AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE...

10
AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE

Transcript of AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE...

Page 1: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

AN E VENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FR OM THE MUNDHWA BRIDGE

AUGUST 2020MONTHLY UPDATE

Page 2: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

Refer your family member to be a part of this Luxurious River front Community

LIMITED EDITION LUXURIOUS 3 BHK RIVERFRONT RESIDENCES

Referral Reward Slab

₹1,50,000/-

Page 3: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

Site Address: New Kharadi - Shivane Riverside Road, Behind Zensar IT Park, Kharadi, Pune 411 014 Maha RERA Registration No.: Riverdale Suites - P52100014163 | Riverdale Heights - P52100008035 | Riverdale Residences - P52100004692

+91 7620 974 974 www.riverdalepune.com

K H A R A D I , P U N E

₹1,50,000/- ₹1,00,000/-Suites

₹50,000/-

Referral Reward Slab

This pandemic has made us realize the importance of family living close by. You could refer your sibling or your relative and make the comfort of family being nearer a reality.

YOUR PARENTS SILVER JUBILEE CELEBRATIONS ARE THAT MUCH MORE SPECIAL WHEN THE ENTIRE FAMILY CELEBRATES

Precious moments like these are not just timeless but can be aplenty when his family lives on another �oor within the same community

Page 4: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

Riverdale Heights

2 BHK - Tower A | B | C | D

RIVERDALE HEIGHTS AS SEEN FROM THE NEW KHARADI-SHIVANE RIVERSIDE ROAD

Tower - A & B

POSSESSION DELIVERED AT

TOWER A & B

Page 5: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

Tower - C

Above Terrace slab Completed/ Terrace Water-proo�ng work complete/ Toilet

rdWater-proo�ng 23 Floor Complete

rd23 Floor Internal Door Frame Fixing Complete/Reception Lobby wall Flooring complete/ Reception Lobby wall cladding work-in-progress/Lobby Parking Paver work in progress

rd Living Balcony SS Railing 23 Floor complete/ Staircase Railing Complete/ Staircase Fire Door installed/ Garbage Chute installation complete

rdWall Gypsum Plasters 23 Floor complete/rd Balcony Waterproo�ng 23 Floor complete/

Solar Panel, Water Puri�er & Inverter installation in progress/ Pressurization Fan installed

rd23 Floor Toilet wall Dado work-in-progressrd& 23 Floor Toilet Flooring complete/ CP &

rd Sanitary Fittings �xing 23 Floor complete/ Podium Garden soil �lling in progress

Kitchen Platform & Kitchen Dado of rd23 Floor complete/ Kitchen Cabinet th20 Floor work-in-progress

Unitized Glass Curtain Wall installation complete/ rdDoor shutters �xing 23 Floor complete/

Flooring 23rd Floor complete

rdInternal Wall Paint 23 Floor complete / rdWall putty & Primer Paint 23 Floor complete/

rdElectrical Switch installation 23 Floor in progress

Lift Architrave, Lift Lobby Flooring & Lift Lobby rdFalse ceiling 23 Floor complete/ Passenger Lift

installation complete/ Service Lift installationin progress

External Texture Paint work-in-progress/Aluminum Sliding Door, Toilet & Utility

rdWindows 23 Floor complete

ALL INTERNAL WORKS COMPLETE.

OC AWAITED

Page 6: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

Tower - DAbove Terrace slab Completed/ Plumbing & Electrical work 100% completed/ Terrace

rd Water-proo�ng complete/ 23 Floor wall Gypsum plasters complete

Staircase Railing work in progress/ P1, P2 & P3 Parking painting, External Texture

thPaint, 17 Floor Flooring & Passenger Lift Granite Architrave complete

th nd18 Floor Kitchen Dado & 22 Floor Kitchen Platform work-in-progress/ Plumbing work

nd22 �oor in Progress/ Internal Painting work-in-progress

th19 Floor Toilet Water-proo�ng in progress/th18 Floor Toilet Wall Dado work-in-progress/

