An Assessment for Technical, Economic, and - Universität Kassel
Transcript of An Assessment for Technical, Economic, and - Universität Kassel
An Assessment for Technical, Economic, and Environmental
Challenges Facing Renewable Energy Strategy in Egypt
By
Eng. Ehab Mohamed Farouk Abd El Aziz Mohi El Din
A Thesis Submitted to the
Faculty of Engineering at Kassel University
Faculty of Engineering at Cairo University
In Partial Fulfillment of the
Requirements for the Degree of
MASTER OF SCIENCE
In
RENEWABLE ENERGY AND ENERGY EFFICIENCY
REMENA
FACULTY OF ENGINEERING, KASSEL UNIVERSITY
KASSEL, GERMANY
2011
An Assessment for Technical, Economic, and Environmental
Challenges Facing Renewable Energy Strategy in Egypt
By
Eng. Ehab Mohamed Farouk Abd El Aziz Mohi El Din
A Thesis Submitted to the
Faculty of Engineering at Kassel University
Faculty of Engineering at Cairo University
In Partial Fulfillment of the
Requirements for the Degree of
MASTER OF SCIENCE
In
RENEWABLE ENERGY AND ENERGY EFFICIENCY
REMENA
Under Supervision of
FACULTY OF ENGINEERING, KASSEL UNIVERSITY
KASSEL, GERMANY
2011
Prof. Dr.-Ing. Jürgen Schmid Prof. Dr. Mohamed Salah El Sobki (Jr.)Fraunhofer-IWES Professor Electric Power Systems
Universität Kassel Cairo University
Dr. Mohamed Moustafa El khayatNew and Renewable Energy Authority (NREA)
An Assessment for Technical, Economic, and Environmental Challenges
Facing Renewable Energy Strategy in Egypt
By
Eng. Ehab Mohamed Farouk Abd El Aziz Mohi El Din
A Thesis Submitted to the
Faculty of Engineering at Kassel University
Faculty of Engineering at Cairo University
In Partial Fulfillment of the
Requirements for the Degree of
MASTER OF SCIENCE
In
RENEWABLE ENERGY AND ENERGY EFFICIENCY
REMENA
Approved by the Examining Committee
Prof. Dr.
Prof. Dr.
Prof. Dr.
FACULTY OF ENGINEERING, KASSEL UNIVERSITY
KASSEL, GERMANY
2011
I
TABLE OF CONTENTSLIST OF FIGURES................................................................................................. VI
LIST OF TABLES ............................................................................................... VIII
NOMENCLATURE................................................................................................ IX
ACKNOWLEDGMENT......................................................................................... XI
ABSTRACT ...........................................................................................................XII
1 CHAPTER ONE: ENERGY SITUATION IN EGYPT ..................................... 1
1.1 Introduction .................................................................................................. 1
1.2 Energy........................................................................................................... 3
1.3 Institutions and Governance in the Energy Sector ....................................... 4
1.3.1 The Ministry for Electricity and Energy (MOEE) ................................. 4
1.3.2 The Ministry of Petroleum (MOP)......................................................... 6
1.3.3 Supreme Council of Energy (SCE) ........................................................ 6
1.4 Energy Policy ............................................................................................... 7
1.5 Energy Situation in Egypt ............................................................................ 8
1.5.1 Oil ........................................................................................................... 8
1.5.2 Natural Gas........................................................................................... 10
1.6 Electricity situation in Egypt ...................................................................... 12
1.6.1 Conventional Thermal.......................................................................... 14
1.6.2 Hydropower.......................................................................................... 14
1.6.3 Wind ..................................................................................................... 17
1.6.4 Solar...................................................................................................... 19
1.6.5 Nuclear ................................................................................................. 19
1.6.6 International Connections .................................................................... 20
2 CHAPTER TOW: ELECTRICITY DEMAND AND SUPPLY IN EGYPT... 22
2.1 Energy Demand Scenarios for Egypt ......................................................... 22
2.1.1 Energy Consumption............................................................................ 22
II
2.1.2 Drivers of Energy Demand .................................................................. 25
2.2 Electricity Market Design........................................................................... 29
2.2.1 Background .......................................................................................... 29
2.2.2 Present Status of Electricity Market..................................................... 29
2.2.3 The Proposed Electricity Market Structure.......................................... 31
2.2.4 Tariffs ................................................................................................... 33
2.3 Independent Power Producers, IPPs........................................................... 35
2.3.1 IPP frameworks and projects developed.............................................. 36
2.3.2 IPPs Projects in Egypt .......................................................................... 36
2.3.3 Future IPPs Projects in Egypt .............................................................. 38
2.3.4 IPPs Projects Evaluation ...................................................................... 39
3 CHAPTER THREE: NATIONAL RENEWABLE ENERGY STRATEGYin Egypt ................................................................................................................... 40
3.1 Introduction ................................................................................................ 40
3.2 Incentives for the Private Sector................................................................. 41
3.3 Energy Planning Model .............................................................................. 43
3.3.1 The Methodology of Data Processing.................................................. 44
3.4 The Current Situation at the Year 2009/2010 ............................................ 47
3.5 The Expected Situation of Electricity By 2020.......................................... 47
3.6 Wind Energy Situation ............................................................................... 50
3.6.1 The Land Required For Wind Farms ................................................... 51
3.6.2 The Available Land for Wind Projects ................................................ 51
3.6.3 Wind Atlas for Egypt ........................................................................... 52
3.6.4 Wind Farm Area Calculator ................................................................. 57
3.6.5 Repowering of wind turbines ............................................................... 59
3.7 Solar Energy Situation................................................................................ 60
3.7.1 Solar Atlas ............................................................................................ 61
III
3.7.2 EM Power Program, Country visit Report........................................... 62
3.7.3 CSP+D potential in Egypt “SolarPACES” .......................................... 65
3.8 The complete evaluation for the targeted plan ........................................... 71
4 CHAPTER FOUR: ECONOMIC AND FINANCIAL EVALUATION.......... 73
4.1 Renewable Energy Market and Industry Highlights .................................. 73
4.2 Economic and Financial Evaluation for Wind Projects ............................. 74
4.2.1 Investment costs ................................................................................... 75
4.2.2 Lifecycle Cost of Energy ..................................................................... 76
4.2.3 Operations and Maintenance................................................................ 76
4.3 Financing Schemes for Wind Park Projects in Egypt ................................ 77
4.3.1 Grant Scheme ....................................................................................... 77
4.3.2 Self-Finance/Grant Scheme.................................................................. 77
4.3.3 Self-Finance Scheme............................................................................ 77
4.4 The expected investment cost for wind projects ........................................ 78
4.5 The Expected Projects in the East and West Nile Banks ........................... 80
4.6 Economic and Financial Evaluation for Concentrating Solar power ........ 83
4.6.1 Investment Costs .................................................................................. 83
4.6.2 Operation and maintenance costs......................................................... 84
4.6.3 Costs of providing finance for CSP plants........................................... 84
4.6.4 Generating costs ................................................................................... 85
4.6.5 The expected investment cost of CSP in Egypt ................................... 85
4.6.6 Parabolic Trough Modeling in Solar Advisor Model (SAM).............. 86
4.6.7 Concentrating Solar Power Plant Model.............................................. 88
4.7 Economic and Financial Evaluation for Photovoltaic PV.......................... 90
4.7.1 Levelized Energy Production Cost....................................................... 91
4.7.2 Cost Reduction Goals........................................................................... 92
4.7.3 Cost of Turnkey PV in Germany drops, (the German experience) ..... 92
IV
4.7.4 The Expected Investment Cost of PV in Egypt ................................... 94
4.7.5 Tariff Requirements ............................................................................. 95
4.7.6 PV Power Plant SAM Model ............................................................... 95
4.8 General Economic evaluation and Impacts ................................................ 97
4.8.1 General economic indicators................................................................ 97
4.8.2 General economic impacts ................................................................... 98
5 CHAPTER FIVE: ENVIRONMENTAL IMPACTS EVALUATION OFRENEWABLE ENERGY....................................................................................... 99
5.1 Introduction ................................................................................................ 99
5.2 The Impact of Wind Energy on Climate Change ..................................... 100
5.3 Carbon Dioxide Emissions and Pollution ................................................ 101
5.3.1 How Much CO2 Can Wind Energy Save?.......................................... 101
5.4 Environmental Impacts of Wind farms .................................................... 103
5.4.1 Noise Problems .................................................................................. 103
5.4.2 Interference......................................................................................... 104
5.4.3 Appearance......................................................................................... 104
5.4.4 Land use ............................................................................................. 104
5.4.5 Impact on wildlife .............................................................................. 105
5.4.6 Safety.................................................................................................. 105
5.5 The Environmental Impacts of Wind farms in Egypt .............................. 107
5.5.1 Land characteristics and use: ............................................................. 107
5.5.2 Flora and Fauna (without avi-fauna):................................................. 107
5.5.3 Avifauna: ............................................................................................ 107
5.5.4 Water quality: ..................................................................................... 108
5.5.5 Air quality: ......................................................................................... 108
5.5.6 Noise levels: ....................................................................................... 108
5.6 Environmental Effects of Solar Energy.................................................... 109
V
5.6.1 Carbon Emissions............................................................................... 110
5.6.2 Abundant Components....................................................................... 110
5.6.3 Cadmium ............................................................................................ 110
5.6.4 Ecological Concerns........................................................................... 110
6 CHAPTER SIX: CONCLUSION AND RECOMMENDATIONS ............... 112
6.1 Introduction .............................................................................................. 112
6.2 Conclusions on the Present Work............................................................. 112
6.3 Recommendations and Proposed Action to Speed RE In Egypt.............. 114
6.3.1 Fossil-Fuels Subsidy .......................................................................... 115
6.3.2 Access to Transmission, Grid Connection......................................... 115
6.3.3 Promoting and Encouraging Solar Water Heating Systems .............. 116
6.3.4 Educate the awareness about the role of wind energy ....................... 117
6.3.5 Research, development and demonstration support of local industry 117
6.3.6 Garbage-To-Energy- Recycling instead of Burning .......................... 117
Energy Production per Ton of Garbage.......................................................... 118
REFERENCES...................................................................................................... 119
VI
LIST OF FIGURESFigure 1-1: Egypt’s Oil Production and Consumption 1990-2010, source EIA........... 9
Figure 1-2: Egypt’s NG Production and Consumption 1990-2010, source EIA ........ 10
Figure 1-3: fuel input and electricity generation in power plants in Egypt, in Mtoe
(EEHC). ................................................................................................................ 13
Figure 1-4: Development of Hydro Generated Energy (GWh), source EEHC .......... 15
Figure 2-1 Share of Egypt’s Total Energy Consumption, by Sector, 2007 ................ 23
Figure 2-2: Share of Egypt’s Total Energy Consumption, by Fuel Type, 2007 ......... 24
Figure 2-3: Share of Egypt’s Total Primary Energy Production, by Source, 2007, F 24
Figure 2-4: Historic and Future Population Trends in Egypt, 1990–2030.................. 25
Figure 2-5: Egypt’s GDP Growth, Two Scenarios, 1993–2030, ................................ 27
Figure 2-6: Egypt’s Real Per Capita GDP, 1993–2030, ............................................. 27
Figure 2-7: Egypt’s Economic Growth by Sector, 1993–2030,.................................. 28
Figure 2-8: Egypt’s Economic Growth by Sector, 1993–2030,.................................. 28
Figure 2-9: Structure of the EEHC, source H. El Salmawy........................................ 30
Figure 2-10: Power sector structure, source H. El Salmawy ...................................... 31
Figure 2-11: The proposed Electricity Market Structure ............................................ 32
Figure 3-1: Energy Planning Model Components....................................................... 44
Figure 3-2: current situation of electricity 2009/2010 ................................................ 47
Figure 3-3: the forecasting of total electricity generated up to 2020 .......................... 48
Figure 3-4: Estimate Targeted share of renewable energy up to 2020 ....................... 49
Figure 3-5 : Elevation map of Egypt showing the meteorological stations used for the
Wind Atlas for Egypt............................................................................................ 53
Figure 3-6: Mean wind speeds and power densities at a height of 50 m over
roughness class 1 (z0 = 0.03 m) for the 30 stations in Egypt............................... 54
Figure 3-7 Wind resource map of Egypt: mean wind speed at 50 m a.g.l. determined
by mesoscale modeling (Wind Atlas for Egypt, 2006). ....................................... 55
VII
Figure 3-8: offshore wind resource map of Egypt: mean wind speed at 50 m a.g.l.
determined by mesoscale modeling (Wind Atlas for Egypt, 2006). .................... 56
Figure 3-9: Solar Atlas of Egypt, source NREA annual report 2010.......................... 61
Figure 3-10: Egypt coastal strip in the Mediterranean Sea in red color...................... 66
Figure 3-11: Elevation profile of the Egypt coastal strip in the Mediterranean ......... 66
Figure 3-12: Egypt coastal strip in the Red sea in red color, ...................................... 67
Figure 3-13: Elevation profile of the Egypt coastal strip in the Red sea .................... 67
Figure 3-14: DNI results of the Egypt coastal strip in the Mediterranean Sea, .......... 68
Figure 3-15: Elevation profile of the Egypt coastal strip in the Red sea, ................... 69
Figure 3-16: Comparison between the planned targeted and the estimated planned
projects GWh........................................................................................................ 72
Figure 4-1: SAM Model Processing............................................................................ 88
Figure 4-2: result of CSP SAM modeling................................................................... 89
Figure 4-3: current performance and price of different PV module technologies, ..... 91
Figure 5-1: Global Power Capacity and avoided CO2 emissions (2008-2030)........ 102
VIII
LIST OF TABLESTable 1-1: Generated Energy (GWh), source EEHC .................................................. 15
Table 1-2: Hydro Power Indicators, source EEHC ..................................................... 16
Table 1-3: Fuel Saved Due to the Use of Hydro Power, source EEHC...................... 16
Table 1-4: Total Installed Capacity of Wind Energy, source Wind Energy Council . 17
Table 1-5: Egyptian Energy overview, source EIA .................................................... 21
Table 2-1: Egypt’s IPPs, source Anton Eberhard and Katharine Gratwick ................ 38
Table 3-1: The weighted capacity factor..................................................................... 50
Table 3-2: Estimated land for wind energy, scenario 1, source NREL web site ........ 58
Table 3-3: Estimated land for wind energy, scenario 2 .............................................. 58
Table 3-4: Proposed lands suitable for solar projects, source Em Power, .................. 63
Table 3-5: expected electricity generated from Kom Ombo,...................................... 64
Table 3-6: Targeted Strategy by 2020......................................................................... 71
Table 3-7: Real projects .............................................................................................. 71
Table 3-8: shortage from the targeted and planned projects ....................................... 72
Table 4-1: the expected investment of wind farm, source, 200 MW FS .................... 78
Table 4-2: Operation and Maintenance, source, 200 MW FS..................................... 79
Table 4-3: technical data of 200 MW wind in West of Nile ....................................... 80
Table 4-4: the expected cost of the project ................................................................. 81
Table 4-5: the results of the project of west of Nile.................................................... 81
Table 4-6: expected investment cost for CSP projects, PFC Kom Ombo .................. 86
Table 4-7: investment cost of 100 MW PV power plants, source PFC of PV in Kom
Ombo .................................................................................................................... 94
Table 4-8: results of SAM simulation for 20 MW PV................................................ 96
Table 5-1: Global Power Capacity and avoided CO2 emissions (2008-2030), source
wind roadmap ..................................................................................................... 102
IX
NOMENCLATURE
MW Mega Watt
GW Giga Watt
KWh Kilo Watt Hour
OPEC Organization of Petroleum Exporting Countries
MOEE Ministry Of Electricity and Energy
MOP Ministry of Petroleum
EEHC Egyptian Electricity Holding Company
EETC Egyptian Electricity Transmission Company
SCE Supreme Council of Energy
REF Renewable Energy Fund
EEL Energy Efficiency Labeling
GCC Gulf Cooperation Council
EGPC Egyptian General Petroleum Corporation
Tcf Trillion Cubic Feet
LPG Liquefied Petroleum Gas
AGP Arab Gas Pipeline
CC Combined Cycle
GHG Greenhouse Gas
X
Mtoe Million Ton Oil Equivalent
IEA International Energy Agency
GEF Global Environmental Facility
PPA Power Purchase Agreement
BAU Business-As-Usual
GDP Gross Domestic Product
HEG High Economic Growth
BOOT Build-Own-Operate-Transfer
EHV Extra High Voltage
HV High Voltage
TSO Transmission System Operators
EEUCPRA Egyptian Electric Utility and Consumer Protection Regulatory
Authority
IPPs Independent Power Producers
NECC National Energy Control Center
LCA life cycle assessment
UTM Universal Transverse Mercator
A.G.L Above Ground Level
Acre area unit (1 acre = 4000 m2)
XI
ACKNOWLEDGMENT
I would like to express my deep gratitude to my supervisors Prof. Dr. Ing. Jurgen
Schmid, Prof. Dr. Eng. Mohamed Salah El Sobki, Dr. Mohamed El Khayat for
their continuous help in my work and guidance to complete this thesis. I would also
like to thank them for their valuable advices in the different contexts of this
document.
My heartfelt thanks are due to Prof. Dr. Adel Khalil for his great help and support
during the time of this work.
Many thanks go to Dr. John Severs for his help and support during the various
stages of this thesis work. His insightful comments and notes were of great
significance for this work.
Many thanks to Eng. Ehab Ismaiel for his help, and providing me by all required
data and advices throughout this work. His contributions were of great impact on this
work.
I also wish to thank my colleagues at the REMENA Program for their friendship,
support and for creating an enjoyable working atmosphere throughout my working
period, specially Mustafa Shaban and Mohamed Rany.
Finally, I would like to express my gratefulness to my Family, my Wife and my
daughter Mai, my sons Omar and Ziad for their continuous care, patience, tolerance,
encouragement, and support.
XII
ABSTRACTSecuring energy demand for next generations is one of the most challenges aspects
facing any sustained development plans, due to the growing electric energy demand
and Egypt as a country of limited fossil fuel resources has to diversify its energy
portfolio by utilization of its renewable energy resources, mainly wind due to its
economic potential and solar as proved by Egypt's wind and solar atlases. In the year
2009/2010, the total installed capacity in Egypt was 24726 MW with electricity
generation 139,000 GWh, of which 89 % was delivered by thermal plants and about
10% from Hydro power with total installed 2800 MW and electricity generated is
about 12863 GWh and 1% from Wind energy with total installed 550 MW and
electricity generated 1542 GWh.
In the solar energy field, the first solar thermal power plant of 140 MW with a solar
share of 20 MW using parabolic trough technology was started the initial work since
the 1st of July with estimated total energy generated of 852GWh/year. Recently,
Egypt has adopted an ambitious plan to cover 20% of the generated electricity by
renewable energy by 2020, including a 12% contribution from wind energy,
translating more than 7200 MW grid-connected wind farms. Such plan gives a room
enough to the private investment to play the major role in realizing this goal. The plan
includes also a 100 MW Solar thermal energy CSP with parabolic trough technology
in Kom Ombo city, and also two PV plants in Hurgada and Kom Ombo with a total
installed capacity 20 MW each. Due to the high investment cost of solar energy
technologies, still limited in spread all over the world on the other hand wind energy
has an economic potential and becomes a commercial technology but the future
potential for solar energy due to the limited land for wind energy. Current study will
evaluate the Egyptian strategy for renewable energy up to 2020 and find how much
the planned projects from the Egyptian government will fulfill its target, the
economic study and the expected investment cost of these projects, and the
environmental impacts of the renewable energy.
1
1. CHAPTER ONE: ENERGY SITUATION IN EGYPT
1.1 IntroductionEgypt is a Middle Income Country with strong ownership of its development strategy.
The Government has established a good track record of economic reform. This has led
to a friendlier investment climate, which in turn has yielded a strong private sector
response. However, this economic growth has been accompanied by a growth in energy
use, especially higher demand for electricity implying adding about 1500 – 2000
MW/year.
