existing Power Plants of NLC.

    MINE-II

    14.7. The second mine was implemented in two stages. In the first stage the productioncapacity was 4.7 MTPA and in second stage it was increased to 10.5 MTPA and theexpansion was completed in December, 1991 with the commissioning of last overburden

    system. Specialized Mining Equipment, viz., BWEs, Spreaders, Mobile TransferConveyors were imported from Germany with sizeable indigenous content. The

    conveyors for Second Mine were supplied by M/s. Elecon Engineering, India.

    THERMAL POWER STATION-II

    14.8. The second power station was implemented in two stages. Under Stage-I, 3 unitsof 210 MW each were commissioned between March, 1986 to March 1988. Boilers weresupplied by M/s. Trans-Electro, Hungary and Turbo Generators by M/s. Franco Tosi of

    Italy. Under Stage-II, 4 units of 210 MW each were commissioned between March 1991

    and June1993. Equipment were supplied by M/s. Bharat Heavy Electricals Limited(BHEL), India. Power generated from the Second Thermal Power Station after meetingNLC's internal requirements is shared by the Southern States viz. Tamilnadu, AndhraPradesh, Karnataka, Kerala and Union Territory of Pondicherry in accordance with the

    formula on sharing of power applicable to the power stations set up in the Central Sector.

    PROJECTS UNDER CONSTRUCTION

  • 7/27/2019 Ann 0304 Chap 14

    3/24

    14.9. Thermal Power Station-I Expansion (2 X 210 Mw Units) : Government ofIndia sanctioned the installation of 2 units of 210 MW for expansion of first Thermal

    Power Station on 12th February96 at a cost of Rs. 1590.58 Crores. The first 210 MWunit was synchronized on 21st October 2002 and Unit-I was dedicated to the Nation by

    Honble Union Minister of Coal & Mines on 18.12.2002. Subsequently the second 210

    MW Unit was synchronized on 22

    nd

    July 2003.

    PROJECTS IN PIPELINE

    14.10. Mine-II Expansion (4.5 MTPA) The project was placed before the PIB for aninvestment decision. PIB in its meeting held on 17th February 2004 had considered theproject and recommended to place the project proposal before the CCEA for their

    consideration and approval. Draft CCEA note is under preparation in the Department.Tender for appointment of consultant for project monitoring was opened on 25th February

    2004 and evaluation is in progress. Certain clarifications have been sought by NLC fromthe participating firms.

    14.11. TPS-II Expansion (2x250 MW) The project was placed before the PIB for aninvestment decision. PIB in its meeting held on 17th February, 2004 had considered the

    project and recommended to place the project proposal before the CCEA for theirconsideration and approval. The draft CCEA note is under preparation in theDepartment. NLC has appointed M/s TATA Consulting Engineers, Bangalore as the

    project consultant on 19th November, 2003. Preparation of tender documents withspecifications is under progress.

    14.12. Barsingsar Mine Project (2.10 MTPA.) This project was considered in theIMG meeting held in November 2002 and recommended to PIB for investment decision.

    The feasibility report has been re-cast for the option of outsourcing OB removal andlignite mining departmentally. The Revised Cost Estimates for the above option have

    been worked out and with the approval of NLC Board, the revised project cost estimateswere submitted to Department of Coal for further processing. The revised PIBmemorandum for the OB removal by outsourcing and lignite mining departmentally was

    sent to Department of Coal. The PIB memorandum has been circulated to the variousappraisal agencies. The PIB meeting to discuss the above project is yet to be held.

    Advance Action proposal For the Geo Technical Investigation work, Tenderwas opened on 27th Feb. 04. Eight firms quoted. Clarifications were sent to the firms on

    31st March 2004.

    14.13. Barsingsar Power Project (2x125 MW.) This project was considered in theIMG meeting held in November 2002 and recommended to PIB for investment decision.The revised draft PIB memorandum with updated project cost was submitted to

    Department of Coal in November, 2003. The PIB memorandum has been circulated tovarious appraisal agencies. The PIB meeting to discuss the above project is yet to be

    held. Power Purchase Agreement (PPA) with M/s. RVPN and water supply agreementwith M/s. IGNP were signed on 8th October 2003. Press tender issued in August, 2003

  • 7/27/2019 Ann 0304 Chap 14

    4/24

    for appointment of Project Consultants and preparation of tender documents withspecifications and the tender was opened by NLC on 22nd September, 2003. Evaluation

    is in progress.

    PROJECTS UNDER CONSIDERATION OF GOVERNMENT OF INDIA

    14.14. Refinery Residue based Power Plant at Chennai (492 MW) (Joint Venture

    project with Chennai Petroleum Corporation Limited) Department of Coal granted inprinciple approval to the project in October 2003. NLC has sent the draft MOU sent to

    M/s. CPCL for their comments and review on 29th October 2003. Advance ActionProposal for incurring expenditure for carrying out certain pre-project activities such aspreparation of FR, environment report etc. has been sanctioned by the Department in

    February, 2004. NLC has initiated action to fix an agency to prepare detailed feasibilityreport. A meeting was held at Neyveli on 24th February, 2004 with Executive Director

    and other Officials of CPCL. ED/CPCL informed that the expansion project of CPCL hasbeen commissioned as per schedule during February, 2004. Hence, CPCL requestedNLC to expedite the project. Press tender for preparation of Detailed Feasibility Report

    issued by NLC on 26th of March, 2004. Sale of tender was open from 26th March 2004 to24th April 2004. Tender opening was scheduled on 26th April 2004.