Living Balcony Sliding Door, Utility & Toilet nd thwindow 2 to 4 Floor installation in progress

st21 Floor Internal Door Frame Fixing work-in-progress/ Curtain Wall (Façade) &Passenger Lift installation in progress/Pressurization Fan installation in progress

GIVEN THE EXTREME MAN POWER CONSTRAINTS FACED BY THE INDUSTRY AND THE OVERALL

SLOW DOWN DUE TO IN-AVAILABILITY OF LABOUR, WE

HAVE YET BEEN ABLE TO KEEP THE SITE WORK FORCE AT THE LABOUR

CONSTRUCTION CAMP AND CONSTRUCTION & FINISHING

ACTIVITY IS IN PROGRESS.

Page 7: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

Tower - E

Terrace Slab complete/ Over Head Water Tank RCC work complete

Above Terrace Water-proo�ng complete/rdPlumbing 23 Floor work complete

rdDrainage piping 23 �oor work complete/ rdElectrical conduiting and chasing 23  

Floor complete

Electrical cabling work complete/ rdWall Gypsum Plasters 23 �oor complete/

Internal Paint Flat series work-in-progress

nd rdFloor Tiling Flat Series 1 & 2, 2 to 23 Floor/nd rd nd rd9 & 10, 2 to 23 Floor/ 5 & 6, 2 to 23 Floor/

nd rd7 & 8, 2 to 23 Floor work complete/ Flat Series nd th3 & 4 Flooring work-in-progress - 2 to 10

th rdcomplete- 11 to 23 Work-in-progress

AAC Block works complete/ External Paint work in progress/ Water-proo�ng done

rdup to 23 �oor

Fire Staircase Railing complete/ Toilet CP & Sanitary �xing work-in-progress/ Passenger & service Lift installation complete/ External Paint work in progress.

Internal Door Frame Fixing complete/rd 23 Floor Kitchen Platform Fixing complete/

st nd th thDoor Shutter �xing Flat series 1 , 2 & 5 to 9 & th10 in progress

Kitchen Utility Aluminum sliding window &Cabinet Flat Series 1, 2, 9 & 10 installations

ndcomplete for 22 Floors / Flat Series 1, 2, 9 & 10 complete/ Flat Series 5, 6, 7 & 8 work in progress

nd th2 to 12 Floor Lobby False Ceiling/ Lift Installations/ st rdLobby Flooring 1 to 23 Floor complete/

Lift Door Fixed/ Lift Architrave & Lift Granite Architrave complete

ODU Balcony Block Work complete/ ODU Balcony MS Grill & Railing work-in-progress/ ODU Flooring

rdwork – Flat Series1, 8, 9, 10 completed up 23 Floor/ st thODU Flooring work Flat Series 1 & 10 work-in-progress

Unitized Glass Curtain Wall (facade) installations in progress West side Flat Series 1, 2, 9 & 10 complete

ndup to 22 Floor & East side 5, 6, 7 & 8 complete up to nd22 Floor, 3 & 4 work-in-progress

Staircase ceiling putty & Fire staircase complete/ East side podium work-in-progress/ Kitchen Utility Aluminum sliding window Flat Series 1, 2, 9 & 10 complete. Series 5, 6, 7 & 8 work-in-progress

Living Room Sliding Door – Flat Series 1 & 2 completed rdup to 23 Floor. Flat Series 9 & 10 completed up to

rd23 Floor. Flat Series 5,6,7 & 8 work-in-progress

Fire �ghting works complete/rd23 �oor Dado Wall Tiling Kitchen/rd23 Floor Dado Wall Tiling Toilets complete

Page 8: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

EXTERNAL WORKS

Clubhouse Interior �nishes (furniture, gaming zone, library, Gymnasium) complete

Swimming Pool testing complete/ Curtain Wall (Facade) installation Tower A & B complete &Curtain Wall installation Tower C & E in progress

