ANALISA HARGA SATUAN PEKERJAAN SEMARANG
No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP)I PEKERJAAN PERSIAPAN 1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M
a Tiang kayu borneo 4/6 0.05 m3 4,000,000.00
200,000.00
b Semen PC (abu-abu) 0.05 sak 49,500.00
2,475.00
c Seng gelombang 1.20 lbr 67,000.00
80,400.00
d Pasir beton 0.01 m3 140,000.00
700.00
e Split (batu pecah) 0.01 m3 140,000.00
1,260.00
f Balok kayu borneo 4/6 0.05 m3 4,000,000.00
200,000.00
g Paku 5 - 10 cm 0.06 kg 14,700.00
882.00
h Meni Besi 0.45 kg 18,000.00
8,100.00
i Tukang kayu 0.20 org 42,000.00
8,400.00
j Pembantu tukang 0.10 org 27,500.00
2,750.00
Jumlah 504,967.00
Dibulatkan
504,960.00 2 1 M¹ PAGAR KAWAT BERDURI TINGGI : 1,8 M
a Tiang kayu borneo 4/6 0.05 m3 4,000,000.00
200,000.00
b Semen PC (abu-abu) 0.04 sak 49,500.00
1,980.00
c Kawat duri 2.50 kg 145,500.00
363,750.00
d Pasir beton 0.01 m3 140,000.00
700.00
e Split (batu pecah) 0.01 m3 140,000.00
1,260.00
f Paku 5 - 10 cm 0.06 kg 14,700.00
882.00
g Tukang kayu 0.20 org 42,000.00
8,400.00
h Pembantu tukang 0.30 org 27,500.00
8,250.00
Jumlah 585,222.00
Dibulatkan 585,220.00
3 1 M1 PENGUKURAN & PEMASANGAN BOWPLANK
a Kayu kaso 5/7 borneo 0.02 m3 4,000,000.00
80,000.00
b Paku 5 - 10 cm 0.02 kg 14,700.00
294.00
c Papan papan kayu terentang 2/20 0.00 m3 1,750,000.00
7,000.00
d Tukang kayu 0.10 org 42,000.00
4,200.00
e Pembantu tukang 0.10 org
27,500.00 2,750.00
Jumlah 94,244.00
Dibulatkan 94,240.00
4 1 M2 PEMBUATAN KANTOR DIREKSI
a Kayu kaso 5/7 borneo 0.02 m3 4,000,000.00
80,000.00
b Papan kayu terentang 0.18 m3 1,750,000.00
315,000.00
c Paku semua ukuran 0.85 kg 14,700.00
12,495.00
d Besi strip 1.10 kg 11,000.00
12,100.00
e Semen PC (abu-abu) 35.00 kg 49,500.00
1,732,500.00
f Pasir pasang 0.15 m3 125,000.00
18,750.00
g Pasir beton 0.10 m3 140,000.00
14,000.00
h Split (batu pecah) 0.15 m3 140,000.00
21,000.00
i Bata merah 30.00 bh 325.00
9,750.00
j Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 58,000.00
69,600.00
k Seng plat BJLS 32 1.00 m2 32,000.00
32,000.00
l Kawat harmonika 2.00 m2 19,000.00
38,000.00
m Kaca polos 3 mm 0.08 m2 52,000.00
4,160.00
n Kunci tanam standar 0.15 bh 55,000.00
8,250.00
o Triplek 120 x 240 x 0,4 cm 0.06 lbr 50,000.00
3,000.00
p Tukang kayu 2.00 org 42,000.00
84,000.00
q Tukang batu 1.00 org 42,000.00
42,000.00
r Pembantu tukang 2.00 org 27,500.00
55,000.00
Jumlah 2,551,605.00
Dibulatkan 2,551,600.00
5 1 M2 PEMBUATAN GUDANG PROYEK
a Kayu kaso 5/7 borneo 0.02 m3 4,000,000.00
80,000.00
b Papan kayu terentang 0.10 m3 1,750,000.00
175,000.00
c Paku 0.30 kg 14,700.00
4,410.00
d Semen PC (abu-abu) 0.21 sak 49,500.00
10,395.00
e Pasir beton 0.03 m3 140,000.00
4,200.00
f Split (batu pecah) 0.05 m3 140,000.00
7,000.00
g Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 58,000.00
69,600.00
h Tukang kayu 1.00 org 42,000.00
42,000.00
i Pembantu tukang 1.00 org 27,500.00
27,500.00
Jumlah 420,105.00
Dibulatkan 420,100.00
6 1 M2 MEMBERSIHKAN LOKASI ROYEK
a Pembantu tukang 0.10 org 27,500.00
2,750.00
Jumlah 2,750.00
Dibulatkan 2,700.00
7 1 M2 MEMBERSIHKAN PUING-PUING
a Pembantu tukang 0.20 org 27,500.00
5,500.00
Jumlah 5,500.00
Dibulatkan 5,500.00
8 1 BH MEMBERSIHKAN TUNGGUL TANAMAN
a Pembantu tukang 2.00 org 27,500.00
55,000.00
Jumlah 55,000.00
Dibulatkan 55,000.00
9 1 M2 PEMBUATAN JALAN MASUK PROYEK
a Batu belah 15/20 0.10 m3 120,000.00
12,000.00
b Koral 5/7 (sirtu) 0.05 m3 80,000.00
4,000.00
c Pasir urug 0.01 m3
70,000.00 700.00
d Pembantu tukang 1.00 org 27,500.00
27,500.00
Jumlah 44,200.00
Dibulatkan 44,200.00
10 1 M3 PEMBONGKARAN BETON
a Pembantu tukang 6.20 org 27,500.00
170,500.00
Jumlah 170,500.00
Dibulatkan 170,500.00
11 1 M3 PEMBONGKARAN DINDING BATA
a Pembantu tukang 4.60 org 27,500.00
126,500.00
Jumlah 126,500.00
Dibulatkan 126,500.00
12 1 M2 PEKERJAAN PAGAR PAPAN RANGKA BALOK
a Papan kayu borneo 0.02 m3 4,800,000.00
96,000.00
b Balok kayu borneo 5/7 0.02 m3 4,000,000.00
80,000.00
c Pasir beton 0.08 m3 140,000.00
11,200.00
d Split (batu pecah) 0.15 m3 140,000.00
21,000.00
e Semen abu-abu 0.50 sak 49,500.00
24,750.00
f Tukang kayu 0.13 org 42,000.00
5,460.00
g Pembantu tukang 0.38 org 27,500.00
10,450.00
Jumlah 248,860.00
Dibulatkan 248,800.00
II PEKERJAAN TANAH 1 1 M3 GALIAN TANAH SEDALAM 1 M
a Pembantu tukang 0.40 org 27,500.00
11,000.00
b Tukang gali 0.02 org 30,000.00
600.00
Jumlah 11,600.00
Dibulatkan 11,600.00
21 M3 G
a Pembantu tukang 0.53 org 27,500.00
14,575.00
b Tukang gali 0.02 org 30,000.00
600.00
Jumlah 15,175.00
Dibulatkan 15,170.00
31 M3 G
a Pembantu tukang 0.74 org 27,500.00
20,350.00
b Tukang gali 0.02 org 30,000.00
600.00
Jumlah 20,950.00
Dibulatkan 20,950.00
41 M3 G
a Pembantu tukang 0.45 org 27,500.00
12,375.00
b Tukang gali 0.02 org 30,000.00
600.00
Jumlah 12,975.00
Dibulatkan 12,970.00
5 1 M2 PEKERJAAN PENGUPASAN TANAH SETEBAL 10 CM
a Pembantu tukang 0.05 org 27,500.00
687.50
b Tukang gali 0.02 org 30,000.00
450.00
Jumlah 1,137.50
Dibulatkan 1,130.00
61 M3 PE
a Pembantu tukang 0.42 org 27,500.00
11,550.00
b Tukang gali 0.02 org
30,000.00 600.00
Jumlah 12,150.00
Dibulatkan 12,100.00
7 1 M3 URUGAN TANAH KEMBALI
a Pembantu tukang 0.19 org 27,500.00
5,225.00
b Tukang gali 0.02 org 30,000.00
600.00
Jumlah 5,825.00
Dibulatkan 5,800.00
8 1 M3 PEMADATAN TANAH
a Pembantu tukang 0.50 org 27,500.00
13,750.00
b Tukang gali 0.02 org 30,000.00
600.00
Jumlah 14,350.00
Dibulatkan 14,300.00
9 1 M3 URUGAN PASIR
a Pasir urug 1.20 m3 70,000.00
84,000.00
b Pembantu tukang 0.30 org 27,500.00
8,250.00
c Tukang gali 0.02 org 30,000.00
600.00
Jumlah 92,850.00
Dibulatkan 92,800.00
10 1 M3 URUGAN TANAH
a Tanah urug 1.20 m3 75,000.00
90,000.00
b Pembantu tukang 0.30 org 27,500.00
8,250.00
c Tukang gali 0.02 org 30,000.00
600.00
Jumlah 98,850.00
Dibulatkan 98,800.00
11 1 M3 URUGAN SIRTU
a Sirtu (koral) 1.20 m3 80,000.00
96,000.00
b Pembantu tukang 0.25 org 27,500.00
6,875.00
c Tukang gali 0.02 org 30,000.00
600.00
Jumlah 103,475.00
Dibulatkan 103,400.00
III PEKERJAAN FONDASI 1 1 M3 PASANG FONDASI BT KALI , 1 Pc : 3 Ps
a Batu belah 1.10 m3 120,000.00
132,000.00
b Semen PC (abu-abu) 4.04 sak
49,500.00 199,980.00
c Pasir pasang 0.49 m3 125,000.00
60,625.00
d Pembantu tukang 1.50 org 27,500.00
41,250.00
e Tukang batu 0.60 org 42,000.00
25,200.00
Jumlah 459,055.00
Dibulatkan 459,050.00
2 1 M3 PASANG FONDASI BT KALI , 1 Pc : 4 Ps
a Batu belah 1.10 m3 120,000.00
132,000.00
b Semen PC (abu-abu) 3.26 sak 49,500.00
161,370.00
c Pasir pasang 0.52 m3 125,000.00
65,000.00
d Pembantu tukang 1.50 org 27,500.00
41,250.00
e Tukang batu 0.60 org 42,000.00
25,200.00
Jumlah 424,820.00
Dibulatkan 424,820.00
3 1 M3 PASANG FONDASI BT KALI , 1 Pc : 5 Ps
a Batu belah 1.10 m3 120,000.00
132,000.00
b Semen PC (abu-abu) 2.72 sak 49,500.00
134,640.00
c Pasir pasang 0.54 m3
125,000.00 68,000.00
d Pembantu tukang 1.50 org 27,500.00
41,250.00
e Tukang batu 0.60 org 42,000.00
25,200.00
Jumlah 401,090.00
Dibulatkan 401,090.00
4 1 M3 PASANG FONDASI BATU KOSONG ( AANSTAMPING )
a Batu belah 1.20 m3 120,000.00
144,000.00
b Pasir urug 0.30 m3 70,000.00
21,000.00
c Pembantu tukang 0.78 org 27,500.00
21,450.00
d Tukang batu 0.39 org 42,000.00
16,380.00
Jumlah 202,830.00
Dibulatkan 202,800.00
5 1 M3 MEMBUAT BETON BERTULANG UNTUK FONDASI 1 Pc : 2 Ps : 3 Kr
a Semen PC (abu-abu) 6.72 sak 49,500.00
332,640.00
b Pasir beton 0.54 m3 140,000.00
75,600.00
c Split (batu pecah) 0.81 m3 140,000.00
113,400.00
d Pembantu tukang 2.00 org 27,500.00
55,000.00
e Tukang batu 0.35 org
42,000.00 14,700.00
Jumlah 591,340.00
Dibulatkan 591,300.00
6 1 KG PENULANGAN BETON FONDASI
a Besi beton polos 1.05 kg 8,750.00
9,187.50
b Kawat beton 0.02 kg 15,000.00
225.00
c Pembantu tukang 0.01 org 27,500.00
192.50
d Tukang besi 0.01 org 42,000.00
294.00
Jumlah 9,899.00
Dibulatkan 9,800.00
7 1 M2 PEKERJAAN BEKISTING UNTUK FONDASI
a Papan kayu terentang 0.04 m3 1,750,000.00
70,000.00
b Paku 5 - 12 cm 0.30 kg 1,925.00
577.50
c Pelumas bekisting (oli/minyak) 0.10 Ltr 10,000.00
1,000.00
d Pembantu tukang 0.30 org 27,500.00
8,250.00
e Tukang kayu 0.26 org 42,000.00
10,920.00
Jumlah 90,747.50
Dibulatkan
90,700.00 8 1 M3 PASANG FONDASI CYCLOOP (60 %BETON : 40% BATU KALI)
a Besi beton polos 50.00 kg 8,750.00
437,500.00
b Semen PC (abu-abu) 4.04 sak 49,500.00
199,980.00
c Pasir beton 0.32 m3 140,000.00
44,800.00
d Split (batu pecah) 0.49 m3 140,000.00
68,600.00
e Kawat beton 0.80 kg 15,000.00
12,000.00
f Batu belah 0.40 m3 120,000.00
48,000.00
g Pembantu tukang 2.00 org 27,500.00
55,000.00
h Tukang batu 0.85 org 42,000.00
35,700.00
Jumlah 901,580.00
Dibulatkan 901,500.00
9 1 M3 PASANG FONDASI SUMURAN DIAMETER 100 cm
a Batu belah 0.45 m3 120,000.00
54,000.00
b Semen PC (abu-abu) 5.60 sak 49,500.00
277,200.00
c Pasir beton 0.45 m3 140,000.00
63,000.00
d Split (batu pecah) 0.67 m3 140,000.00
93,800.00
e Pembantu tukang 2.38 org
27,500.00 65,450.00
f Tukang batu 0.30 org 42,000.00
12,600.00
Jumlah 566,050.00
Dibulatkan 566,000.00
10 1 M¹ PEMBUATAN FONDASI TIANG BETON BERTULANG UKURAN 40 X 40 Cm
a Pasir beton 0.10 m3 140,000.00
14,000.00
b Split (batu pecah) 0.15 m3 140,000.00
21,000.00
c Semen PC (abu-abu) 1.21 sak 49,500.00
59,895.00
d Besi beton polos 45.00 kg 8,750.00
393,750.00
e Kawat beton 0.90 kg 15,000.00
13,500.00
f Balok kayu borneo super 5/7 0.03 m3 4,000,000.00
128,000.00
g Papan kayu terentang 0.01 m3 1,750,000.00
17,500.00
h Paku 5 - 12 cm 0.12 kg 14,700.00
1,764.00
i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00
900.00
j Plamir tembok 0.24 kg 9,000.00
2,160.00
k Pembantu tukang 1.00 org 27,500.00
27,500.00
l Tukang batu 0.67 org 42,000.00
28,140.00
Jumlah 708,109.00
Dibulatkan 708,100.00
11 1 M¹ PEMBUATAN FONDASI TIANG BETON BERTULANG UKURAN 35 X 35 CM
a Pasir beton 0.08 m3 140,000.00
11,200.00
b Split (batu pecah) 0.13 m3 140,000.00
18,200.00
c Semen PC (abu-abu) 0.98 sak 49,500.00
48,510.00
d Besi beton polos 34.50 kg 8,750.00
301,875.00
e Kawat beton 0.70 kg 15,000.00
10,500.00
f Balok kayu borneo super 5/7 0.03 m3 4,000,000.00
120,000.00
g Papan kayu terentang 0.01 m3 1,750,000.00
17,500.00
h Paku 5 - 12 cm 0.12 kg 14,700.00
1,764.00
i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00
900.00
j Plamir tembok 0.20 kg 9,000.00
1,800.00
k Pembantu tukang 0.80 org 27,500.00
22,000.00
l Tukang batu 0.50 org 42,000.00
21,000.00
Jumlah 575,249.00
Dibulatkan 575,200.00
12 1 M3 MEMBUAT FONDASI TIANG PANCANG UKURAN 25 X 25
a Pasir beton 0.06 m3 140,000.00
8,400.00
b Split (batu pecah) 0.11 m3 140,000.00
15,400.00
c Semen PC (abu-abu) 0.82 sak 49,500.00
40,590.00
d Besi beton polos 34.50 kg 8,750.00
301,875.00
e Kawat beton 0.60 kg 15,000.00
9,000.00
f Balok kayu borneo super 5/7 0.03 m3 4,000,000.00
120,000.00
g Papan kayu terentang 0.01 m3 1,750,000.00
17,500.00
h Paku 5 - 12 cm 0.11 kg 14,700.00
1,617.00
i Pelumas begisting (oli/minyak) 0.08 Ltr 10,000.00
800.00
j Plamir tembok 0.20 kg 9,000.00
1,800.00
k Pembantu tukang 0.80 org 27,500.00
22,000.00
l Tukang batu 0.50 org 42,000.00
21,000.00
Jumlah 559,982.00
Dibulatkan 559,900.00
13 1 M3 MEMBUAT FONDASI PLAT BETON (PENULANGAN 125 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,750,000.00