    14.15. TPS-I Expansion Stage-II (Power Plant at B&C Site) (1x125 MW) Thefeasibility report had been sent to the Planning commission for obtaining their in

    principle clearance. The Planning Commission has granted in principle approval tothe project. NLC has been requested to modify the feasibility repot as per the observation

    of Planning Commission before the proposal is processed further. EIA/EMP report wassubmitted by Consultant, M/s. Vimta Lab, Hyderabad on 27th November 2003. Actionhas been initiated to obtain NOC from Tamil Nadu Pollution Control Board for the

    project. M/s KSEB have expressed to draw 50 MW from this project. Karnataka PowerTransmission Corporation Ltd. have expressed conditional acceptance for 50 MW from

    this project. Reply to queries raised by the public during the public hearing submitted toTamil Nadu Pollution Control Board by NLC.

    14.16. Coal based Thermal Power Plant at Tuticorin (2x500 MW) (Joint VentureProject with TNEB) Department of Coal had sanctioned Advance Action Plan for Rs.

    2.50 crores in July 2003. Draft joint venture agreement, draft Memorandum ofAssociation and draft Articles of Association were sent to TNEB for review and remarks.The remarks/comments furnished by TNEB were incorporated and sent to TNEB for

    perusal on 15th December 2003. In respect of coal linkage for the project, M/s. MahanadiCoalfields Ltd. has informed that the coal linkage will depend upon the availability of

    coal either from Talcher coalfields or from Ib coalfields and will inform afterexamination. Southern Railways has been requested to indicate their requirement ofpower from this proposed power project. M/s DCPL, Chennai was appointed as a

    consultant on 24th November 2003 for preparation of feasibility report(FR). Preparationof draft FR is under progress. M/s KSEB has informed that 100 MW of power is required

    by them from this project. Meeting has been held with Port Trust officials on 15th December 2003 with regard to leasing of port land to the JV coal based power project at

  • 7/27/2019 Ann 0304 Chap 14

    5/24

    Tuticorin. A meeting was held at Neyveli on 21st Feb.04 with Chairman, TNEB and otherofficials on the issues like leasing of land, finalisation of plant layout, registration of joint

    venture and MOA, etc.

    EIA EMP Report LOI issued to M/s Kirlosar on 29th March 2004 for

    conducting rapid EIA study and preparation of Environmental report.

    NLC has remitted Rs.500/- as registration fee for the availability of name for theJoint Venture Company to the Registrar of Companies (ROC), Chennai in March 2004

    and subsequently the ROC has issued the availability of the name NLC Tamil NaduPower Ltd.

    14.17. Coal based Thermal Power Plant at Orissa (4x500 MW) The Department ofCoal granted in principle approval for taking up of the project in June 2003 and the

    Advance Action Proposal for 18.65 crores sanctioned by the Department of Coal in July2003 for incurring expenditure on certain preliminary activities. NLC gave apresentation to the constituent members of the Western Region Electricity Board at

    Mumbai in July 2003 and also to the members of Southern Regional Electricity Board atBangalore in September 2003. WREB, GEB, MSEB, Electricity Department, Goa and

    SREB had been addressed to indicate the quantum of power required from the proposedpower project and the same is awaited.

    M/s. PGCIL has been asked to take up the preliminary study for making arrangementfor evacuation of power to Western and Southern Regions as indicated by the

    constituents of State Electricity Boards. LOI has been issued to M/s. Mathenson Records Management Pvt. Ltd. Mumbai on

    4th Feb.04 for digitizing 24 village maps which will be used for preparing the land

    acquisition map. Soft copy of the 20 digitized village maps have been received on23rd Feb.04 from the consultant.

    EIA-EMP Report LOI has been issued to M/s. Vimta Labs Hyderabad on 29th March, 2004 for rapid EIA study and preparation of Environmental report.

    Purchase of Power KPTCL has indicated their intention to draw 400 MW power

    from this project.

    14.18. Coal based Thermal Power Plant at Madhya Pradesh (1000 MW) Department of Coal had requested NLC to examine the possibility of setting up a coalbased thermal power plant of 1000 MW capacity in Madhya Pradesh. NLC examined the

    proposal and sent an overall plan for the project to the Department in July, 2003 with arequest to issue in-principle approval to take up the project. With regard to coal

    linkage, M/s. South Eastern Coalfields Ltd. has been requested either to indicate theavailability of coal in Madhya Pradesh or to indicate a captive coal block that could bereleased for this power project. NLC will submit a detailed proposal after finalising the

    coal linkage, location and water source.

  • 7/27/2019 Ann 0304 Chap 14

    6/24

    14.19. Mine-III (8.0 MTPA) FR is under finalization. Draft EIA-EMP reports havebeen prepared and the same will be finalized after finalizing FR. Since the lignite price

    projected in FR is on higher side, alternate mining technology options are being explored.

    14.20. TPS-III (2x500 MW) The project is linked to NLCs Mine III project. Draft FR

    has been made ready. The FR could be finalized only after finalizing the linked MiningFR. Draft EIA-EMP reports have been prepared and the same will be finalized after

    finalizing FR.

    PERFORMANCE OF EXISTING PROJECTS :

    14.21. Overburden removal, lignite production, gross power generation and its export

    during the year 2003-2004 (April 2003 to March 2004) are indicated below :

    April 2003 to March 2004Product Unit

    Target Actual

    Overburden LM 3 1160.00 1160.70

    Lignite LT 209.00 205.57

    Power Gross MU 15006.00 16388.21

    Power Export MU 12481.00 13920.18

    Reasons for shortfall

    MINES

    Lignite production:

    Lignite production in Mine-I (including Expn.) has exceeded the target. However,

    lignite production was affected in Mine-II and Mine-IA.

    Mine-II Lignite production could not reach the target as lignite exposure couldnot be developed due to non-availability of BWEs working in overburden systemwhich were taken up for overhaul/modification works and also due to higher

    overburden to lignite ratio encountered in the area of present operation.

    Mine-IA Lignite production was affected mainly owing to teething problems inestablishing the lignite systems till August 03 and less off-take from M/s ST-CMS during the year.

