Mid Term Review Meeting, 26 September 2012 A. Shornikov1
* The research project has been supported by a Marie Curie Early Initial Training Network Fellowship of the European Community’s Seventh Program under contract number (PITN-GA-2010-264330-CATHI)
CATHIMarie Curie Initial Training Network
Cryogenics, Accelerators and Targets at HIE-ISOLDE
Andrey ShornikovWP8, ER3
Mid Term Review Meeting, 26 September 2012
Mid Term Review Meeting, 26 September 2012 A. Shornikov2
Outline
Background;
Activity at CERN;
Project status and achievement;
Experience in the project;
Conclusions;
Mid Term Review Meeting, 26 September 2012 A. Shornikov3
Background
PhD at university of Heidelberg/MPIK (DE)
Project : Electron cooler for Cryogenic Storage Ring (CSR) at MPIK (Heidelberg).
Tasks: • Numerical simulations of electron optics;• Experiments on dense ultra-low energy electron beams;• Mechanical and thermal design, applied cryogenics.
Achievements: • Simulation based specs for magnets;• LNeon closed cycle cryogenic cooling system designed and built;• Prototype HTS superconducting magnet designed and built;• Cooling system and magnets put in test operation.
Mid Term Review Meeting, 26 September 2012 A. Shornikov4
Activity at CERN
WP8: Radioactive Ion Beam Quality Improvement / ER3:Charge breeder design study
Simulations of high current space charge limited electron beam for HIE-EBIS;
Simulation based design of High Energy Current and Compression (HEC2) electron gun, drift tubes, High Power Collector (HPC) and spec for the magnetic system;
General design concept of the HIE-EBIS;
Mid Term Review Meeting, 26 September 2012 A. Shornikov5
Project status and achievements after 3 months
Active knowledge transfer:
Visited best performing relevant EBIT/S groups at MPIK, BNL, MSU/NSCL.
Preliminary agreement on collaborative construction of the HEC2 gun with BNL, getting approval at CERN. If approved and funded the gun can be built and tested within the 2 years WP*.
HIE-EBIS wide board workshop** with attendance of 28 on 16-17.10 to discuss the options and get feedback from CERN and external experts
* Goes beyond WP **CATHI sponsored
Mid Term Review Meeting, 26 September 2012 A. Shornikov6
Project status and achievements after 3 months
ER3 Charge B reeder Upgrade
M39 Evaluation of breeder options
M40Evaluation report on electron beam simulation tools
M41 HIE-EBIS workshop
D42
Preliminary report on magnetic field configuration and electron beam design
TC18
An adapted version of the NSCL/MSU trapping and charge breeding code
D43
First order mechanical design of electron gun, drift tube structures and collector
D44
Final report on magnetic field, electron beam and ion optics, and breeding performance
W12 CAS, Conferences, workshops
I19 Internship at NSCL and other associated partners
9 Theme 9: Safety & Radiation Protection 3 6 9 12 15 18 21 24
Mid Term Review Meeting, 26 September 2012 A. Shornikov7
Outlook and options
The gun HEC2 will be built and experimentally tested at BNL EBTS facility *
HPC and drift tube structure will be designed adopting BNL/ANL scheme to a detailed phase.
Simulation based specs for the magnet and general design concept of the HIE-EBIS will be elaborated
The HEC2 gun will be modeled and designed
HPC and the drift tube structure will be simulated and designed to the first order.
Simulation based specs for the magnet and general design concept of the HIE-EBIS will be elaborated
VS.
Mid Term Review Meeting, 26 September 2012 A. Shornikov8
Experience in the project
Trainings and personal development
Learning from best performing EBIT/S groups
Intensive training in COMSOL to utilize multiphysics approach in design (Sep 12)
CERN Accelerator School to extend accelerator physics background (Oct 12)
Mid Term Review Meeting, 26 September 2012 A. Shornikov9
Conclusion
Keeping up with the plan
Trainings: according to the CDP (COMSOL taken, CAS – registered Oct, French - registered Oct)
Milestones: M41 first one to be delivered by mid October (HIE-EBIS WS)
Deliverables: according to the plan
Meetings (CERN TE-MSC, TE-VSC, MPIK), secondments (BNL, MSU/NSCL) : according to the CDP.
Conferences: EMIS 2012 registered according to the CDP.
Networking/collaboration: if approved the HEC2 collaboration with BNL profits both the ER3 and the HIE-EBIS project by more effective use of resources, saving time, working with and learning from the best specialists using the unique facility.