350,000.00
b Paku 5 - 12 cm 1.50 kg 14,700.00
22,050.00
c Pelumas begisting (oli/minyak) 0.40 Ltr 10,000.00
4,000.00
d Besi beton polos 125.00 kg 8,750.00
1,093,750.00
e Kawat beton 2.25 kg 15,000.00
33,750.00
f Semen PC (abu-abu) 6.46 sak 49,500.00
319,770.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Pembantu tukang 3.90 org 27,500.00
107,250.00
j Tukang batu 0.35 org 42,000.00
14,700.00
k Tukang kayu 1.04 org 42,000.00
43,680.00
l Tukang besi 1.05 org 42,000.00
44,100.00
Jumlah 2,215,050.00
Dibulatkan 2,215,000.00
14 1 M3 MEMBUAT FONDASI PLAT BETON (PENULANGAN 150 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,750,000.00
350,000.00
b Paku 5 - 12 cm 1.50 kg 14,700.00
22,050.00
c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00
4,000.00
d Besi beton polos Polos 150.00 kg 8,750.00
1,312,500.00
e Kawat beton 2.25 kg 15,000.00
33,750.00
f Semen PC (abu-abu) 6.46 sak 49,500.00
319,770.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Pembantu tukang 4.00 org 27,500.00
110,000.00
j Tukang batu 0.40 org 42,000.00
16,800.00
k Tukang kayu 1.00 org 42,000.00
42,000.00
l Tukang besi 1.00 org 42,000.00
42,000.00
Jumlah 2,434,870.00
Dibulatkan 2,434,800.00
15 1 M3 MEMBUAT FONDASI BETON BOREPILE (PENULANGAN 125 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,750,000.00
350,000.00
b Paku 5 - 12 cm 1.50 kg 14,700.00
22,050.00
c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00
4,000.00
d Besi beton polos 125.00 kg 8,750.00
1,093,750.00
e Kawat beton 2.10 kg 15,000.00
31,500.00
f Semen PC (abu-abu) 6.46 sak 49,500.00
319,770.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Pembantu tukang 3.90 org 27,500.00
107,250.00
j Tukang batu 0.40 org 42,000.00
16,800.00
k Tukang kayu 1.00 org 42,000.00
42,000.00
l Tukang besi 1.00 org 42,000.00
42,000.00
Jumlah 2,211,120.00
Dibulatkan 2,211,100.00
16 1 M3 MEMBUAT FONDASI BETON BOREPILE (PENULANGAN 150 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,750,000.00
350,000.00
b Paku 5 - 12 cm 1.50 kg 14,700.00
22,050.00
c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00
4,000.00
d Besi beton polos 150.00 kg 8,750.00
1,312,500.00
e Kawat beton 2.25 kg 15,000.00
33,750.00
f Semen PC (abu-abu) 6.46 sak 49,500.00
319,770.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Pembantu tukang 4.00 org 27,500.00
110,000.00
j Tukang batu 0.40 org 42,000.00
16,800.00
k Tukang kayu 1.00 org 42,000.00
42,000.00
l Tukang besi 1.00 org 42,000.00
42,000.00
Jumlah 2,434,870.00
Dibulatkan 2,434,800.00
IV PEKERJAAN BETON NON STRUKTUR DAN BETON STRUKTUR A PEKERJAAN BETON
11 M3 MEMBUAT BETON NON STRUKTUR, 1 Pc : 3 Ps : 5 Splt
a Semen PC (abu-abu) 4.36 sak 49,500.00
215,820.00
b Pasir beton 0.52 m3 140,000.00
72,800.00
c Split (batu pecah) 0.87 m3 140,000.00
121,800.00
d Pembantu tukang 2.00 org 27,500.00
55,000.00
e Tukang batu 0.35 org 42,000.00
14,700.00
Jumlah
480,120.00
Dibulatkan 480,100.00
2 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 4 Splt
a Semen PC (abu-abu) 4.64 sak 49,500.00
229,680.00
b Pasir beton 0.52 m3 140,000.00
72,800.00
c Split (batu pecah) 0.78 m3 140,000.00
109,200.00
d Pembantu tukang 2.00 org 27,500.00
55,000.00
e Tukang batu 0.35 org 42,000.00
14,700.00
Jumlah 481,380.00
Dibulatkan 481,300.00
3 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 3 Splt
a Semen PC (abu-abu) 6.72 sak 49,500.00
332,640.00
b Pasir beton 0.54 m3 140,000.00
75,600.00
c Split (batu pecah) 0.81 m3 140,000.00
113,400.00
d Pembantu tukang 2.00 org 27,500.00
55,000.00
e Tukang batu 0.35 org 42,000.00
14,700.00
Jumlah 591,340.00
Dibulatkan
591,300.00 4 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 225
a Semen PC (abu-abu) 7.76 sak 49,500.00
384,120.00
b Pasir beton 0.65 m3 140,000.00
91,000.00
c Split (batu pecah) 0.65 m3 140,000.00
91,000.00
d Pembantu tukang 2.00 org 27,500.00
55,000.00
e Tukang batu 0.35 org 42,000.00
14,700.00
Jumlah 635,820.00
Dibulatkan 635,800.00
5 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 275
a Semen PC (abu-abu) 8.00 sak 49,500.00
396,000.00
b Pasir beton 0.55 m3 140,000.00
77,000.00
c Split (batu pecah) 0.70 m3 140,000.00
98,000.00
d Pembantu tukang 2.02 org 27,500.00
55,550.00
e Tukang batu 0.40 org 42,000.00
16,800.00
Jumlah 643,350.00
Dibulatkan 643,300.00
B PEKERJAAN PEMBESIAN
1 1 KG PENULANGAN BETON/Besi beton polos
a Besi beton polos 1.05 kg 8,750.00
9,187.50
b Kawat beton 0.02 kg 15,000.00
300.00
c Pembantu tukang 0.01 org 27,500.00
275.00
d Tukang besi 0.01 org 42,000.00
420.00
Jumlah 10,182.50
Dibulatkan 10,100.00
2 1 KG PENULANGAN BETON/BESI BETON ULIR
a Besi Beton Ulir 1.10 kg 10,000.00
11,000.00
b Kawat beton 0.02 kg 15,000.00
225.00
c Pembantu tukang 0.01 org 27,500.00
275.00
d Tukang besi 0.02 org 42,000.00
840.00
Jumlah 12,340.00
Dibulatkan 12,300.00
C PEKERJAAN BEGISTING 1 1 M2 PASANG BEKISTING UNTUK SLOOF
a Papan kayu terentang 0.05 m3 1,750,000.00
78,750.00
b Paku 5 - 12 cm 0.30 kg 14,700.00
4,410.00
c Pelumas begisting (oli/minyak) 0.10 Ltr 10,000.00
1,000.00
d Pembantu tukang 0.30 org 27,500.00
8,250.00
e Tukang kayu 0.26 org 42,000.00
10,920.00
Jumlah 103,330.00
Dibulatkan 103,300.00
2 1 M2 PASANG BEKISTING UNTUK KOLOM
a Papan kayu terentang 0.04 m3 1,750,000.00
70,000.00
b Paku 5 - 12 cm 0.40 kg 14,700.00
5,880.00
c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00
2,000.00
d Balok kayu borneo 0.04 m3 4,000,000.00
160,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00
36,750.00
f Pembantu tukang 0.30 org 27,500.00
8,250.00
g Tukang kayu 0.33 org 42,000.00
13,860.00
Jumlah 296,740.00
Dibulatkan 296,700.00
3 1 M2 PASANG BEKISTING UNTUK BALOK
a Papan kayu terentang 0.04 m3 1,750,000.00
70,000.00
b Paku 5 - 12 cm 0.40 kg 14,700.00
5,880.00
c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00
2,000.00
d Balok kayu borneo 0.04 m3 4,000,000.00
160,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00
36,750.00
f Pembantu tukang 0.32 org 27,500.00
8,800.00
g Tukang kayu 0.33 org 42,000.00
13,860.00
Jumlah 297,290.00
Dibulatkan 297,200.00
4 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI
a Papan kayu terentang 0.04 m3 1,750,000.00
70,000.00
b Paku 5 - 12 cm 0.40 kg 14,700.00
5,880.00
c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00
2,000.00
d Balok kayu borneo 0.04 m3 4,000,000.00
160,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00
36,750.00
f Pembantu tukang 0.32 org 27,500.00
8,800.00
g Tukang kayu 0.33 org 42,000.00
13,860.00
Jumlah 297,290.00
Dibulatkan 297,200.00
5 1 M2 PASANG BEKISTING UNTUK TANGGA
a Papan kayu terentang 0.03 m3 1,750,000.00
52,500.00
b Paku 5 - 12 cm 0.40 kg 14,700.00
5,880.00
c Pelumas begisting (oli/minyak) 0.15 Ltr 10,000.00
1,500.00
d Balok kayu borneo 0.02 m3 4,000,000.00
80,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00
36,750.00
f Pembantu tukang 0.32 org 27,500.00
8,800.00
g Tukang kayu 0.33 org 42,000.00
13,860.00
Jumlah 199,290.00
Dibulatkan 199,200.00
D PEKERJAAN BETON BERTULANG 1 1 M3 MEMBUAT SLOOF BETON BERTULANG ( 200 kg BESI + BEKISTING ) K225
a Papan kayu terentang 0.27 m3 1,750,000.00
472,500.00
b Paku 5 - 12 cm 2.00 kg 14,700.00
29,400.00
c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00
6,000.00
d Besi beton polos 200.00 kg 8,750.00
1,750,000.00
e Kawat beton 3.00 kg
15,000.00 45,000.00
f Semen PC (abu-abu) 8.00 sak 49,500.00
396,000.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Pembantu tukang 4.50 org 27,500.00
123,750.00
j Tukang batu 0.35 org 42,000.00
14,700.00
k Tukang kayu 1.56 org 42,000.00
65,520.00
l Tukang besi 1.40 org 42,000.00
58,800.00
Jumlah 3,143,670.00
Dibulatkan 3,143,600.00
2 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 125 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,750,000.00
700,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00
58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00
20,000.00
d Besi beton polos 125.00 kg 8,750.00
1,093,750.00
e Kawat beton 4.50 kg 15,000.00
67,500.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.30 m3 4,000,000.00
1,200,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00
367,500.00
k Pembantu tukang 7.30 org 27,500.00
200,750.00
l Tukang batu 0.35 org 42,000.00
14,700.00
m Tukang kayu 3.30 org 42,000.00
138,600.00
n Tukang besi 2.10 org 42,000.00
88,200.00
Jumlah 4,451,075.00
Dibulatkan 4,451,000.00
3 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 150 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,750,000.00
700,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00
58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00
20,000.00
d Besi beton polos 150.00 kg 8,750.00
1,312,500.00
e Kawat beton 4.50 kg 15,000.00
67,500.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.30 m3 4,000,000.00
1,200,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00
367,500.00
k Pembantu tukang 7.30 org 27,500.00
200,750.00
l Tukang batu 0.35 org 42,000.00
14,700.00
m Tukang kayu 3.30 org 42,000.00
138,600.00
n Tukang besi 2.10 org 42,000.00
88,200.00
Jumlah 4,669,825.00
Dibulatkan 4,669,800.00
4 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 160 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,750,000.00
700,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00
58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00
20,000.00
d Besi beton polos 160.00 kg 8,750.00
1,400,000.00
e Kawat beton 4.50 kg 15,000.00
67,500.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.30 m3 4,000,000.00
1,200,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00
367,500.00
k Pembantu tukang 7.30 org 27,500.00
200,750.00
l Tukang batu 0.35 org 42,000.00
14,700.00
m Tukang kayu 3.30 org 42,000.00
138,600.00
n Tukang besi 2.10 org 42,000.00
88,200.00
Jumlah 4,757,325.00
Dibulatkan 4,757,300.00
5 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 175 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,750,000.00
700,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00
58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00
20,000.00
d Besi beton polos 175.00 kg 8,750.00
1,531,250.00
e Kawat beton 4.50 kg 15,000.00
67,500.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.30 m3 4,000,000.00
1,200,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00
367,500.00
k Pembantu tukang 7.30 org 27,500.00
200,750.00
l Tukang batu 0.35 org 42,000.00
14,700.00
m Tukang kayu 3.30 org 42,000.00
138,600.00
n Tukang besi 2.10 org 42,000.00
88,200.00
Jumlah 4,888,575.00
Dibulatkan 4,888,500.00
6 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 200 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,750,000.00
700,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00
58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00
20,000.00
d Besi beton polos 200.00 kg 8,750.00
1,750,000.00
e Kawat beton 4.50 kg 15,000.00
67,500.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.30 m3 4,000,000.00
1,200,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00
367,500.00
k Pembantu tukang 7.30 org 27,500.00
200,750.00
l Tukang batu 0.35 org 42,000.00