Securing energy demand on continuous bases is a vital element for sustained
development plans and Egypt as a country of limited fossil fuel resources
In this sense and in line with the general framework of energy policies in Egypt, the
Supreme Council of Energy in Egypt announced the strategy for the electric power
based on diversifying energy sources of production, rationalizing the use of energy and
expanding use of renewable energy sources as a component of energy provision. The
strategy, which was approved in February 2008, aims to: “Contribution of renewable
energies by 20% of the total electricity generation by the year 2020. The share from the
grid-connected wind power is 12% of the total electricity generation, and that represents
about 7200 MW total capacities. Also, other renewable energy applications, led by
hydropower and solar energy, will have a significant contribution."
The polices to foster increasing private sector participation consist of two phases;
Competitive Bidding, which will apply for around 5 years, and Feed-in-Tariff
approaches. Current study will focus on analyzing main challenges facing the
renewable energy strategy of Egypt, such as:
A) High penetration of wind projects with very large scale projects will be
concentrated in 3 main regions. Such situation entails considering several issues
2
such as wind forecasting systems, wake effects of large farms, Energy security,
as well as grid stability issues.
B) Implementing about 600 MW yearly during the next 10 years in spite of
implementing 550 Mw during the last 10 years.
C) Recent financial crises could represent one of the main obstacles cause delay in
achieving the strategy target.
D) How to cover the gap between the production cost and the selling price.
E) Are current planned projects able to fulfill the strategy targets? If not, what are
the possible scenarios to reach 20% of electricity production from renewable
resources by the year 2020?
F) What is the Cost/Benefit Analysis of implementing such renewable energy
projects?
G) Environmental assessment for the implementing different scenarios.
3
1.2 EnergyEnergy plays a significant role in any nation’s development, and securing energy is one
of the most important challenges facing any development plans. We can understand
“Energy security” more when take it literally. We need to be secure in our energy in
terms of the source, i.e. where it comes from, the control of the consumption and
distribution of that energy, and having alternatives in place to allow us to withstand
highs and lows associated with any commodity. Securing energy resources and
production to meet the national demand both on the short and long terms, along with
adequate attention to environmental impacts concerns, are considered vital elements for
sustainable development. To face all these challenges Egypt takes a different effective
measures to increase the role of RE in the energy supply and use matrix. The very high
potential of renewable energy supports this orientation from the energy sector, which
are not completely exploited. Egypt is also still in the development phase of legislation
supporting the use of RE. A proposed electricity law is currently under construction and
development. It would include some legislation supporting RE in terms of obligations
or commitments on both energy consumers and producers to assign a part of their
production capacity and/or consumption to be from RE. In the same time there is a
renewable energy fund has been established between the Ministry of Electricity and
Energy “MOEE” and Ministry of Petroleum “MOP”, funded from the difference
between the international and local price of fuel saved by using RE. This difference will
be split equally between the two ministries. The share of MOEE will be directed to
support RE. Another incentive tool is that the Egyptian Electricity Transmission
Company (EETC) bears the cost of wind farms connection to the 220 kV transmission
lines until and including 22 kV in addition to paying a tariff per kWh about 10% higher
than that paid to conventional generation companies, finally the support of RE fund box
which ratified from the Egyptian Cabinet, [1].
Fossil fuels (Oil and NG) considered the main energy source, Egypt considered an
important non-OPEC energy producer. The large Commercial quantities of oil were
4
first found in 1908, and more petroleum was found in the late 1930s along the Gulf of
Suez. Later, there is large oil fields were discovered in the regions (Sinai Peninsula,
Gulf of Suez, Western Desert, and the Eastern Desert). The Abu Rudeis and Ra's Sudr
oil fields in the Sinai, captured by Israel in 1967, were returned to Egyptian control in
November 1975, and the remaining Sinai oil fields reverted to Egyptian control by the
end of April 1982, [2] . In terms of electricity generation, natural gas considered the
main fuel source and accounts for over 70 % of the total energy mix, the remainder
being met mostly by hydroelectricity. Plans are underway to further expand electricity
generation capacity by utilizing the country’s vast wind and solar resources.
1.3 Institutions and Governance in the Energy Sector
The Egyptian energy sector consists of a variety of institutions and organizations, some
of these have direct influence on the governance while others more indirectly influence
activities and decisions. Ministry of Electricity and Energy, and Ministry of Petroleum,
are basically taken care of the fields of electricity and of petroleum and natural gas, and
their connected authorities and organizations. In addition to the ministries, a Supreme
Council of Energy has been established; more details for each of them and the
responsibilities will be below.
1.3.1 The Ministry for Electricity and Energy (MOEE)
The main objective of the Ministry is to provide the electricity for all consumers all
over the country. In order to full fill that obligation, the ministry has to:-
Settle the general plane & energy generation, transmission and distribution using
the high-tech and the latest scientific development and supervise the execution of
such plan and follow-up the different activities concerning the electrical
network.
Suggest the electric energy prices for all different voltage levels and different
usages.
5
Supervise the study and execution of essential electrical projects.
Publish the statistics and data relating to electric energy production &
consumption
Supply the technical consultancies and services in the electric fields to Arab
countries and all others.
Ministry of electricity and energy has a lot of goals to be achieved includes:
Optimize use of available energy sources and minimize environment pollution
Provide electricity with minimum price and best quality
Expand utilization of new and renewable energy resources
Support electricity availability in towns and cities and complete electrifying the
urban areas and low population communities.
Interconnect the Egyptian Electrical network to African, west and east
neighboring countries
Boost local and domestic contribution to design, implementation and
manufacturing of electrical equipment’s.
Develop peaceful use of nuclear power.
Restructure electricity sector to optimize investments and improve electrical
services.
Utilize modern and sophisticated technical systems in electricity sector's
operation and activities.
Develop the expertise and skills of engineers and technicians working in the
electricity sector.
Export Egyptian expertise in design, manufacture, negotiation, construction and
operation of electrical projects.
Use soft loans as much as possible, [3].
Ministry of Electricity and Energy consists of Institutions and Authorities includes:
Egyptian Electricity Holding Company” (EEHC) which considered the main player and
6
consists of generation, transmission and distribution companies, Rural Electrification
Authority (REA) which had been canceled, New and Renewable Energy Authority
(NREA) the responsible entity for Renewable energy, The Electric Utility and
Consumer Protection Regulatory Agency, Hydropower Project Authority, Nuclear
Power Plants Authority, Atomic Energy Authority, Nuclear Materials Authority.
1.3.2 The Ministry of Petroleum (MOP)
The main strategy of Ministry of Petroleum is supporting oil and gas reserves and
increasing their production, meeting the local demand of oil, gas and petrochemicals,
supporting the exports and increasing Egypt's income from foreign currency and the
state's treasury. In 2000, the ministry of petroleum adopted an integrated strategy, the
most important mechanism to implement it is to develop and amend the structure of the
Egyptian petroleum sector through separating the activities of the natural gas and
petrochemicals from the activities of the Egyptian General Petroleum Corporation, and
establishing a strong entity for each of them, in addition to focusing the attention on
Upper Egypt through establishing an independent entity. After adding the activities of
the mineral resources to the duties of the ministry of petroleum and establishing the
Mineral Resources Authority on the 14th of October 2004, the petroleum sector now
consists of five strong entities cooperating and integrating to make the best use of
petroleum and mineral resources wealth. They are: The Egyptian General Petroleum
Corporation, The Egyptian Natural Gas Holding Company, The Egyptian
Petrochemicals Holding Company, Ganoub El-Wadi Holding Company and The
Egyptian Mineral Resources Authority, [4].
1.3.3 Supreme Council of Energy (SCE)
The Supreme Council of Energy (SCE) considered as the highest policy making
authority in the energy sector in Egypt, it was established in 1979 by the Prime
Minister's decree, No. 1093/1979. The decree defines SCE responsibility as short and
7
long-term energy planning reporting directly to president. Membership of the council
includes ministers of petroleum, electricity, industry, water supply, transportation and
housing; however, the council undertakes very limited activities and has thus presently
no importance for the decisions in the energy sector.
1.4 Energy PolicyThe energy policy is mainly prepared by The SCE. The main structure of it consists of
the ministers of electricity and petroleum, with consultations in the parliamentary
committee for industry and energy. Egypt's policy aims to increase the use of
renewables with in part by environmental considerations, and in part by an interest in
diversification of energy supply. Moreover, in Sept. 2006, the direction for using
nuclear technology to generate electricity and increase dependence on RE has been
announced by the ruling National Development Party, but still up to now the real
construction of the power plan postponed due to more safety.
The energy policy in Egypt focuses on the following;
- Enhancement of natural gas utilization,
- Adjustment of energy price and removal of subsidies,
- Energy conservation and efficient energy use,
- Promotion of renewable energy utilization.
There was an agreement in June, 2004 between the Ministry of Petroleum and the
Ministry of Electricity and Energy had been signed and established the “Renewable
Energy Fund, REF”. The REF aims to support the renewable energy resources by
around 0.3 Cent US$/kWh, this amount represent the difference between the prices of
selling N.G. inside and outside Egypt. The methodology behind REF is that, the
production of RE saves the consumption of natural gas in domestic thermal power
plants and also it can be exported, incentives for installing wind farms include
assignation free of charge lands, and exempting imported equipment from the Tax
Tariff. For solar heating systems there is a domestic standard code, meanwhile for wind
8
turbines and PV systems international codes; e.g. DIN, Germanschier Loyed, and IEC
are applied, [5].
The strategy for the electricity generation based on diversifying energy sources of
production, rationalizing the use of energy and expanding use of renewable energy
sources as a component of energy provision. The strategy, which was approved in
February 2008, aims to: Contribution of renewable energies by 20% of the total
electricity generation by the year 2020. The share from the grid-connected wind power
is 12% of the total electricity generation, i.e., reaching more than 7200 MW grid-
connected wind farms while the remaining will be from mainly hydro 4% and solar
energies 4%.
1.5 Energy Situation in Egypt
1.5.1 Oil
Crude oil is located in the Gulf of Suez, Sinai and western desert and recently
exploration activities have extended to southern Egypt and the east of Oweiynat.
Egypt’s proven oil reserves stand at 4.4 billion barrels, an increase from 2010 reserve
estimates of 3.7 billion barrels, according to the Oil and Gas Journal’s January 2011
estimation. The total oil production in Egypt averaged 660,000 (bbl/d), of which
approximately 540,000 bbl/d was crude oil, in 2010. Crude oil production continues its
decline, despite the new discoveries and enhanced oil recovery (EOR) techniques at
mature fields. At the same time, natural gas still increase in production due to new
fields production liquids and lease condensates which have offset some of the declines
in total oil liquids production.
The total estimation of Oil consumption is about 710,000 bbl /d, which slightly higher
than production and makes gap. To cover the gap with the increase of domestic demand
growth, oil imports are expected to continue with some refined product exports in the
short-term.
9
The government direction is to gradually lifting subsidized prices and targeting
subsidizes more effectively to reduce the demand growth of oil, despite this is a
politically and socially very sensitive issue that will be difficult to fully implement, [6].
Figure 1-1: Egypt’s Oil Production and Consumption 1990-2010, source EIA
1.5.1.1 Exploration and Production
There are mainly five areas for the production of the Egyptian oil: the first and more
effective is the Gulf of Suez and the Nile Delta but also the Western Desert, the Eastern
Desert, and the Mediterranean Sea. Most of the fields are mature, relatively small that
are connected to larger regional production systems. The Overall production of the old
fields especially the Gulf of Suez is in decline. However, these declines have been
compensated by small yet commercially viable discoveries in all producing areas, [6].
10
1.5.1.2 Exports
Egypt registered exports of crude oil about 145,000 bbl/d in 2010, although it is a net
oil importer. These exports went to India (50,000 bbl/d) as the first level, followed by
Italy (29,000 bbl/d), and the United States (16,000 bbl/d). The remainder of Egypt’s
crude oil exports went to other European countries and Asia, [6].
1.5.2 Natural Gas
The production of natural gas in Egypt is expanding rapidly with production
quadrupling between 1998 and 2009. The natural gas reserves stand at 77 trillion cubic
feet (Tcf), an increase from 2010 estimates of 58.5 Tcf and the third highest in Africa,
according to the Oil and Gas Journal 2011. In 2009, Egypt produced roughly 2.3 Tcf
and consumed 1.6 Tcf. Egypt will continue to be one of the most an important supplier
of natural gas to Europe and the Mediterranean region.
Figure 1-2: Egypt’s NG Production and Consumption 1990-2010, source EIA
11
In 2009 the electricity sector accounted for the largest share of natural gas consumption
(54 %) using mainly in electricity generation, followed by industrial sector (29 %)
according to Cedigaz. While still using natural gas in transportation sector through the
use and development of compressed natural gas vehicles and fueling stations a
relatively small share. For residential consumption and business use, the government is
encouraging the use of natural gas as a substitute for petroleum and coal. The World
Bank approved loans for the Natural Gas Connections Project, in January 2008 which
solve the problem of using liquefied petroleum gas (LPG) to natural gas through
investment in new connections and to further expand natural gas use in densely
populated, low income areas, [6].
1.5.2.1 Exploration and Production
In the Egyptian natural gas sector exploration and production activities continue its
growing. While there have been marked decreases in the production of natural gas
associated with oil extraction, new finds of non-associated gas fields combined with
growing domestic demand and export capacity, are increasing interest. Most industry
analysts place Egypt’s natural gas production on an upward trend in the short- and
medium-term despite the existing limitations to the sector’s growth. To promote
exploration in the more expensive deep-water offshore, the Egyptian government
revised pricing policies by agreeing to pay more for natural gas produced in these areas,
assuring continued international interest in developing these potential resources. Over
80 % of Egypt’s natural gas reserves and 70 % of production is in the Mediterranean
and Nile Delta but exploration and production continue in all major hydrocarbon rich
areas including the Western Desert.
Natural gas is locally distributed by Egypt Gas, City Gas, Natgas and Nile Valley Gas
Company. It is planned to supply natural gas to 2.5 million housing units by the end of
the 4th five years plan in the year 2002. It is expected that the demand on natural gas
will increase to 28, 36 and 52 billion m3 in 2002, 2007 and 2017, respectively, [6].
12
1.5.2.2 Exports
The exporting of natural gas began in the mid-2000s after the completion of the Arab
Gas Pipeline (AGP) in 2004 and the startup of the first three LNG trains at Damietta in
2005. Egypt exported about 650 billion cubic feet (Bcf) of natural gas in 2009, around
70 % of which was exported in the form of LNG and the remaining 30 percent via
pipelines, [6].
1.6 Electricity situation in Egypt
The power generation in Egypt is characterized by a prevalence of natural gas as the
main fuel, the absence of coal, as well as rather low generation losses (Fig 1-4) due to
significant hydro-power and a substantial capacity of efficient combined cycle (CC)
natural gas plants. This structure results in a rather low grid greenhouse gas (GHG)
emissions factor of approximately 0.5 kg CO2/kWh. The total losses due to on-site
consumption and the transmission and distribution system account for approximately
15% of gross production.
The plan will change when the ambitious plan of electricity generation expanded and
almost triple 2007 capacity by 2022, the fuel mix will become more unbalanced in the
power sector. According to this plan, most new capacity would be natural gas combined
cycle and steam turbine plants, the latter also being capable of using heavy fuel oil, [7].
13
Figure 1-3: fuel input and electricity generation in power plants in Egypt, in Mtoe (EEHC).
The Egyptian electrification rate in 2008 was approximately 99.4 %, according to the
International Energy Agency (IEA); this rate is among the highest in Africa with a 100
% urban access to electricity and 99.1 in rural areas.
The total installed capacity of electricity reached to be about 24.7 GW with total
generated electricity about 139000 GWh at the year 2009/ 2010, 21.4 GW of which was
conventional thermal generation capacity, 2800 MW hydro power with generated
electricity 12863 GWh and 550 MW of wind energy with total generated electricity
1540 GWh. Current peak demand is estimated to be 22.7 (GW). The rising demand and
ageing infrastructure have led to intermittent blackouts. The summer of 2010
highlighted these problems, as the country experienced rolling nationwide blackouts.
The Egyptian government planning to invest over $100 in the power sector over the
next decades to cover the increase of electricity consumption, and at the same time
seeking financing from external sources. Egypt encourage the privet sector to establish
more power plants and the other international organizations, and renewable energy
14
funds such as the World Bank’s Clean Technology Fund have all provided investment
in the sector. Under existing plans, Egypt hopes to produce 20 % of its electricity from
renewable energy by 2020 while also developing a nuclear power industry, (EIA Feb.
2011).
1.6.1 Conventional Thermal
The thermal power plant is the main player in the electricity generated in Egypt, in
2010, conventional thermal energy sources accounted for 125.5 GWh of electricity
generation, about 89% of the total. Almost natural gas is the main fuel used to produce
this electricity. Existing natural gas subsidies combined with plans to expand gas-fired
generation capacity indicate that the fuel will continue to play an important role in
Egypt’s electricity mix.
1.6.2 Hydropower
Hydro power is considered one of the cheapest and cleanest sources of power
generation. In Egypt, the power generation from hydro resources started in 1960, with
the construction of Aswan Dam to control the Nile water discharge for irrigation. In
1967 the 2.1 GW High Dam hydro power plants was commissioned, followed by the
commissioning of Aswan 2 power plant in 1985 and in cooperation with the Ministry of
Water Resources and Public Works; Isna hydropower plant was commissioned in 1993
and Naga-Hamadi in year 2008. Egypt generated around 14 Bkwh from hydroelectric
resources, the share of hydro generation represents about 9.2% from total generation in
2009/2010, almost all of which came from the Aswan High Dam and the Aswan
Reservoir Dams, (EEHC annual report).
15
Table 1-1: Generated Energy (GWh), source EEHC
Figure 1-4: Development of Hydro Generated Energy (GWh), source EEHC
It’s clear from the above figure (1-5) the decrease of the generated electricity from the
hydropower from 15510 GWh at the year 2007/2008 to 12863 GWh at the year
2009/2010 due to the decrease of the efficiency of the turbines.
16
Table 1-2: Hydro Power Indicators, source EEHC
Table 1-3: Fuel Saved Due to the Use of Hydro Power, source EEHC
the fuel saved by using hydropower energy is estimated to about 2773 Ktoe in the year
2009/2010 which equvelent to about 613 Million EGP.
17
1.6.3 Wind
The renewable energy in Egypt has gained momentum over the last two decades, thanks
to the successful international cooperation and the support of RE from the government.
The New and Renewable Energy Authority (NREA) was established in 1986 as the
national focal point to develop and introduce renewable energy technologies to Egypt
on a commercial scale together with implementation of related energy conservation
programs and investigate technology options through studies and demonstration
projects. Another aim of NREA is to introduce mature technologies into the Egyptian
market and to support the activities of the domestic industry. For the wind energy
technology in Egypt which considered the largest in Africa, since the 1980s, a series of
large-scale grid connected wind energy projects were installed, and 120 MW were
added in 2010, taking the total installed wind capacity to 550 MW, [8].
Year 1999/
2000
2000/
2001
2001/
2002
2002/
2003
2003/
2004
2004/
2005
2005/
2006
2006/
2007
2007/
2008
2008/
2009
2008/
2010
MW 5 5 68 98 145 145 230 310 365 430 550
Table 1-4: Total Installed Capacity of Wind Energy, source Wind Energy Council
1.6.3.1 Operating and planned wind farms in Egypt
Zafarana wind farm
Zafarana wind farm by the Red Sea coast considered the largest farm in Africa; it has
been constructed in stages since 2001, the international cooperation with Germany,
Denmark and Spain shared in financing these farms through a grants. Lastly in 2010,
120 MW of wind capacity were added to Zafarana in cooperation with the Danish
International Development Agency (DANIDA), taking the total installed capacity to
545 MW. The total generated electricity from the wind farm is about 1,147 GWh. The
18
region of the Gulf of El Zayt has an excellent wind regime, there are currently about
1,120 MW at various stages of development in cooperation with Germany, the
European Investment Bank (EIB), Japan and Spain. These include:
200 MW in cooperation with KFW, EU and the EIB. After a tender in 2010, the
contractor is expected to be selected at the beginning of 2011 and the project is
scheduled to start operations by the end of 2012.