    PRODUCTIVITY

  • 7/27/2019 Ann 0304 Chap 14

    7/24

    14.22. The productivity performance in 2002-2003 and 2003-2004 (April 2003 to

    March 2004) are furnished in the table below:

    OUTPUT PER MANSHIFT (OMS)

    2002-2003 2003-2004(Apr. 03 to March 04)Unit

    Actual Target Actual

    Mine-I (OB+ Lig.) Tonne 132.82 108.71 99.66

    Mine-II (OB+ Lig.) Tonne 156.00 110.89 117.64

    T.P.S-I KwHr 13225 8608 11784

    T.P.S-II KwHr 20859 12477 17024

    14.23. The PLF achieved by TPS-I and TPS-II during 2002- 2003 and 2003-2004 (April2003 to March 2004) are as under :

    (in percentage)

    2002-20032003-2004

    (Apr 2003 to March 2004)UnitActual Target Actual

    T.P.S-I 83.31 69.82 83.49

    T.P.S-II 81.56 69.82 77.48

    AUTHORISED CAPITAL

    14.24. The authorised capital of NLC is Rs2000 crores. The investment by Govt.of Indiaupto 31.03.2004 is as under :-

    FINANCIAL PERFORMANCE

    14.25. NLC has been making profits since 1976-77. During 2002-2003 the Corporationearned a pretax profit of Rs.1687.83 Crores. The Corporation has earned pretax profit ofRs.1362.82 Crore (Prov.) during 2003-2004 (upto March 2004). Reserves and surplus as

    on 31.03.2003 was Rs.4290.46 Crs.

    NLC has declared its dividend of Rs.264.97Crores (including distributiontax) for the year 2002-2003.

    14.26. NLCs sales turnover in 2002-2003 was Rs.2681.48 Crores against Rs.2236.95Crores during 2001-2002. The sales turnover during 2003-2004 (upto March 2004) was

    Rs.2815.96 Crores (Provl.) as against Rs.2681.48 Crores during the correspondingperiod of last year.

    Equity (GOI portion) Rs.1569.64 Crore

    Loan from GOI (including accrued interest) Nil

  • 7/27/2019 Ann 0304 Chap 14

    8/24

    Product wise sales during 2003-2004 (Up to March 2004) is as under :(Rs. In crores)

    Product Value (Provl)

    Lignite 189.98

    Power 2622.57

    Others3.41

    Total 2815.96

    State Electricity Boards Dues: Based on the tripartite agreement for settlement

    of dues upto 30.09.2001, under securitisation scheme, an amount of Rs.2590.77Crs. (8.5% Tax free bonds) was received on 01.09.2003. Outstanding dues fromthe State Electricity Boards as on 31.03.2004 was Rs.626.33 Crores.

    (Provisional).

    LIGNITE EXPLORATION

    14.27. Lignite reserves in India have been currently estimated at around 35636 million

    tonnes. The state wise distribution of lignite reserves is as follows :-

    As on 01.01.2003

    State Area Geological reserves(M.T.)

    Tamilnadu

    &

    Pondicherry

    Neyveli

    Bahur

    West of Bahur

    Jayamkondachola puram

    Mannargudi

    East of VeeranamKudikadu

    Micheal Patti

    Kulanchavadi

    4150.00

    575.00

    58.60

    1168.00

    22898.00

    1342.45133.38

    23.07

    175.00

    30523

    Rajasthan 3099

    Gujarat 1778

    Jammu & Kashmir 128

    Kerala 108

    Total 35636

  • 7/27/2019 Ann 0304 Chap 14

    9/24

    CONTRACTUAL EXPLORATION & DRILLING ACTIVITIES

    14.28. With in the lease hold area of NLC, Block-B and Devangudi lignite blocks areidentified for future development by NLC. The lignite reserves in these two blocks are

    placed under indicated category only. Hence, NLC proposed 8500M of drilling to be

    carried out during 2002 to 2004 in order to bring the reserves under proved category anddemarcate mining blocks to enable NLC to attempt feasibility studies for future mining.

    The drilling work was carried out by M/s. MECL.

    Drilling achievement for the period during April 2002 to March 2004 in Block-Band Devangudi are as follows:

    Block No. of BH Meterage drilled

    Devangudi 32 2471

    Block-B 36 5611

    Total 68 8082

    DRILLING UNDER PROMOTIONAL SCHEME (FUNDED BY GOVT. OF

    INDIA)

    14.29. Lignite exploration under promotional scheme funded by Department of Coal is

    being carried out by MECL in Mannargudi lignite field in Tamilnadu, Riri lignite blocksin Bikanar District and Nimbalkot blocks in Barmer District of Rajasthan. Theexploration is monitored by CMPDIL, Ranchi.

    RESEARCH AND DEVELOPMENT

    14.30. The Research and Development activities were continued during the year. TheCentre for Applied Research & Development (CARD) is the in-house R&D Centre of

    NLC and has been recognized by the Department of Science & Technology since 1975.CARD is carrying out various research works on lignite utilization, diversification,

    product development, by-product utilization wasteland reclamation etc. Based on theR&D works, some of the processes have been scaled up to pilot plant scale. CARD isalso carrying out various environmental monitoring of air, water and soils. It is having

    well-established analytical facilities and is rendering analytical services towards qualitycontrol of various materials/products used in mines and power stations and also to other

    outside industries. The details of various R&D activities being carried out are as under:-

    DEPARTMENT OF COAL S&T PROJECTS ON GOING

    A) Pond Ash Reclamation and Possibilities of Utilization of Industrial Waste

    for the Re-vegetation and Developing Green Cover.

    Description of the Project

  • 7/27/2019 Ann 0304 Chap 14

    10/24

    The main objective of the project is to reclaim ash pond area through greeningwith field and horticultural crops such as trees and shrubs having high nutrient

    utilization efficiency and bio-mass production capacity in order to create andconserve stable bio-diversity in the ash pond site.