14,700.00
m Tukang kayu 3.30 org 42,000.00
138,600.00
n Tukang besi 2.10 org 42,000.00
88,200.00
Jumlah 5,107,325.00
Dibulatkan 5,107,300.00
7 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 250 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,750,000.00
700,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00
58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00
20,000.00
d Besi beton polos 250.00 kg 8,750.00
2,187,500.00
e Kawat beton 4.50 kg 15,000.00
67,500.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo super 0.30 m3 4,000,000.00
1,200,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00
367,500.00
k Pembantu tukang 7.30 org 27,500.00
200,750.00
l Tukang batu 0.35 org 42,000.00
14,700.00
m Tukang kayu 3.30 org 42,000.00
138,600.00
n Tukang besi 2.10 org 42,000.00
88,200.00
Jumlah 5,544,825.00
Dibulatkan 5,544,800.00
8 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 300 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,750,000.00
700,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00
58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00
20,000.00
d Besi beton polos 300.00 kg 8,750.00
2,625,000.00
e Kawat beton 4.50 kg 15,000.00
67,500.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.30 m3 4,000,000.00
1,200,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00
367,500.00
k Pembantu tukang 7.30 org 27,500.00
200,750.00
l Tukang batu 0.35 org 42,000.00
14,700.00
m Tukang kayu 3.30 org 42,000.00
138,600.00
n Tukang besi 2.10 org 42,000.00
88,200.00
Jumlah 5,982,325.00
Dibulatkan 5,982,300.00
9 1 M3 MEMBUAT BALOK BETON BERTULANG ( 125 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,750,000.00
560,000.00
b Paku 5 - 12 cm 3.20 kg 14,700.00
47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00
16,000.00
d Besi beton polos 125.00 kg 8,750.00
1,093,750.00
e Kawat beton 2.25 kg 15,000.00
33,750.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.12 m3 4,000,000.00
480,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00
294,000.00
kDolken Ø-8 cm atau kayu 4 x 6 cm / 4m
32.00 btg 18,000.00
576,000.00
l Pembantu tukang 5.80 org 27,500.00
159,500.00
m Tukang batu 0.35 org 42,000.00
14,700.00
n Tukang kayu 2.80 org 42,000.00
117,600.00
o Tukang besi 1.05 org 42,000.00
44,100.00
Jumlah 3,937,715.00
Dibulatkan 3,937,700.00
10 1 M3 MEMBUAT BALOK BETON BERTULANG ( 150 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,750,000.00
560,000.00
b Paku 5 - 12 cm 3.20 kg 14,700.00
47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00
16,000.00
d Besi beton polos 150.00 kg 8,750.00
1,312,500.00
e Kawat beton 2.25 kg
15,000.00 33,750.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.12 m3 4,000,000.00
480,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00
294,000.00
kDolken Ø-8 Cm atau kayu 4 x 6 cm / 4m
32.00 btg 18,000.00
576,000.00
l Pembantu tukang 5.80 org 27,500.00
159,500.00
m Tukang batu 0.35 org 42,000.00
14,700.00
n Tukang kayu 2.80 org 42,000.00
117,600.00
o Tukang besi 1.05 org 42,000.00
44,100.00
Jumlah 4,156,465.00
Dibulatkan 4,156,400.00
11 1 M3 MEMBUAT BALOK BETON BERTULANG ( 200 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,750,000.00
560,000.00
b Paku 5 - 12 cm 3.20 kg 14,700.00
47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00
16,000.00
d Besi beton polos 200.00 kg 8,750.00
1,750,000.00
e Kawat beton 3.00 kg 15,000.00
45,000.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.14 m3 4,000,000.00
560,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00
294,000.00
kDolken Ø-8 Cm atau kayu 4 x 6 cm / 4m
16.00 btg 18,000.00
288,000.00
l Pembantu tukang 5.96 org 27,500.00
163,900.00
m Tukang batu 0.35 org 42,000.00
14,700.00
n Tukang kayu 2.80 org 42,000.00
117,600.00
o Tukang besi 1.40 org 42,000.00
58,800.00
Jumlah 4,416,315.00
Dibulatkan 4,416,300.00
12 1 M3 MEMBUAT BALOK BETON BERTULANG (200 kg BESI + BEKISTING)
a Papan kayu terentang 0.32 m3 1,750,000.00
560,000.00
b Paku 5 - 12 cm 3.20 kg
14,700.00 47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00
16,000.00
d Besi beton polos 225.00 kg 8,750.00
1,968,750.00
e Kawat beton 4.00 kg 15,000.00
60,000.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo Super 0.14 m3 4,000,000.00
560,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00
294,000.00
kDolken Ø-8 Cm atau kayu 4 x 6 cm / 4m
16.00 btg 18,000.00
288,000.00
l Pembantu tukang 5.96 org 27,500.00
163,900.00
m Tukang batu 0.35 org 42,000.00
14,700.00
n Tukang kayu 2.80 org 42,000.00
117,600.00
o Tukang besi 1.40 org 42,000.00
58,800.00
Jumlah 4,650,065.00
Dibulatkan 4,650,000.00
13 1 M3 MEMBUAT BALOK BETON BERTULANG ( 250 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,750,000.00
560,000.00
b Paku 5 - 12 cm 3.20 kg 14,700.00
47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00
16,000.00
d Besi beton polos 250.00 kg 8,750.00
2,187,500.00
e Kawat beton 6.00 kg 15,000.00
90,000.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo super 0.14 m3 4,000,000.00
560,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00
294,000.00
kDolken Ø-8 Cm atau kayu 4 x 6 cm / 4m
16.00 btg 18,000.00
288,000.00
l Pembantu tukang 5.96 org 27,500.00
163,900.00
m Tukang batu 0.35 org 42,000.00
14,700.00
n Tukang kayu 2.80 org 42,000.00
117,600.00
o Tukang besi 1.40 org 42,000.00
58,800.00
Jumlah 4,898,815.00
Dibulatkan
4,898,800.00 14 1 M3 MEMBUAT TANGGA BETON BERTULANG ( 200 kg BESI + BEKISTING )
a Papan kayu terentang 0.25 m3 1,750,000.00
437,500.00
b Paku 5 - 12 cm 3.00 kg 14,700.00
44,100.00
c Pelumas begisting (oli/minyak) 1.20 Ltr 10,000.00
12,000.00
d Besi beton polos 200.00 kg 8,750.00
1,750,000.00
e Kawat beton 3.00 kg 15,000.00
45,000.00
f Semen PC (abu-abu) 6.45 sak 49,500.00
319,275.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Balok kayu borneo super 0.30 m3 4,000,000.00
1,200,000.00
j Multiplex 120 x 240 x 9 mm 2.50 lbr 105,000.00
262,500.00
k Pembantu tukang 5.60 org 27,500.00
154,000.00
l Tukang batu 0.35 org 42,000.00
14,700.00
m Tukang kayu 2.30 org 42,000.00
96,600.00
n Tukang besi 1.40 org 42,000.00
58,800.00
Jumlah 4,576,475.00
Dibulatkan 4,576,400.00
15 1 M3 MEMBUAT PLAT LANTAI Tb. 10 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )
aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr
1.00 m3 591,340.00
591,340.00
b Pasang bekisting untuk lantai 10.00 m2 297,290.00
2,972,900.00
c Besi beton rakit 100.00 kg 8,750.00
875,000.00
Jumlah 4,439,240.00
Dibulatkan 4,439,200.00
16 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )
aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr
1.00 m3 591,340.00
591,340.00
b Pasang bekisting untuk lantai 8.33 m2 297,290.00
2,476,425.70
c Besi beton rakit 115.00 kg 8,750.00
1,006,250.00
Jumlah 4,074,015.70
Dibulatkan 4,074,000.00
17 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 125 kg BESI + BEKISTING )
aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr
1.00 m3 591,340.00
591,340.00
b Pasang Bekisting untuk lantai 8.33 m2 297,290.00
2,476,425.70
c Besi Beton rakit 125.00 kg 8,750.00
1,093,750.00
Jumlah
4,161,515.70
Dibulatkan 4,161,500.00
18 1 M3 MEMBUAT PLAT LANTAI Tb. 15 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )
aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr
1.00 m3 591,340.00
591,340.00
b Pasang Bekisting untuk lantai 6.67 m2 297,290.00
1,982,924.30
c Besi Beton rakit 100.00 kg 8,750.00
875,000.00
Jumlah 3,449,264.30
Dibulatkan 3,449,200.00
19 1 M3 MEMBUAT PLAT LANTAI Tb. 20 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )
aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr
1.00 m3 591,340.00
591,340.00
b Pasang Bekisting untuk lantai 7.50 m2 297,290.00
2,229,675.00
c Besi Beton rakit 115.00 kg 8,750.00
1,006,250.00
Jumlah 3,827,265.00
Dibulatkan 3,827,200.00
20 1 M3 MEMBUAT RING BALK BETON BERTULANG ( 175 kg BESI + BEKISTING ) K225
a Papan kayu terentang 0.27 m3 1,750,000.00
472,500.00
b Paku 5 - 12 cm 2.00 kg 14,700.00
29,400.00
c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00
6,000.00
d Besi beton polos 175.00 kg 8,750.00
1,531,250.00
e Kawat beton 3.00 kg 15,000.00
45,000.00
f Semen PC (abu-abu) 8.00 sak 49,500.00
396,000.00
g Pasir beton 0.52 m3 140,000.00
72,800.00
h Split (batu pecah) 0.78 m3 140,000.00
109,200.00
i Pembantu tukang 4.85 org 27,500.00
133,375.00
j Tukang batu 0.40 org 42,000.00
16,800.00
k Tukang kayu 1.75 org 42,000.00
73,500.00
l Tukang besi 1.45 org 42,000.00
60,900.00
Jumlah 2,946,725.00
Dibulatkan 2,946,700.00
V PEKERJAAN DINDING 1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 3 Ps
a Bata merah 140.00 bh 325.00
45,500.00
b Semen PC (abu-abu) 0.65 sak 49,500.00
32,175.00
c Pasir pasang 0.09 m3 125,000.00
11,250.00
d Pembantu tukang 0.65 org 27,500.00
17,875.00
e Tukang batu 0.20 org 42,000.00
8,400.00
Jumlah 115,200.00
Dibulatkan 115,200.00
2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 4 Ps
a Bata merah 140.00 bh 325.00
45,500.00
b Semen PC (abu-abu) 0.55 sak 49,500.00
27,225.00
c Pasir pasang 0.09 m3 125,000.00
11,250.00
d Pembantu tukang 0.65 org 27,500.00
17,875.00
e Tukang batu 0.20 org 42,000.00
8,400.00
Jumlah 110,250.00
Dibulatkan 110,200.00
3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 5 Ps
a Bata merah 140.00 bh 325.00
45,500.00
b Semen PC (abu-abu) 0.45 sak 49,500.00
22,275.00
c Pasir pasang 0.10 m3 125,000.00
12,500.00
d Pembantu tukang 0.65 org 27,500.00
17,875.00
e Tukang batu 0.20 org 42,000.00
8,400.00
Jumlah 106,550.00
Dibulatkan 106,500.00
4 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 3 Ps
a Bata merah 70.00 bh 325.00
22,750.00
b Semen PC (abu-abu) 0.29 sak 49,500.00
14,355.00
c Pasir pasang 0.04 m3 125,000.00
5,000.00
d Pembantu tukang 0.32 org 27,500.00
8,800.00
e Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 55,105.00
Dibulatkan 55,100.00
5 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 4 Ps
a Bata merah 70.00 bh 325.00
22,750.00
b Semen PC (abu-abu) 0.25 sak 49,500.00
12,375.00
c Pasir pasang 0.05 m3 125,000.00
6,250.00
d Pembantu tukang 0.32 org 27,500.00
8,800.00
e Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 54,375.00
Dibulatkan 54,300.00
6 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 5 Ps
a Bata merah 70.00 bh 325.00
22,750.00
b Semen PC (abu-abu) 0.22 sak 49,500.00
10,890.00
c Pasir pasang 0.05 m3 125,000.00
6,250.00
d Pembantu tukang 0.32 org 27,500.00
8,800.00
e Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 52,890.00
Dibulatkan 52,800.00
7 1 M2 PASANG DINDING BATA ROOSTER / BATA TERAWANG
aRooster/Terawang ukuran 12 x 11 x 24
37.00 bh 3,000.00
111,000.00
b Semen PC (abu-abu) 0.27 sak 49,500.00
13,365.00
c Pasir pasang 0.04 m3 125,000.00
5,000.00
d Pembantu tukang 0.30 org 27,500.00
8,250.00
e Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 141,815.00
Dibulatkan 141,800.00
8 1 M2 PASANG DINDING GLASSBLOCK
a Glassblock ukuran 18 x 18 cm 30.00 bh 17,000.00
510,000.00
b Semen Putih 0.27 sak 12,700.00
3,429.00
c Pembantu tukang 0.30 org 27,500.00
8,250.00
d Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 525,879.00