220 MW in cooperation with Japan and 120 MW in cooperation with Spain are
in the pipeline.
Further projects in preparation include: 180 MW in cooperation with Spain; 200
MW in cooperation with Abu Dhabi’s MASDAR programme; and 200 MW in
cooperation with Germany, the EU and the EIB, [8].
1. Western Bank of the Nile
200 MW installed capacity are planned on the Western Bank of the Nile in cooperation
with Japan.
2. Gulf of El Zayt
The Gulf of El Zayt region had a good potential of wind with a high speed varies
between 7-10 m/s, the Egyptian government, in cooperation with the World Bank in
May 2009, published an international tender for a wind farm at the Gulf of El Zayt, and
inviting private sector from inside Egypt and international developers to submit their
prequalification documents for the first competitive bid to plan build and operate a 250
MW wind farm. The project will benefit from the conditions outlined above. Following
the tender, 34 offers were received and a short list of ten qualified developers was
announced in November 2009. A second stage of the tender calling for final bids will
be issued mid-2011 and the project is scheduled to start operations by 2014, (World
Wind Energy Council).
19
3. Gulf of Suez
The Egyptian government plans to install about 2,000 MW of wind power in the Gulf
of Suez region, through four stages. A first tender was published in January 2010 for
two projects of 250 MW each, again on a build, own and operate basis and a 20 year
PPA. A second tender for the same amount of wind power – two projects of 250 MW
each - is expected for July 2011, (World Wind Energy Council).
1.6.4 Solar
Egypt has an excellent potential of solar energy which will be suitable for a lot of solar
technologies projects even Concentrating Solar Power (CSP) or Photo Voltaic (PV), the
construction of the first solar thermal power plant at Kuraymat City with total installed
capacity of 140MW and solar share of 20MW, using parabolic trough technology integrated
with combined cycle power plant using natural gas as a fuel. Global Environmental Facility
(GEF) and the Japan Bank for International Development will finance this power plant. The
initial operation of this power plant started at the 1st of July 2011 with estimated total energy
generated of 852GWh/year.
1.6.5 Nuclear
Egypt is also working on developing nuclear power as an energy source. It has a 22-MW
nuclear research reactor at Inshas in the Nile Delta which began operation in 1997. The
Ministry of Electricity and Energy in 2010 approved a 1,200 MW power station at al-Dab’a
which is open to international participation and expected to become operational by 2019 as the
country’s first nuclear power plant. Bidding for the development of this plant was supposed to
have started in early 2011. Three additional plants are planned by 2025, (Source EIA 2011).
20
1.6.6 International Connections
Egypt has established an electric transmission grid with other countries in the region.
The five-country interconnection of Egypt's system with those of Jordan, Syria, and
Turkey was completed by 2002, and Egypt also activated a link to Libya's electric grid
in December 1999.
Gulf Cooperation Council (GCC) Power Grid
The GCC Power Grid project plans to link Egypt to the GCC through Saudi Arabia.
The link is expected to be complete between 2013 and 2015 and will allow the sharing
of 3GW of electricity between the two countries. This project will indirectly expand
each country’s electricity capacity by pulling from each other’s supplies at different
peak hours. Longer-term plans call for broader interconnections that would include
North Africa, the Middle East and Europe, (Source EIA).
21
As conclusion for the energy situation in Egypt, production and consumption and the
reserve of fossil fuels in this table:
Proven Oil Reserves (January 1, 2011) 4.4 billion barrels (Oil & Gas Journal)
Oil Production (2010) 660 thousand barrels per day
Oil Consumption (2010) 710 thousand barrels per day
Refining Capacity (2009) 975,000 bbl/d (OGJ and APS Review)
Proven Natural Gas Reserves (January 1,2011)
77.2 trillion cubic feet (Oil & GasJournal)
Natural Gas Production (2009) 2.21 trillion cubic feet
Natural Gas Consumption (2009) 1.57 trillion cubic feet
Recoverable Coal Reserves (2009) 23.1 million short tons (World EnergyCouncil)
Coal Production (2009) 0.03 million short tons
Coal Consumption (2009) 1.39 million short tons
Electricity Installed Capacity (2008) 23.4 gigawatts
Electricity Generation (2008) 124 billion kilowatt hours
Electricity Consumption (2008) 109 billion kilowatt hours
Total Energy Consumption (2008) 3.2 quadrillion Btus
Total Per Capita Energy Consumption(2008)
41.0 million Btus
Energy Intensity (2008) 7,681 Btu per $2005-PPP**
Table 1-5: Egyptian Energy overview, source EIA
22
2 CHAPTER TOW: ELECTRICITY DEMAND AND SUPPLY
IN EGYPT
“Egypt has witnessed growth in energy demand attributed to demographic trends,
increased industrial production as well as rising penetration of consumer products such
as electric and electronic home devices. In 2008, Egypt has reached a peak demand of
21,500 MW, 23,000 at 2009 and it is expected to reach 54,200 MW by the year 2027.
Moving to the installed electric capacity, it reached around 24,726 MW in 2010,
compared to 23,502 MW in 2009 with variance 5.2%, and to be 20,593 MW in
2005”, [9].The electricity demand increased by 6.7% between 2007 and 2008, and
expected to increases with around 7% annum until 2014 as a result of increasing the
electricity demand in the industry, agriculture and tourism largely as a result of rising
demand from the residential and commercial sectors, [10]. The key technological
option for fostering this high increase in demand is the direction of renewable energy
and energy efficiency. Rather than the burning of fossil fuels energy reserves
considered a spurious industrial competition that has no future, especially with a
country like Egypt gas a limited resources, by applying these programs it could build on
its engineering and industrial base and become a competitive player and regional leader
in the “new” energy economy of the 21st century.
2.1 Energy Demand Scenarios for Egypt
2.1.1 Energy Consumption
The indications of energy balance in Egypt for the year 2007 referees that the industrial
sector energy consumption was the largest share sector with about (34.2 %), followed
by transportation (24.2 %), residential (18.8 %), and agriculture and mining (4.7 %)
together accounting for 81.9 % of total consumption. On the other hand the energy
consumption by the fuel type, oil products account for (54.1 %), followed by natural
gas (20.6 %), and electricity (18.3 %) together comprising 93 % of total demand. The
23
remainder is non-energy use. Energy transformation for the internal market occurs
mainly via oil-refining activities, natural gas treatment, and power generation (hydro
and thermal). Natural gas (56.2 %) and oil (38.2 %) account for the bulk of primary
energy supply, representing 94.4 % of the total. The rest is mainly electricity, generated
with hydropower (3.9 %, according to IEA methodology) and other primary sources
(1.7 %), [11].
Figure 2-1 Share of Egypt’s Total Energy Consumption, by Sector, 2007, source Francisco Figueroa de
la Vega,
24
Figure 2-2: Share of Egypt’s Total Energy Consumption, by Fuel Type, 2007, source FranciscoFigueroa de la Vega
Figure 2-3: Share of Egypt’s Total Primary Energy Production, by Source, 2007, Francisco Figueroa de la Vega
25
2.1.2 Drivers of Energy Demand
There are several major factors contributing to the rapid growth in Egypt’s energy
demand, these factors including population growth, economic growth, and increased
motorization. We have to take these in our consideration to understand the present and
future dynamics of Egypt’s energy economy.
2.1.2.1 Population
Egypt is considered to be one of the populous countries in Africa and the Arabic
Region; it is estimated to be around 82,079,636 million people with growth rate 1.96%
(2011est.)[12], but the growth rate is expected to slow in the future, at a rate of 1.56 %
for 2030 as shown in fig (2-3) .
Figure 2-4: Historic and Future Population Trends in Egypt, 1990–2030, source Francisco Figueroa de
la Vega,
26
2.1.2.2 Economic Development
Egypt’s GDP witnessed a real increase of 5.0 % annually during 1993–99, which was
similar to the average growth rate of 5.2 % annually during 2000–07, and reached to be
5.3% in 2010. The evaluation of the real per capita growth has been positive
throughout the last two decades. According to the study of Francisco Figueroa de la
Vega, JCEE and GTZ, there are two future economic growth scenarios:
The first scenario is called business-as-usual (BAU) scenario for GDP in 2007–
30, which depends on assumption of a constant increase of 3.1 % year, or
roughly half the per capita GDP growth of the past. This scenario also assumes
that Egypt will pull out of the current economic crisis relatively slowly.
The second scenario is called high economic growth (HEG) scenario, which
depends on assumes that the economy continues to grow dynamically, at an
average annual rate of 4.5 %, on the basis that Egypt will implement important
investments in economic and social infrastructure that stimulate the internal
market for goods and services and for the domestic labor force.
There is no significant change in the economic growth by sector up to 2030; only a
modest increase in agriculture and mining, there will be a higher growth in industry
and slight reduction in commerce and construction growth. Nevertheless, there will
be an increase in economic activity in all sectors in terms of real GDP growth, [11].
27
Figure 2-5: Egypt’s GDP Growth, Two Scenarios, 1993–2030, Source: Francisco Figueroa de la Vega
Figure 2-6: Egypt’s Real Per Capita GDP, 1993–2030, source: Francisco Figueroa de la Vega,
28
Figure 2-7: Egypt’s Economic Growth by Sector, 1993–2030, Source: Francisco Figueroa de la Vega
Figure 2-8: Egypt’s Economic Growth by Sector, 1993–2030, Source: Francisco Figueroa de la Vega
29
2.2 Electricity Market Design
2.2.1 Background
The Egyptian electricity was introduced as the first time in the late of 19th century. And
since that time, the network of electricity has grown to supply and cover all the
locations in Egypt and rural areas to reach about 99.4% according to the estimation of
2008. The electricity sector market for the first time was totally in private hands. Then
after the revolution of 1952 the sector was nationalized. The competitive form is the
main change of the electricity market with applying the new the new electricity law
which has been prepared and will be ratified from the people’s assembly next elections.
The complete sector mostly owned by the government and the responsible entity is the
Egyptian Electricity Holding Company (EEHC) which manages the portfolio on behalf
of the government, and the sector activities were separated into generation, transmission
and distribution activities.
2.2.2 Present Status of Electricity Market
The present market status of electricity in Egypt is considered a monopoly market,
mainly consists of a single buyer form. Because of this we can find all generation
companies, including the four generating companies with their thermal power plants,
the three private BOOT projects, a wind farm sell their product to a transmission
company. The transmission company in turn is the responsible entity to sells the
electricity to all the customers and the nine distribution companies. Because of this
system of monopoly the market does not allow free competition among incumbent
generation companies, [13]. However, it’s the direction of the government towards the
establishment of a real liberal electricity market and builds a new system for a new
market. The Egyptian Electricity Holding Company “EEHC” owns about 90% of the
market electricity generation with installed generation capacity, and the three private
BOOT projects contribute with 9% of the installed generation capacity, when the last
30
1% is made of the present wind farms and small isolated units. The Egyptian Electricity
Transmission Company “EETC”, which considered the Single Buyer is the only
company licensed for EHV and HV electricity transmission, purchases electrical energy
from all generation companies and sells the electrical energy to:
the present nine distribution companies (23 million consumers),
the present 81 EHV and HV consumers, and
The seven private distribution companies (less than1% of the market).
Furthermore, EETC is exchanging energy with neighboring countries over the present
interconnections, [14].
Figure 2-9: Structure of the EEHC, source H. El Salmawy
31
Figure 2-10: Power sector structure, source H. El Salmawy
2.2.3 The Proposed Electricity Market Structure
The direction of the energy sector is to liberate the electricity market; the proposed
electricity market will be harmonized with the present practices in the EU. To that end,
to reach to the final situation, we have the transitional market which will be composed
of two submarkets working in parallel:
A competitive market where eligible consumers enjoy the liberty of choosing
their electricity supplier (outside and inside the regulated market);
A regulated market for non-eligible consumers.
The regulated market should gradually contract to the account of the competitive
market up to the point where the whole market is fully competitive.
Wind
32
Figure 2-11: The proposed Electricity Market Structure
2.2.3.1 The regulated market (single buyer model)
In the regulated market, like the current market, non-eligible consumers shall purchase
their electricity needs against a regulated tariff approved by the regulatory agency. The
government which owned companies is responsible for satisfying the needs of non-
eligible customer class. The prices of this class are sold at the regulated price on an
economic basis. The private generation entities will participate for satisfying a part of
the market needs in the regulated market. Under the single-buyer market model, the
Transmission System Operator perform the same function it does today, purchasing all
generation, and in turn, selling this power to wholesale customers including the
distribution companies and the EHV and HV customers directly connected to the
transmission system, [14].
33
2.2.3.2 The competitive market (bilateral model)
The second market model is the competitive market, in this there will be a free market
and every consumers shall have the right to sign a direct bilateral contracts with
present/future generation companies to satisfy their needs of electricity according to the
free competition, the transmission system operator (TSO) shall be responsible for
fulfilling those contracts for a unified transmission access charge proposed by the TSO
and approved by the EEUCPRA, the TSO shall purchase the required balancing energy
to the account of consumers or generator in the case of any deviation from the
quantities specified in the concluded contracts. This enables the settlement of
imbalances between contracted power flows against actual flows (balancing
mechanism) and helps the Transmission System Operator carry out its responsibilities
related to system security, [13].
2.2.4 Tariffs
The tariff will different from the old to new system or market design, currently the
Cabinet of Ministers approves tariffs. In the future, the intention is for the EEUCPRA
to decide on tariffs. Use of Network tariffs do not exist presently.
The history of retail tariffs have been below costs. There have been increases in tariff
levels (up to 7٫5٪ p.a.) Since 2004, to recover operating costs and fuel price rises. In
2006/2007 the government tried to increase the tariff and managed its revenues to at
least cover costs (companies almost broke even) but still these revenues not enough to
provide funds for new investments. The pricing system has substantial subsidies,
natural gas is subsidized as a fuel in the electricity generation and they do not pay taxes
on natural gas, this subsidizing system to encourage its use and achieve environmental
benefits. The categories of using natural gas as of 65٪ of the residential sector is
subsidized, 25٪ breakeven, remaining 10٪ pays above costs. The structure of tariffs
needs to be changed in order to provide the correct economic signals; tariffs are single
rate energy tariffs with some maximum demand charging for certain tariff categories.
34
The proposed change is to increase the charge tariff during the contribution to system
peak separately through a demand charge, this may avoid some of the customers of
consumers to use electricity during the peak and at the same time the investors can
generate electricity at this time to cover the shortage (approx. 1500MW is estimated to
be needed each year to cover the increase in peak demand). This means that the impact
on the high demand customers may not be significant (their average price paid is lower
than the highest tariff that applies to them), [14].
35
2.3 Independent Power Producers, IPPs.
Independent Power Producers or IPPs is the private investment in electricity generation
in grew dramatically in developing countries during the 1990s; now a day IPPs have
developed into a large market through a lot of projects and participate in the electricity
market.
The privet sector participation in the electricity market in Egypt started in 1996, with a
law that laid the foundations for a competitive bidding process for three IPPs that were
awarded in 1998 and 1999. The three projects sell electricity to the Egyptian electricity
holding company under long term contract, EEHC that are backed by a Central Bank
guarantee. The natural gas is used as a fuel in all projects which is provided by the
Egyptian gas monopoly at a substantial discount from market rates. The Egyptian IPPs
are occasionally cited as the most competitive in the world—for example, InterGen’s
(now Globeleq) SidiKrir project bid a price of US$0.0254 per kWh. Turbulence in
Egypt’s IPP arrangements arrived with a 2002 economic downturn and subsequent
devaluation of the Egyptian pound from 3.2 to 6 pounds against the US dollar.
According to the contract between the IPPs and the Egyptian government, all new
power generation projects must secure their own customers, i.e. the state utility will no
longer be the guaranteed buyer of electricity and all foreign currency debt must be
sourced from abroad. The project sample in Egypt contains all three operating IPPs.
These three projects are structured substantially similarly. The only variation exists
along in a few factors. First, SidiKrir was sponsored by a major US power company
(Intergen), while Suez and Port Said were sponsored by the French utility Electricité de
France. Second, SidiKrir obtained debt finance entirely from commercial banks, while
the EdF found few commercial options available and ultimately turned to multilateral
sources (the IFC) for substantial debt financing, [15].
36
2.3.1 IPP frameworks and projects developed
The starting of the IPPs in Egypt was with three generation facilities, built by InterGen
with Edison and EdF, respectively, the total installed capacity is about 2048 MW.
Despite large currency devaluation, there have been no renegotiations of contract terms,
but there has been high equity turnover. As noted by numerous stakeholders, it is
required another framework for the future instead of the current one, the proposed one
will evolve to accommodate future development for additional IPPs in Egypt.
The structure of the current framework which contains the (3 IPPs), BOOT structure -
20 year PPA -EEA/EEHC sole off-taker – (65-70%) take-if-tendered -Backed by
Central Bank Guarantee
When the 2ndframework underdevelopment for the future investment, foreign currency
must be obtained from abroad - local designers, contractors, and manufacturers must
contribute substantially to projects, the local currency must be paid for local costs, bids
with an increased equity-financing stake and a larger local investment component
favored, [16].
2.3.2 IPPs Projects in Egypt
Egypt currently has three IPPs, with a combined capacity of approximately 2,050 MW.
2.3.2.1 Sidi Krir.
Sidi Krir power plant considered the first IPP project in Egypt with total installed
capacity 682.5 MW, and the fuel used is natural gas. In 1996, a competitive bidding
process was generated substantial interest; more than fifty firms were applying for pre-
qualification. The project was awarded in February 1998 to a consortium consisting of
Intergen and Edison Mission Energy from the United States. The winning bid was
US$0.0254/kWh, which was considered the lowest electricity prices for an IPP in the
developing world. The project fired on natural gas that was domestically produced and
37
supplied at a healthy discount by the Egyptian state gas monopoly. Domestic Egyptian
banks provided most of the financing on a project basis; the Project debt is wholly
private, albeit denominated in dollars. International commercial banks provided the rest
of the debt, with no involvement from multilateral or bilateral lenders. The plant is
presently owned by Globeleq, which was spun off the UK’s Commonwealth
Development Corporation (CDC) in 2002. Intergen and Edison Mission sold their
interests in SidiKrir in 2005, apparently as part of global restructuring of their power
business, and not as a reflection of troubles in the project itself, [15].
2.3.2.2 Suez & Port Said.
Egypt’s second and third IPPs are Suez & Port Said, these projects are each 683MW
with natural gas-fired power plants awarded to Electricite de France. The projects were
awarded and developed along substantially similar lines as SidiKrir. EdF sourced its
lending from the IFC and a syndicate of international banks and institutional investors;
this was the significant difference between the two projects. This difference reportedly
reflects the fact that by the time the projects sought financing, Egyptian officials lacked
the appetite to mobilize additional domestic lending for power plants. With European
commercial banks reluctant to invest in what they deemed insufficiently environmental
projects (i.e. plants were for gas-fired steam generators and not combined cycle), EdF
turned to a multilateral, namely IFC to help secure additional debt. EdF, citing its plans
to concentrate its assets in Europe, sold its equity in the plants in 2006; both Port Said
and Suez are presently owned by KusasNusajaya, a subsidiary of the Malaysian firm
Tanjong Public Limited Company, [15].