    Status as on March 2004:Preliminary survey, lab/pot culture experiments were completed. Surface

    and profile soil samples were collected and analysed for their physico chemicalproperties. Preliminary field trial was completed. Among the different crops,

    tested crops like cucumber, maize, black gram has grown well.

    Ash & water samples were collected from observatory bore wells and analyzed

    for heavy metal content. The study indicates that the heavy metal leaching isnegligible in the abandoned ash pond. Biometric observation is being recorded

    regularly. Best treatments from the 3rd, 4th & 5th phase selected and cultivated inlarger area during last week of Nov 2002. Large-scale demonstration completedwith Maize, Sorghum, groundnut, sunflower, bhendi and cluster bean, and field

    harvest inaugurated by CMD/NLC on 26.02.03. Statistical analysis and heavymetal analysis in plant & soil is in progress. Plant produces were sent to CFTRI,

    Mysore for heavy metal analysis. Ash and water collected during the currentperiod are being analyzed. Consolidation of data, statistical analysis and draftreport will be submitted shortly.

    B) Field Studies on Application of Lignite Humic acid on Various Crop

    Responses in Different Agro - Climatic Conditions .

    Description of the Project

    The main objective of the project is to study the soil/crop requirement of humicacid on five different crops at various soil types and to popularize to farmers

    through Tamil Nadu Agricultural University Demonstration Centres located atCuddalore, Neyveli, Tanjore and Coimbatore.

    Status as on March 2004:Preliminary survey, sample collection, procurement of equipments and pot

    culture experiments were completed. Humic Acid sample was given for fieldtrial works. More than 55 field trials completed at different agro climaticconditions were tested with varying levels of humic acid and found that there is a

    good crop response in all locations to the HA applied. Application of HAincreased the yield by 20-30 % in most of the crops including tea. Post harvest

    soil samples were also collected from different locations for analysis.Construction of Poly green house completed at CARD and first phaseexperiments completed with hybrid tomato, hybrid chilies, beans and cabbage.

    Test verification trials at farmers holdings and in TNAU research stations are inprogress.

  • 7/27/2019 Ann 0304 Chap 14

    11/24

    C) Bio processing of Lignite and Bioremediation of its Sulphur Rich Wastes forDevelopment of Value Added Products.

    Description of the Project

    The main objective of the project is to develop a technology to solubilize lignite

    by employing microorganisms, to study the production of methane from lignite bythe anaerobic methanogenic bacteria, to microbiologically desulphurise bottom

    slag and Marcasite so as to recover sulphur, to microbiologically desulpurise thelignite to reduce the environmental pollution.

    Status as on March2004:Slag, lignite and soil samples were collected from Mines and TPS and used in thestudy. Microorganisms associated with the habitat were isolated. Preliminary lab

    studies were completed. Microbial leaching study using glass column methodcompleted.

    At IIT/Delhi, they have conducted a literature survey at IIT/Delhi, NationalMedical Library, NIC, JNU, DBT and Procured bacterial strains viz. Thiobacillus

    ferroxidans and Sulfolobus acidocaldarius from MTCC, Chandigarh. By usingthese cultures along with culture developed at CARD / NLC, they are conducting

    desulphurization experiments and found that 33% desulphurization in Neyvelilignite. Further enrichment culture studies and time optimization studies on theprocess of biodesulfurisation were undertaken.

    An experiment was conducted on lignite biomethanation. Lignite was added in

    different proportion with cow dung and biogas generation was measured atperiodical intervals. It was observed that cow dung with 20 % lignite producedmore biogas than other treatments.

    Heap leaching on bottom slag using nutrient solution with sulphur oxidizing

    bacterium Thiobacillus ferroxidans was conducted. Periodical analysis found thatde-sulphurization is taking place. Bio methanation of studies with lignite andisolation of methanogenic bacteria are in progress by using anaerobic chamber.

    D) Development of cost effective high Performance Highway using fly ash

    composite:

    Description of the Project

    The main objective of the project is to develop a cost effective high performanceroad in the following ways: To prepare a suitable mix using fly ash, soil and

    additives for the sub base of the road. To prepare a suitable mix using fly ash,cement and aggregate for the top wearing layer of the road. To preparelightweight porous skirting blocks and aggregate with a suitable mix using fly

    ash, lime and additives for drains of the road.

    Status as on March 2004:

  • 7/27/2019 Ann 0304 Chap 14

    12/24

    Characterization of raw material completed. Mix design of sub base using flyash, sand, gravel & lime arrived, Mix design for concrete pavement using M-40

    grade high performance concrete completed. Due to administrative reasons AnnaUniversity could not lay the model road so it was decided to lay short stretch of

    road in NLC area at Neyveli and then going for 2KM road as contemplated in the

    project. Laying of model road at NLC township area completed and the road wasopened to traffic on 31.01.2004. Extension of project duration up to April 2005

    requested to study the performance in two consecutive rainy seasons. Reappropriation of funds for the project requested. Preparatory work for laying

    experimental stretches of road is in progress.

    E) Enhancement of recharge potential in the recharge area to the Neyveli deep-

    seated aquifers.

    Description of the Project:Studying the effectiveness of three different artificial recharge arrangements(percolation pond, recharge wells and check dams) for enhancement of recharge

    and to study the variability of recharge season-wise. Comparative evaluation ofdifferent alternative artificial recharge arrangement and to suggest the suitable

    technique with reference to space. To study the combined effect of three differenttypes of artificial recharge structures in a single area. This study will throw lighton the effect of recharge structures in off setting the deficit condition thus

    avoiding the possible adverse effects such as decline in water level, change inwater quality and salt water intrusion. To delineate strategies for maintenance of

    artificial recharge arrangements.

    Status on March 2004:

    Construction of artificial recharge structures i.e checks dams; water rechargewells and percolation wells are completed. Monitoring the ground water quality

    and quantity, establishment of piezometer wells and observation wells arecompleted and the monitoring activities are in progress.