Dibulatkan 525,800.00
9 1 M2 PASANGAN BATACO PUTIH, CAMPURAN 1 Pc : 5 Ps
a Batako putih 15.00 bh 4,200.00
63,000.00
b Semen PC (abu-abu) 0.25 sak 42,000.00
10,500.00
c Pasir pasang 0.03 m3 68,000.00
2,040.00
d Pembantu tukang 0.30 org 27,500.00
8,250.00
e Tukang batu 0.15 org 40,000.00
6,000.00
Jumlah 89,790.00
Dibulatkan 89,700.00
10 1 M2 PASANGAN BATACO PRES SEMEN, CAMPURAN 1 Pc : 5 Ps a Bataco press semen 15.00 bh
2,650.00 39,750.00
b Semen PC (abu-abu) 0.20 sak 49,500.00
9,900.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Pembantu tukang 0.30 org 27,500.00
8,250.00
e Tukang batu 0.15 org 42,000.00
6,300.00
Jumlah 66,700.00
Dibulatkan 66,700.00
11 1 M2 PASANGAN BATA RINGAN ( HEBEL/CELCON )
a Bata ringan ( hebel/celcon ) 8.00 bh 2,550.00
20,400.00
b Semen instan 11.45 kg 2,450.00
28,052.50
c Pembantu tukang 0.30 org 27,500.00
8,250.00
d Tukang batu 0.20 org 42,000.00
8,400.00
Jumlah 65,102.50
Dibulatkan 65,100.00
VI PEKERJAAN PLESTERAN/ACCI 1 1 M2 PLESTERAN CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm a Semen PC (abu-abu) 0.14 sak
49,500.00 6,930.00
b Pasir pasang 0.02 m3 125,000.00
2,500.00
c Pembantu tukang 0.20 org 27,500.00
5,500.00
d Tukang batu 0.15 org 42,000.00
6,300.00
Jumlah 21,230.00
Dibulatkan 21,200.00
2 1 M2 PLESTERAN CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.13 sak 49,500.00
6,435.00
b Pasir pasang 0.02 m3 125,000.00
2,500.00
c Pembantu tukang 0.20 org 27,500.00
5,500.00
d Tukang batu 0.15 org 42,000.00
6,300.00
Jumlah 20,735.00
Dibulatkan 20,700.00
3 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.10 sak 49,500.00
4,950.00
b Pasir pasang 0.02 m3 125,000.00
2,500.00
c Pembantu tukang 0.20 org 27,500.00
5,500.00
d Tukang batu 0.15 org
42,000.00 6,300.00
Jumlah 19,250.00
Dibulatkan 19,200.00
4 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.09 sak 49,500.00
4,455.00
b Pasir pasang 0.02 m3 125,000.00
2,500.00
c Pembantu tukang 0.20 org 27,500.00
5,500.00
d Tukang batu 0.15 org 42,000.00
6,300.00
Jumlah 18,755.00
Dibulatkan 18,700.00
5 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 2,0 cm
a Semen PC (abu-abu) 0.17 sak 49,500.00
8,415.00
b Pasir pasang 0.03 m3 125,000.00
3,750.00
c Pembantu tukang 0.22 org 27,500.00
6,050.00
d Tukang batu 0.16 org 42,000.00
6,720.00
Jumlah 24,935.00
Dibulatkan 24,900.00
6 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 2,0 cm
a Semen PC (abu-abu) 0.15 sak 49,500.00
7,425.00
b Pasir pasang 0.03 m3 125,000.00
3,750.00
c Pembantu tukang 0.25 org 27,500.00
6,875.00
d Tukang batu 0.20 org 42,000.00
8,400.00
Jumlah 26,450.00
Dibulatkan 26,400.00
7 1 M2 BERAPEN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.11 sak 49,500.00
5,445.00
b Pasir pasang 0.03 m3 125,000.00
3,125.00
c Pembantu tukang 0.15 org 27,500.00
4,125.00
d Tukang batu 0.07 org 42,000.00
2,940.00
Jumlah 15,635.00
Dibulatkan 15,600.00
8 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.19 sak 49,500.00
9,405.00
b Pasir pasang 0.02 m3 125,000.00
2,500.00
c Pembantu tukang 0.26 org 27,500.00
7,150.00
d Tukang batu 0.20 org 42,000.00
8,400.00
Jumlah 27,455.00
Dibulatkan 27,400.00
9 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.15 sak 49,500.00
7,425.00
b Pasir pasang 0.02 m3 125,000.00
2,500.00
c Pembantu tukang 0.26 org 27,500.00
7,150.00
d Tukang batu 0.20 org 42,000.00
8,400.00
Jumlah 25,475.00
Dibulatkan 25,400.00
10 1 M2 PLESTERAN SKONENG CAMPURAN 1 Pc : 2 Ps
a Semen PC (abu-abu) 0.01 sak 49,500.00
495.00
b Pasir pasang 0.01 m3 125,000.00
1,250.00
c Pembantu tukang 0.06 org 27,500.00
1,650.00
d Tukang batu 0.04 org 42,000.00
1,680.00
Jumlah 5,075.00
Dibulatkan 5,000.00
11 1 M2 ACIAN PLESTERAN
a Semen PC (abu-abu) 0.08 sak 49,500.00
3,960.00
b Pembantu tukang 0.14 org 27,500.00
3,850.00
c Tukang batu 0.11 org 42,000.00
4,620.00
Jumlah 12,430.00
Dibulatkan 12,400.00
12 1 M2 PLESTERAN SIAR CAMPURAN 1 Pc : 2 Ps
a Semen PC (abu-abu) 0.09 sak 49,500.00
4,455.00
b Pasir pasang 0.02 m3 125,000.00
2,500.00
c Pembantu tukang 0.15 org 27,500.00
4,125.00
d Tukang batu 0.07 org 42,000.00
2,940.00
Jumlah 14,020.00
Dibulatkan 14,000.00
VII PEKERJAAN PELAPIS LANTAI 1 1 M2 P
a Keramik ukuran 40 x 40 cm 1.00 m2 200,000.00
200,000.00
b Semen PC (abu-abu) 0.16 sak 49,500.00
7,920.00
c Pasir pasang 0.02 m3 125,000.00
2,687.50
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.25 org 27,500.00
6,875.00
f Tukang batu 0.12 org 42,000.00
5,040.00
Jumlah 222,776.50
Dibulatkan 222,770.00
2 1 M2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm UNPOLISH
a Keramik ukuran 40 x 40 cm 1.00 m2 200,000.00
200,000.00
b Semen PC (abu-abu) 0.16 sak 49,500.00
7,920.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.26 org 27,500.00
7,150.00
f Tukang batu 0.13 org 42,000.00
5,250.00
Jumlah 223,074.00
Dibulatkan 223,070.00
3 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 60 cm
a Keramik ukuran 60 x 60 cm 1.00 m2 276,000.00
276,000.00
b Semen PC (abu-abu) 0.18 sak 49,500.00
8,910.00
c Pasir pasang 0.02 m3 125,000.00
2,687.50
d Semen warna 0.01 kg 12,700.00
165.10
e Pembantu tukang 0.25 org 27,500.00
6,875.00
f Tukang batu 0.12 org 42,000.00
5,040.00
Jumlah 299,677.60
Dibulatkan 299,670.00
4 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 90 cm
a Keramik ukuran 60 x 90 cm 1.00 m2 300,000.00
300,000.00
b Semen PC (abu-abu) 0.17 sak 49,500.00
8,415.00
c Pasir pasang 0.02 m3 125,000.00
2,687.50
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.26 org 27,500.00
7,150.00
f Tukang batu 0.14 org 42,000.00
5,880.00
Jumlah 324,386.50
Dibulatkan 324,380.00
5 1 M2 PASANG LANTAI KERAMIK 10 x 20 cm
a Keramik lantai 10 x 20 cm 1.00 m2 35,000.00
35,000.00
b Semen PC ( abu-abu ) 0.18 sak 49,500.00
8,910.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.22 org 27,500.00
6,050.00
f Tukang batu 0.40 org 42,000.00
16,800.00
Jumlah 69,514.00
Dibulatkan 69,510.00
6 1 M2 PASANG LANTAI KERAMIK POLOS 20 x 20 cm
a Keramik polos 20 x 20 cm 1.00 m2 35,000.00
35,000.00
b Semen PC (abu-abu) 0.17 sak 49,500.00
8,415.00
c Pasir pasang 0.02 m3 125,000.00
2,687.50
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.30 org 27,500.00
8,250.00
f Tukang batu 0.15 org 42,000.00
6,300.00
Jumlah 60,906.50
Dibulatkan 60,900.00
7 1 M2 PASANG LANTAI KERAMIK MOTIF 20 x 20 cm
a Keramik motif 20 x 20 cm 1.00 m2 37,000.00
37,000.00
b Semen PC (abu-abu) 0.17 sak 49,500.00
8,415.00
c Pasir pasang 0.02 m3 125,000.00
2,687.50
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.30 org 27,500.00
8,250.00
f Tukang batu 0.15 org 42,000.00
6,300.00
Jumlah 62,906.50
Dibulatkan 62,900.00
8 1 M2 PASANG LANTAI KERAMIK POLOS 30 x 30 cm
a Keramik polos 30 x 30 cm 1.00 m2 33,000.00
33,000.00
b Semen PC (abu-abu) 0.16 sak 49,500.00
7,920.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.25 org 27,500.00
6,875.00
f Tukang batu 0.12 org 42,000.00
5,040.00
Jumlah 55,589.00
Dibulatkan 55,580.00
9 1 M2 PASANG LANTAI KERAMIK MOTIF 30 x 30 cm
a Keramik motif 30 x 30 cm 1.00 m2 42,000.00
42,000.00
b Semen PC (abu-abu) 0.16 sak 49,500.00
7,920.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.25 org 27,500.00
6,875.00
f Tukang batu 0.12 org 42,000.00
5,040.00
Jumlah 64,589.00
Dibulatkan 64,580.00
10 1 M2 PASANG LANTAI MARMER
a Marmer standart 1.00 m2 135,000.00
135,000.00
b Semen PC (abu-abu) 0.48 sak 49,500.00
23,760.00
c Pasir pasang 0.10 m3 125,000.00
12,500.00
d Semen warna 0.20 sak 12,700.00
2,540.00
e Pembantu tukang 0.62 org 27,500.00
17,050.00
f Tukang batu 0.35 org 42,000.00
14,700.00
Jumlah 205,550.00
Dibulatkan 205,550.00
11 1 M2 PASANG LANTAI PARQUET JATI
a Parquet jati 1.05 m2 260,000.00
273,000.00
b Lem vinyl 0.60 kg 30,800.00
18,480.00
c Pembantu tukang 0.65 org 27,500.00
17,875.00
d Tukang 0.35 org 42,000.00
14,700.00
Jumlah 324,055.00
Dibulatkan 324,050.00
12 1 M2 PASANG LANTAI GRANIT
a Granit Standart 1.00 m2 650,000.00
650,000.00
b Semen PC (abu-abu) 0.48 sak 49,500.00
23,760.00
c Pasir pasang 0.08 m3 125,000.00
10,000.00
d Semen warna 0.10 sak 12,700.00
1,270.00
e Pembantu tukang 0.60 org 27,500.00
16,500.00
f Tukang batu 0.48 org 42,000.00
20,160.00
Jumlah 721,690.00
Dibulatkan 721,690.00
VIII PEKERJAAN PELAPIS DINDING 1 1 M2 P
a Keramik motif 10 x 20 cm 1.00 m2 37,000.00
37,000.00
b Semen PC ( abu-abu ) 0.18 sak 49,500.00
8,910.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.22 org 27,500.00
6,050.00
f Tukang batu 0.40 org 42,000.00
16,800.00
Jumlah 71,514.00
Dibulatkan 71,510.00
2 1 M2 PASANG DINDING KERAMIK POLOS 10 x 20 cm
a Keramik polos 10 x 20 cm 1.00 m2 34,000.00
34,000.00
b Semen PC ( abu-abu ) 0.18 sak 49,500.00
8,910.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.22 org
27,500.00 6,050.00
f Tukang batu 0.40 org 42,000.00
16,800.00
Jumlah 68,514.00
Dibulatkan 68,510.00
3 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 20 cm
a Keramik motif 20 x 20 cm 1.00 m2 37,000.00
37,000.00
b Semen PC ( abu-abu ) 0.17 sak 49,500.00
8,415.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Semen warna 0.02 kg 12,700.00
254.00
e Pembantu tukang 0.20 org 27,500.00
5,500.00
f Tukang batu 0.39 org 42,000.00
16,380.00
Jumlah 70,049.00
Dibulatkan 70,040.00
4 1 M2 PASANG DINDING KERAMIK POLOS 20 x 20 cm
a Keramik polos 20 x 20 cm 1.00 m2 38,000.00
38,000.00
b Semen PC ( abu-abu ) 0.17 sak 49,500.00
8,415.00
c Pasir pasang 0.02 m3 125,000.00
2,500.00
d Semen warna 0.02 kg
12,700.00 254.00
e Pembantu tukang 0.20 org 27,500.00
5,500.00
f Tukang batu 0.39 org 42,000.00
16,380.00
Jumlah 71,049.00
Dibulatkan 71,040.00
5 1 M2 PASANG DINDING KERAMIK POLOS 20 x 25 cm
a Keramik polos 20 x 25 cm 1.00 m2 38,500.00
38,500.00
b Semen PC ( abu-abu ) 0.16 sak 49,500.00
7,920.00
c Pasir pasang 0.02 m3 125,000.00
2,250.00
d Semen warna 0.01 kg 12,700.00
165.10
e Pembantu tukang 0.19 org 27,500.00
5,156.25
f Tukang batu 0.38 org 42,000.00
15,750.00
Jumlah 69,741.35
Dibulatkan 69,740.00
6 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 25 cm
a Keramik motif 20 x 25 cm 1.00 m2 38,500.00
38,500.00
b Semen PC ( abu-abu ) 0.16 sak 49,500.00
7,920.00
c Pasir pasang 0.02 m3
125,000.00 2,250.00
d Semen warna 0.01 kg 12,700.00
165.10
e Pembantu tukang 0.19 org 27,500.00
5,156.25
f Tukang batu 0.38 org 42,000.00
15,750.00
Jumlah 69,741.35
Dibulatkan 69,740.00
7 1 M2 PASANG DINDING MARMER
a Marmer standar 1.00 m2 135,000.00
135,000.00
b Paku sekrup 4.00 bh 700.00
2,800.00
c Semen PC ( abu-abu ) 0.25 sak 49,500.00
12,375.00
d Pasir pasang 0.03 m3 125,000.00
3,125.00
e Semen warna 1.50 kg 12,700.00
19,050.00
f Kawat ikat 0.03 kg 15,000.00
375.00
g Paku 0.03 kg 14,700.00
367.50
h Pembantu tukang 0.72 org 27,500.00
19,800.00
i Tukang batu 0.65 org 42,000.00
27,300.00
Jumlah 220,192.50
Dibulatkan 220,190.00
8 1 M2 PASANG DINDING GRANIT
a Granit standar 1.00 m2 650,000.00
650,000.00
b Paku sekrup 2.00 bh 700.00
1,400.00
c Semen PC ( abu-abu ) 0.25 sak 49,500.00
12,375.00
d Pasir pasang 0.03 m3 125,000.00
3,125.00
e Semen warna 1.50 kg 12,700.00
19,050.00
f Kawat ikat 0.03 kg 15,000.00
375.00
g Paku 0.03 kg 14,700.00
367.50
h Pembantu tukang 0.72 org 27,500.00
19,800.00
i Tukang batu 0.65 org 42,000.00