38
ProjectSize
(MW)
Cost
(US$)
$/
KWhFuel
Contract
type
Contract
years
project
operation
Sidi
Krir682.5 417.8 612.61
Gas fired
steam
generator
BOOT 20 1996 – 2002
Port
Said683 340 497.8
Gas fired
steam
generator
BOOT 20 1998 - 2002
Suez 683 338 494.87
Gas fired
steam
generator
BOOT 20 1998 - 2002
Total 2048.5 1095.8 - - - - -
Table 2-1: Egypt’s IPPs, source Anton Eberhard and Katharine Gratwick
2.3.3 Future IPPs Projects in Egypt
The Egyptian electricity sector plans to develop an Independent Power Provider in
Dairut, Egypt through the Egyptian Electricity Holding Company, Egyptian Electricity
Transmission Company which considered the responsible entity. The purpose of the
project is to meet the increasing electricity needs in the country. The total installed
capacity of Dairut's combined cycle power plant is about 1,500 MW combined cycle
power plant consisting of two 750 MW blocks, each comprising two GTs and one ST,
with a capacity of 250 MW each. The output electricity guarantee form The Egyptian
Electricity Transmission Company (EETC) which will buy it under a PPA over a
period of 20 years. The natural gas will be provided from The Egyptian Natural Gas
Holding (Egas). The secondary feedstock will consist of light oil. The project is
expected to be completed in 2014, [17].
39
2.3.4 IPPs Projects Evaluation
2.3.4.1 Investment Outcomes:
The final evaluation for the IPPs projects in Egypt rated as Positive; there is no major
disruptions in the construction of these projects, the operations during this period or
payment have been reported. The contracts of power sales have weathered a
macroeconomic shock intact, and continue to generate revenue. The only negative
outcome identified was that sponsors for each project had invested at least partly on the
assumption that Egypt would continue to open investment opportunities. Egypt did
have plans to solicit additional projects (up to a total of fifteen IPPs), but reversed
course after the cost of the projects spiraled with the devaluation, [15].
2.3.4.2 Development Outcomes
The evaluation of the rate of development of IPPs projects is Positive, The cost of the
payments to the IPPs have almost doubled with the 2002-3 devaluation of the Egyptian
pound, and Egyptian officials now express some dissatisfaction with the projects as
being too expensive. Nonetheless, because (i) the original bids were very competitive,
(ii) the IPP sector remains small, and payments manageable even if unexpectedly high,
and (iii) electricity is being generated, the experience seems a positive one for Egypt.
Additionally, although the government has turned to state and multilateral sources of
capital for new development, the early IPP investments have been conducted in a
manner that provided valuable experience to the country, and have not unduly
prejudiced the prospects for future investment, [15].
40
3 CHAPTER THREE: NATIONAL RENEWABLE ENERGY
STRATEGY in Egypt
3.1 IntroductionRenewable Energy is one of the most potential measures to meet the challenges of
increasing energy demand and the best solution for securing energy use to the next
generations and the concern of environmental impact and climate change, every country
all over the world build its own strategy according to the available natural resources to
face the energy crisis which may face the world in the few coming years. Renewable
energy offers a promising alternative to traditional energy sources in developing
countries, which may face several constraints in meeting their energy requirements in
future. Most of developing countries have tried to promote renewable energy but till
now their efforts towards renewable energy contribution to the total energy use has not
achieved the targeted as the developed countries. The investment direction still towards
conventional energy technologies and it’s applications, even where commercially
available energy efficient and renewable technologies are technically feasible and
economically attractive, specially wind energy which take an effective steps to become
more economically and commercially. The fact that renewable energy accounts for only
a modest proportion in meeting the world’s commercial energy demand means that
there is a missing link in their potential and their implementation. In the early of
eighties the government of Egypt recognized the importance of renewable energy
sources and formulated a national strategy for the development of energy conservation
measures and renewable energy applications in 1982 as an integral element of national
energy planning. The New and Renewable Energy Authority (NREA) was established
in 1986 to be the focal point for renewable energy activities in Egypt, [18]. In February
2008, the Supreme Council of Energy in Egypt announced the strategy for the electric
power based on diversifying the energy sources of production and rationalizing the use
of energy and expanding use of renewable energy sources as a component of energy
41
provision. The strategy aims to contribution of renewable energies by 20% of the total
electricity generation by the year 2020. The share from the grid-connected wind power
is 12% of the total electricity generation of 31000 GWh. Also, other renewable energy
technologies of hydropower will share by 4% with generated electricity 10333 GWh;
solar energy will share by 4% with total generated electricity 10333 GWh. In the past,
renewable energy development in Egypt has been carried out through encouraging
programs for developing the renewable energy resource, setting up specialized bodies
to implement national renewable energy plans, and promoting business opportunities
for renewable energy projects. Now efforts are being exerted in order to reach total
capacities of 7200 MW and this will be achieved through two main paths: State-owned
projects implemented by the NREA with total capacities of 2375 MW (represents 33%
of total installed capacities). These projects will be financed through governmental
agreements. Private sector projects with total capacities of 4825 MW (represents 76%
of total installed capacities). Policy of increasing the participation of private sector will
include two phases:
Phase I: Adopting Competitive Bids approach as the Egyptian Electricity Transmission
Company will issue tenders internationally requesting private sector to supply power to
build, own, operate wind farms and selling electricity for the company with price
agreed upon between the company and the investor.
Phase II: Application of Feed-in-tariff system, taking into consideration the prices and
experience achieved in phase I, (NREA 2010).
3.2Incentives for the Private Sector
In 26/7/2009, the Supreme Council of Energy has approved the following policies in
order to stimulate and support generating electricity from wind energy:
Approving private sector participation through competitive tender and bilateral
agreements.
42
Reducing project risks through signing long term Power Purchase Agreement,
PPA, for 20-25 years.
The Government of Egypt will guarantee all financial obligations under the PPA.
The selling price for energy generated from renewable energy projects will be in
foreign currency in addition to a portion, covers operation and maintenance
costs, in local currency.
Investors will benefit from selling certificates of emission reduction resulted
from the project implemented.
Evaluation criteria for tenders of renewable energy projects will give privilege
for local components.
Forming mutual committee of representatives from Ministers of Petroleum,
Electricity, Finance and Investment in order to prepare and encourage proposal
against allocating lands to implement wind projects. In 26/5/2010 the cabinet has
approved the committee proposal of encouraging private sector participation
through :
Exempting renewable energy equipment from custom duties.
Obtaining approvals and all the required permits to obtain lands and
clearing it from land mines.
Preparing the studies required for implementing projects such as
environmental, bird migration and soil research studies, (NREA annual
report 2010).
43
3.3Energy Planning Model
This model was designed to calculate the current share of Renewable Energy from the
total electricity generated at the base case year 2009/2010 and the expected electricity
generated up to 2020, and also find if the planned projects of Renewable energy will
cover the targeted of Ministry of Electricity and Energy or will be there a deficit to
achieve this targeted and how we can cover this shortage to fulfill the Egyptian strategy
from Renewable Energy up to 2020.
The structure of this model consists of the input data which will be, the total generated
electricity at the base case year 2009/2010 (139,000GWh) and also the targeted of
Renewable energy share which will be 20% (12% wind, 4% Solar, 4% hydro), the
expected growth rate of electricity according to the previous growth rates and that
expected from the planning side of energy planning according to the increase in demand
and to achieve the targeted of RE up to 2020 (6.4% growth rate), and the data
processing which include the calculations of each technology and it’s generated
electricity, then find the shortage between the targeted and estimated share and how to
cover this shortage, then finally the results or the output which include how much of
Megawatts of installed of each technology to cover the shortage and the possible place
to install these projects.
44
Figure 3-1: Energy Planning Model Components
3.3.1 The Methodology of Data Processing
The energy planning model consists of 6 sheets; each one contains different data and
different technology calculations as follow:
Input Data: Sheet number (6) includes the input data which considered the
targeted to be achieved, according to the Egyptian strategy by 2020 includes
20% sharing of RE (12% wind, 4% solar, and 4% hydro)
Generated electricity forecasting: sheet number (1) includes the calculation to
estimate the forecasting of electricity generated by 2020, reference to the
generated in the year 2009/2010 and with the growth rate 6.4% , which expected
by the energy planning makers
Wind energy scenario: Sheet number (3) includes the calculations of wind
energy, how much generated from the planned projects and the deficit from the
targeted, finally how much GWh needed to cover this shortage. To calculate the
approximate annual energy production by multiplying the capacity factor (RCF)
with the rated power and time period, thus
InputsElectricity generated
2009/2010
Growth rate 6.4%
Targeted share of RE
DataProcessing
Outputs
Shortage
How much to cover
Possible projects
45
Total generated electricity KWh/year = (RCF) * PR KW *8760, (Dr. Sathyajith
Mathew, Springer-Verlag Berlin Heidelberg 2006)
Solar Energy Scenario: Sheet number (4) the calculations of solar energy
including CSP and PV and the generated electricity, the shortage and how much
needed to cover this shortage
PV system: the generating electricity from the PV power plant system calculated
as the equation of how much your Solar PV installation would produce every
year.
Predicted Generation (measured in kWh/year) = kWp x Shading factor x
Irradiance x 0.8, (http://www.uenergysolar.co.uk/domestic-pv/solar).
The KWp is the maximum power that your Solar PV system is able to work at,
based on it functioning under perfect conditions in the lab
Shading describes the proportion of panel which is not receiving full exposure to
sunlight. 1.0 describes a system where no part is shaded, 0.8 when there is slight
shading and 0.6 where there is moderate shading.
CSP system: the generated electricity based on the calculation of the last
feasibility study in Kom Ombo
Hydropower energy: Sheet number (5) hydropower which considered
approximately not constant but decreased by the time due to the efficiency, there
is no effective measures will be taken in this share, no projects planned
Cumulated RE: Finally sheet number (2) which includes the calculations of all
RE and the sum of it and make comparison between the estimated and the
targeted RE
46
The methodology of processing the data depends on the base case information and the
growth rate of energy sector which will lead to the expected target, according to the
calculations of each renewable technology and the generated electricity from the
planned projects to fulfill the announced strategy, and then we compare the generated
electricity from these planned projects with the targeted electricity, if there is any
deficit try to cover it with an expected projects even Wind, Solar or other technology
according to the land and the investment cost, also the sale tariff /kwh to the end user
or the consumers.
Taking in our consideration a suitable uncertainty when comparing the difference
between the targeted and the estimated share of RE
47
3.4 The Current Situation at the Year 2009/2010In the year 2009/2010, the total installed capacity in Egypt was 24726 MW with
electricity generation 139,000 GWh, of which 89 % was delivered by thermal plants
and about 10% from Hydro power with total installed 2800 MW and electricity
generated is about 12863 GWh and 1% from Wind energy with total installed 550 MW
and electricity generated 1542 GWh.
Figure 3-2: current situation of electricity 2009/2010
3.5 The Expected Situation of Electricity By 2020
According to the data analysis and the growth rate of 6.4% the estimated expected
generated electricity according to the calculation of the model, will be 258482.46 GWh
and the estimated sharing of renewable energy will be 20% with total electricity
generated about 51696.492 GWh divided as follow, 12% wind with total generated
electricity 31017.895 GWh, 4% Solar energy with total generated electricity 10339.298
GWh, and 4% Hydro power with total generated electricity about 10339.298 GWh.
89.64%
9.25%1.11%
Thermal
Hydro
Wind
48
When comparing the targeted and the estimated electricity and the share of RE we find
that the targeted wind energy was 31000 GWh when the estimated will be 31017 GWh
with difference about 17 GWh which will be allowed according to the uncertainty limit
with 50 GWh to mention the real targeted.
Figure 3-3: the forecasting of total electricity generated up to 2020
The situation will change completely when we change the expected growth rate
according to the energy demand, so the calculation depends on our expected growth
rate and this percentage 6.4% related to the Egyptian strategy and so they put the
targeted of RE for each technology according to it, so we can expect another growth
rate and investigate the results of each target of RE, to find how to cover this deficit in
this case.
0.00
50000.00
100000.00
150000.00
200000.00
250000.00
300000.00258482.46
The Forecasting Of total Electricity GeneratedGWh, with GR 6.4%
Total Electricity Generated
49
Figure 3-4: Estimate Targeted share of renewable energy up to 2020
The data will be in this section discussed in details, each technology and the
comparison between the targeted and the really estimated according to the prepared
projects and also how we can cover this shortage to its targeted share
0
5000
10000
15000
20000
25000
30000
35000
Wind Solar Hydro
31017.8
10339.2 10339.2
Estemated shared of RE GWh up to 2020
Targeted shared of RE up to 2020
50
3.6 Wind Energy SituationSince the 1980s, a series of large-scale grid connected wind energy projects were
installed in Egypt, the total installed wind capacity till now is 550 MW.
The targeted wind energy up to 2020 is to generate electricity about 31017.89531 GWh,
but when we calculate the planned projects which mentioned by the government to
achieve this target, find there is a shortage, because the total installed capacity will be
7200 MW with a total generated electricity about 22299.89 GWh , these projects will
be in the regions of Hurgada, Zaafarana, Suez Gulf and West of Nile with weighted
capacity factor 35% for all locations which related to the sum of the total capacity of
each location multiplied by the capacity factor of this location and divided by the total
installed, this means the weighted capacity will change according to the added installed
capacity and the location of these projects.
The total generated electricity from the mentioned wind projects represents about
8.63% from the total generated electricity which means the deficit will be about 3.37%
with 8718 GWh,
Location Installed Capacity factor
Hurgada 5 0.15 0.75
Zaafarana 545 0.32 174.4
Suez Gulf 2500 0.5 1250
Western Nile 4150 0.27 1120.5
Total 7200 0.35 2545.65
Table 3-1: The weighted capacity factor
51
From the above information we find that we need about8718 GWh to cove the deficit of
generate electricity from the wind according to the target of 2020.
This means that we have to find other locations to build new projects with a different
weighted capacity factor.
Still, critics often charge that renewable-energy sources require large amounts of land
compared to conventional energy-generation options, also the cost investment for the
renewable projects and the final tariff, We will try to find the available land for the
different proposed renewable projects in Egypt which will be suitable to cover this
deficit in the our targeted
3.6.1 The Land Required For Wind Farms
The required land area for wind power farm depends on the turbines’ spacing and their
configuration. The land required for a GWh of electricity from wind turbines typically
is larger than that needed for the solar-electric cycle. Wind turbines use only 1–10% of
the wind farm areas. The remaining free lands typically are utilized for grazing,
agriculture, and recreation. According to the estimation of indirect land transformation
from two LCA studies for an on-shore wind farm in Denmark. We adopted the
materials and energy inputs given by Schleisner and Vestas along with the Ecoinvent
database. The former source, based on 0.5 MW wind turbine, results in 5.5 m2 /GWh
while the latter, based on 1.65 MW wind turbine, gave 1.84 m2 /GWh assuming a 30-
years lifetime, [19].
3.6.2 The Available Land for Wind Projects
In light of the technical studies, especially wind Atlas, NREA selects sites suitable for
carrying out wind project. Then NREA obtains required approvals from various
authorities to allocate lands to carry wind project, helping the investor to avoid carrying
all the required procedures, not used for other purposes. Land proposed for carrying
wind projects by the private sector is desert areas. In May 10th 2006 Red Sea Governor
52
decree No. 136 for the year 2006 was issued allocating about 656 km2 to NREA to
establish wind farm projects. In May 30th 2009 a presidential decree No. 138 for the
year 2009 was issued to allocate about 1229 km2 at west of Suez Gulf.
In September 17th 2009, a presidential decree No. 319 for the year 2009 was issued
allocating of some lands to implement wind projects. This land is located in Upper
Egypt, West and East of the Nile to governorates of Beni Sueif, Minya, Assuit with
total amount of 6418 km2. The lands will be used according to a usufruct contracts and
to some rules approved by the cabinet, (NREA annual report 2010).
3.6.3 Wind Atlas for Egypt
The Wind Atlas for Egypt is one of the first – and certainly the most comprehensive –
numerical wind atlases ever established. The wind resource over an area of more than
one million square kilometers – much of which consists of mountains and remote desert
tracts – has been determined by two independent methods: a traditional wind atlas
based on observations from more than 30 stations all over Egypt, and a numerical wind
atlas based on long-term reanalysis data and a mesoscale model. The wind atlas allows
for wind resource assessment and siting anywhere in Egypt, and further provides
bankable resource estimates in the most promising regions. The measurement sites were
selected to cover six regions: the Northwest Coast, the Northeast Coast, and the Gulf of
Aqaba, the Gulf of Suez, the Red Sea and the Western Desert. The sites were chosen to
represent the most promising areas for wind energy exploitation, as well as to provide
information on all significant types of wind climatology in Egypt. Logistical aspects
have limited the site selection somewhat as large parts of the Western Desert and
mountainous areas are fairly inaccessible.
It will therefore be useful for decision making, identification of new measurements
sites, planning of feasibility studies and for actual project preparation. In areas where
wind atlas stations are in operation, such as in the Gulf of Suez and along the Northwest
53
Coast, the resource estimates may meet bankable accuracy – though this has to be
confirmed on a project by project basis, [20].
Figure 3-5 : Elevation map of Egypt showing the meteorological stations used for the Wind Atlas for
Egypt. The geographic and Cartesian (UTM) coordinates are referenced to the World Geodetic System
1984. Source: wind atlas for Egypt 2006.
54
Figure 3-6: Mean wind speeds and power densities at a height of 50 m over roughness class 1 (z0 =0.03 m) for the 30 stations in the Wind Atlas for Egypt. Source wind atlas for Egypt
55
Figure 3-7 Wind resource map of Egypt: mean wind speed at 50 m a.g.l. determined by mesoscale
modeling (Wind Atlas for Egypt, 2006).
West of Nile
East of Nile
Gulf of Suez
56
Figure 3-8: offshore wind resource map of Egypt: mean wind speed at 50 m a.g.l. determined by
mesoscale modeling (Wind Atlas for Egypt, 2006).
The Wind Atlas for Egypt confirms the existence of a widespread and particularly high
wind resource along the Gulf of Suez. The Wind Atlas further indicates that the wind
energy resource in large regions of the Western and Eastern Desert – in particular west
and east of the Nile valley between 27°N and 29°N, but also north and west of the city
57
of Kharga – are much higher than hitherto assumed. The mean wind speeds predicted
here are between 7 and 8 ms-1 and the power densities between 300 and 400 Wm-2,
estimated at a height of 50 m a.g.l. There are no meteorological stations for verification
in these regions; however, comparisons elsewhere in the Western Desert of predictions
derived from the mesoscale modeling to those derived from measurements suggest that
the mesoscale model is indeed able to resolve and predict the wind resource in this type
of terrain.
The Wind Atlas for Egypt represents a significant step forward in the application of the
wind atlas methodology in Egypt. Not only does it provide a coherent and consistent
overview of the wind energy resource over the entire land (and sea) area of Egypt, the
results of the mesoscale modeling are further available in a database (numerical wind
atlas) that may be employed directly for detailed wind resource assessments and siting
of wind turbines and wind farms. Utilizing this database together with elevation maps
derived from the Space Shuttle Topography Mission and land-use maps constructed
from satellite imagery, the wind resource and likely power production of a given wind
farm can be estimated in a matter of hours – anywhere in Egypt, [21].
3.6.4 Wind Farm Area Calculator
From the calculated data we find that we need generated electricity about 8718 GWh to
cover the deficit of the targeted which means if we use the location of west and east of
Nile with capacity factor 27%, the weighted capacity factor will be about 33% and so
the total installed capacity needed will be about 3700 MW will be installed in this
region, we can estimate the total land needed for these projects by using the wind farm
area calculator by NREAL with two scenarios
58
The first scenario, when using wind turbine with capacity of 2 MW each
Input Value 3700000 (kW)
Area per turbine 0.25 (Acres)
Size of turbine 2000 (kW)
Table 3-2: Estimated land for wind energy, scenario 1, source NREL web site
The estimated land area required is: 462.5 acres. (1850000 m2), this calculation
assumes 3"700"000 kW and 1850 turbines each requiring an area of 0.25 acres.