    F) Separation of Marcasite from pulverized lignite using fluidized bed

    Description of the Project:The project is aimed to study the effect of parameters namely flow rates of thephases, material characteristics and composition of light and dense particles on

    the separation of higher density material (Marcasite) from lower density material(Lignite) in a Laboratory fluidized bed and to optimize the operational parameters

    to achieve maximum separation. Mathematical model is to be developed for themechanism of the separation of particles.

    Status as on March 2004.The project has been sanctioned with effect form 01 October 2003.As per the

    schedule literature survey are being done; lignite & Marcasite samples were

  • 7/27/2019 Ann 0304 Chap 14

    13/24

    collected. Samples prepared at CARD and dispatched to IIT/Madras to conductexperiments. Characterization of samples is under progress.

    G) Development of a process for the production of activated carbon from

    Neyveli Lignite

    Description of the Project:

    The project is aimed to develop a process for the conversion of lignite topowdered activated carbon involving reactive solids & to optimize the process

    parameters. Obtaining process engineering data for scale up to commercialplant level. The product obtained will be characterized as per national andinternational standards and also to confirm techno economic feasibility for

    commercial scale production.

  • 7/27/2019 Ann 0304 Chap 14

    14/24

    Status as on March 2004.The project has been sanctioned with effect from 01 November 2003.

    Preliminary discussions and preparation of equipment specifications are inprogress. Staff recruitment for RRL/T completed. The design of the plant is in

    progress. The pilot plant will be installed at NLC for which approval has been

    obtained from CMPDIL. Lignite sample has been sent to RRL/T for conductingthe study in their laboratory.

    IN HOUSE RESEARCH PROJECTS

    IX TH PLAN Projects:

    1. Laboratory study on the effect of quality of lignite on ash fusioncharacteristics and heat value

    Outlay: Rs. 58.62 lakhs.

    The aim of the project is to study the fusion property of ash and heat value with

    respect to quality variation. The study will help to predict the effect of impuritieson the possible working problems of thermal power stations, apart from lignite

    quality evaluation. Studies were carried out with lignite by adding differentproportion of impurities like marcasite, silica, alumina and calcium. By addingmarcasite, the ash fusion temperature is decreasing and in all other cases it is

    increasing. Using Heating Microscope, a study to find the fusion characteristic oflignite ash generated in TPS-II is a gas atmosphere similar to flue gas was carried

    out. The study indicated that the fusion characteristics of the samples are notmuch affected by the flue gas atmosphere. It is also observed that the fusioncharacteristics of the ash depend on the chemical composition of the individual

    ashes. The variations of heat value with ash content of lignite samples werestudied. It is observed that the heat value of lignite decreases with increase in ash

    content. The experimental part of the project is completed.

    2. Study on the micropetrographic analysis (Reflectance and maceral studies)

    of lignite.Outlay: Rs. 45.00 Lakhs.

    The aim of the project is to study and analyze the lignite/coal megascopically aswell as microscopically to describe its maceral, mineral constituents in detail.

    This will help to determine the maturity (rank) of coal and distribution ofmacerals percentage, which can give information about the different chemical and

    technological behaviour of lignite on briquetting, combustion etc. The Trinocularmicroscope purchased for this study has been commissioned during June 2003.Lignite samples have been collected. Microscopic observations are under

    progress.

    3. Studies on the characteristic of product/waste substance developed bybiological methods.

  • 7/27/2019 Ann 0304 Chap 14

    15/24

    Outlay: Rs. 30.66 lakhs.

    The aim of the project is to investigate preliminarily the production of valueadded products from lignite such as solubilised lignite and methane by the

    application of biotechnology. This study will be useful to exploit the utilization of

    lignite deposits as thin seams or as deep deposits or in the proximity of seamaking it inaccessible for mining. The best strain screened was multiplied in the

    pilot fermentor and solubilisation was studied in larger scale. The equipmentapproved for the project has been commissioned. Experiments were conducted to

    increase the solubilisation by biotechnical method. Methane producingmicroorganisms were isolated from the samples & observed that methanegeneration is possible from lignite, and it was characterized. The project is

    completed.

    4. Environmental studies for Neyveli and adjacent areas.Outlay: Rs. 70.18 Lakhs.

    To conduct a comprehensive study on the prevailing levels of pollution in air,water and soil in the project area and identify the possible impacts of expansion

    projects in the future scenario and suggest remedial measure. The study ofbackground level of pollution and the projection of anticipated environmentalimpacts will help in taking adequate control measures well in advance to prevent

    adverse impacts on environment. The study has been completed.

    5. Combustion studies.Outlay: Rs. 80.62 Lakhs.

    Lignite fired power plants are facing different types of problems due to thepresence of high ash and marcasite in the lignite. In this connection UNIDO has

    given funds for installation of combustion test furnace at LERI, to study thecombustion characteristic of lignite. Some preliminary studies have beenconducted. The project will be useful for power plants to reduce the forced

    outages due to the presence of marcasite in lignite.

    6. Studies on the distribution of trace elements/leaching and exploring the

    possibility of bulk disposal of fly ash as subsoil spread in back-filled areas ofmine.

    Outlay: Rs. 64.71 lakhs.

    The aim of the project is to make a comprehensive study of safe bulk disposal offly ash/pond ash in mine back-fills as subsoil spread and also to investigate theimpact due to movement of trace elements etc. on crop growth and on subsoil

    water. Lab studies have been carried out to characterize the fly ash, soil and minespoil using XRF spectrometer. Field investigation was carried out at ash pond,

    TPS-I. A laboratory experiment was carried out simulating the filling of fly ash inmine spoil. Leachates were collected and analyzed. From the results, it is

  • 7/27/2019 Ann 0304 Chap 14

    16/24

    observed that there is no appreciable leaching of heavy metals. The project iscompleted

    7. Studies on the biological reclamation of mine spoil and monitoring crops

    productivity at Mines

    Outlay: Rs. 4.02 Lakhs.