27,300.00
Jumlah 733,792.50
Dibulatkan 733,790.00
9 1 M2 PASANG DINDING BATU TEMPEL HITAM
a Batu tempel hitam 1.00 m2 80,000.00
80,000.00
b Semen PC ( abu-abu ) 0.24 sak 49,500.00
11,880.00
c Pasir pasang 0.04 m3 125,000.00
4,375.00
d Pembantu tukang 0.32 org 27,500.00
8,800.00
e Tukang batu 0.25 org 42,000.00
10,500.00
Jumlah 115,555.00
Dibulatkan 115,550.00
10 1 M2 PASANG DINDING BATU ALAM
a Batu alam 1.00 m2 78,000.00
78,000.00
b Semen PC ( abu-abu ) 0.25 sak 49,500.00
12,375.00
c Pasir pasang 0.04 m3 125,000.00
4,375.00
d Pembantu tukang 0.32 org 27,500.00
8,800.00
e Tukang batu 0.25 org 42,000.00
10,500.00
Jumlah 114,050.00
Dibulatkan 114,050.00
11 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 40 cm
a Plint keramik ukuran 10 x 40 cm 2.65 bh 7,500.00
19,875.00
b Semen PC (abu-abu) 0.02 sak 49,500.00
990.00
c Pasir pasang 0.01 m3 125,000.00
1,250.00
d Semen warna 0.10 kg 12,700.00
1,270.00
e Pembantu tukang 0.06 org 27,500.00
1,650.00
f Tukang batu 0.03 org 42,000.00
1,260.00
Jumlah 26,295.00
Dibulatkan 26,290.00
12 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 30 cm
a Plint keramik ukuran 10 x 30 cm 3.30 bh 6,500.00
21,450.00
b Semen PC (abu-abu) 0.02 sak 49,500.00
990.00
c Pasir pasang 0.01 m3 125,000.00
1,250.00
d Semen warna 0.12 kg 12,700.00
1,524.00
e Pembantu tukang 0.06 org 27,500.00
1,650.00
f Tukang batu 0.03 org 42,000.00
1,260.00
Jumlah 28,124.00
Dibulatkan 28,120.00
IX PEKERJAAN KUSEN, PINTU, JENDELA, PARTISI 1 1 M3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER SAMARINDA
a Balok kayu kamper samarinda 1.20 m3 5,000,000.00
6,000,000.00
b Pembantu tukang 6.00 org 27,500.00
165,000.00
c Tukang kayu 15.00 org 42,000.00
630,000.00
Jumlah 6,795,000.00
Dibulatkan 6,795,000.00
2 1 M3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER MEDAN / KRUING
a Balok kayu kamper medan 1.20 m3 4,100,000.00
4,920,000.00
b Pembantu tukang 6.00 org 27,500.00
165,000.00
c Tukang kayu 15.00 org 42,000.00
630,000.00
Jumlah 5,715,000.00
Dibulatkan 5,715,000.00
3 1 M3 PASANG KUSEN PINTU & JENDELA KAYU BORNEO SUPER
a Kayu balok borneo super 1.20 m3 4,000,000.00
4,800,000.00
b Pembantu tukang 6.00 org 27,500.00
165,000.00
c Tukang kayu 15.00 org 42,000.00
630,000.00
Jumlah 5,595,000.00
Dibulatkan 5,595,000.00
4 1 M2 PASANG PINTU PANEL KAYU KAMPER SAMARINDA a Papan kayu kamper samarinda 0.04 m3
5,350,000.00 214,000.00
b Pembantu tukang 1.00 org 27,500.00
27,500.00
c Tukang kayu 2.50 org 42,000.00
105,000.00
Jumlah 346,500.00
Dibulatkan 346,500.00
5 1 M2 PASANG PINTU PANEL KAYU KAMPER MEDAN / KRUING
a Papan kayu Kamper Medan 0.04 m3 4,275,000.00
171,000.00
b Pembantu tukang 1.00 org 27,500.00
27,500.00
c Tukang kayu 2.50 org 42,000.00
105,000.00
Jumlah 303,500.00
Dibulatkan 303,500.00
6 1 M2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.04 m3 4,275,000.00
117,600.00
b Pembantu tukang 0.80 org 27,500.00
44,100.00
c Tukang kayu 2.00 org 42,000.00
117,600.00
Jumlah 279,300.00
Dibulatkan 279,300.00
7 1 M2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO
a Papan kayu borneo super 0.04 m3 4,800,000.00
47,040.00
b Pembantu tukang 0.80 org 27,500.00
16,000.00
c Tukang kayu 2.00 org 42,000.00
84,000.00
Jumlah 147,040.00
Dibulatkan 147,000.00
8 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.06 m3 4,275,000.00
273,600.00
b Pembantu tukang 1.00 org 27,500.00
27,500.00
c Tukang kayu 3.00 org 42,000.00
126,000.00
Jumlah 427,100.00
Dibulatkan 427,100.00
9 1 M2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.02 m3 4,275,000.00
83,790.00
b Paku 1 s/d 5 cm 0.03 kg 14,700.00
441.00
c Lem kayu 0.30 Ltr 20,000.00
6,000.00
d Triplek 0,4 cm ukuran pintu 1.00 lbr 36,000.00
36,000.00
e Pembantu tukang 0.60 org 27,500.00
16,500.00
f Tukang kayu 2.00 org 42,000.00
84,000.00
Jumlah 226,731.00
Dibulatkan 226,700.00
10 1 M2 PASANG JALUSI MATI KUSEN KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.06 m3 4,275,000.00
256,500.00
b Paku 1 s/d 5 cm 0.15 kg 14,700.00
2,205.00
c Pembantu tukang 0.50 org 27,500.00
13,750.00
d Tukang kayu 2.00 org 42,000.00
84,000.00
Jumlah 356,455.00
Dibulatkan 356,400.00
11 1 M2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU BORNEO SUPER
a Papan kayu borneo Super 0.02 m3 4,800,000.00
94,080.00
b Paku 1 s/d 5 cm 0.03 kg 14,700.00
441.00
c Lem Kayu 0.30 Ltr 20,000.00
6,000.00
d Triplek 0,4 cm ukuran pintu 1.00 lbr 36,000.00
36,000.00
e Pembantu tukang 0.60 org 27,500.00
16,500.00
f Tukang kayu 2.00 org 42,000.00
84,000.00
Jumlah 237,021.00
Dibulatkan 237,000.00
12 1 M2 PASANG PINTU TEAKWOOD RANGKAP , RANGKA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.02 m3 4,275,000.00
83,790.00
b Paku 1 s/d 5 cm 0.30 kg 14,700.00
4,410.00
c Lem kayu 0.30 Ltr 20,000.00
6,000.00
d Teakwood 120 x 240 x 0,4 cm 1.00 lbr 85,000.00
85,000.00
e Pembantu tukang 0.60 org 27,500.00
16,500.00
f Tukang kayu 2.00 org 42,000.00
84,000.00
Jumlah 279,700.00
Dibulatkan 279,700.00
13 1 M2 PASANG PINTU TRIPLEK & FORMIKA RANGKA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.02 m3 4,800,000.00
94,080.00
b Paku 1 s/d 5 cm 0.30 kg 14,700.00
4,410.00
c Lem Kayu 0.80 Ltr 20,000.00
16,000.00
d Triplek 0,4 cm ukuran pintu 1.00 lbr 36,000.00
36,000.00
e Formica 3" x 6" 0.50 lbr 135,000.00
67,500.00
f Pembantu tukang 0.80 org 27,500.00
22,000.00
g Tukang kayu 2.50 org 42,000.00
105,000.00
Jumlah 344,990.00
Dibulatkan 344,900.00
14 1 M2 PASANG PINTU TEAKWOOD & FORMIKA RANGKA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.02 m3 4,275,000.00
83,790.00
b Paku 1 s/d 5 cm 0.30 kg 14,700.00
4,410.00
c Lem Kayu 0.80 Ltr 20,000.00
16,000.00
d Teakwood 120 x 240 x 0,4 cm 0.50 lbr 85,000.00
42,500.00
e Vernis 0.50 Ltr 27,500.00
13,750.00
a Formica 4" x 8" 0.50 lbr 135,000.00
67,500.00
b Pembantu tukang 0.80 org 27,500.00
22,000.00
c Tukang kayu 2.50 org 42,000.00
105,000.00
Jumlah 354,950.00
Dibulatkan 354,900.00
15 1 M2 PASANG DINDING PEMISAH DOUBLE TEAKWOOD, RANGKA KAYU KAMPER MEDAN
a Balok kayu Kamper Medan 0.02 m3 4,100,000.00
79,950.00
b Papan kayu Kamper Medan 0.01 m3 4,275,000.00
29,925.00
c Paku 5 - 12 cm 0.10 kg 14,700.00
1,470.00
d Lem Kayu 0.56 Ltr 20,000.00
11,200.00
e Teakwood 120 x 240 x 0,4 cm 1.00 lbr 85,000.00
85,000.00
f Pembantu tukang 0.15 org 27,500.00
4,125.00
g Tukang kayu 0.45 org 42,000.00
18,900.00
Jumlah 230,570.00
Dibulatkan 230,500.00
16 1 M2 PASANG DINDING PEMISAH DOUBLE GRC, RANGKA KAYU KAMPER MEDAN
a Balok kayu kamper medan 0.02 m3 4,100,000.00
79,950.00
b Papan kayu kamper medan 0.01 m3 4,275,000.00
29,925.00
c Paku 5 - 12 cm 0.10 kg 14,700.00
1,470.00
d Lem Kayu 0.56 Ltr 20,000.00
11,200.00
e Triplek 0,4 cm ukuran pintu 1.00 lbr 36,000.00
36,000.00
f Pembantu tukang 0.20 org 27,500.00
5,500.00
g Tukang kayu 0.60 org 42,000.00
25,200.00
Jumlah 189,245.00
Dibulatkan 189,200.00
17 1 Bh PASANG PINTU ALUMINIUM / PINTU PVC
a Pintu aluminium/Pintu PVC 1.00 bh 375,000.00
375,000.00
b Alat bantu 10 % harga material 1.00 ls 37,500.00
37,500.00
c Tukang kayu 0.02 org 42,000.00
882.00
Jumlah 413,382.00
Dibulatkan 413,300.00
18 1 M2 PASANG KUSEN PARTISI DOUBLE TRIPLEK
a Balok kayu borneo super 0.11 m3 4,000,000.00
420,000.00
b Triplek 0,4 cm ukuran pintu 5.00 lbr 36,000.00
180,000.00
c Paku 1 s/d 3 cm 2.00 kg 14,700.00
29,400.00
d Ampelas 2.00 lbr 3,200.00
6,400.00
e Engsel 4.00 bh 22,000.00
88,000.00
f Grendel/Slot 4.00 bh 31,000.00
124,000.00
g Pembantu tukang 0.30 org 27,500.00
8,250.00
h Tukang kayu terampil 1.30 org 42,000.00
54,600.00
Jumlah 910,650.00
Dibulatkan 129,530.00
19 1 M2 PASANG KUSEN PARTISI DOUBLE GYPSUM + RANGKA KAYU
a Balok kayu borneo super 0.11 m3 4,000,000.00
420,000.00
b Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 59,000.00
42,480.00
c Paku 1 s/d 3 cm 2.00 kg 14,700.00
29,400.00
d Ampelas 2.00 lbr 3,200.00
6,400.00
e Engsel 4.00 bh 22,000.00
88,000.00
f Grendel/Slot 4.00 bh 31,000.00
124,000.00
g Pembantu tukang 0.30 org 27,500.00
8,250.00
h Tukang kayu 1.30 org 42,000.00
54,600.00
Jumlah 773,130.00
Dibulatkan 129,530.00
20 1 M2 PASANG DINDING PARTISI GYPSUM BOARD + RANGKA BESI HOLLOW
a Hollow 4/4 Zincromate 0.42 btg 45,000.00
18,900.00
b Hollow 2/4 Zincromate 0.15 btg 32,000.00
4,800.00
c Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 59,000.00
42,480.00
d Paku sekrup 25.00 bh 700.00
17,500.00
e Ramset / dina bolt 4.00 bh 2,400.00
9,600.00
f Cotton plaster 0.10 bh 56,000.00
5,600.00
g Compoun 0.13 kg 28,500.00
3,705.00
h Pembantu tukang 0.10 org 27,500.00
2,750.00
i Tukang kayu 0.05 org 42,000.00
2,100.00
Jumlah 107,435.00
Dibulatkan 107,430.00
X PEKERJAAN RANGKA ATAP DAN PENUTUP ATAPA PEKERJAAN RANGKA ATAP 1 1 M3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU KAMPER MEDAN
a Balok kayu kamper medan 1.10 m3 4,100,000.00
4,510,000.00
b Besi Strip 15.00 kg 11,000.00
165,000.00
c Paku Ukuran besar 0.80 kg 14,700.00
11,760.00
d Meni kayu 0.40 kg 15,000.00
6,000.00
e Pembantu tukang 4.00 org 27,500.00
110,000.00
f Tukang kayu 12.00 org
42,000.00 504,000.00
Jumlah 5,306,760.00
Dibulatkan 5,306,700.00
2 1 M3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU BORNEO SUPER
a Balok kayu borneo super 1.10 m3 1,378,000.00
1,515,800.00
b Besi Strip 15.00 kg 11,000.00
165,000.00
c Paku ukuran besar 0.80 kg 14,700.00
11,760.00
d Meni kayu 0.40 kg 15,000.00
6,000.00
e Pembantu tukang 4.00 org 27,500.00
110,000.00
f Tukang kayu 12.00 org 42,000.00
504,000.00
Jumlah 2,312,560.00
Dibulatkan 2,312,500.00
3 1 M2 PASANG KASO + RENG GENTENG PLENTONG KAYU BORNEO SUPER
a Balok kayu borneo super 0.01 m3 4,000,000.00
48,000.00
b Paku 7 - 10 cm 0.15 kg 14,700.00
2,205.00
c Pembantu tukang 0.10 org 27,500.00
2,750.00
d Tukang kayu 0.10 org 42,000.00
4,200.00
Jumlah
57,155.00
Dibulatkan 57,100.00
4 1 M2 PASANG KASO + RENG GENTENG BETON KAYU BORNEO SUPER
a Balok kayu borneo super 0.01 m3 4,000,000.00
56,000.00
b Paku 7 - 10 cm 0.15 kg 14,700.00
2,205.00
c Pembantu tukang 0.10 org 27,500.00
2,750.00
d Tukang kayu 0.10 org 42,000.00
4,200.00
Jumlah 65,155.00
Dibulatkan 65,100.00
5 1 M1 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 20 cm
a Papan kayu Kamper Medan 0.01 m3 4,275,000.00
30,780.00
b Paku 7 - 10 cm 0.05 kg 14,700.00
735.00
c Pembantu tukang 0.10 org 27,500.00
2,750.00
d Tukang kayu 0.20 org 42,000.00
8,400.00
Jumlah 42,665.00
Dibulatkan 42,600.00
6 1 M2 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 30 cm
a Papan kayu Kamper Medan 0.01 m3 4,275,000.00
47,025.00
b Paku 7 - 10 cm 0.05 kg 14,700.00
735.00
c Pembantu tukang 0.11 org 27,500.00
3,025.00
d Tukang kayu 0.22 org 42,000.00
9,240.00
Jumlah 60,025.00
Dibulatkan 60,000.00
7 1 M3 PEKERJAAN NOK/GORDING/JURAY KAYU BORNEO SUPER
a Balok kayu borneo super 1.05 m3 4,000,000.00
4,200,000.00
b Paku 10 - 15 cm 0.20 kg 14,700.00
2,940.00
c Pembantu tukang 2.00 org 27,500.00
55,000.00
d Tukang kayu 2.00 org 42,000.00
84,000.00
Jumlah 4,341,940.00
Dibulatkan 4,341,900.00
B PEKERJAAN PENUTUP ATAP 1 1 M2 PASANG ATAP GENTENG PLENTONG
a Genteng palentong 25.00 bh 800.00
20,000.00
b Pembantu tukang 0.15 org 27,500.00
4,125.00
c Tukang kayu 0.08 org 42,000.00
3,150.00
Jumlah
27,275.00