The second scenario when using wind turbine with capacity 1 MW each
Input Value 3700000 (kW)
Area per turbine 0.25 (Acres)
Size of turbine 1000 (kW)
Table 3-3: Estimated land for wind energy, scenario 2
The estimated land area required is: 925 acres. (3700000 m2)
This calculation assumes 3"700"000 kW and 3700 turbines each requiring an area
of 0.25 acres.
Note: This value represents the area taken out of production on a farm.
The area within the perimeter of the wind farm will be larger due to spacing
of the turbines, but is still useable by the farm.
Typical turbine spacing in wind farms is placing the towers 5 to 10
turbine diameters apart, depending on local conditions, [22], [23].
59
From the above information we can find that the region East and west Nile, we need
total area 462.5 acres (1850000 m2), to install a total capacity of 3700 MW wind energy
with a capacity factor of 27%, so we can cover the shortage.
3.6.5 Repowering of wind turbines
The suggested option also to cover this deficit is to repowering the wind farms in the
highest capacity factor regions, like Suez gulf and especially in the old wind farm in
Zafarana, we can use a wind turbine with capacity of 1.5 MW or 2 MW instead of 850
KW, which means we will double the generated electricity. The expression
“Repowering” refers to power plant in general and includes all measures which
improve the efficiency and capacity by means of retrofit to the latest technology.
Considering a coal power plant, repowering could mean to install a new steam
generator or a new turbine. Possible modifications on wind turbines are limited, thus
repowering affects the whole plant in general and essentially the entire wind farm. In
short, aim of the repowering is to use the existing renewable energy resources on site
more efficiently, respectively in a technically adapted or improved manner. Progressing
technology provides the option for operators to improve the profitability of their site, or
to cope with new technical or legal conditions. Frequently planned and often locally
supported is to restore the landscape. The reduction of the number of plant is linked
with a significant growth of hub heights and a reduction of the rotational speed.
Presently, the individual capacity of a wind turbine has advanced enough to fulfill the
initially formulated aim of doubling the capacity and reducing the number of plant by
50. The 2 MW turbines class and upward emit considerably less noise and comply with
the actual grid code to feed in larger capacities, [24].
60
3.7 Solar Energy Situation
The total solar power plant according to the Egyptian plan is the solar power plant in
Kuraymat with total installed 20 MW and generated electricity about 33 GWh, and the
solar power plant in Kom Ombo, 40 km North of Aswan and 150 km South of Luxor
with total installed capacity about 100 MW and generated electricity 256 GWh, so the
total generated electricity from concentrated solar power CSP will be 289 GWh.
On the other hand the planned projects for photovoltaic technology is about 40 MW
will be installed in Kom Ombo with total electricity generated about 77 GWh grid
connected electricity.
The total electricity generated from the solar power will be 366 GWh which considered
only about 0.14% from the targeted solar power by 3.86% with total electricity
generated about 9973 GWh deficit from the total 10339 GWh.
Because of the perfect location of Egypt which considered one of the Sun Belt countries
and the Egypt has a high potential of solar energy can cover any deficit in the future but
still the main barrier for introducing solar thermal power technology CSP are the large
initial investment and the inefficiency of the Egyptian electricity sector. Public utilities
are reluctant to charge higher electricity tariffs from their customers, and thus follow
mainly a business as usual approach, in many cases even making losses on conventional
electricity tariffs.
61
Figure 3-9: Solar Atlas of Egypt, source NREA annual report 2010
3.7.1 Solar Atlas
The Solar Atlas in Egypt was issued in 1991, indicating that Egypt as one of the sun
belt countries is endowed with high intensity of direct solar radiation ranging between
1970 to 3200 kwh / m2 / year from North to South. The sunshine duration ranges from
9 - 11 hours with few cloudy days all over the year and total sunshine hours varies
between 3200- 3600 hours/year, [NREA 2010]. The solar atlas of Egypt refers to a huge
suitable land for solar power plants including CSP or PV, Many studies have been
established to investigate, evaluate and asses the suitability of sites for implementation
and development of a CSP or PV power plants.
62
3.7.2 EM Power Program, Country visit Report
The EM Power study by the United Nations Environment program (UNEP), German
Ministry of Economic cooperation and Development (BMZ), which made a visit study
to about 13 places to investigate, evaluate and asses the suitability of sites for
implementation and development of a CSP or PV power plants and asses usable area to
determine the potential size of the power plants.
The final results of this study visit included the estimation of the suitable land, the
direct normal irradiation and the global horizontal irradiations and finally the
recommended projects for this area according to the land qualifications, [25].
63
Site name: Solar resources Used land Recommended projects
Abu Simbel DNI: 1980 KWh/m2a
GHI: 2100 KWh/m2a
500 * 500 m2
800 * 1500m2
10 MW PV
50 MW CSP (no TES)
30 MW CSP (with TES)
Toshka DNI: 2100 KWh/m2a
GHI: 2150 KWh/m2a
2 * 20 Km2 Up to 1600 MW PV
1000 MW CSP (with TES)
Toshka
15 KM
DNI: 2100 KWh/m2a
GHI: 2150 KWh/m2a
3 * 4 Km2 Up to 300 MW CSP (with TES)
Kom Ombo DNI: 2500 KWh/m2a
GHI: 2280 KWh/m2a
1.5 * 5 Km2 200 MW CSP (with TES)
Esna Edfu DNI: 2430 KWh/m2a
GHI: 2240 KWh/m2a
1 * 2.5 Km2 60 MW CSP (with TES)
Marsa Alam DNI: 3370 KWh/m2a
GHI: 2570 KWh/m2a
1000 * 2000 m2 Up to 100 MW CSP (with TES)
50 MW CSP with 10 h TES or
80 MW PV
Quseir Resory DNI: 3350 KWh/m2a
GHI: 2550 KWh/m2a
2*(1000*2000 m2) Up to 100 MW CSP (no TES)
50 MW CSP (10 h TES)
80 MW PV
West of Safaga DNI: 3300 KWh/m2a
GHI: 2520 KWh/m2a
500 * 300 m2 Too small for CSP
South of Safaga DNI: 3250 KWh/m2a
GHI: 2490 KWh/m2a
500 * 500 m2 10 MW PV
NREA Wind
park at Hurgada
DNI: 3110 KWh/m2a
GHI: 2410 KWh/m2a
1000 * 500 m2
500 * 700 m2
500 * 200 m2
Up to 15 MW CSP and up to 20
MW PV
Kuraymat
Extension
DNI: 2000 KWh/m2a
GHI: 2010 KWh/m2a
800 * 700 m2
200 * 1000 m2
10 MW CSP or 22 MW PV
8 MW PV
Farafra Oasis site GHI: 2000 KWh/m2a 900 * 900 m2 Up to 35 MW PV
Siwa Oasis site DNI: 2464 KWh/m2a
GHI: 2249 KWh/m2a
Not feasible
Table 3-4: Proposed lands suitable for solar projects, source Em Power, country visit
64
The conclusion of the above table refers to the total recommended projects are
estimated as 1863 MW installed capacity of PV and about 1935 MW installed capacity
of CSP.
The Kom Ombo site is a barren land located at N24.62° and E32.89° at the b order of
the village Faris, Kom Ombo, and about 40 km North of Aswan and 150 km South of
Luxor. Access to the site is through a paved road connecting Kom Ombo to the desert
highway Aswan-Luxor. Grid connection to the site will be through a substation (to be
constructed) connecting to a medium voltage line (66 kV) 1 km away from the site. The
total available land for CSP plant is approximately 750 hectares (750 * 104 m2). The
site is flat though slightly sloping to the East. The soil is compacted sand-gravel
sediments. Minor leveling will be required to prepare for flat collector fields. Several
meteorological data sources have been analyzed and compared. For the study the data
set generated with the Metronome database has been used. It shows an annual sum for
direct normal irradiation (DNI) of 2516 kWh/m2 for the site. The monthly DNI data of
the site shows some seasonal variations, [26].
CSP Description
Installed
Capacity
MW
Generated
Electricity
GWh
Capacity
factor
expected
installed
capacities
Generated
Electricity
Solar only 100 256 29.20% 2403.906 6154
Solar + 10% Auxilary
heating 100 281 32.10% 2190.035 6154
Solar + 6 Hours storage 50 195 44.50% 1577.948 6154
Solar + 8 Hours storage 50 263 51.40% 1169.961 6154
Solar + 12 Hours
storage 50 283 64.60% 1087.279 6154
Table 3-5: expected electricity generated from Kom Ombo, source PFC of Kom Ombo
65
3.7.3 CSP+D potential in Egypt “SolarPACES”
The main objective of this project is the assessment of concentrator power plant and
Desalination Potential in the MENA Area. Provide development of an implementation
strategy for the adoption of solar disinfection of drinking water as an appropriate,
effective and acceptable intervention against waterborne disease for vulnerable
communities in developing countries without reliable access to safe water, or in the
immediate aftermath of natural or man-made disasters.
One of the most important tasks of this project is the estimation of the solar resource
potential in the Egypt coastal strip using satellite images, the study done by the Spanish
company “IrSOLaV” in the framework of the activity “Assessment of CSP+D potential
in the MENA area” of SolarPACES.
It includes Yearly sums of global horizontal (GHI) and direct normal irradiance (DNI)
are calculated in all the Egypt coastal strip distributed with a mean distance of 5km
from the sea and separated between each other with a spatial resolution of 5km.
66
Figure 3-10: Egypt coastal strip in the Mediterranean Sea in red color, source IrSOLaV study
Figure 3-11: Elevation profile of the Egypt coastal strip in the Mediterranean, source IrSOLaV study
67
Figure 3-12: Egypt coastal strip in the Red sea in red color, The red line inland corresponds to the Egypt
border drawn by Google Earth, source IrSOLaV study
Figure 3-13: Elevation profile of the Egypt coastal strip in the Red sea, source IrSOLaV study
68
The results of this study is presented in an excel sheet containing yearly sums of global
horizontal and direct normal irradiance (kWh/ m2/ year) and yearly averages of
temperature (OC). In general terms, the dynamic of yearly solar radiation can be divided
in two main zones.
The Mediterranean Sea zone shows the yearly DNI results for each site. The range
oscillation is at 1854 to 2247 kWh/ m2/ year, [27].
Figure 3-14: DNI results of the Egypt coastal strip in the Mediterranean Sea, source IrSOLaV study
The Red sea zone shows the yearly DNI results for each site. Overall, the DNI values
show higher mean than the results for the Mediterranean zone. The minimum value is
2082 and the maximum 2611 kWh/ m2/ year. In this zone, there is higher variability
than in the Mediterranean cost due to the abruptness of the terrain, [27]
69
Figure 3-15: Elevation profile of the Egypt coastal strip in the Red sea, source IrSOLaV study
The study of “ASSESSMENT OF CSP+D POTENTIAL IN THE MENA AREA” has
been carried out considering the location of Port Safaga (Red Sea, Egypt), with an
estimated yearly DNI of 2496 kWh/m2. Considered distance from the sea is between 2
and 5 km. This last figure is the maximum distance to the sea to consider suitable the
facility. 50 MWe and 40520 m3/day have been considered as net power and water
production respectively, and 58ºC (0.18 bar abs) as the exhaust steam outlet turbine
conditions.
When all Egyptian coasts are analysed, in the Mediterranean strip and considering
radiation and orographic constrains, the 25% of the coast (900 km) can be considered
suitable to combined solar power and desalination facilities. In the case of the Red Sea
(1550 km), the estimated percentage is about 40 %. If 50 MW solar power plants +
40000 m3/day desalination facilities are considered at 20 km distance interval
70
(reasonable distance to provide power and water to nearby locations), the estimated
number of suitable CSP+D units in the Mediterranean Egyptian and Red Sea would be
11 and 31, respectively. This would means about 2.1 GW of installed power and 1.7
Hm3 of installed desalination capacity. [28]
So that we have the perfect land to install and generate the needed electricity from the
solar and more than the targeted, but still the main barrier is the investment cost of these
projects
71
3.8 The complete evaluation for the targeted plan
After making these data analysis for each technology and its share from the total
electricity generated by the year 2020, we have to evaluate the situation and From the
above technologies we find that the planned projects will not satisfy the targeted plan
there is a gap between the targeted and the estimated electricity according to the real
projects, the total targeted electricity from the renewable is about 51696.492 GWh,
when the estimated electricity is about 35528.694 GWh, which considered 13.75%
from the total expected generated, it means we need to generate 16167.798 GWh from
the renewable to achieve the targeted plan by 2020.
This will be possible to cover this deficit by more projects in the proposed land even for
wind farms or solar power plants.
Targeted Strategy by 2020 GWh
Wind Solar Hydro
31017.89 10339.29 10339.29
Table 3-6: Targeted Strategy by 2020
Real Projects planned GWh
Wind Solar Hydro
22299.89 365.80 12863.00
Table 3-7: Real projects
72
Shortage GWh
Wind Solar Hydro
8718.00 9973.49 -2523
Table 3-8: shortage from the targeted and planned projects
Figure 3-16: Comparison between the planned targeted and the estimated planned projects GWh
0
5000
10000
15000
20000
25000
30000
35000
Wind Solar Hydro
31017.89531
10339.29844 10339.29844
22299.894
365.800
12863.000
Planned up to 2020 estimated projects
73
4 CHAPTER FOUR: ECONOMIC AND FINANCIAL
EVALUATION
In this section an evaluation for economic analysis for the energy resources and
the investment costs of the future projects to cover the demand, as the result the
expected tariff of electricity which will be generated from the different
resources.
The evaluation depends on the data collection from global market and the
worldwide investment cost of these technologies projects, also according to the
estimated prices from the different feasibility studies which prepared in many
projects in Egypt even in wind or solar energy projects
4.1 Renewable Energy Market and Industry Highlights
The global market of the renewable energy technologies witnessed a fast growth during
the last few years, or a fast review of the global market of the most used renewable
technology (wind, CSP, and PV), the total installed all over the world and the total
investment cost of each of them which will be related to the Egyptian market and the
project’s cost even in wind and solar energy power plant.
The total investment in renewable energy reached $211 billion in 2010, up from $160
billion in 2009, continuing the steady annual increase seen since tracking first began in
2004. Including the unreported $15 billion (estimated) invested in solar hot water
collectors; total investment exceeded $226 billion. An additional $40–45 billion was
invested in large hydropower.
Asset finance of new utility-scale projects (wind farms, solar parks, and biofuel and
solar thermal plants) accounted for a record $128 billion in 2010, almost 60% of the
total and was the largest investment asset class. Wind power dominated the utility-scale
asset finance sector (70%), with $90 billion invested in projects, a 33% rise over 2009.
74
Large-scale solar power plants represented the second largest sector under utility-scale
asset financing, at $19 billion in 2010. This was about 5% higher than the financing
secured in 2009, although still below the 2008 record of $23 billion due to the sharp
decline in PV panel prices. Investment in small-scale distributed generation projects
(mainly solar PV) amounted to $60 billion and accounted for more than 25% of total
investment in renewable energy. For the first time, investment in renewable energy
companies and utility scale generation and biofuel projects in developing countries
surpassed that in developed economies. China attracted more than a third of global
investment during 2010, making it the leader for the second year in a row.
The total installed capacity of wind energy is about 198 GW by the end of 2010, The
PV industry had an extraordinary year, with global production and markets more than
doubling in 2010. An estimated 17 GW of capacity was added worldwide (compared
with just under 7.3 GW in 2009), bringing the global total to about 40 GW, the CSP
market has come back to life with nearly 740 MW added between 2007 and the end of
2010. More than half of this capacity was installed during 2010. Parabolic trough
plants continued to dominate the market. Dramatic reductions in PV costs are
challenging the growing market for CSP, at least in the United States, where several
planned projects were redesigned to use utility-scale PV technologies. At the same
time, project development is moving beyond the U.S. southwest and Spain to other
regions and countries, particularly the MENA region, [29].
4.2 Economic and Financial Evaluation for Wind Projects
The economic situation of wind energy considered the most promised in the
commercial way and under specific conditions, onshore wind energy is competitive
with newly built conventional power plants today, for example where the carbon cost is
effectively internalized, the resource is good, and conventional generation costs are
high, as in California. In Europe, with a stable, meaningful carbon price under the
European Emission Trading System, competition with newly built coal plants would be
75
possible at many sites. However, the competitiveness is not yet the rule, and reduced
life cycle cost of energy (LCOE) from wind is the main primary objective for the wind
industry. Therefore, the achievement of competitiveness with conventional electricity
production as a key goal, which is necessary so that market forces can be more heavily
relied upon to incentivize investment in new wind power deployment, [30].The main
parameters affecting the governing wind power economics include the following:
Investment costs, including auxiliary costs for foundation, grid-connection,
and so on.
Operation and Maintenance (O&M) costs.
Electricity production/average wind speed.
Turbine lifetime.
Discount rate.
Hence, from these the most important parameters are the wind turbines’ (WT)
electricity production and their investment costs. As electricity production is highly
dependent on wind regime conditions, choosing the right site is critical to achieving
economic viability, [31].
4.2.1 Investment costs
The investment cost of wind energy generation according to the reports in 2008 for the
installed projects in the European land ranged from USD 1.45 to USD 2.6 million/MW
(EUR 1 to EUR 1.9 million). This cost will different in other locations like n North
America, investment costs ranged from USD 1.4 to USD 1.9 million/MW (EUR 0.98 to
EUR 1.3 million); and in Japan from USD 2.6 to USD 3.2 million (EUR 1.8 to EUR 2.2
million) (IEA Wind, 2009). Costs in India and China stand at just under and just over
USD 1 million/MW (EUR 1.45), respectively (GWEC, 2009).
Following a period of steadily declining investment costs, from the late 1980s,
investment costs rose considerably in 2004, doubling in the United States for example.
This increase was due mostly to supply constraints on turbines and components
76
(including gear-boxes, blades and bearings) that made it difficult to meet the increasing
demand for these parts; as well as, to a lesser extent, higher commodity prices,
particularly for steel and copper. While the current recession has loosened the turbine
market, supply bottlenecks are likely to recur when markets fully recover, particularly if
new investment in manufacturing has stagnated in the meantime, and may lead to re-
inflated investment costs, [29].
4.2.2 Lifecycle Cost of Energy
The lifecycle cost of energy (LCOE) of wind energy can vary significantly according to
the investment cost, the quality of the wind resource, operation and maintenance
(O&M) requirements, turbine longevity and the date of commissioning, and the cost of
investment capital. Regional differences such as geography, population density and
regulatory processes contribute to variations in development and installation costs and
ultimately the LCOE of wind energy. Wind LCOE is considered to range from a low of
USD 70 (EUR 50)/MWh, under the best circumstances, to a high of USD 130 (EUR
90).
According to the last estimation of US Department of Energy Wind Technologies
Market Report the nation-wide capacity-weighted average price paid for wind power in
2008 (generated by projects commissioned during the period 2006 to 2008) was around
USD 47/MWh. This price includes the benefit of the federal production tax credit,
which has a value of at least USD 20/MWh according to the report, and other state level
incentives (US DOE, 2009), [29].
4.2.3 Operations and Maintenance
Operation and maintenance costs considered the most important component player in
the total investment cost of wind energy projects. (O&M) cost of wind turbines
including service, spare parts, insurance, administration, site rent, consumables and
power from the grid. It is difficult to extrapolate general cost figures due to low
77
availability of data. Because of the fast evolving of the technology, O&M requirements
differ greatly, according to the sophistication and age of the turbine. A sample of
projects examined recently in the United States suggested that O&M costs since 2000
range from USD 32/MWh (EUR 22) for projects built in the 1990s to USD 12/MWh
(EUR 8) for projects built in the 2000s (US DOE, 2009), [29]. Based on experiences
from Germany, Spain, the UK and Denmark, O&M costs are, in general, estimated to
be at a level of approximately 1.2 to 1.5 c€/kWh of produced wind power seen over the
total lifetime, (Wind facts, costs and price).