    The aim of the project is to make a comprehensive study on the establishment ofgreen crops and biological nitrogen fixation, enrichment in mine spoil and to

    evaluate the beneficial effects of their incorporation on thephysiochemical/biological properties of mine spoil for cultivation of agricultural,horticultural and floricultural crops. Confirmatory field trials are being conducted

    at afforestation Mine-II with crops such as paddy, maize, green gram andsugarcane. Field experiments are conducted based on the recommendations of

    previous coal S&T projects. It is found that in the mine spoil, the yield wasachieved on par with normal soil. The project is completed.

    8. Field studies on the application of developed bio-products on various crops/tree species in various soil types.

    Outlay: Rs. 4.41 Lakhs.

    The aim of the project is to test the products developed by CARD/NLC namely

    biofertilizers, VAM and humic acid on the growth of orchid / forest tree species.The yields of certain crop species either alone or in combination with mycorrhizal

    fungi, which will be useful, for developing green belt in wastelands will bestudied. As a long-term study field trials were carried out with the humic acid,biofertilizer and VAM. In the short duration crops such as green gram, black

    gram, brinjal, tomato, groundnut, radish, carrot, beat root, cabbage, turnip,cauliflower etc, it is observed that application of humic acid at the rate of 10 kg/ha

    increased the yield from 20-60%. The humic acid developed by biological methodhas been tested in the field crops. It is observed that application of humic acid,biofertilizers and VAM increases the yield in the crops as well increases the

    growth of trees. The project has been completed.

    9. Studies on the possibilities of bioremediation, conversion of bottom slag and

    biodegradation of industrial wastes.Outlay: Rs. 32.44 Lakhs.

    The aim of the study is to develop efficient mesophilic and thermophilic strains of

    bacteria, capable of leaching iron/sulphur from bottom slag, marcasite and ligniteand also bacterial strains capable of degrading aromatic compounds to hetro-cyclic compounds in the phenolic effluents for the safe disposal. This study aims

    to reduce the environment pollution arising due to slag disposal by ThermalPower Stations. Desulphurisation experiments were conducted using isolated

    microorganisms from lignite, slag dumped at Mine II by TPS-II. There is a

  • 7/27/2019 Ann 0304 Chap 14

    17/24

    remarkable reduction in the Iron and sulphur contents and the extraction ispossible from the bottom slag. The project is completed.

    10. Developmental studies on humic acid.

    Outlay: Rs. 17.44 lakhs.

    This study is undertaken with reference to Department of Coal suggestionsto provide infrastructure facilities/support to Coal S&T project. Humic acid at

    different concentration 0.1% to 10% is tested for its properties in comparison withsome of the imported product available in the market. The product was suppliedto Tamil Nadu Agricultural University for field trials and also to outside agencies.

    Poly Green House construction had been completed and first phase pot cultureexperiment has been completed with various crops. Procurement of certain drying

    equipments and second phase pot culture experiments are in progress.

    X TH PLAN PROJECTS

    1. Long term studies on utilization /popularization studies of fly ash in

    agricultural crops/soil.Recently NLC and CFRI completed the Coal S&T Project Fly ash

    utilization in agriculture and found that fly ash application beneficial to crops.

    However, long-term studies are required in the same field as well as other soils inorder to study the heavy metal uptake and leaching of fly ash. The studies are in

    progress.

    2. Long term studies on Humic acid / VAM application.

    VAM application studies were completed and report submitted to SSRC.Monitoring of the growth of the plants, which are planted during the trials are in

    progress. Long-term field studies on the effect of humic acid on various crops alsoto be studied. Regarding this preparation of estimate is in progress.

    3. Transforming NLC mine spoil into productive agricultural land through eco-

    friendly forming system. (NLC and TNAU/Coimbatore)

    NLC is mining out the over burden and back filling it in the mined outarea. Back filled area soils contain no nutrients and also microbes. The project isto develop agricultural land by integrated forming with crop production, animal

    husbandry, fishery, mushroom, biogas generation etc., After completion of theproject period, the land will be fit enough for agricultural use along with other

    systems. MOU has been signed and the project will be taken up from 01-04-2004.

  • 7/27/2019 Ann 0304 Chap 14

    18/24

    4. Pilot studies on the stabilization, revegetation and restoration of ecology inNLC mine spoil. (NLC and TNAU/Coimbatore)

    The mined out soil is initially dumped in an area as over burden andslopes are formed. As no care was taken the slope is not fit enough for the

    vegetation and gully formation is made due to rain. To stabilize the slope and

    also for revegetation various methods will be evaluated to conserve the soil andalso to control erosion. It is also decided to develop a green cover in the slopes.

    MOU has been signed and the project will be taken up from 01-04-2004.

    FOREIGN COLLABRATION IN THE FIELD OF SCIENCE & TECHNOLOGYPROJECTS NIL

    UNDP PROJECTS NILMANPOWER

    14.31. The total manpower of NLC as on 31.03.2004 is indicated below :

    Category Technical Non- Technical Total

    Executives 3096 548 3644

    Supervisor 513 0 513

    Staff 3058 3152 6210

    Workmen 2673 6140 8813

    Total 9340 9840 19180

    INDUSTRIAL RELATIONS

    14.32. The Industrial Relations atmosphere in NLC signifies employee friendly attitudeof the management which shows greater care in dealing with human resources. The

    recognised Unions and Associations in turn are looking beyond their own problems torealise their responsibility to be more responsive to the needs of increasing productivity.

    RESERVATION

    14.33. NLC is following reservation rules prescribed by the Government of India fromtime to time. All directives issued by Government of India in the matter of reservation in

    recruitment & promotions are being followed. A cell exclusively for SC/ST matters isfunctioning under a Liaison Officer at the level of General Manager to ensure that thereservation rules and guide lines for SC/ST are implemented properly.