Dibulatkan 27,270.00
2 1 M2 PASANG NOK/BUBUNGAN GENTENG KERAMIK GLAZUR
a Genteng nok/bubungan plentong 5.00 bh 16,500.00
82,500.00
b Semen PC (abu-abu) 0.16 sak 49,500.00
7,920.00
c Pasir pasang 0.03 m3 125,000.00
4,000.00
d Pembantu tukang 0.30 org 27,500.00
8,250.00
e Tukang kayu 0.20 org 42,000.00
8,400.00
Jumlah 111,070.00
Dibulatkan 111,070.00
3 1 M2 PASANG ATAP FIBREGLASS UKURAN 180 X 90 cm
a Atap fibreglass 0.60 lbr 60,000.00
36,000.00
b Paku 2 - 5 cm 0.05 kg 14,700.00
735.00
c Pembantu tukang 0.14 org 27,500.00
3,850.00
d Tukang kayu 0.07 org 42,000.00
2,814.00
Jumlah 43,399.00
Dibulatkan 43,390.00
4 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,05 m TEBAL 4 mm
a Asbes gelombang 0.35 lbr 63,000.00
22,050.00
b Paku payung 0.12 kg 14,700.00
1,764.00
c Pembantu tukang 0.14 org 27,500.00
3,850.00
d Tukang kayu 0.07 org 42,000.00
2,940.00
Jumlah 30,604.00
Dibulatkan 30,600.00
5 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,05 m TEBAL 4 mm
a Asbes gelombang 0.42 lbr 50,000.00
21,000.00
b Paku payung 0.12 kg 14,700.00
1,764.00
c Pembantu tukang 0.14 org 27,500.00
3,850.00
d Tukang kayu 0.07 org 42,000.00
2,940.00
Jumlah 29,554.00
Dibulatkan 29,550.00
6 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,02 m TEBAL 5 mm
a Asbes gelombang 0.44 lbr 82,000.00
36,080.00
b Paku payung 0.12 kg 14,700.00
1,764.00
c Pembantu tukang 0.14 org 27,500.00
3,850.00
d Tukang kayu 0.07 org 42,000.00
2,814.00
Jumlah 44,508.00
Dibulatkan 44,500.00
7 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,02 m TEBAL 5 mm
a Asbes gelombang 0.51 lbr 82,000.00
41,820.00
b Paku payung 0.12 kg 14,700.00
1,764.00
c Pembantu tukang 0.14 org 27,500.00
3,850.00
d Tukang kayu 0.07 org 42,000.00
2,814.00
Jumlah 50,248.00
Dibulatkan 50,240.00
8 1 M2 PASANG ATAP ASBES GELOMBANG ( 1,50 x 1,02 m ) x 5 mm
a Asbes gelombang 0.80 lbr 35,000.00
28,000.00
b Paku payung 0.12 kg 14,700.00
1,764.00
c Pembantu tukang 0.14 org 27,500.00
3,850.00
d Tukang kayu 0.07 org 42,000.00
2,940.00
Jumlah 36,554.00
Dibulatkan 36,550.00
9 1 M¹ PASANG ATAP SIRAP
a Genteng sirap 80.00 bh 1,450.00
116,000.00
b Paku 0.20 kg 14,700.00
2,940.00
c Pembantu tukang 0.10 org 27,500.00
2,750.00
d Tukang kayu 0.20 org 42,000.00
8,400.00
Jumlah 130,090.00
Dibulatkan 130,090.00
10 1 M2 PASANG ATAP GENTENG BETON
a Genteng beton 1.10 bh 62,500.00
68,750.00
b Paku 5 - 12 cm 0.03 kg 14,700.00
441.00
c Pembantu tukang 0.20 org 27,500.00
5,500.00
d Tukang kayu 0.10 org 42,000.00
4,200.00
Jumlah 78,891.00
Dibulatkan 78,890.00
11 1 M2 PASANG ATAP GENTENG METAL + C301
a Genteng metal 1.02 lbr 130,000.00
132,600.00
b Paku 5 - 12 cm 0.20 kg 14,700.00
2,940.00
c Pembantu tukang 0.20 org
27,500.00 5,500.00
d Tukang kayu 0.10 org 42,000.00
4,200.00
Jumlah 145,240.00
Dibulatkan 145,240.00
12 1 M¹ PASANG NOK GENTENG BETON
a Nok genteng beton 3.50 bh 16,000.00
56,000.00
b Paku 5 - 12 cm 0.05 kg 14,700.00
735.00
c Semen PC (abu-abu) 0.22 sak 49,500.00
10,692.00
d Pasir pasang 0.03 m3 125,000.00
4,000.00
e Semen warna 1.00 kg 12,700.00
12,700.00
f Pembantu tukang 0.40 org 27,500.00
11,000.00
g Tukang kayu 0.20 org 42,000.00
8,400.00
Jumlah 103,527.00
Dibulatkan 103,520.00
13 1 M¹ PASANG NOK GENTENG METAL
a Nok genteng metal 1.10 bh 54,000.00
59,400.00
b Paku payung 0.05 kg 14,700.00
735.00
c Pembantu tukang 0.25 org
27,500.00 6,875.00
d Tukang kayu 0.15 org 42,000.00
6,300.00
Jumlah 73,310.00
Dibulatkan 73,310.00
14 1 M2 PASANG ATAP SENG GELOMBANG
a Seng gelombang 0.70 lbr 67,000.00
46,900.00
b Paku payung 0.02 kg 14,700.00
294.00
c Pembantu tukang 0.12 org 27,500.00
3,300.00
d Tukang kayu 0.06 org 42,000.00
2,520.00
Jumlah 53,014.00
Dibulatkan 53,010.00
15 1 M2 PASANG NOK SENG UNTUK ATAP SENG GELOMBANG
a Seng plat BJLS 1.05 M1 32,000.00
33,600.00
b Paku payung 0.04 kg 14,700.00
588.00
c Pembantu tukang 0.15 org 27,500.00
4,125.00
d Tukang kayu 0.07 org 42,000.00
2,940.00
Jumlah 41,253.00
Dibulatkan
41,250.00 16 1 M2 PASANG ATAP POLYCARBONATE
a Polycarbonate 1.05 m2 200,000.00
210,000.00
b Besi Hollow 1.50 btg 45,000.00
67,500.00
c Alat bantu 20 % harga material 1.00 ls 42,000.00
42,000.00
d Pembantu tukang 0.15 org 27,500.00
4,125.00
e Tukang kayu 0.05 org 42,000.00
2,100.00
Jumlah 325,725.00
Dibulatkan 325,720.00
17 1 M2 PASANG ALUMINIUM FOIL
a Aluminium foil 1.05 m2 4,300.00
4,515.00
b Alat bantu 20 % harga material 1.00 ls 903.00
903.00
c Pembantu tukang 0.15 org 27,500.00
4,125.00
d Tukang kayu 0.05 org 42,000.00
2,100.00
Jumlah 11,643.00
Dibulatkan 11,640.00
XI PEKERJAAN PENUTUP PLAFON
1 1 M2 PASANG RANGKA PLAFON ( ukrn 0,50 x 1,00 ) m, KAYU BORNEO SUPER
a Balok kayu borneo super 4 x 6 cm 0.01 m3 4,000,000.00
48,000.00
b Paku 5 - 12 cm 0.10 kg 14,700.00
1,470.00
c Pembantu tukang 0.15 org 27,500.00
4,125.00
d Tukang kayu 0.25 org 42,000.00
10,500.00
Jumlah 64,095.00
Dibulatkan 64,000.00
2 1 M2 PLAFON GRC ( 60 x 1,20 ) m, TEBAL 4 mm
a Pelat GRC tebal 4 mm 1.10 lbr 45,600.00
50,160.00
b Paku 1 cm 0.01 kg 14,700.00
147.00
c Pembantu tukang 0.03 org 27,500.00
825.00
d Tukang kayu 0.07 org 42,000.00
2,940.00
Jumlah 54,072.00
Dibulatkan 54,070.00
3 1 M2 PLAFON ASBES ( 1,00 x 1,00 ) m, TEBAL5 mm
a Pelat asbes tebal 5 mm 1.10 lbr 11,500.00
12,650.00
b Paku 1 cm 0.01 kg 14,700.00
147.00
c Pembantu tukang 0.03 org
27,500.00 825.00
d Tukang kayu 0.07 org 42,000.00
2,940.00
Jumlah 16,562.00
Dibulatkan 16,560.00
4 1 M2 PLAFON AKUSTIK ( 60 x 120 ) cm
a Akustik 600 x 1200 x 15 mm 1.50 lbr 78,000.00
117,000.00
b Paku 2 - 5 cm 0.05 kg 14,700.00
735.00
c Pembantu tukang 0.06 org 27,500.00
1,650.00
d Tukang kayu 0.10 org 42,000.00
4,200.00
Jumlah 123,585.00
Dibulatkan 123,580.00
5 1 M2 PLAFON AKUSTIK ( 60 x 120 ) cm + RANGKA ALUMUNIUM
a Profil alluminium "T" 3.60 M¹ 26,000.00
93,600.00
b Kawat seng polos 0.15 kg 15,000.00
2,250.00
c Ramset / dina bolt 1.00 bh 2,400.00
2,400.00
d Akustik 600 x 1200 x 15 mm 1.50 lbr 78,000.00
117,000.00
e Pembantu tukang 0.15 org 27,500.00
4,125.00
f Tukang kayu 0.20 org
42,000.00 8,400.00
Jumlah 227,775.00
Dibulatkan 227,770.00
6 1 M¹ LIST PLAFON PROFIL KAYU
a List profil kayu 1.10 M¹ 12,500.00
13,750.00
b Paku 2 cm 0.01 kg 14,700.00
147.00
c Pembantu tukang 0.05 org 27,500.00
1,375.00
d Tukang kayu 0.05 org 42,000.00
2,100.00
Jumlah 17,372.00
Dibulatkan 17,370.00
7 1 M¹ LIST PLAFON KAYU 1/4
a List kayu 1/4 1.10 M¹ 5,000.00
5,500.00
b Paku 2 cm 0.01 kg 14,700.00
147.00
c Pembantu tukang 0.05 org 27,500.00
1,375.00
d Tukang kayu 0.05 org 42,000.00
2,100.00
Jumlah 9,122.00
Dibulatkan 9,120.00
8 1 M2 PLAFON TRIPLEK 4 mm + RANGKA KAYU BORNEO SUPER
a Balok kayu borneo super 0.02 m3 4,000,000.00
92,000.00
b Paku 1- 12 cm 0.06 kg 14,700.00
882.00
c Triplek 120 cm x 240 cm x 0,4 cm 0.39 lbr 36,000.00
14,040.00
d Pembantu tukang 0.27 org 27,500.00
7,425.00
e Tukang kayu 0.40 org 42,000.00
16,800.00
Jumlah 131,147.00
Dibulatkan 131,140.00
9 1 M2 PLAFON TEAKWOOD 4 mm + RANGKA KAYU BORNEO SUPER
a Balok kayu borneo super 0.02 m3 4,000,000.00
92,000.00
b Paku 1 - 12 cm 0.06 kg 14,700.00
882.00
cTeakwood 120 cm x 240 cm x 0,4 cm
0.39 lbr 85,000.00
33,150.00
d Pembantu tukang 0.27 org 27,500.00
7,425.00
e Tukang kayu 0.40 org 42,000.00
16,800.00
Jumlah 150,257.00
Dibulatkan 150,250.00
10 1 M2 PLAFON PAPAN 10 cm, TEBAL 1 cm + RANGKA KAYU BORNEO SUPER
a Balok kayu borneo super 0.02 m3 4,000,000.00
92,000.00
b Paku 2 - 12 cm 0.20 kg 14,700.00
2,940.00
c Papan kayu kamper 0.02 m3 5,350,000.00
107,000.00
d Pembantu tukang 0.35 org 27,500.00
9,625.00
e Tukang kayu 0.50 org 42,000.00
21,000.00
Jumlah 232,565.00
Dibulatkan 232,560.00
11 1 M2 PLAFON GYPSUM BOARD, TEBAL 9 mm + RANGKA BESI HOLLOW
a Hollow 4/4 Zincromate 0.42 btg 45,000.00
18,675.00
b Hollow 2/4 Zincromate 0.15 btg 32,000.00
4,800.00
c Gypsum board ( 120 x 240 x 9 ) mm 0.36 lbr 59,000.00
21,476.00
d Paku sekrup 25.00 bh 700.00
17,500.00
e Ramset / dina bolt 4.00 bh 2,400.00
9,600.00
f Cotton plaster 0.07 bh 56,000.00
4,032.00
g Compoun 0.13 kg 28,500.00
3,562.50
h Pembantu tukang 0.10 org 27,500.00
2,750.00
i Tukang kayu 0.05 org 42,000.00
2,100.00
Jumlah 84,495.50
Dibulatkan 84,490.00
XII PEKERJAAN SANITAIR 1 MEMASANG 1 BH KLOSET DUDUK/MONOBLOK
a Kloset duduk/monoblok 1.00 bh 2,280,000.00
2,280,000.00
b Perlengkapan (10% hrg kloset) 228,000.00
228,000.00
c Pembantu tukang 3.30 org 27,500.00
90,750.00
d Tukang batu 1.10 org 42,000.00
46,200.00
Jumlah 2,644,950.00
Dibulatkan 2,644,950.00
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN
a Kloset jongkok porselen 1.00 bh 140,000.00
140,000.00
b Semen PC (abu-abu) 0.12 sak 49,500.00
5,940.00
c Pasir pasang 0.01 m3 125,000.00
1,250.00
d Pembantu tukang 1.00 org 27,500.00
27,500.00
e Tukang batu 1.50 org 42,000.00
63,000.00
Jumlah 237,690.00
Dibulatkan 237,690.00
3 MEMASANG 1 BUAH URINOIR
a Urinoir 1.00 bh 375,000.00
375,000.00
b Perlengkapan ( 30% hrg urinoir ) 112,500.00
112,500.00
c Semen PC (abu-abu) 0.12 sak 49,500.00
5,940.00
d Pasir pasang 0.01 m3 125,000.00
1,250.00
e Pembantu tukang 1.00 org 27,500.00
27,500.00
f Tukang batu 1.00 org 42,000.00
42,000.00
Jumlah 564,190.00
Dibulatkan 564,190.00
4 MEMASANG 1 BUAH WASTAFEL DINDING
a Wastafel 1.00 bh 230,000.00
230,000.00
b Perlengkapan ( 12% hrg kloset ) 27,600.00
27,600.00
c Semen PC ( abu-abu ) 0.12 sak 49,500.00
5,940.00
d Pasir pasang 0.01 m3 125,000.00
1,250.00
e Pembantu tukang 1.20 org 27,500.00
33,000.00
f Tukang batu 1.45 org 42,000.00
60,900.00
Jumlah 358,690.00
Dibulatkan 358,690.00
5 MEMASANG 1 BUAH WASTAFEL KAKI
a Wastafel 1.00 bh 248,000.00
248,000.00
b Perlengkapan ( 12% hrg kloset ) 29,760.00
29,760.00
c Semen PC ( abu-abu ) 0.12 sak 49,500.00
5,940.00
d Pasir pasang 0.01 m3 125,000.00
1,250.00
e Pembantu tukang 1.20 org 27,500.00
33,000.00
f Tukang batu 1.45 org 42,000.00
60,900.00
Jumlah 378,850.00
Dibulatkan 378,850.00
6 MEMASANG 1 BH SHOWER DINDING
a Shower dinding 1.00 bh 130,000.00
130,000.00
b Pembantu tukang 0.01 org 27,500.00
275.00
c Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 134,475.00
Dibulatkan 134,470.00
7 MEMASANG BAK MANDI FIBERGLASS UKURAN SEDANG a Bak fibreglass 1.00 bh
150,000.00 150,000.00
b Perlengkapan ( 20% hrg bak ) 27,000.00
27,000.00
c Pembantu tukang 1.80 org 27,500.00
49,500.00
d Tukang batu 2.70 org 42,000.00
113,400.00
Jumlah 339,900.00
Dibulatkan 339,900.00
8 MEMASANG BAK KONTROL PASANGAN BATU BATA UKURAN 30 X 30 CM, TINGGI 35 CM
a Batu bata 0.15 m3 325.00
48.75
b Semen PC (abu-abu) 0.88 sak 49,500.00
43,560.00
c Pasir pasang 0.07 m3 125,000.00
8,750.00
d Batu kerikil 0.07 m3 78,000.00
5,460.00
e Besi beton 1.60 kg 10,000.00
16,000.00
f Pasir beton 0.06 m3 140,000.00
8,400.00
g Pembantu tukang 3.20 org 27,500.00
88,000.00
h Tukang batu 1.02 org 42,000.00
42,840.00
Jumlah 213,058.75
Dibulatkan 213,050.00
9 MEMASANG KITCHEN ZINK/BAK CUCI PIRING STAINLESS STEEL
a Bak cuci stainless steel 1.00 bh 173,000.00
173,000.00
b Water Drain + Asesories 1.00 Set 70,000.00
70,000.00
c Pembantu tukang 0.03 org 27,500.00
825.00
d Tukang batu 0.30 org 42,000.00
12,600.00
Jumlah 256,425.00
Dibulatkan 256,420.00
10 MEMASANG 1 BH KRAN DIAMETER 3/4 " ATAU 1/2 "