4.3 Financing Schemes for Wind Park Projects in Egypt
Egypt has many different types of financing its renewable projects as follows:
4.3.1 Grant Scheme
Grants was the first financing scheme, in this scheme local works such as civil works,
and local transportation had been financed by NREA. This scheme applied for
financing the pioneer and demonstration wind projects erected in Hurghada, in co-
operation with USA, Denmark, and Germany. In addition used also for financing the
first commercial large scale wind farm at Zafarana, with a total installed of 30 MW in
co-operation with DANIDA.
4.3.2 Self-Finance/Grant Scheme
In this scheme the maximum share of grants didn't exceed 25% of the total project
investment. This regime has been applied for three large-scale wind farms in co-
operation with DANIDA and KfW, with 110 MW total capacities.
4.3.3 Self-Finance Scheme
Self-Finance Scheme; has been applied for the 85 MW wind farm in co-operation with
the Spanish Government, in addition to three projects in the implementation phase with
320 MW total capacities. Foreign loans applied for the second or the third financing
78
schemes vary between soft, mixed credit, and commercial loans. Meanwhile, local
loans offered from the Egyptian National Investment Bank, NIB, are commercial loans,
[32].
4.4 The expected investment cost for wind projects
According to the last feasibility study for wind farm with a total capacity of 200 MW
installed in Gulf of El Zayt we can expect the cost analysis for the other which will be
installed in the future and may be will less than the investment cost due to the decrease
of the cost with the time and especially wind projects which become commercialized
projects.
The cost estimates for the “KfW wind park” considered a proportional share of cost for
the NREA service installations, the main substation and the OHTL interconnection. The
estimated cost including consultancy services and 10% contingencies, and include even
the local (EGP) or hard currency (EUR)
100 x 2 MW
EUR EGP
189,550,000 598.000.000
Table 4-1: the expected investment of wind farm, source, 200 MW FS
The wind park shall be operated by NREA. For that service installations shall be
erected near the wind parks. A good indication for the expected O&M cost are the
recently contracted
Spare Part, Consumables and Service Cost for a three year warranty period. After the
warranty and service period a portion of foreign currency cost is shifted towards local
cost of NREA. The expected O&M cost are indicated below.
79
100 x 2 MW
EUR EGP
First 3 years 6.5 Mio 1.6 Mio
After 3 years 6.0 Mio 6.0 Mio
Table 4-2: Operation and Maintenance, source, 200 MW FS
The financing requirements amount to 280 million EUR without interest during
construction. Including IDC, the financing requirements ascend to 310 million EUR.
The analysis shows clearly that the present feed-in tariffs are insufficient to achieve a
satisfactory cash-flow in the first 10 years of the project life. A minimum feed-in tariff
of some 35 Pt/kWh would be needed without income from CDM: In case of additional
income from CDM, the minimum required feed-in tariff for financial sustainability is
about 31 Pt /kWh, [33].
From the above data we can find that the total investment cost of the wind farm with
total installed capacity about 200 MW in Egypt will be about 310 million Euros, and
the sale tariff at least must be 35 pt. /kWh
80
4.5 The Expected Projects in the East and West Nile Banks
When we apply the data of the expected land in the East and West Nile into the
economic model of the previous project of Gulf of El Zayt, to install one project with a
total installed capacity of 200 MW as an example to investigate the investment cost
indications of this region, the input data of the project as follow
Technical Data
Project location West of the Nile Potential Site
Installed Capacity 200.00 MW
Capacity factor 31%
Energy Produced 543120.00 MWhr/Year
Equipment % 70%
Table 4-3: technical data of 200 MW wind in West of Nile
The weighted capacity factor is 31% according to the added land of the expected region
and so the total generated electricity less than the other regions with about 543
GWh/year.
For the expected cost of this project according to the mentioned cost for wind farms we
found the cost of each MW between 0.98 and 1.9 mil Euros /MW installed, it means the
average cost of each MW installed is about 1.44 mil/ MW
81
Expected Cost
EURO/kW 1440.00
Taxes (EURO/KW) 100.80
Total Required Budget 308.160 mio Euro
Market Distortion
Include Tax Duties 10.00%
Include Customs 0.00%
Table 4-4: the expected cost of the project
The expected results of the data processing is as follow
Levelized Prod. Cost Without CDM 7.25 Cent EURO/kWhr 57.96 P.T./kWhr
Levelized Prod. Cost With CDM 6.90 Cent EURO/kWhr 55.22 P.T./kWhr
SUBSIDY FROM CDM 0.34 Cent EURO/kWhr 2.75 P.T./kWhr
Net Cash -28.42 Mio. EURO
IRR -4%
Table 4-5: the results of the project of west of Nile
These results means that the project will not be feasible for investment, because the
selling tariff less than the LPC (40 PT/KWh), so the IRR negative and there is no
income
We have to sell the produced electricity from the wind farm by at least 60 PT/KWh to
cover the investment cost of these projects.
In this case we can find the change in the other results which means that the project will
feasible economically
By changing the sell price or feed in tariff we can increase the income from these
projects
82
The 1st scenario when we put feed in tariff 60 PT/KWh
Net Cash 44.02 Mio. EURO
IRR 9%
The 2nd scenario FIT is 65 PT/KWh
Net Cash 80.25 Mio. EUROIRR 18%
The 3rd scenario FIT 70 PT/KWh
Net Cash 116.47 Mio. EUROIRR 27%
We have to make balance between the levelized production cost and the selling price to
get an appropriate benefit and attract the private sector.
This balance according to the agreement between the investors and the government to
encourage the private sector.
83
4.6 Economic and Financial Evaluation for Concentrating Solar power
Although the big difference in the capital investment cost between the projects of CSP
and wind energy, currently CSP requires higher capital investments than wind energy, it
offers considerable long-term benefits because of minimum fuel costs for
backup/hybridization. Moreover, the initial investment costs varies from the small to
big plants and decrease with the increase of the project, competition increases,
equipment is mass produced, technology improves and the financial community gains
confidence in CSP. In the near term, the economics of CSP will remain more favorable
for peak and intermediate loads than for base loads, for reasons explained in this
section, [34].
4.6.1 Investment Costs
For the CSP power plants with the most technology used is parabolic trough plants,
current investment costs are USD 4200/KW to USD 8400/KW depending on many
factors like labor and land costs, technologies, the amount and distribution of DNI and,
above all, the amount of storage and the size of the solar field. Plants without storage
that benefit from excellent DNI are on the low side of the investment cost range; plants
with large storage and a higher load factor but at locations with lower DNI (around
2000 kWh/m2/year) are on the high side. These investments costs are slightly higher
than those of PV devices, but CSP plants have a greater energy output per MW
capacity.
It is expected for the future the decrease of investment cost per watt for larger trough
plants, going down by 12% when moving from 50 MW to 100 MW, and by about 20%
when scaling up to 200 MW. Costs associated with power blocks, balance of plant and
grid connection are expected to drop by 20% to 25% as plant capacity doubles.
Investment costs are also likely to be driven down by increased competition among
technology providers, mass production of components and greater experience in the
financial community of investing in CSP projects. On the other hand the investment
84
costs for parabolic trough plants could fall by 10% to 20% by using DSG, which allows
higher working temperatures and better efficiencies. Turbine manufacturers will need to
develop effective power blocks for the CSP industry. In total, investment costs have the
potential to be reduced by 30% to 40% in the next decade if these proposed action
taken, [34].
4.6.2 Operation and maintenance costs
Operation and maintenance costs for CSP include plant operation, fuel expenses in the
case of hybridization or backup, feed and cooling water, and field maintenance costs. A
typical 50 MW trough plant requires about 30 employees for plant operation and 10 for
field maintenance. Operation and maintenance costs have been assessed from USD
13/MWh to USD 30/MWh, including fuel costs for backup. As plants become larger,
operation and maintenance costs will decrease, [34].
4.6.3 Costs of providing finance for CSP plants
There is a big difference between the financing schemes of CSP technology from one
investment and legal environment to another according to significant consequences for
the costs of generating electricity and the expected rates of return on investment. Large
utilities building their own plants with available cash do not incur the costs that utilities
or investors face when combining equity and loans from various sources to finance
plants. Differences among fiscal regimes, in particular with respect to corporate taxes,
have an impact on the turnkey costs (the expenditures necessary before a plant is ready
for use) depending on how long it takes to secure financing and build the plant. This
impact might be significant for CSP plants that may require one to two years of
construction. The same parameters will have an even greater impact on the electricity
generating costs, as capital expenses are much larger for CSP plants than for, say,
fossil-fuel plants, [34].
85
4.6.4 Generating costs
The actual cost of electricity generated from CSP depends mostly on the available
sunlight and how many hours the sun shining. Levelised energy costs, which estimate a
plant’s annualized lifetime cost per unit of electricity generation, range from USD
200/MWh to USD 295/MWh for large trough plants, the technology for which figures
are most readily available. The impact of storage on generating costs is not as simple as
it may seem. The investment cost increase when there is storage capacity, with the size
of the solar field and the added storage but so do the capacity factor and the yearly
electrical output (e.g. up to 6 600 hours in Spain with 15 hours of storage), thus the
energy cost changes only marginally.
In any case, the main merit of storage is not to reduce the cost of electricity but to
increase the value of the plant to the utility in making its capacity firm and allowing
solar plants to compete with fossil-fuel plants by supplying base-load power in the not-
too-distant future, [32].
4.6.5 The expected investment cost of CSP in Egypt
According to the feasibility study which has been prepared to the solar power plant in
Kom Ombo with total installed capacity of 100 MW, the total investment cost was 398
Million Euros for the solar only without storage.
And the next table refers to the expected generated electricity from each scenarios of
solar only and solar with auxiliary heating and finally solar with storage, we can find
the simplest and cheapest one is the solar power plant only without storage, due to the
increase in cost with more storage.
The expected investment cost per MW for solar CSP plant is about 933TEGP (124
Euro), when the required or expected FIT will be about 2.12EGP/KWh, which
considered more expensive than the mentioned in the wind energy.
86
Plant design100 MWel
Solar only
100 MWel + 10%
Auxiliary heating
50 MWel + 12h
Storage
Power block nominal
capacity (electric)
100 MWel 100 MWel 50 MWel
Net Electricity
Generation [GWhel]
256 281 283
Investment cost [Mio
EUR]
398 411 465
Specific investment
cost [EUR/kW]2
3,975 4,105 9,300
Economic Levelized
Unit Costs (ELUC)
TEGP/MWh
933
984 1,044
EUR/MWh 124 123 130
feed in tariff required
EGP/kWh
2.12 2.34 2.41
Table 4-6: expected investment cost for CSP projects, PFC Kom Ombo
4.6.6 Parabolic Trough Modeling in Solar Advisor Model (SAM)
4.6.6.1 Overview of SAM
SAM is a performance and economic model designed to facilitate decision making for
people involved in the renewable energy industry, ranging from project managers and
engineers to incentive program designers, technology developers, and researchers.
SAM makes performance predictions for grid connected solar, small wind, and
geothermal power systems and economic estimates for distributed energy and
central generation projects. The model calculates the cost of generating electricity
based on information you provide about a project's location, installation and
87
operating costs, type of financing, applicable tax credits and incentives, and system
specifications. SAM also calculates the value of saved energy from a domestic solar
water heating system.
SAM is based on an hourly simulation engine that interacts with performance, cost, and
finance models to calculate energy output, energy costs, and cash flows. The software
can also account for the effect of incentives on project cash flows. SAM's spreadsheet
interface allows for exchanging data with external models developed in
Microsoft® Excel. The model provides options for parametric studies, sensitivity
analysis, optimization, and statistical analyses to investigate impacts of variations
and uncertainty in performance, cost, and financial parameters on model results.
SAM models system performance using the TRNSYS software developed at the
University of Wisconsin combined with customized components. TRNSYS is a
validated, time-series simulation program that can simulate the performance of
photovoltaic, concentrating solar power, water heating systems, and other renewable
energy systems using hourly resource data. TRNSYS is integrated into SAM so there is
no need to install TRNSYS software or be familiar with its use to run SAM, [35].
88
4.6.7 Concentrating Solar Power Plant Model
We can use Solar Advisor Modeling to simulate a solar power plant using parabolic
trough technology in Aswan region with a total installed capacity 100 MW solar only
without storage.
Figure 4-1: SAM Model Processing
Aswan region is one of the regions has a good potential in solar energy with a direct
normal irradiation of 2916.7 KWh/m2/year which will be suitable for a promised solar
power plant and can be connected to the Aswan – Luxor grid connection line
The output data or the result of the simulation is
89
Figure 4-2: result of CSP SAM modeling
The results refer to the approximately similarity between the SAM modeling and the
results from the feasibility study in the case of technical data and the Net annual energy
produce from the power plant and also in the LCOE, taking in our consideration the
change in the location and so the DNI
From the simulation of parabolic trough, it’s found that the LCOE is nearly 21.68 Cent
USD /KWh, about 1.19 EGP, which means we can change the FIT according to this
amount and so the change will be in IRR, in this case IRR is 15%
90
4.7 Economic and Financial Evaluation for Photovoltaic PV
Due to the large variety of the applications of PV allows for a range of different
technologies to be present in the market, from low-cost, lower efficiency technologies
to high-efficiency technologies at higher cost. Note that the lower cost (per watt) to
manufacture some of the module technologies, namely thin films, is partially offset by
the higher area-related system costs (costs for mounting and the required land) due to
their lower conversion efficiency. Figure (4-3) gives an overview of the cost and
performance of different PV technologies. High investment costs, or total system costs,
represent the most important barrier to PV deployment today, although they are
decreasing rapidly as a result of technology improvements and economies of volume
and scale. Total system costs are composed of the sum of module costs plus the
expenses for the “balance-of-system”, including mounting structures, inverters, cabling
and power management devices. While the costs of different technology module types
vary on a per watt basis, these differences are less significant at the system level, which
also takes into account the efficiency and land-use needs of the technology. Total
system costs are sensitive to economies of scale and can vary substantially depending
on the type of application. Typical turn-key prices in 2008 in leading market countries
ranged from USD 4000 /kW for utility scale, multi-megawatt applications, to USD 6
000 /kW for small-scale applications in the residential sector, [36].
With expanding polysilicon supplies, average PV prices are projected to drop to $2000/
Kw in 2010. For thin-film PV alone, production costs are expected to reach $1000/Kw
in 2010, at which point solar PV will become competitive with coal-fired electricity.
91
Figure 4-3: current performance and price of different PV module technologies, source, PV road map
4.7.1 Levelized Energy Production Cost
The levelized electricity generation costs (LEGC) of PV systems depend mainly on two
factors: the amount of irradiation of sunlight during the year (and associated capacity
factor), and the interest/discount rate. The operation and maintenance costs of the PV
systems relatively small, there are no moving parts, estimated at around 1% of capital
investment per year. Assuming an interest rate of 10%, the PV electricity generation
costs in 2008 for utility-scale applications ranged from USD 240 /MWh in locations
with very high irradiation and capacity factor (2 000 kWh/kW, i.e. a 23% capacity
factor), to USD 480 /MWh in sites with moderate-low irradiation (1000 kWh/kW,
corresponding to a capacity factor of 11%). When the cost of electricity generated for a
92
residential use, PV systems ranged from USD 360-720 /MWh, depending on the
relevant incident solar energy. While these residential costs are very high, it should be
noted that residential PV systems provide electricity at the distribution grid level.
Therefore they compete with electricity grid retail prices, which, in a number of OECD
countries, can also be very high, [34].
4.7.2 Cost Reduction Goals
The essential target of PV economic is to reduce turnkey system prices and electricity
generation costs; it is expected to reduce by more than two-thirds by 2030. Turn-key
system prices are expected to drop by 70% from current USD 4000 to USD 6000 per
kW down to USD 1200 to USD 1800 per kW by 2030, with a major price reduction
(over 50%) already achieved by 2020. Large scale utility system prices are expected to
drop to USD 1800 per kW by 2020 and USD 800 per kW by 2050, and in the best case
will lead to long-term levelised generation costs lower than USD 50/MWh, [36].
4.7.3 Cost of Turnkey PV in Germany drops, (the German experience)
The German experience with PV technology system considered the leading and the
most successful all over the world, through encouraging spreading this technology.
Germany installed a record 3.8 GW of solar PV in 2009; in contrast, the US installed
about 500 MW in 2009. The previous record, 2.6 GW, was set by Spain in 2008.
Germany was also the fastest growing major PV market in the world from 2006 to 2007
industry observers speculate that Germany could install more than 4.5 GW in 2010. In
fact Germany installed 7.25 GW in 2010. The German PV industry generates over
10,000 jobs in production, distribution and installation. By the end of 2006, nearly 88%
of all solar PV installations in the EU were in grid-tied applications in Germany, [37].
According to Germany's PhotovoltaikZentrum, which interests for surveys of the PV
projects installation prices in Germany, in 2010 the price of installed PV dropped by
20.58% to 2,740 euros per installed kilowatt? The survey is based on responses given
93
by 2,758 array owners from all over Germany who installed arrays smaller than 100
kilowatts in 2010.
This decrease in the price considered the greatest since the first survey in 2006, when
an installed kilowatt of photovoltaic cost around 5000 euros. In 2007, prices had only
dropped slightly down to around 4,800 euros, but prices began plummeting in 2008,
when an installed kilowatt cost around 4,300 euros, a decrease of just over 10 percent.
In 2009, prices then dropped by 19.77% to around 3,450 euros. In total, the price of
installed photovoltaic has dropped by around 45 % in Germany since 2006. It is
important to keep in mind that the prices for crystalline panels on the spot market in
Germany have fallen to around 1.8 euros per watt for modules from Europe and Japan
and to around 1.60 euros for modules from China. It is therefore roughly possible to
estimate what the local added value is even if the panels themselves are imported from
China. If we assume that the difference between 2.70 (installed price) and 1.60 euros
per watt (module price) is locally made installation equipment and local services
charged by installers, then the local added value is potentially already at 42 % in
Germany even if the panels are imported from China. Furthermore, Germany proves
that feed-in tariffs with a regular schedule of decreasing rates can bring down prices
drastically. While the official figures are not yet in from Germany's Network Agency,
the German Solar Industry Association estimates that some 7-8 giga watts were newly
installed in Germany in 2010. Spread across an estimated 230,000 solar arrays, the
average array size comes in at roughly 32.6 kilowatts, which shows that Germany
remains a market largely driven by homeowners. Thanks to this unparalleled growth, a
strong wholesale market and a large pool of skilled installers have been created in
Germany.
At the current exchange rate of roughly 1.33 US dollars per euro, 2,740 euros is
equivalent to 3,644 US dollars, but the cost of installed photovoltaic in the US is
nowhere near 3,600 dollars. In December, the Lawrence Berkeley National
Laboratory published its estimates of the installed cost of photovoltaic in the US for
94
2010. After stagnating at around 7.50 US dollars per watt in 2008 in 2009, the price of
an installed array smaller than 100 kilowatts in California had fallen in the first six
months of 2010 to 6.1 dollars, compared to 5.7 dollars per watt (or 5,700 dollars per
kilowatt) in New Jersey -- but prices can be expected to be much greater in other states,
where PV markets are far less mature. Those who argue that feed-in tariffs keep the
cost of photovoltaic high should explain why arrays in the US cost at least 60 percent
more than they do in Germany, [38].
4.7.4 The Expected Investment Cost of PV in Egypt
With reference to the feasibility study which prepared by EM power program for 100
MWp Solar PV Plant – Kom Ombo, Jan 2010
The investment costs used in the analysis represent first quarter 2010 market prices and
are based on benchmark cost of EPC contracts for private investors, which have been
obtained through evaluation of numerous EPC contracts in southern Europe. A minor
discount on the services and components with higher national share of supply has been
considered. The costs reflect the current market price of contracts from international
EPC contractors with experience in large scale PV plant erection. The cost indicated
above covers the complete PV power plant including land preparation, control and
security, access and grid connection.