    The details relating to the percentage of reserved categories of employees as on31/03/04 are furnished below:

    Applicable

    Percentage of

    Reservation

    Manpower positionAvailable

    PercentageGroup

    SC ST Total SC ST SC ST

    A 15 7.5 2764 560 50 20.26 1.81

    B 16.66 7.5 880 174 44 19.77 5.00

  • 7/27/2019 Ann 0304 Chap 14

    19/24

    C 19 1 11892 2594 132 21.81 1.11

    Excl.

    Sweepers19 1 3547 611 20 17.23 0.56

    D

    Sweepers 97 70 -- 72.16 0.00

    Total 19180 4009 246 20.90 1.28

    VIGILANCE

    14.34. To make the administration efficient, effective and clean without corruption,

    multifaceted strategy covering areas of preventive, detective and punitive vigilance arecontinued to be adopted as per the guidelines of Chief Vigilance Commissioner.

    Periodical surveillance, collection of intelligence information and frequent surprisechecks are being carried out in various corruption prone areas in order tominimize/eradicate various malpractices.

    Allegations of corrupt practices, favouritism, breach of rules and procedures were

    enquired into thoroughly and the Management was appraised for initiating necessaryaction. Close liaison is being maintained with the local Police Departments, CBI/Chennaiand CVC for carrying out vigilance activities of NLC. In terms of instructions of the

    Government, Agreed List of Officers of doubtful integrity is prepared in consultationwith Central Bureau of Investigation and surveillance mounted on the activities of the

    executives. In addition to this, punitive action was also recommended against workmen,supervisors, executive and suppliers/contractors whose lack of integrity came to notice.

    Total number of complaints and the source information received and disposed off

    during 2003-2004 are tabulated below:

    Description 2003-2004

    Complaints brought forward fromprevious year (2002 2003)

    32

    Complaints received during this year 132

    Complaints disposed 122

    Complaints pending 42

    WELFARE

    HOUSING

    14.35. The sprawling residential township with a maze of roads, excellent drainagesystems, waste disposal arrangements, water facility and other recreational facilities

    provide the perfect ambience for the employees and their dependents to feel comfortable,secured and create the atmosphere of being well cared for by the Management. As high as21,510 houses nestled in the green canopy of trees make NLC Township a place

    ecologically balanced and environment friendly to live in to achieve quality of work life.

  • 7/27/2019 Ann 0304 Chap 14

    20/24

    It is abound with facilities for quality education up to college level, medical care,recreation, religious needs and shopping.

    MEDICAL SERVICES

    14.36.NLC Hospital is contemplating the best posture it can take in providing a widerange of Health Care Services to its employees, dependent population and other rural

    communities (over 3,00,000). It engages in four broad areas of activity:

    (i) Operation of the General Hospital (369 bedded acute-care Hospital).

    (ii) Operation of 5 peripheral dispensaries to ensure better accessibility in the

    area of out-patient care to residents.

    (iii) Operation of community Health programme to help the surrounding ruralpopulations meet their basic medical needs. Eye Camps, Polio, ScreeningCamps and General Community Health Screening form, part of this

    programme. During the year 2003-04, a number of medical camps wereconducted which include a major Opthal Screening Camp for implanting

    IOL to selected rural patients with cataract problems.

    (iv) Operation of occupational Health services to ensure optimal Health, safety

    and well being of employees and first aid care at plant level.

    FAMILY WELFARE

    14.37. NLC Hospital has been signed out as one of the best medical institutions in the

    State for performing sterlisations with zero failures. During the year 2003-2004 as highas 580 sterlisations were performed.

    EDUCATION

    14.38. The NLC township is teeming with over 34 schools and a college for meeting theeducational needs of children of employees and children from nearby villages. Drawing

    support from participation of other institutions, NLC offers quality education with mostof the children making appreciable grades at High School and plus two levels. 18 NLCmanaged schools have also come into the limelight in the recent years for achieving

    excellence in the school and college curriculum. NLC has also instituted number ofscholarship scheme to harness the full potential of children.

    SPORTS

    14.39. The bottom-line equations of NLC include programmes and facilities for thedevelopment of sports among employees as well as students. This goal is best served by

  • 7/27/2019 Ann 0304 Chap 14

    21/24

    the development of sports stadium that houses facilities for conducting state and nationallevel tournaments. Schools make best use of these facilities to give equal importance to

    sports activities that help the students achieve overall development. The Sports ControlBoard is behind planning sports activities and developing facilities to meet the growing

    needs for sports and leisure time games.

    CONCERN FOR SOCIAL WELFARE

    14.40. NLCs concern for social welfare is highlighted by its commitment to serve the

    cause in general and more particularly of physically, mentally and socially handicappedpopulation of Neyveli and beyond through Organisations such as Neyveli HealthPromotion and Social Welfare Society and SNEHA Opportunity School. While the

    former upholds the specific needs of physically handicapped and destitute womenthrough rehabilitation programmes the latter offers timely succour to mentally retarded

    children in making them useful and productive members of the society. NLC has not onlyprovided infrastructure facilities for the operation of these programmes but moreimportantly extends financial support for their sustained growth.

    HUMAN RESOURCE DEVELOPMENT

    14.41. Training is the powerful tool which NLC utilises effectively to harness its vasthuman resource potential, manage their career development and plan for enriching their

    skills/professions in line with the technological advancement. The training complex withmodern facilities organise various training programmes to make the employees update

    their knowledge. The demands for continuing education at shop-floor level are also fullymet. To nourish managerial excellence, executives, professionals and skilled workmenare sent for training outside in premier training institutions in India and abroad. Training

    facilities offered by equipment manufacturers are also being utilised before installing newequipment/machinery. Details of training during 20032004 upto March 2004 are

    Details April 2003 to March 2004

    In-house programme 7363

    Deputation training within India 552

    Training abroad 16

    Total 7931

  • 7/27/2019 Ann 0304 Chap 14

    22/24

    ENERGY CONSERVATION

    14.42. Separate cell is functioning with adequate staff to continuously monitorconservation of energy in the production units as also service units and township.