a Kran air 1.00 bh 55,000.00
55,000.00
b Perlengkapan ( 2% hrg kran ) 1.00 ls 1,100.00
1,100.00
c Pembantu tukang 0.01 org 27,500.00
275.00
d Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 60,575.00
Dibulatkan 60,570.00
11 MEMASANG 1 BH KRAN AIR ANGSA
a Kran air angsa 1.00 bh 155,000.00
155,000.00
b Perlengkapan ( 2% hrg kran ) 1.00 ls 3,100.00
3,100.00
c Pembantu tukang 0.01 org
27,500.00 275.00
d Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 162,575.00
Dibulatkan 162,570.00
12 MEMASANG 1 BH FLOOR DRAIN
a Floor drain 1.00 bh 59,500.00
59,500.00
b Pembantu tukang 0.01 org 27,500.00
275.00
c Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 63,975.00
Dibulatkan 63,970.00
13 MEMASANG 1 BH TEMPAT SABUN
a Tempat Sabun 1.00 bh 30,000.00
30,000.00
b Pembantu tukang 0.01 org 27,500.00
275.00
c Tukang batu 0.10 org 42,000.00
4,200.00
Jumlah 34,475.00
Dibulatkan 34,470.00
XIIIPEKERJAAN PERPIPAAN DAN POMPA
1 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ½"
a Pipa galvanis dia 1/2" 1.10 M¹ 13,400.00
14,740.00
b Perlengkapan ( 30% harga pipa ) 4,020.00
4,020.00
c Pembantu tukang 0.05 org 27,500.00
1,485.00
d Tukang pipa 0.09 org 42,000.00
3,780.00
Jumlah 24,025.00
Dibulatkan 24,020.00
2 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ¾"
a Pipa galvanis 1.10 M¹ 19,500.00
21,450.00
b Perlengkapan ( 30% harga pipa ) 5,850.00
5,850.00
c Pembantu tukang 0.05 org 27,500.00
1,485.00
d Tukang pipa 0.09 org 42,000.00
3,780.00
Jumlah 32,565.00
Dibulatkan 32,560.00
3 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1"
a Pipa galvanis 1.10 M¹ 21,250.00
23,375.00
b Perlengkapan ( 30% harga pipa ) 6,375.00
6,375.00
c Pembantu tukang 0.05 org
27,500.00 1,485.00
d Tukang pipa 0.09 org 42,000.00
3,780.00
Jumlah 35,015.00
Dibulatkan 35,010.00
4 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1½"
a Pipa galvanis 1.10 M¹ 31,700.00
34,870.00
b Perlengkapan ( 30% harga pipa ) 9,510.00
9,510.00
c Pembantu tukang 0.11 org 27,500.00
2,970.00
d Tukang pipa 0.18 org 42,000.00
7,560.00
Jumlah 54,910.00
Dibulatkan 54,910.00
5 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 3"
a Pipa PVC type D 1.10 M¹ 6,400,000.00
7,040,000.00
b Perlengkapan ( 30% harga pipa ) 1,920,000.00
1,920,000.00
c Pembantu tukang 0.10 org 27,500.00
2,750.00
d Tukang pipa 0.18 org 42,000.00
7,560.00
Jumlah 8,970,310.00
Dibulatkan
8,970,310.00 6 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 4"
a Pipa PVC type D 1.10 M¹ 8,500.00
9,350.00
b Perlengkapan ( 30% harga pipa ) 2,550.00
2,550.00
c Pembantu tukang 0.13 org 27,500.00
3,575.00
d Tukang pipa 0.22 org 42,000.00
9,240.00
Jumlah 24,715.00
Dibulatkan 24,710.00
7 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ½"
a Pipa PVC 1.10 M¹ 5,000.00
5,500.00
b Perlengkapan ( 30% harga pipa ) 1,500.00
1,500.00
c Pembantu tukang 0.04 org 27,500.00
990.00
d Tukang pipa 0.06 org 42,000.00
2,520.00
Jumlah 10,510.00
Dibulatkan 10,510.00
8 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ¾"
a Pipa PVC 1.10 M¹ 5,625.00
6,187.50
b Perlengkapan ( 30% harga pipa ) 1,687.50
1,687.50
c Pembantu tukang 0.03 org 27,500.00
825.00
d Tukang pipa 0.06 org 42,000.00
2,520.00
Jumlah 11,220.00
Dibulatkan 11,220.00
9 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 1"
a Pipa PVC 1.10 M¹ 7,000.00
7,700.00
b Perlengkapan ( 30% harga pipa ) 2,100.00
2,100.00
c Pembantu tukang 0.04 org 27,500.00
990.00
d Tukang pipa 0.06 org 42,000.00
2,520.00
Jumlah 13,310.00
Dibulatkan 13,310.00
10 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 2"
a Pipa PVC 1.10 M¹ 9,500.00
10,450.00
b Perlengkapan ( 30% harga pipa ) 2,850.00
2,850.00
c Pembantu tukang 0.05 org 27,500.00
1,485.00
d Tukang pipa 0.09 org 42,000.00
3,780.00
Jumlah 18,565.00
Dibulatkan 18,560.00
11 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 4"
a Pipa PVC 1.10 M¹ 28,000.00
30,800.00
b Perlengkapan ( 30% harga pipa ) 8,400.00
8,400.00
c Pembantu tukang 0.08 org 27,500.00
2,227.50
d Tukang pipa 0.14 org 42,000.00
5,670.00
Jumlah 47,097.50
Dibulatkan 47,090.00
12 MEMBUAT 1 BH SEPTICTANK PASANGAN BATU BATA DAN REMBESAN
a Galian tanah Septictank & rembesan 7.5m3 20,950.00
157,125.00
b Pasir urug 0.21m3 70,000.00
14,700.00
c Lantai kerja 2.25 m3 480,100.00
1,080,225.00
d Pasang bata 1 Pc : 2 Psr 15.00 m2 55,100.00
826,500.00
e Pelat beton penutup dan balok 0.30 m3 4,071,500.00
1,221,450.00
fPipa PVC 4 inci AW & perlengkapannya
5.40 M1 28,000.00
151,200.00
g Plesteran 1 Pc : 3 Psr 30.00 m2 20,700.00
621,000.00
h Pasangan ijuk 5.00 IKAT 7,000.00
35,000.00
i Urugan kerikil 3,5 cm 1.05 m3 103,400.00
108,570.00
J Pipa PVC 4 inci AW dilobang 9.00 M1 28,000.00
252,000.00
q Urugan kembali 1.13 m3 5,800.00
6,554.00
r Pembantu tukang 4.00 org 27,500.00
110,000.00
s Tukang batu 3.00 org 42,000.00
126,000.00
Jumlah 4,710,324.00
Dibulatkan 4,710,320.00
13 MEMASANG 1 BH POMPA AIR
a Pompa Air 100 Watt 1.00 bh 780,000.00
780,000.00
b Perlengkapan ( 25% harga pompa ) 195,000.00
195,000.00
c Pembantu tukang 0.08 org 27,500.00
2,227.50
d Tukang Pipa 0.14 org 42,000.00
5,670.00
Jumlah 982,897.50
Dibulatkan 982,890.00
XIV PEKERJAAN PENUTUP BESI DAN BAJA 1 1 KG PASANG RANGKA ATAP BAJA a Besi profil WF 1.10 kg
11,500.00 12,650.00
b Meni besi 0.08 kg 22,000.00
1,760.00
c Peralatan las ( 5 % material ) 1.00 ls 632.50
632.50
d Elektroda 0.20 ls 12,000.00
2,400.00
e Tukang besi 0.04 org 42,000.00
1,680.00
f Pembantu tukang 0.06 org 27,500.00
1,650.00
Jumlah 20,772.50
Dibulatkan 20,770.00
2 1 KG PASANG RANGKA ATAP BESI SIKU
a Besi siku 1.10 kg 11,500.00
12,650.00
b Meni besi 0.10 kg 22,000.00
2,200.00
c Peralatan las ( 5 % material ) 1.00 ls 632.50
632.50
d Elektroda 0.15 ls 12,000.00
1,800.00
e Baud 0.20 kg 10,000.00
2,000.00
f Tukang besi 0.04 org 42,000.00
1,680.00
g Pembantu tukang 0.06 org 27,500.00
1,650.00
Jumlah 22,612.50
Dibulatkan 22,610.00
3 1 KG PASANG GORDING BESI C
a Besi C 1.10 kg 11,000.00
12,100.00
b Meni besi 0.10 kg 15,000.00
1,500.00
c Peralatan las ( 5 % material ) 1.00 ls 605.00
605.00
d Elektroda 0.15 ls 12,000.00
1,800.00
e Baud 0.20 kg 10,000.00
2,000.00
f Tukang besi 0.04 org 42,000.00
1,680.00
g Pembantu tukang 0.06 org 27,500.00
1,650.00
Jumlah 21,335.00
Dibulatkan 21,330.00
4 1 m2 Pasang Pintu Rolling Door besi
a Rolling door besi 1.00 m2 230,000.00
230,000.00
b Tukang besi 1.50 org 42,000.00
63,000.00
c Pembantu tukang 1.05 org 27,500.00
28,875.00
Jumlah 321,875.00
Dibulatkan 321,870.00
5 1 bh Pasang Pintu besi ukuran 0,8 x 2 m
a Pintu besi jadi 1.00 bh 375,000.00
375,000.00
b Tukang besi 1.05 org 42,000.00
44,100.00
c Pembantu tukang 1.05 org 27,500.00
28,875.00
Jumlah 447,975.00
Dibulatkan 447,970.00
6 1 M2 PASANG TERALIS BESI
a Besi strip 2 mm x 3 cm 11.50 M¹ 11,000.00
126,500.00
b Tukang las 1.20 org 42,000.00
50,400.00
c Pembantu tukang 1.20 org 27,500.00
33,000.00
Jumlah 209,900.00
Dibulatkan 209,900.00
7 1 M2 PASANG KAWAT HARMONIKA
a Kawat harmonika 1.10 m2 12,000.00
13,200.00
b Paku 2 - 5 cm 0.02 kg 14,700.00
294.00
c Papan kayu kamper medan 0.00 m3 4,275,000.00
7,695.00
d Pembantu tukang 0.10 org 27,500.00
2,750.00
e Tukang kayu 0.10 org
42,000.00 4,200.00
Jumlah 28,139.00
Dibulatkan 28,130.00
8 1 M1 PASANG TALANG DATAR, SENG PLAT BJLS
a Seng plat BJLS 1.00 M1 32,000.00
32,000.00
b Paku 2 - 5 cm 0.02 kg 14,700.00
220.50
c Papan kayu borneo super 0.01 m3 4,800,000.00
46,080.00
d Flincote / meni besi 0.25 kg 18,000.00
4,500.00
e Pembantu tukang 0.15 org 27,500.00
4,125.00
f Tukang kayu 0.40 org 42,000.00
16,800.00
Jumlah 103,725.50
Dibulatkan 103,720.00
9 1 M1 PASANG TALANG MIRING, SENG PLAT BJLS
a Seng plat BJLS 0.50 M1 32,000.00
16,000.00
b Paku 2 - 5 cm 0.02 kg 14,700.00
220.50
c Papan kayu borneo super 0.02 m3 4,800,000.00
91,200.00
d Flincote / meni besi 0.30 kg 18,000.00
5,400.00
e Pembantu tukang 0.04 org
27,500.00 1,100.00
f Tukang kayu 0.40 org 42,000.00
16,800.00
Jumlah 130,720.50
Dibulatkan 130,720.00
XV PEKERJAAN ALUMINIUM 1 1 M2PASANG PINTU ROLLING DOOR ALUMINIUM
a Rolling door aluminium 1.00 m2 230,000.00
230,000.00
b Tukang besi konstruksi 1.50 org 42,000.00
63,000.00
c Pembantu tukang 1.05 org 27,500.00
28,875.00
Jumlah 321,875.00
Dibulatkan 321,870.00
2 1 M2 PASANG PINTU ALUMINIUM PABRIKAN
a Pintu alluminium 1.00 bh 375,000.00
375,000.00
b Tukang batu 1.05 org 42,000.00
44,100.00
c Pembantu tukang 1.05 org 27,500.00
28,875.00
Jumlah 447,975.00
Dibulatkan 447,970.00
3 1 UNIT KUSEN JENDELA ALUMINIUM 2 LUBANG DGN 2 DAUN JENDELA (UKURAN 1,6 X 1,5 M)
aProfil aluminium 4" natural (+ spare 20 %)
9.24 M1 80,000.00
739,200.00
bProfil daun jendela alm.( + spare 20%)
11.04 M1 80,000.00
883,200.00
c Kaca polos 3 mm 2.40 m2 52,000.00
124,800.00
d Engsel jendela 4.00 ps 20,000.00
80,000.00
e Grendel jendela 2.00 bh 19,100.00
38,200.00
f Kait angin 2.00 bh 15,000.00
30,000.00
g Aksesoris ( 6 % harga bahan) 1.00 ls 104,832.00
104,832.00
hUpah pembuatan profil ( 20 % bahan )
1.00 ls 147,840.00
147,840.00
iUpah pembuatan daun jendela (20 % bahan)
1.00 ls 176,640.00
176,640.00
Jumlah 2,324,712.00
Dibulatkan 2,324,710.00
41 UNIT KUSEN JENDELA ALUMINIUM 3 LUBANG DGN 2 DAUN JENDELA DAN 1 KACA MATI (UKURAN 2 X 1,5 M)
aProfil aluminium 4" natural (+ spare 20 %)
12.00 M1 80,000.00
960,000.00
bProfil daun jendela alm.( + spare 20%)
11.04 M1 80,000.00
883,200.00
c Kaca polos 3 mm 3.00 m2 52,000.00
156,000.00
d Engsel jendela 4.00 ps
20,000.00 80,000.00
e Grendel jendela 2.00 bh 19,100.00
38,200.00
f Kait angin 2.00 bh 15,000.00
30,000.00
g Aksesoris ( 6 % harga bahan ) 1.00 ls 119,952.00
119,952.00
hUpah pembuatan profil ( 20 % bahan )
1.00 ls 192,000.00
192,000.00
iUpah pembuatan daun jendela (20 % bahan)
1.00 ls 176,640.00
176,640.00
Jumlah 2,267,352.00
Dibulatkan 2,267,350.00
51 UNIT KUSEN PINTU JENDELA GENDONG ALUMINIUM DGN 2 JNDL DAN 1 PNT TEAKWOOD (UKR 2,2 X 2,7 M)
aProfil aluminium 4" natural (+ spare 20 %)
17.04 M1 80,000.00
1,363,200.00
bProfil daun jendela alm.( + spare 20%)
14.88 M1 80,000.00
1,190,400.00
c Kaca polos 3 mm 3.96 m2 52,000.00
205,920.00
d Daun pintu teakwood 1.80 m2 279,700.00
503,460.00
e Engsel jendela 4.00 ps 20,000.00
80,000.00
f Grendel jendela 2.00 bh 19,100.00
38,200.00
g Kait angin 4.00 bh 15,000.00
60,000.00
h Engsel pintu 3.00 ps
22,000.00 66,000.00
i Grendel pintu 1.00 bh 31,000.00
31,000.00
j Kunci tanam 1.00 bh 13,000.00
13,000.00
k Aksesoris ( 6 % harga bahan ) 1.00 ls 137,976.00
137,976.00
lUpah pembuatan profil ( 20 % bahan )
1.00 ls 16,000.00
16,000.00
mUpah pembuatan daun jendela (20 % bahan)
1.00 ls 7,640.00
7,640.00
Jumlah 3,712,796.00
Dibulatkan 3,712,790.00
6 1 UNIT KUSEN PINTU ALUMINIUM UKR 0.9 X 2,7 M
aProfil aluminium 4" natural (+ spare 20 %)
7.56 M1 80,000.00
604,800.00
b Kaca polos 3 mm untuk bovenlight 0.45 m2 52,000.00
23,400.00
c Daun pintu tekwood 1.68 m2 279,700.00
469,896.00
d Engsel pintu 3.00 ps 22,000.00
66,000.00
e Grendel pintu 1.00 bh 31,000.00
31,000.00
f Kunci tanam 1.00 bh 13,000.00
13,000.00
g Aksesoris ( 6 % ) 1.00 ls 37,692.00
37,692.00
hUpah pembuatan profil ( 20 % bahan )
1.00 ls 120,960.00
120,960.00
Jumlah 1,366,748.00
Dibulatkan 1,366,740.00