System Kom Ombo 100 MWp
grid connected system
Investment cost [Mio EUR] 246.4
Specific investment cost [EUR/kW] 2,460
Table 4-7: investment cost of 100 MW PV power plants, source PFC of PV in Kom Ombo
95
4.7.5 Tariff Requirements
According to the financial analysis which was carried out to determine the project’s
required tariff given the target indicators for investor’s financial benefits, using the
same cost assumptions and time schedules as in the economic analysis. The expected
economic levelized unit costs amounted to 1,242 TEGP/MWh which is within the
typical range for photovoltaic installations in tropical climates. On the other hand, the
economic rate of the project is negative. Among the funding options, Development
Bank Financing generates the lowest project feed-in tariff requirement of 1.60
EGP/kWh (0.20 EUR/kWh) and payback period of 7 years, [39].
4.7.6 PV Power Plant SAM Model
Using PV model with total installed 20 MW in Cairo airport weather to verify the
results coming from the feasibility study or make comparison, After making the
simulation using the SAM modeling we found the technical results in the annual energy
production is nearly similar, but the change in economic results due to the different
installed capacity
In the feasibility study the total installed capacity is about 100 MW and the the SAM
model is 20 MW, it means that, the increase in the installed capacity will decrease the
investment cost and so the LCOE
96
Table 4-8: results of SAM simulation for 20 MW PV
97
4.8 General Economic evaluation and Impacts
4.8.1 General economic indicators
To conclude the economic evaluation for the three technologies, it is clear that the wind
energy is the leading and the commercial technology which reached to be a competitive
energy source with the other traditional resources.
The market investment cost of the wind energy become about USD 1.45 to USD 2.6
million/MW (EUR 1 to EUR 1.9 million), and the production cost range from a low of
USD 70 (EUR 50)/MWh, under the best circumstances, to a high of USD 130 (EUR
90), the expected production cost for the electricity generated in Egypt is to be
72Euro/MWh without the CDM subsidize, and so the selling tariff will be about at least
8 cent Euro /KWh (65 PT)
For the CSP technology the market cost is more expensive than the wind energy and
expected to be decreased with the next few years, it reached to be about USD 4200/KW
to USD 8400/KW (Euro 525 to 1050)/ KW, and the generating costs range from USD
200/MWh to USD 295/MWh (Euro 25 to 37)/ MWh, the expected investment cost for
the CSP plants in Egypt is to be about 933 EGP (124 Euro), when the required or
expected FIT will be about 2.12EGP/KWh
For the PV technology and according to the German projects at the year 2010, the
estimation is about 2,740 Euros/KW; the production cost was about from USD 240
/MWh to USD 480 /MWh (Euro 30 to 60)/MWh, and the expected investment cost for
the Egyptian market is 2,460 Euro/KWh and The expected economic levelized unit
costs amounted to 1,242 TEGP/MWh, the lowest project feed-in tariff requirement of
1.60 EGP/kWh (0.20 EUR/kWh) and payback period of 7 years
98
4.8.2 General economic impacts
The expected wind projects during the wind park construction and operation
would have many economic benefits.
About 30 to 40 % of the investment volume would be produced locally.
During construction there will be an employment opportunities, local personnel
would be employed for civil, electrical and installation works. The works would
be carried out essentially by Egyptian companies.
During the operation a significant number of electricians, mechanics, engineers
and workers would be employed for O&M of the wind park.
At steadily increasing oil prices wind power utilization, especially at a site with
very high wind energy potential like the NREA area, is approaching
competitiveness. It saves indigenous gas and oil reserves, which alternatively
could be exported at world market prices.
For the CSP projects the expected impacts will be to offer Jobs:
- Direct Jobs, Temporary Engineering, Procurement, Construction,
Permanent Operations, Maintenance, Engineering, Administrative
- Indirect Jobs. Manufacturing, Hospitality & Services, Infrastructure,
Ancillary Commerce
Private Investment: Plant and transmission facilities, ancillary businesses and
infrastructure
Tax Base Increase: Real and personal property tax, sales tax, employment and
income taxes
99
5 CHAPTER FIVE: ENVIRONMENTAL IMPACTS
EVALUATION OF RENEWABLE ENERGY
In this section an evaluation for environmental impacts of different renewable
energy and specially the projects which will be in Egypt mainly wind and solar
energy, the evaluation depends on the data collection from different web sites
and papers.
The general view of the land location which used for the wind farms or solar
power plants are desert land, it means that most of the environmental impacts
are very low and in some regions neglected, it is far from the population, the
agriculture regions and may be far from the bird migrations direction.
5.1 Introduction
The environmental problems is the result for the fossil and nuclear energy sources use,
the energy use and supply is the most fundamental importance to society and life.
The most environmental impacts of burning fossil fuels including: Global climate
change, acidification of ecosystems, risks from nuclear accidents, long term
accumulation of radioactive waste, and effects on the public health from air pollution.
With the possible exception of agriculture and forestry, energy has made the greatest
impact on the environment of any human activity - a result of the large scale and
pervasive nature of energy related activities. Although the local effect of using energy
on the environment such as problems associated with extraction, transport or noxious
emissions - they have now widened to cover regional and global issues such as acid rain
and the greenhouse effect. Such problems have now become major political issues and
the subject of international debate and regulation, [40]. It is a great challenge to win the
fight against climate change without a dramatic shift in the way of electricity
production and encouraging the use of renewable energy resources to face the increase
in electricity demand. The power sector accounts for around 40% of global CO2
100
emissions, renewable energy technologies must be rolled out quickly to provide
emissions-free renewable electricity for industrialized and developing countries alike.
As renewable energy technologies rely on natural energy and material flow cycles, they
can reduce the environmental impact of energy supply. Although for most of them the
energy conversion process is emission free, environmental impacts result from the
provision of raw materials and the manufacturing and disposal of components, [41].
Electricity consumption will be changed due to the Climate change which will alter
energy demand patterns. Electricity consumption in the Mediterranean region will
increase due to projected temperature increases and the associated increasing demand
for space cooling. Energy demand for space heating in northern Europe will decrease,
but the net effect across Europe is difficult to predict. Climate change will affect power
production. Due to projected changes in river runoff, hydropower production will
increase in northern Europe and decrease in the south. Furthermore, across Europe,
summer droughts are projected to be more severe, limiting the availability of cooling
water and thus reducing the efficiency of thermal power plants. Both types of impacts
may lead to changes in emissions of air pollutants and greenhouse gases from energy,
which are, however, difficult to estimate at present, [42].
5.2 The Impact of Wind Energy on Climate Change
The impact of Wind farms may be strong on the surrounding area and it may affect
weather in their immediate vicinity. The mixing of heat and water vapor which
generated from the closed box of turbine rotors generate a lot of turbulence in their
wakes like the wake of a boat. This turbulence affects the meteorological conditions
downwind. Many studies had been demonstrated to investigate the impacts of wind
farms on weather and climate used a regional climate model. The main results of these
studies refer to; wind farms lead to a warming at night and cooling during the day time.
Which means a kind of climate change will happen in this region and to reduce this
effect we have to use more efficient rotors or placing wind farms in regions with high
101
natural turbulence. Other studies have used climate models to study the effect of
extremely large wind farms. The result of the simulations shows detectable changes in
global climate for very high wind farm usage, on the order of 10% of the world's land
area. Wind power has a negligible effect on global mean surface temperature, and it
would deliver "enormous global benefits by reducing emissions of CO2 and air
pollutants". Another study suggested that by using wind turbines to meet 10% of global
energy demand in 2100 this could actually have a warming effect, causing temperatures
to rise by one degree Celsius in the regions on land where the wind farms are installed,
including a smaller increase in areas beyond those regions, [43].
5.3 Carbon Dioxide Emissions and Pollution
Wind power is clean electricity without any other pollution during the operation and
there is no emissions directly related to production. Wind turbines produce no carbon
dioxide, sulfur dioxide, mercury, particulates, or any other type of air pollution, unlike
fossil fuel power sources. Wind power plants consume resources in manufacturing and
construction. using fossil fuels During manufacture of the wind
turbine, steel, concrete, aluminium and other materials will have to be made and
transported using energy-intensive processes, this will cause emissions. The wind
turbine manufacturer Vestas states that initial carbon dioxide emissions "payback" is
within about 9 months of operation for off shore turbines. There was a study in 2006
found that the total emissions of CO2 of wind power to range from 14 to 33 tons per
GWh of energy produced. Most of the CO2 emission comes from producing the
concrete for wind-turbine foundations. On the other hand the generating electricity from
wind energy instead of fossil fuels makes reductions of in CO2 emissions ranging from
0.33 to 0.59 tons of CO2 / MWh, [43].
5.3.1 How Much CO2 Can Wind Energy Save?
The calculations on just how much CO2 could be saved by wind energy is based on an
assumption for the carbon intensity of the global electricity sector, i.e. the typical
102
amount of CO2 emitted by producing one kWh of power. Individual countries’
emissions differ substantially, but here we use the IEA’s estimate of 600g/kWh as an
average value for the carbon dioxide reduction to be obtained from wind generation,
(wind road map, 2010).
Figure 5-1: Global Power Capacity and avoided CO2 emissions (2008-2030), source wind roadmap
2008 2012 2020 2030
GW 121 277 1,081 2,375
mil tCO2/year 157 408 1,591 3,236
Table 5-1: Global Power Capacity and avoided CO2 emissions (2008-2030), source wind roadmap
The expected CO2 emission will be avoided by the generated electricity from wind
energy up to 2020 will be estimated as approximately 18.6 mil ton CO2.
103
5.4 Environmental Impacts of Wind farms
The environmental impact of wind energy is relatively minor when comparing it with
the huge impact of fossil fuels specially the amount of CO2 emission. Wind energy
does not consume any fuel and there is no any pollution production, so it is considered a
free emission energy source. Wind farms are seen as a great way of generating green
electricity without polluting the environment; however do they cause their own
environmental problems? There are plenty of concerns about the environmental
problems caused by wind farms which will be explained in details below.
5.4.1 Noise Problems
The noises created by wind turbine make people worried; the noise has been
minimized, by designing the turbines to minimize noise. Modern wind farms do not
create huge amounts of noise as many people expect.
Modern wind turbines produce significantly less noise than older designs. Turbine
designers work to minimize noise, as noise reflects lost energy and output. Noise levels
at nearby residences may be managed through the siting of turbines, the approvals
process for wind farms, and operational management of the wind farm. In a 2009 report
about "Rural Wind Farms", a Standing Committee of the Parliament of New South
Wales, Australia, recommended a minimum setback of two kilometers between wind
turbines and neighboring houses (which can be waived by the affected neighbor) as a
precautionary approach. In July 2010, Australia's National Health and Medical
Research Council reported that "there is no published scientific evidence to support
adverse effects of wind turbines on health".
A 2008 guest editorial in Environmental Health Perspectives' published by the National
Institute of Environmental Health Sciences, the U.S. National Institutes of Health,
stated: "Even seemingly clean sources of energy can have implications on human
health. Wind energy will undoubtedly create noise, which increases stress, which in
turn increases the risk of cardiovascular disease and cancer." A 2007 report by the U.S.
104
National Research Council noted that noise produced by wind turbines is generally not
a major concern for humans beyond a half-mile or so. Low-frequency vibration and its
effects on humans are not well understood and sensitivity to such vibration resulting
from wind-turbine noise is highly variable among humans. There are opposing views on
this subject, and more research needs to be done on the effects of low-frequency noise
on humans, [43].
5.4.2 Interference
Wind turbines have moving blades which could make disturbance for the TV and Radio
signal, and so cause interference affecting TV and radio transmissions. It is well known
that obstacles affect radio and TV transmissions. However the blades are made out of
synthetic materials to minimize the risk. The generator and transformer could
potentially emit small levels of electromagnetic radiation, however these emissions will
be very week, and as the turbines are located off the ground, there is no risk at all, [44].
5.4.3 Appearance
The appearance of wind turbine different from person to another, so it is a very personal
topic; it depends mainly on whether people like the look of them or thinks that they
destroy the look of the landscape. This opinion depends on the background of each one,
if he knows the benefits of the using of wind energy instead of traditional energy or just
a structure like anything.
5.4.4 Land use
The land of wind farms can be used for another purposes like farming for example,
wind farms are normally built in mountainous regions to get higher wind speeds. In
mountainous or desert regions, farming normally concentrates on sheep and goats. The
sheep actually like wind turbines as they provide shade during hot days.
105
The land can still be used for farming and cattle grazing. Livestock are unaffected by
the presence of wind farms. International experience shows that livestock will "graze
right up to the base of wind turbines and often use them as rubbing posts or for shade".
Wind-energy advocates contend that less than 1% of the land would be used for
foundations and access roads, the other 99% could still be used for farming. Critics
point out that the clearing of trees around tower bases may be necessary for installation
sites on mountain ridges, such as in the northeastern U.S.
Turbines are not generally installed in urban areas. Buildings interfere with wind,
turbines must be sited a safe distance ("setback") from residences in case of failure, and
the value of land is high. There are a few notable exceptions to this, [43].
5.4.5 Impact on wildlife
Environmental assessments are routinely carried out for wind farm proposals, and
potential impacts on the local environment (e.g. plants, animals, soils) are
evaluated. Turbine locations and operations are often modified as part of the approval
process to avoid or minimize impacts on threatened species and their habitats. Any
unavoidable impacts can be offset with conservation improvements of similar
ecosystems which are unaffected by the proposal.
Projects such as the Black Law Wind Farm have received wide recognition for its
contribution to environmental objectives, including praise from the Royal Society for
the Protection of Birds, who describe the scheme as both improving the landscape of a
derelict opencast mining site and also benefiting a range of wildlife in the area, with an
extensive habitat management projects covering over 14 square kilometers, [43].
5.4.6 Safety
Operation of any utility-scale energy conversion system presents safety hazards. Wind
turbines do not consume fuel or produce pollution during normal operation, but still
have hazards associated with their construction, operation and maintenance.
106
With the installation of industrial sized wind turbines numbering in the thousands, there
have been at least 40 fatalities of workers due to the construction, operation, and
maintenance of wind turbines, and other injuries and deaths attributed to the wind
power life cycle. Most worker deaths involve falls or becoming caught in machinery
while performing maintenance inside turbine housings. If a turbine's brake fails, the
turbine can spin freely until it disintegrates or catches fire. Often turbine fires cannot be
extinguished because of the height, and are left to burn themselves out. In the process,
they generate toxic fumes and can scatter flaming debris over a wide area, starting
secondary fires below. Several turbine-ignited fires have burned hundreds of acres of
vegetation each, and one burned 800 square kilometers (200,000 acres) of Australian
National Park.
During winter ice may form on turbine blades and subsequently be thrown off during
operation. This is a potential safety hazard and has led to localized shut-downs of
turbines.
Electronic controllers and safety sub-systems monitor many different aspects of the
turbine, generator, tower, and environment to determine if the turbine is operating in a
safe manner within prescribed limits. These systems can temporarily shut down the
turbine due to high wind, electrical load imbalance, vibration, and other problems.
Recurring or significant problems cause a system lockout and notify an engineer for
inspection and repair. In addition, most systems include multiple passive safety systems
that stop operation even if the electronic controller fails.
In his book Wind Energy Comes of Age, Paul Gipe estimated that the mortality rate for
wind power from 1980–1994 was 0.4 deaths per terawatt-hour. Paul Gipe's estimate as
of end 2000 was 0.15 deaths per TWh, a decline attributed to greater total cumulative
generation, [43].
107
5.5 The Environmental Impacts of Wind Farms in Egypt
The assessment of the different possible environmental impacts, which may be caused
by wind power development Egypt, did not show any significant bottleneck except
limitations set by expected impacts to the avi-fauna. The Consideration of competing
environmental interests, such as bird protection and renewable energy generation and
implied CO2 avoidance is the most important aspects, the most environmental impacts
of wind farms in Egypt according to the last feasibility study for wind farm and this
land similar to the other regions in the other promised locations for other wind farms in
Egypt, the source (200MW FS in GZ 2008).
5.5.1 Land characteristics and use:
All the area is consisting of desert ground (compacted gravel or rocky) and not
ecologically sensitive. Very little deterioration is expected. According to the previous
information received from last feasibility studies, the selected area is free from oil
concessions.
5.5.2 Flora and Fauna (without avi-fauna):
The field survey revealed that due to the desert nature of the land, there is a complete
absence of flora and very limited expected fauna, which is of common nature.
Accordingly, wind park utilization in the area will have no impacts on the biodiversity
and other environmental characteristics of the site. Not a single specie or animal
recorded in the area or expected to occur in it, is included in the Red Lists, both
internationally or nationally. Moreover, the nature of wind parks, which leaves most of
the wind park area untouched, is not critical to the rare existing fauna (not considering
avifauna) in that area, if basic mitigation measures are kept.
5.5.3 Avifauna:
Although, this area is away from the main migration routes and does not show
topographical bottlenecks, some smaller amounts of migrating birds were assessed to
108
likely occur in that part of the greater area. Therefore, the wind park installation
requires technical Avoidance/mitigation measures at the plants and in the infra-structure
itself as to the best practicable standard. Moreover, a careful post installation
monitoring programme needs to be executed to assess, whether the impacts in a wind
park will remain on acceptable level or whether additional measures will have to be
carried out.
5.5.4 Water quality:
Wind power utilization in the area will not have any effects to the groundwater and
surface water. Eventually constructed service buildings near to the area, such as store,
control and apartment buildings, shall be interconnected to the existing water pipeline
and equipped with an appropriate waste water treatment system (e.g. septic tank with
underground seepage and regular sludge collection).
5.5.5 Air quality:
Some additional dust will occur locally during construction works what, however, is
not critical because of the absence of population or wildlife, which may be affected.
5.5.6 Noise levels:There is no settlement area in the surroundings of the proposed area.
Antiquities or sites of historical & cultural importance: None
109
5.6 Environmental Effects of Solar EnergySolar energy is the source for electricity without air pollution during operation and
generation mode, only the impact of solar on the environment and the health during the
manufacturing, installation and the wastes after finishing. Materials used in some solar
systems can create health and safety hazards for workers and anyone else coming into
contact with them. The most danger comes from the manufacturing of Photovoltaic
cells often requires hazardous materials such as arsenic and cadmium. Even relatively
inert silicon, a major material used in solar cells, can be hazardous to workers if it is
breathed in as dust. Effective measures must be taken to protect the Workers involved
in manufacturing photovoltaic modules and components to protect them from exposure
to these materials. There is an additional-probably very small-danger that hazardous
fumes released from photovoltaic modules attached to burning homes or buildings
could injure fire fighters. None of these potential hazards is much different in quality or
magnitude from the innumerable hazards people face routinely in an industrial society.
This danger can be removed or reduce through effective regulation, the dangers can
very likely be kept at a very low level. For the Wildlife protection when using the large
amount of land required for utility-scale solar power plants- which approximately one
square kilometer for every 20-60 megawatts (MW) generated. Ecosystems can also be
affected by Water from underground wells may be required to clean concentrators and
receivers and to cool the generator, which may harm the ecosystem in dry climates.
Large central power plants are not the only option for generating energy from sunlight,
however, and are probably among the least promising. Because sunlight is dispersed,
small-scale, dispersed applications are a better match to the resource. They can take
advantage of unused space on the roofs of homes and buildings and in urban and
industrial lots. And, in solar building designs, the structure itself acts as the collector, so
there is no need for any additional space at all, [45].