    Energy conservation measures taken during this year

    A. MINES SECTORThe following measures have been taken in respect of both the mines to ensure

    energy conservation. Energy Audit was conducted in Mine-II by M/s. MECON and a draft

    report was received. Final report expected shortly.

    Using of Auxiliary drive for teeth changing during maintenance hours. Cutting of one of the drives during loading near to the Drive Heads.

    All old lighting luminaries are being replaced with energy efficientlighting luminaries. Providing timer switches/Photo Volt switches for thecontrol of out door illuminations.

    Optimization of conveyor operation with particular reference to idlerunning.

    Judicious reduction in the operating hours off GWC pumps. Motivation and Awareness creation among operation personnel.

    B. POWER SECTOR

    Auxiliary Power consumption was at below 12.00% for TPS-I and atbelow 10.00 % TPS-II.

    500W incandescent bulbs were being replaced with 40W tube light fittings

    in TPS-I. Timer circuits have been provided for the roof lights in Turbine hall in

    TPS-I.C. TOWNSHIP ADMINISTRATION

    Running hours of water supply pumps reduced by 1 Hrs./Day. Unnecessary burning of streetlights has been controlled by streetlight

    timers. Tube light fittings are being replaced with C.F.L. fittings.

    D. TRAINING & DEVELOPMENT

    In house training programme on Energy Conservation was conducted to

    create awareness among employees on energy conservation.

    E-GOVERNANCE

  • 7/27/2019 Ann 0304 Chap 14

    23/24

    1. LOA for the implementation of IVDFN (Integrated Voice and Data FiberOptic Network) has been awarded to M/s. CMC Ltd., on 18.06.2003. The

    project has started and the laying of Fiber Optic cable has been completed.Network switches have been supplied by the firm. Project has to be

    implemented in 10 months from the date of placing the order. Network

    switches are being installed in various locations.2. Intranet Application: Intranet web based applications like leave

    regularization, online availability of various application forms, BulletinBoard, Employees bio-data etc has been implemented utilizing the LAN

    connectivity established in the Corporate Office. In the ongoing IVDFNproject the above facilities will be extended to all the units and offices inNLC. Further other group ware applications like Work Flow. Email

    Facilities for NLC officials etc will be implemented in the same project.URS (User Requirement Specification) for the work flow application has

    been finalised. E-mail server has been received and being tested.

    3. Actions have been taken for the implementation of LAN in TPS-I, TPS-IIand TPS-I Expansion and also in GH & TA. In the consolidated purchase

    of Computer, Servers and Network Components and implementation ofLocal Networks, which is about to be finalized, the formations of the

    above LANs are included. Purchase order is being placed.

    4. Online Integrated Material Management System: The purchase orderhas been already placed on IIT, Kharagpur for the Application Software

    Development and Implementation of OLIMMS covering Indenting,Material control, Stock Accounting, Issues and purchase co-ordination.

    This comprises of 2 phase involving 5 major activities phase-1 iscompleted in full. The software development is in progress. Purchase

    order is placed for the procurement of Hardware for the above project.This project will be implemented before May 2004. The supply,installation and commissioning of all the hardware items are in progress.

    5. Implementation of Attendance Monitoring System: Purchase orderwas placed on M/s. CMS Ltd., for the implementation of ComputerizedPunching and Attendance Monitoring System in all the units of NLC. The

    card readers had been installed in all locations of various units. Theattendance Monitoring System has been implemented successfully in all

    Industrial and Service Units and offices in NLC during January2004Central Server implementation was tested.

    6. Implementation of Online System: Online system for FinancialAccounting is implemented. Online Payroll has been implemented fromApril 2002. Orders have been placed with M/s. DDE ORG on 14.05.2002

    for the development of Rent Accounting system, Sales Accounting Systemand AMC Systems. The development work is in progress. The softwaremodule development for sales accounting & AMC is in progress.

    AWARDS

  • 7/27/2019 Ann 0304 Chap 14

    24/24

    14.43. Neyveli Lignite Corporation Ltd., received the Human Resource Development

    National Award - 2002 for the best training practice issued by National Power TrainingInstitute. New Delhi on 5th December 2003.

    MOU RANKING

    14.44. NLC is a MOU signing PSU and its MOU rating for the year 2002-2003 isVery Good.

    14.45. GENERAL

    Parliamentary Committee on the Welfare of SC/ST visited Chennai on 13th June,2003 and held discussion with NLC officials.

    An MOU was signed on 19th June,2003 at Chennai between NLC andTNEB in the presence of Honble Chief Minister of Tamil Nadu and theHonble Minister for Coal, Govt. of India for setting up of a 1000 MW

    coal based Thermal Power Plant as a joint venture at Tuticorin. Shri P.K. Mishra, I.A.S., Secretary (Coal) visited Neyveli on 10th Aug.03

    and inaugurated the 2nd Unit (210 MW) of Thermal Power Station-IExpansion. Project. The Secretary (Coal) has also planted saplings in theMine-IA area, under Mass plantation Programme.

    Sub-Committee-III for Ministry of Heavy Industries & Public Enterprisesof the Parliamentary Standing Committee on Industry visited Chennai on

    21st September 2003 and held discussion with NLC Officials on MOU

    performance and professionalisation of Boards. The Companys 47th Annual General Meeting was held at Chennai on 29th

    September 2003. A Dividend of 14% was declared to the shareholders forthe year 2002-2003.

    A Committee on Safety in Coal Mines visited Chennai on 20th October 2003and held discussion with NLC officials.

    ----- x ----- x ----- x -----