7 1 BH BOVENLIGHT ALMUNIUM DENGAN KISI-KISI ALMUNIUM PLAT (UKURAN 0,5 X 1 M)
aProfil Aluminium 4" natural + upah 20%
3.60 M1 52,000.00
187,200.00
b Plat Aluminium untuk Jalusi 5.00 M1 17,000.00
85,000.00
c Aksesoris ( 6 % ) 1.00 ls 11,232.00
11,232.00
dUpah pembuatan profil ( 20 % bahan )
1.00 ls 24,192.00
24,192.00
Jumlah 307,624.00
Dibulatkan 307,620.00
8 1 BH BOVENLIGHT ALMUNIUM UKURAN 0,5 X 1 M DENGAN BAGIAN DALAM KACA
aProfil Aluminium 4" natural + upah 20%
3.60 M1 52,000.00
187,200.00
b Kaca Polos 3 mm 0.50 m2 52,000.00
26,000.00
c Aksesoris ( 6 % ) 1.00 ls 11,232.00
11,232.00
dUpah pembuatan profil ( 20 % bahan )
1.00 ls 4,838.40
4,838.40
Jumlah 229,270.40
Dibulatkan 229,270.00
XVI PEKERJAAN KACA & PENGGANTUNG 1 1 BUAH PASANG KUNCI TANAM BESAR
a Kunci tanam besar 1.00 bh 125,000.00
125,000.00
b Pembantu tukang 0.06 org 27,500.00
1,650.00
c Tukang kayu 0.60 org 42,000.00
25,200.00
Jumlah 151,850.00
Dibulatkan 151,850.00
2 1 BUAH PASANG KUNCI TANAM SEDANG
a Kunci tanam sedang 1.00 bh 55,000.00
55,000.00
b Pembantu tukang 0.01 org 27,500.00
275.00
c Tukang kayu 0.50 org 42,000.00
21,000.00
Jumlah 76,275.00
Dibulatkan 76,270.00
3 1 BUAH PASANG KUNCI BULAT PUTAR KAMAR MANDI
a Kunci bulat putar kamar mandi 1.00 bh 50,000.00
50,000.00
b Pembantu tukang 0.01 org 27,500.00
137.50
c Tukang kayu 0.50 org 42,000.00
21,000.00
Jumlah 71,137.50
Dibulatkan 71,130.00
4 1 BUAH PASANG ENGSEL PINTU
a Engsel pintu 1.00 bh 22,000.00
22,000.00
b Pembantu tukang 0.02 org 27,500.00
412.50
c Tukang kayu 0.15 org 42,000.00
6,300.00
Jumlah 28,712.50
Dibulatkan 28,710.00
5 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU
a Engsel jendela 1.00 bh 20,000.00
20,000.00
b Pembantu tukang 0.01 org 27,500.00
275.00
c Tukang kayu 0.10 org 42,000.00
4,200.00
Jumlah 24,475.00
Dibulatkan 24,470.00
6 1 BUAH PASANG KAIT ANGIN
a Kait angin 1.00 bh 15,000.00
15,000.00
b Pembantu tukang 0.02 org 27,500.00
412.50
c Tukang kayu 0.15 org 42,000.00
6,300.00
Jumlah
21,712.50
Dibulatkan 21,710.00
7 1 BUAH PASANG DOOR CLOSER
a Door closer 1.00 bh 350,000.00
350,000.00
b Pembantu tukang 0.05 org 27,500.00
1,375.00
c Tukang kayu 0.50 org 42,000.00
21,000.00
Jumlah 372,375.00
Dibulatkan 372,370.00
8 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER
a Door holder 1.00 bh 50,000.00
50,000.00
b Pembantu tukang 0.05 org 27,500.00
1,375.00
c Tukang kayu 0.50 org 42,000.00
21,000.00
Jumlah 72,375.00
Dibulatkan 72,370.00
9 1 BUAH PASANG PENAHAN PINTU / DOOR STOPER
a Door stoper 1.00 bh 60,000.00
60,000.00
b Pembantu tukang 0.05 org 27,500.00
1,375.00
c Tukang kayu 0.50 org 42,000.00
21,000.00
Jumlah 82,375.00
Dibulatkan 82,370.00
10 1 BUAH PASANG GRENDEL/SLOOT PINTU
a Grendel / sloot pintu 1.00 bh 31,000.00
31,000.00
b Pembantu tukang 0.05 org 27,500.00
1,375.00
c Tukang kayu 0.50 org 42,000.00
21,000.00
Jumlah 53,375.00
Dibulatkan 53,370.00
11 1 BUAH PASANG GRENDEL/SLOOT JENDELA
a Grendel / sloot jendela 1.00 bh 19,100.00
19,100.00
b Pembantu tukang 0.05 org 27,500.00
1,375.00
c Tukang kayu 0.50 org 42,000.00
21,000.00
Jumlah 41,475.00
Dibulatkan 41,470.00
12 1 BUAH PASANG TARIKAN JENDELA
a Tarikan jendela 1.00 bh 15,000.00
15,000.00
b Pembantu tukang 0.05 org 27,500.00
1,375.00
c Tukang kayu 0.50 org
42,000.00 21,000.00
Jumlah 37,375.00
Dibulatkan 37,370.00
13 1 M2 PASANG KACA POLOS, TEBAL 3 MM
a Kaca polos 1.10 m2 52,000.00
57,200.00
b Pembantu tukang 0.02 org 27,500.00
412.50
c Tukang kayu 0.15 org 42,000.00
6,300.00
Jumlah 63,912.50
Dibulatkan 63,910.00
14 1 M2 PASANG KACA POLOS, TEBAL 5 MM
a Kaca polos 1.10 m2 63,000.00
69,300.00
b Pembantu tukang 0.02 org 27,500.00
412.50
c Tukang kayu 0.15 org 42,000.00
6,300.00
Jumlah 76,012.50
Dibulatkan 76,010.00
15 1 M2 PASANG KACA RAY BAND, TEBAL 5 MM
a Kaca 1.10 m2 125,000.00
137,500.00
b Pembantu tukang 0.02 org 27,500.00
412.50
c Tukang kayu 0.15 org 42,000.00
6,300.00
Jumlah 144,212.50
Dibulatkan 144,210.00
XVII PEKERJAAN PENGECATAN 1 1 M2 MENGIKIS / MENGEROK / MENGELUPAS PERMUKAAN CAT TEMBOK LAMA
a Soda api 0.05 kg 42,000.00
2,100.00
b Pembantu tukang 0.05 org 27,500.00
1,375.00
c Tukang cat 0.02 org 42,000.00
840.00
Jumlah 4,315.00 Dibulatkan 4,310.00 2 1 M2 MENDEMPUL DAN MENGGOSOK KAYU
a Dempul jadi 0.10 kg 22,000.00
2,200.00
b Minyak cat 0.03 kg 17,500.00
525.00
c Ampelas kasar 0.30 lbr 32,000.00
9,600.00
d Pembantu tukang 0.04 org 27,500.00
1,100.00
e Tukang cat 0.05 org 42,000.00
2,100.00
Jumlah 15,525.00 Dibulatkan 15,520.00
3 1 M2 PENGECATAN KAYU LAMA
a Cat meni 0.25 kg 15,000.00
3,750.00
b Plamir 0.15 kg 12,000.00
1,800.00
c Ampelas 1.00 lbr 3,200.00
3,200.00
d Cat dasar 0.15 kg 36,000.00
5,400.00
e Cat penutup kwalitas baik 0.60 kg 37,000.00
22,200.00
f Pembantu tukang 0.05 org 27,500.00
1,375.00
g Tukang cat 0.15 org 42,000.00
6,300.00
Jumlah 44,025.00 Dibulatkan 44,020.00 4 1 M2 PENGECATAN KAYU BARU
a Cat meni 0.50 kg 15,000.00
7,500.00
b Plamir 0.15 kg 12,000.00
1,800.00
c Ampelas 1.00 lbr 3,200.00
3,200.00
d Cat dasar 0.15 kg 36,000.00
5,400.00
e Cat penutup kwalitas baik 0.35 kg 37,000.00
12,950.00
f Pembantu tukang 0.05 org 27,500.00
1,375.00
g Tukang cat 0.15 org 42,000.00
6,300.00
Jumlah 38,525.00 Dibulatkan 38,520.00 5 1 M2 PENGECATAN KAYU DENGAN POLITUR
a Politur 0.15 Ltr 29,000.00
4,350.00
b Dempul jadi 0.25 kg 22,000.00
5,500.00
c Ampelas 2.00 lbr 3,200.00
6,400.00
d Pembantu tukang 0.05 org 27,500.00
1,375.00
e Tukang cat 0.15 org 42,000.00
6,300.00
Jumlah 23,925.00 Dibulatkan 23,920.00 6 1 M2 PENGECATAN KAYU DENGAN MELAMIK
a Melamik 0.15 Ltr 30,000.00
4,500.00
b Dempul jadi 0.25 kg 22,000.00
5,500.00
c Ampelas 2.00 lbr 3,200.00
6,400.00
d Pembantu tukang 0.05 org 27,500.00
1,375.00
e Tukang cat 0.15 org 42,000.00
6,300.00
Jumlah 24,075.00 Dibulatkan 24,070.00 7 1 M2 PENGECATAN KAYU DENGAN CAT RESIDU/TER
a Residu atau ter 0.35 Ltr 3,000.00
1,050.00
b Pembantu tukang 0.15 org 4,125.00
27,500.00
c Tukang cat 0.02 org 42,000.00
840.00
Jumlah 6,015.00 Dibulatkan 6,010.00 8 1 M2 PENGECATAN TEMBOK/PLAFON BARU KWALITAS SEDANG
a Plamir 0.10 kg 9,000.00
900.00
b Rol cat 0.01 bh 26,000.00
260.00
c Cat penutup kwalitas sedang 0.45 kg 16,000.00
7,200.00
d Steger (perancah kerja) 0.01 Ls 60,000.00
600.00
e Ampelas 0.50 lbr 3,200.00
1,600.00
f Pembantu tukang 0.06 org 27,500.00
1,650.00
g Tukang cat 0.20 org 42,000.00
8,400.00
Jumlah 20,610.00 Dibulatkan 20,610.00 9 1 M2 PENGECATAN TEMBOK/PLAFON BARU KWALITAS BAIK
a Plamir 0.10 kg 9,000.00
900.00
b Rol cat 0.01 bh 26,000.00
260.00
c Cat penutup kwalitas baik 0.50 kg 16,000.00
8,000.00
d Steger (perancah kerja) 0.01 Ls 60,000.00
600.00
e Ampelas 0.50 lbr 1,600.00
3,200.00
f Pembantu tukang 0.06 org 27,500.00
1,650.00
g Tukang cat 0.20 org 42,000.00
8,400.00
Jumlah 21,410.00 Dibulatkan 21,410.00 10 1 M2 PENGECATAN TEMBOK LAMA
a Cat penutup kwalitas baik 0.40 kg 27,000.00
10,800.00
b Rol cat 0.01 bh 26,000.00
260.00
c Steger (perancah kerja) 0.01 Ls 60,000.00
600.00
d Ampelas 0.50 lbr 3,200.00
1,600.00
e Pembantu tukang 0.06 org 27,500.00
1,650.00
f Tukang cat 0.20 org 42,000.00
8,400.00
Jumlah 23,310.00 Dibulatkan 23,310.00 11 1 M2 PENGECATAN EXTERIOR
a Cat tembok 0.36 kg 72,000.00
25,920.00
b Plamir tembok 0.16 kg 9,000.00
1,440.00
c Rol cat 0.01 bh 26,000.00
260.00
d Steger (perancah kerja) 0.01 Ls 60,000.00
600.00
e Ampelas 0.50 lbr 1,600.00
3,200.00
f Pembantu tukang 0.20 org 27,500.00
5,500.00
g Tukang cat 0.30 org 42,000.00
12,600.00
Jumlah 47,920.00 Dibulatkan 47,920.00 12 1 M2 MEMASANG WALLPAPER
a Wallpaper 1.20 m2 15,700.00
18,840.00
b Lem perekat 0.20 kg 30,800.00
6,160.00
c Pembantu tukang 0.02 org 27,500.00
550.00
d Tukang cat 0.15 org 42,000.00
6,300.00
Jumlah 31,850.00 Dibulatkan 31,850.00 13 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI
a Meni besi 0.10 kg 15,000.00
1,500.00
b Kuas 0.01 bh 13,500.00
135.00
c Pembantu tukang 0.02 org 27,500.00
550.00
d Tukang cat 0.20 org 42,000.00
8,400.00
Jumlah 10,585.00 Dibulatkan 10,580.00 14 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN CAT
a Meni besi 0.10 kg 15,000.00
1,500.00
b Cat besi 0.13 kg 37,000.00
4,810.00
c Kuas 0.01 bh 13,500.00
135.00
d Ampelas 0.50 lbr 3,200.00
1,600.00
e Perancah kayu 0.01 m3 60,000.00
600.00
f Pembantu tukang 0.20 org 27,500.00
5,500.00
g Tukang cat 0.20 org 42,000.00
8,400.00
Jumlah 22,545.00 Dibulatkan 22,540.00
XVIII PEKERJAAN LISTRIK 1 PASANG 1 TITIK STOP KONTAK
a Stop kontak 1.00 bh 12,500.00
12,500.00
b Kabel listrik NYM 3 x 2,5 mm 0.25 rol 625,000.00
156,250.00
c Aksesoris ( 20 % material ) 1.00 ls 31,250.00
31,250.00
d Pembantu tukang 0.20 org 27,500.00
5,500.00
e Tukang listrik 0.60 org 42,000.00
25,200.00
Jumlah 230,700.00
Dibulatkan 230,700.00
2 PASANG 1 TITIK LAMPU
a Saklar 1.00 bh 12,500.00
12,500.00
b Kabel listrik NYM 2 x 2,5 mm 0.25 rol 375,000.00
93,750.00
c Aksesoris ( 20 % material ) 1.00 ls 18,750.00
18,750.00
d Pembantu tukang 0.20 org 27,500.00
5,500.00
e Tukang listrik 0.60 org 42,000.00
25,200.00
Jumlah 155,700.00
Dibulatkan 155,700.00
3 PASANG 1 BUAH LAMPU SL
a Lampu SL 1.00 bh 56,000.00
56,000.00
b Aksesoris (1 % alat) 1.00 ls 560.00
560.00
c Tukang listrik 0.10 org 42,000.00
4,200.00
Jumlah 60,760.00
Dibulatkan 60,760.00
4 PASANG 1 BUAH LAMPU TL
a Lampu TL 1.00 bh 56,000.00
56,000.00
b Aksesoris ( 1 % alat ) 1.00 ls 560.00
560.00
c Tukang listrik 0.12 org
42,000.00 5,040.00
Jumlah 61,600.00
Dibulatkan 61,600.00
5 PASANG 1 BUAH LAMPU BARET
a Lampu baret 1.00 bh 87,000.00
87,000.00
b Aksesoris ( 1 % alat ) 1.00 ls 870.00
870.00
c Tukang listrik 0.15 org 42,000.00
6,300.00
Jumlah 94,170.00
Dibulatkan 94,170.00
6 PASANG 1 BUAH LAMPU PIJAR
a Lampu pijar 1.00 bh 5,000.00
5,000.00
b Aksesoris (1 % alat) 1.00 ls 50.00
50.00
c Tukang listrik 0.10 org 42,000.00
4,200.00
Jumlah 9,250.00
Dibulatkan 9,250.00
7 PASANG 1 BUAH LAMPU TAMAN
a Lampu taman 1.00 bh 152,500.00
152,500.00
b Aksesoris (1 % alat) 1.00 ls 1,525.00
1,525.00
c Tukang listrik 0.35 org 42,000.00
14,700.00
Jumlah 168,725.00
Dibulatkan 168,720.00
8 PASANG 1 BUAH PANEL
a Panel listrik standar untuk rumah 1.00 bh 250,000.00
250,000.00
b Aksesoris (10 % alat) 1.00 ls 25,000.00
25,000.00
c Tukang listrik 1.00 org 42,000.00
42,000.00
Jumlah 317,000.00
Dibulatkan 317,000.00
XIX PEKERJAAN WATERPROOFING 1 PASANG 1 M2 WATERPROOFING MEMBRAN
a Material primer 2.50 kg 2,450.00
6,125.00
b Waterproofing membrane 1.10 m2 60,000.00
66,000.00
c Pengetesan ( 10 % material ) 1.00 ls 6,600.00
6,600.00
d Pembantu tukang 0.20 org 27,500.00
5,500.00
e Tukang batu 0.60 org 42,000.00
25,200.00
Jumlah
109,425.00
Dibulatkan 109,420.00
2 PASANG 1 M2 WATERPROOFING COATING
aPre treatment/cleaning ( 10 % material )
1.00 m2 4,200.00
4,200.00
b Bahan waterproofing coating 1.00 kg 42,000.00
42,000.00
c Kuas 3 " 0.25 bh 13,500.00
3,375.00
d Pembantu tukang 0.20 org 27,500.00
5,500.00
e Tukang batu 0.60 org 42,000.00
25,200.00
Jumlah 80,275.00
Dibulatkan 80,270.00
3 PASANG 1 M2 FLOOR HARDERNER
a Material natural non metalic 1.10 kg 42,000.00
46,200.00
b Aksesori ( 10 % alat ) 1.00 ls 462.00
462.00
c Pembantu tukang 0.20 org 27,500.00
5,500.00
d Tukang batu 0.60 org 42,000.00
25,200.00
Jumlah 77,362.00