110
5.6.1 Carbon Emissions
There is no carbon emissions, this is the best thing when we use solar energy to
generate electricity, so that the there is no greenhouse gases, It doesn't burn oil, it
doesn't produce toxic waste, and its lack of moving parts reduces the chances of an
environmentally devastating accident to nil. By using solar energy to generate
electricity for a large scale will reduce its environmental footprint to tiny fractions of its
current level, [46].
5.6.2 Abundant Components
The photovoltaic cells which constitute most solar energy systems are usually made of
silicon, one of the most common minerals found on Earth. That means that creating the
components is extremely easy, doesn't require mining or drilling in a dangerous locale
to produce, and can be acquired without involvement in politically unstable areas such
as the Middle East. The environmental effects of this are subtle but, because fewer
resources are expended in the acquisition of silicon, its overall effect on the ecosystem
is reduced, [46].
5.6.3 Cadmium
Cadmium is used in cadmium telluride solar cells as a semiconductor to convert solar
energy into electricity. Though used in very small amounts, it is extremely toxic and
can build up in a given ecosystem if it isn't monitored. Firms which make this kind of
solar cell often instigate recycling programs so that damaged or unusable cells don't
inadvertently damage the surrounding environment, [46].
5.6.4 Ecological Concerns
The pro-alternative energy site Cooler Planet points out that many conservationist
groups are concerned about animal habitat depletion. There are concerns that the large
spaces required for solar energy production will create habitat problems, but these
doubts are often not balanced against the environmental needs of other power-
111
generation facilities. For example, a solar power generation plant requires the
destruction of fewer habitats than a coal-generating station when the land space of the
mines producing the coal is added into the equation, [46].
112
6 CHAPTER SIX: CONCLUSION ANDRECOMMENDATIONS
6.1 Introduction
The goal of this thesis is to study the renewable energy strategy in Egypt up to the year
2020, and the different challenges technical, economic and environmental which may
face it. Possible scenarios for the estimating the expected total generated electricity
from different resources thermal and renewables at this year 2020 have been
investigated taking into considerations the renewable energy planned projects.
Is there is a gap between the targeted goals and the projects installed and planned?, and
if there is a gap, how could this gap covered?. Alternative scenarios consider different
site locations according to the projects criteria (wind, solar CSP, solar PV, …), the
expected investment cost, the production cost and the sell tariff.
In this study a model has been built and used to forecasting the electricity generation, a
gap between the targeted goal and the installations has been found. Also SAM,
simulation model has been used to check the findings with the model have been built,
and results are matched. SAM model used also to estimate economic parameters.
Main conclusions on the current study and recommended actions to speed the
renewable energy in Egypt are presented below.
6.2 Conclusions on the Present Work
Energy Planning Model refers to an annual growth rate of electricity generation by
6.4% until the year 2020, this result has been concluded based on past electricity
demand and the expected increased demand. Accordingly, the total generated electricity
will reach 258482 GWh. Consequently the estimated share of renewable energy, 20%
of the total generated electricity, is about 51696 GWh. This renewable energy could be
occurred from different sources, 12% wind with total generated electricity 31017 GWh,
113
4% solar energy with total generated electricity 10339 GWh, and 4% Hydro power with
total generated electricity about 10339 GWh.
The estimated generated electricity from the projects, established and planned, to cover
the strategy is about 35528 GWh, which considered 13.75% from the total expected
generated. So, there is a deficit of about 6.25%, estimates approximately 16167 GWh
by year 2020. To cover this shortage there is a need to plan erecting more wind, solar,
and biomass projects.
For wind energy, based on Egypt Wind Atlas suitable locations for establishing wind
farms could be determined according to the following priorities: the east and west banks
of the Nile, the Gulf of Suez, and some areas located in the Western Desert. These sites
were chosen based on wind energy potential, the wind speed varies between 7 and 8
m/s, which result a weighted capacity factor about 30% to 35%.
Concerning solar energy, solar maps of Egypt indicate some of the promising locations
which are suitable for CSP and PV applications. Such sites exist in Abu Simbel,
Toshka, Kom Umbo, Esna, Marsa Alam, Quseir Resory, West and South of Safaga,
Hurgada, Kuraymat, and Farafra Oasis. The total recommended projects for these
locations are around 1863 MW installed capacity of PV and about 1935 MW installed
of CSP. Moreover the Egypt coastal strip at the Mediterranean and Red Sea have a
good potential for CSP with water desalination projects with estimated capacity of
about 2.1 GW of installed power and 1.7 Mil. m3 of installed desalination water.
Either for solar or wind projects several studies are needed to check the suitability of
these sites such as, environmental impact assessment, ornithological studies, grid
situation, …etc. consequently, it is expected that some of the proposed areas could not
be used as part of the proposed solution.
The economic evaluation for these renewable projects refers to that the investment cost
of the renewable energy technology varies from one to another according to the total
114
installed all over the world and the mass production of its components, the wind energy
is the commercial technology till now and expected decrease in the investment cost of
CSP and PV projects for next years.
The market investment cost of the wind energy become about (EUR 1 to EUR 1.9
million) /MW, and the production cost range from a low of (EUR 50)/MWh, under the
best circumstances, to a high of (EUR 90), the expected production cost for the
electricity generated in Egypt is to be 72Euro/MWh without the CDM subsidize, and so
the selling tariff will be about at least 8 cent Euro /KWh (65 PT)/KWh
For the CSP technology the market cost is more expensive than the wind energy and
expected to be decreased with the next few years, it reached to be about (Euro 525 to
1050)/ KW, and the generating costs range from (Euro 25 to 37) / MWh, the expected
investment cost for the CSP plants in Egypt is to be about 933 EGP (124 Euro), when
the required or expected FIT will be about 2.12EGP/KWh
For the PV technology and according to the German projects at the year 2010, the
estimation is about 2,740 Euros/KW; the production cost was about from (Euro 30 to
60)/MWh, and the expected investment cost for the Egyptian market is 2,460
Euro/KWh and The expected economic levelized unit costs amounted to 1,242
EGP/MWh, the lowest project feed-in tariff requirement of 1.60 EGP/kWh (0.20
EUR/kWh) and payback period of 7 years
The environmental impacts of wind and solar projects in Egypt are limited, the general
view of the land location which used for the wind farms or solar power plants are desert
land, it means that most of the environmental impacts are very low and in some regions
neglected, it is far from the population, the agriculture regions and may be far from the
bird migrations direction.
115
6.3 Recommendations and Proposed Actions to Foster RE In Egypt
Renewable energy is the coming future and the best choice for securing energy demand
to the next generations with clean environment. Egypt is a rich country with renewable
resources which can be used for power generation on a commercial scale.
to foster renewable energy we will need more capacity building with more awareness
through the different media facilities to strength the concept of renewable energy and
the importance of using it instead of conventional resources, and on the other hand the
concept of energy conservation and energy efficiency for electrical appliance which
will reduce the electricity consumption, for this purpose many effective measures must
be taken from the decision maker or suggested from the institutions and organizations
which interested in the field of renewable energy technology development, hereinafter
some suggestions for action plans to speed the utilization of renewable energy
technologies, these actions may be acceptable or non-acceptable from some experts,
this debate very useful for more development and spread the use of RE technologies.
6.3.1 Fossil-Fuels Subsidizes
In Egypt, most of the fossil fuels are subsidized. These subsidies may be reduced
gradually, to make renewable-energy marketable with cost competitiveness, these
resources will be “presented to citizens at its real cost,” but added that butane will
continue to be subsidized through cash payments to individuals, rather than what he
called “in-kind support,”
This will increase the end user electricity price which put the price of conventional and
renewable energy in comparison and the choice will be to the consumers.
6.3.2 Access to Transmission, Grid Connection
The right to access and connect to the grid must be obligated for all renewable plants,
which facilitate the electricity-wheeling between buyer and seller that provides open
116
access to customers. Transmission-services should not discriminate against, or give
unfair advantage to, specific ownership or certain types of generation.
6.3.3 Promoting and Encouraging Solar Water Heating Systems
The use of solar water heater even in the domestic or commercial use will be reduce the
electricity consumption for heating water and we can benefit from this electricity in
another sector and decrease loads from the grid.
The main barrier for the use of SWHS is the high initial cost, financial support from the
government and the private sector and donor agencies should be put in place, so the
proposal action can help and support the use of SWHS and at the same time support the
local industries and decrease the unemployment.
This proposal depends on a financial program to encourage citizens to use the solar
water heater instead of the electrical or gas water heater by the following steps:
Funding system to facilitate the acquisition of solar heaters in Egypt
1. The electricity distribution companies make a contracting with solar water
consumers against payment of 10% of the total cost and the rest will be added as
monthly installment on the electric bill each month so as not to bear the high cost
of consumer the boiler solar.
2. Electricity distribution companies will make contract with the national banks to
finance the project through soft loans to cover 70% of the total cost.
3. The bank benefits will be covered through the support of international
organizations and bodies which encourage and support the clean and renewable
energy
4. The last 20% of the cost will be covered through national funds such as the
support fund for renewable energy which ratified by the supreme council of
energy to encourage the use of RETs
5. The electricity distribution companies will make a contract with the local
manufacturing and suppliers of SWHS for supplying a large number of solar
117
water heaters with capacity of 150 liter, (enough for a family of five persons),
through public tender in accordance with the following specifications:.
The solar water heater certificate quite standard technical specifications
The contract includes the installation and maintenance throughout the
period of hire purchase (5 years, 10 years, and 15 years).
6.3.4 Educate the Awareness about the Role of Renewable Energy
It is very important that the general public and local populations in in Egypt of a
proposed development understand the full value of wind energy and using solar energy
technologies. The variability characteristic of renewable energy is taken by some as a
measure of unreliability so that its role in strategic socio environmental strategy to abate
CO2 emissions is often underestimated. This needs to be addressed with effective
public information campaigns that highlight quantifiable benefits of the technology.
To achieve this awareness, there is a need for training courses, demonstration systems,
brochures, and workshops for targeted users. These programs should be prepared based
on market surveys and studies.
6.3.5 Research, Development and Demonstration Support of Local Industry
Egypt must take effective measures toward encouraging the researches and support the
local manufacturing to transfer the technology from the advanced countries and start
self-reliance
6.3.6 Garbage-To-Energy- Recycling Instead Of Burning
Take one problem - worthless garbage - and solve energy crises.
Garbage then becomes a good thing – a fuel
Some researchers at the University of California have come up with ways to draw
energy from the garbage you dispose into bio-gas that has the potential to
118
generate electricity and can power homes and offices. They have devised a “digester”
which works in two-stages (unlike most digesters which use just one stage).
Typically, all the food waste and other such forms of garbage is collected from homes
and restaurants for instance and is fed into these digesters which allow this feed to
undergo decomposition which is naturally occurring. Different classes of bacteria have
different effects on feed like this, but our group of bacteria actually decomposes the
entire feedstock and produces methane (up to 60-80%) which can then be used as fuel
to provide electricity.[47]
Energy Production per Ton of Garbage,If the landfills can be spared from the leftover food and other digestible waste, it can all
be used to produce power to run our homes. It is estimated that one ton of leftover food
can power a whopping 18 homes. The capacity of this process is slated to power about
25 homes a day and can also be extended to other uses such as fuel processing plants.
This is bound to be eco-friendly, easy for the industry to adopt and a great energy
source for the rest of the world.
For the Egyptian case, we have huge quantities of garbage in every place in all cities
and villages, we can collect every day what we need for producing energy or estimated
energy for each place individually, and use this energy for homes or another purposes
instead of using electricity from the conventional resources
A contract can be signed (were asked to sign) long term in every city or village to
deliver and pay for a guaranteed supply of garbage. If the city didn’t have enough
garbage, it had to pay anyway. The incentive to recycle would be gone.
119
REFERENCES
[1]. Rafik Youssef GEORGY, New and Renewable Energy Authority (NREA) &Mr
Adel Tawfik Soliman, Power Transmission, Energy Efficiency and Renewable
Energy Egypt - National study’s summary, Plan Bleu, Regional Activity Centre,
March 2007
[2] Encyclopedia of the Nations » Africa » Egypt, Energy and power -http://www.nationsencyclopedia.com/Africa/Egypt-ENERGY-AND-POWER.html#ixzz1XgKvNzyZ
[3] . Ministry of Electricity and Energy, http://www.moee.gov.eg/english/e-fr-
main.htm
[4] Ministry of Petroleum, http://www.petroleum.gov.eg/en/pages/default.aspx
[5] . Mohamed Moustafa El Khayat, Renewable Energy Technologies Manufacturing
facilities in Egypt, economic and social commission for western asia, ESCWA,
MAY, 2007
[6] Country analysis briefs, Egypt Energy Data, Statistics and Analysis - Oil, Gas,Electricity, Coal, Energy Information Administration EIA, February 2011
[7] Paul H. Suding, Struggling between resources-based and sustainabledevelopment schemes—An analysis of Egypt’s recent energy policy, DeutscheGesellschaft fur Technische Zusammenarbeit (GTZ) GmbH, DagHammarskjoeldweg 3, 65760 Eschborn, Germany
[8] . Global wind Energy Council, http://www.gwec.net/index.php?id=122
[9]. Egyptian Electricity Holding Company Annual Report 2009/2010
120
[10] . http://www.meed.com/sectors/power/renewable-energy/egypt-pioneering-
renewable-energy-to-meet-demand/3005533.article
[11]. Francisco Figueroa de la Vega,Cairo 2010, Impact of Energy Demand on
Egypt’s Oil and Natural Gas Reserves, Current situation and perspectives to
2030
[12]. https://www.cia.gov/library/publications/the-world-factbook/geos/eg.html
[13]. H. Elsalmawy, H. Waheed, M. Abdel-Rahman, and H. Saleh, The Egyptian
Electricity Market in Transition, Egyptian Electricity Utility and Consumer
Protection Regulatory Agency Egypt
[14]. The Institutional Capacity Building of The Egyptian Electric Utility and
Consumer Protection Regulatory Authority (EEUCPRA), Transitional Market
Plan Assessment of the Transmission System Operations, Submitted by
KANTOR Management Consultants as Leader of the Consortium Implementing
the Framework Contract, Framework Contract – Lot N° 4 Specific Contract N°
2007/143297
[15]. Erik J. Woodhouse, IPP Study Case Selection and Project Outcomes: An
Additional Note, October 2006
[16]. Anton Eberhard and Katharine Gratwick, The Egyptian IPP Experience, August2005 (revised November 2005), Program on Energy and SustainableDevelopment At the Center for Environmental Science and Policy Encina HallEast, Room 415 Stanford University, Stanford, CA 94305-6055
121
[17]. Egypt, EETC,Dairut IPP,http://ae.zawya.com/marketing.cfm?zp&p=/projects/project.cfm/pid030210065322
[18]. Juti Prasad Painuly, Implementation of Renewable Energy Technologies,Opportunities and Barriers, UNEP collaborating center on Energy andEnvironment Riso National Laboratory, Denmark, 2002, ISBN: 87-550- 3013-0
[19]. Vasilis Fthenakis, Hyung Chul Kim, Land use and electricity generation: A life-cycle analysis, Renewable and Sustainable Energy Reviews 13 (2009) 1465–1474, journal homepage: www.elsevier.com/locate/rser
[20]. Niels G. Mortensen, Jake Badger, Ris ّ◌National Laboratory, Roskilde,Denmark , and Usama Said, New and Renewable Energy Authority, Cairo,Egypt, Wind Atlas for Egypt (MENAREC3)
[21]. Niels G. Mortensen, Jens Carsten Hansen, Jake Badger, Bo H. J ّ◌rgensen,Charlotte B. Hasager, Uwe S. Paulsen, Ole F. Hansen, Karen Enevoldsen, WindEnergy Department, Ris ّ ◌National Laboratory, Roskilde, Denmark, LailaGeorgy Youssef, Usama Said Said, Ashour Abd El-Salam Moussa, MohammadAkmal Mahmoud, Wind Energy Department, New and Renewable EnergyAuthority, Cairo, Egypt, WIND ATLAS FOR EGYPT: MEASUREMENTS,MICRO- AND MESOSCALE MODELLING (EWEC)
[22]. Paul Denholm, Maureen Hand, Maddalena Jackson, and Sean Ong, Land-UseRequirements of Modern Wind Power Plants in the United States, NationalRenewable Energy Laboratory, Technical ReportNREL/TP-6A2-45834 August 2009, andhttp://www.nrel.gov/analysis/power_databook/calc_wind.php
[23]. Power technology energy data book,http://www.nrel.gov/analysis/power_databook/calc_wind.php
[24]. http://www.wwindea.org/technology/ch02/en/2_4_3.html
[25]. Country visist report, New and Renewable Energy Authority, Em PowerProgram,United Nations Environment Program (UNEP), German Ministry forEconomic Cooperation and Development BMZ, Represented by KFWdevelopment bank, consulting service for EM power program, LahmeyerInternational GmbH, January 2010
122
[26]. Pre-Feasibility Study Report: CSP Plant Kom Ombo, Lahmeyer InternationalGmbH, United Nations Environment Program (UNEP), German Ministry ofEconomic Cooperation and Development (BMZ), Represented by KfW,EMPower Program, Phase II, Bad Vilbel, 23.06.2010
[27]. Technical Report, Solar Resource Assessment In The Egypt Coastal Strip,Irsolav S. L. (Investigaciones Y Recursos Solares Avanzados). March 4, 2011
[28]. ASSESSMENT OF CSP+D POTENTIAL IN THE MENA AREA,SolarPACES, Solar Energy & Water Processes and Applications, CIEMAT,DLR, NREA, 3 April 2011
[29]. RenewableS 2011 GLOBAL STATUS REPORT, Renewable Energy PolicyNetwork for 21st century REN 21
[30]. Technical roadmap, wind energy, international energy agency, IEA 2009
[31]. Poul Erik Morthorst, Senior Research Specialist at Ris ّ◌National Laboratory,DenmarkWIND ENERGY - THE FACTS, COSTS & PRICES
[32] Eng. Fathy Ameen Mohammad, NREA, Financing Wind Park ProjectsExperience from Egypt
[33]. FEASIBILITY STUDY FOR A 200 MW WIND FARM At the GULF OF ELZAYT, decon DEUTSCHE ENERGIE-CONSULTINGENIEURGESELLSCHAFT mbH, Fichtner ENGINEERING SERVICESAND CONSULTANCY, February 2008
[34]. Technology Roadmap, Concentrating Solar Power, International EnergyAgency, IEA 2010
[35]. System Advisor Model (SAM), User Guide, 2010 National Renewable EnergyLaboratory
[36]. Technology Roadmap, Solar photovoltaic energy, International Energy Agency,IEA 2010
[37]. http://en.wikipedia.org/wiki/Photovoltaics
[38]. Solar energy, cost of turnkey PV in Germany drops ,http://www.renewablesinternational.net/cost-of-turnkey-pv-in-germany-drops/150/510/29911/
123
[39]. 100 MWp Solar PV Plant – Kom Ombo, EMPower Program, Phase II,Represented by KfW, June 2010 © Lahmeyer International GmbH
[40]. http://www.multi-science.co.uk/ee.htm
[41]. Wind power is crucial for combating climate change, wind, climate fact sheet,wind power works, saving CO2 every day, Global Wind Energy Council(GWEC), www.gwec.net, www.windpowerworks.net
[42]. Energy and environment report 2008, European Environment Agency, EEAReport No 6/2008
[43]. http://en.wikipedia.org/wiki/Environmental_impact_of_wind_power
[44] http://www.greenenergyguide.co.uk/wind/environmental-impact-of-wind-farms.php
[45] Environmental Impacts of Renewable Energy Technologies, Union of concernedscientists,http://www.ucsusa.org/clean_energy/technology_and_impacts/impacts/environmental-impacts-of.html
[46] Environmental Effects of Solar Energy,http://www.ehow.com/about_4780168_environmental-effects-solar-energy.html
[47] http://www.brighthub.com/environment/renewable-energy/articles/11255.aspx#ixzz1WNTmSkMi