Tower A & B Private Garden Plantation complete/Tower C Private Garden Soil �lling complete/ Tower D Private garden water-proo�ng in progress Podium Green Landscape plantation complete

Ramp Driveway complete/ DG installations work complete/ Tower A & B Curtain Wall (Façade) installation complete/ Tower E Curtain Wall (Façade) installation in progress

Fire �ghting installed all parking levels/ Tower A & B Tower Ribbons in progress

Step Garden Landscape Garden Soil �lling in progress/ STP complete/ Jogging Track &Badminton court work-in-progress/ Basket Ball court complete

Main Entry Security Cabin with Green Landscape complete / Main Entry Bridge Paver �xing complete

Tower A & B Entrance Lobby & Double Height Reception Lobby complete

External Driveway Paver �xing complete Lobby Level Parking Paver �xing complete/ OWC Complete

Electrical Transformer Room complete/All Parking Lighting works complete

Water Treatment Plant work complete

UGWT Pumps installed and charged & Fire Panels Charged

Page 9: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

Riverdale SuitesSuites

th19 Floor Aluform assembling & reinforcement work in progress/th9 Floor AAC Block work-in-progress

Plinth Level PCC, Complete/ thCeiling Gypsum 8 Floor in progress

Internal Plumbing & electrical work-in-progress

thWall Gypsum 5 Floor in progress/ st thWater-proo�ng 1 to 4 Floor in progress

Electrical conduiting work-in-progress

Page 10: AN EVENING MONSOON SKYLINE OF THE RIVERDALE · 2020. 8. 19. · AN EVENING MONSOON SKYLINE OF THE RIVERDALE RIVERFRONT SHOT FROM THE MUNDHWA BRIDGE AUGUST 2020 MONTHLY UPDATE. Refer

Riverdale Residences

E2 & E3- Parking level Electrical & Panel Rooms thblock work complete/ E3 - Electrical upto10

thFloor & Plumbing upto 17 Floor completed

E1 –Parking P3 complete & Podium Level part slab complete/ Scooter Parking Floor &Podium Level Club House RCC work-in-progress

E1– Under Ground Water Tank RCC Raft and th thWalls/ E2- 12 Floor & E3- 10 Floor Door frame

�xing work-in-progress/ E3- Texture – Surface preparation for external paint

Ramp and Underground Water Tank RCC walls/E2 & E3- Scooter Parking Underground servicesFloor concreting & Podium & Parking level RCC Parapet in progress

E2 – Parking External Plaster/ E3 – Fire Staircase Block work-in-progress/ E2- Toilet Dado �xing &

thE3- Toilet Dado 5 Floor �xing in progress/E1 – Boundary wall work in progress

stE2- 21 Floor wall Gypsum work-in-progress/thE3- 20 Floor wall Gypsum work-in-progress &

E2 & E3 - Lift lobby wall Gypsum work in progress/ Lift Lobby AAC Block work in progress

thE3- 24 Floor MIVAN (Aluform) assembling/ E2- Terrace Floor MIVAN (Aluform) assembling/

E1 - Podium level slab complete/ E2- Electrical upto th th12 Floor & Plumbing upto 10 Floor completed

th thE2- 11 Floor & E3 - 14 Floor Toilet th thWater-proo�ng/ E2- 11 Floor & E3- 18 Floor

Toilet Concealed- Plumbing work-in-progress/ Toilet Flooring work-in-progress

th thE2- 16 & E3- 14 Floor Fire Fighting pipe installation/ E2 & E3- Podium & Parking level RCC Parapet &Fire Fighting line installation in progress

th thE2- 12 Floor & E3- 18 Floor Drainage piping/ E3- Kitchen Platform work-in-progress/

ndKitchen Dado works in progress/ E1 - 2 Floor/ E1 - Club House multipurpose hall PT Slab completereinforcement in progress at E1 Podium Level