Amendment One
RFP– PS-2019-0024 – Civil Engineering Services for 2020 Road Works
Changes, updates, and/or corrections as part of this addendum:
1. Correction of Schedule C1 project label on Map (Annex 4) and corresponding project code
in the Lump Sum table (Annex 5). Change from Countryview North to Wynngate.
2. Clarification of wording in the Schedule B Grading/Reconstruction Lump Sum tables
(Annex 5) from “subgrade” to “structure”.
3. Reference to “GBC” in the Schedule B Grading/Reconstruction Lump Sum tables (Annex 5)
has been removed.
4. Revision of Schedule B1 to remove 1.6km out of 4.8km of Grading, as a portion that was
previously included had already been upgraded. Map in Annex 4 and
Grading/Reconstruction Lump Sum table in Annex 5 have been revised to reflect the
change.
5. Addition of Schedule D Base Pave project. A new Schedule D1 Map (Annex 4) and
Schedule D Base / Pave Details and Lump Sum Tables (Annex 5) has been added. Section
4. Basis of Payment, 4.1.2 Contract value table has also been updated to include Schedule
D.
6. Schedule A Overlay Details and Lump Sum Tables (Annex 5) has had Schedule A1
updated to reflect the corrected project length, County Estimated Total Site Occ. Days, and
County Estimated Paving Days.
Addendum Number: One
File Number: PS-2019-0024
Date of Issue: August 23, 2019
Issued By: County Representative
Total Page(s): One (1)
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 1 of 27
4. Basis of Payment
4.1 Pricing Schedule
4.1.1 Payment for the satisfactory performance of the work under this Contract shall be based on the method of payment as detailed below.
The Schedule of Costs will serve as the basis for invoicing. Invoices must be supplemented with a detailed Expenditure Report showing per Phase percentage completion and costs this period, costs to date, projected final costs, and original estimated costs. As well, a total in each expenditure column summarizing the Total Costs will be required.
The Expenditure Report must include the costs represented by the current invoice and must be attached to the current invoice for easy reference.
4.1.2 This Contract value shall not be exceeded without the approval of the County Project Authority
Schedule A B C D Total Authorized Services Value: (CAD) $ $ $ $
GST payable (5%) $ $ $ $ Total Maximum Authorized Contract Value: (CAD)
$ $ $ $
4.2 Disbursements
4.2.1 The following costs shall be included in the fixed ceiling price in $CAD (with a Maximum of 2% by phase):
Communication expenses including but not limited to facsimile, local phone and cellular charges, administrative support provided by the Consultant’s staff to other members of its staff; and standard PC, presentation projection equipment, or computer aided design and drafting equipment (excludes specialized equipment or software as identified in the Consultant’s submission.);
4.2.2 No other expenses incurred by the Consultant will be reimbursed.
4.3 Method of Payment
4.3.1 Payments under the Contract shall be conditional upon performance, completion and delivery of the work, or any part of the work to the satisfaction of the Project Authority but subject to the submission to and approval by the County Project Representative of a claim for payment.
4.3.2 Subject to Council appropriation of funds and to 4.1.1 above, payment by the Project Authority for the work shall be made:
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 2 of 27
a) in the case of a progress payment, within thirty (30) days following the date of receipt of a dulycompleted work or progress report or within thirty (30) days of receipt of an invoice requestingpayment, whichever is later, and
b) in the case of a final payment, within thirty (30) days following the date of receipt of the completedwork or within thirty (30) days of receipt of an invoice requesting payment, whichever is later.
4.3.3 For purposes of the Contract a full day is any period of seven and one half (7.5) hours within anytwenty-four (24) hour period.
4.3.4 Payment will be made for services rendered, provided that:
a) the work is deemed satisfactory by the County;
b) invoices are submitted in accordance with the invoicing instructions contained herein, and asincorporated by reference in Section 5;
4.4 Invoicing
4.4.1 Invoicing is accepted via email, regular mail or Fax; preferably by email to [email protected]. The County of Grande Prairie’s payment terms are NET 30 unless otherwise posted on the invoice submitted. Cheque runs are processed weekly on Tuesday. For immediate payments, the invoice must be coded and signed by the proper authority and submitted to the accounts payable department no later than Friday to make it into the following cheque run. An EFT deposit is the preferable means of payment and can be set up upon request to the accounts payable department. Physical cheques are sent in regular mail on Wednesdays.
4.4.2 All invoices submitted for payment must be checked over and “signed off” by a project-knowledgeable representative of the Consultant. Failure to do so may result in rejection of the invoice.
4.4.3 The Consultant must include an Expenditure Report with each invoice, which must include the costs represented by the current invoice and must be attached to the current invoice for easy reference. The Report must identify the work completed and/or an itemized list of expenses, including all applicable receipts.
4.4.4 The Consultant is required to provide the following information on each invoice:
a) the legal name of the entity or individual, as applicable, i.e. the name associated with the SocialInsurance Number (SIN) or Business Number (BN), as well as the address and the postal code;
b) the status of the Consultant, i.e. individual, unincorporated business, corporation or partnership;
c) for individuals and unincorporated businesses, the Consultant’s SIN and, if applicable, the BN, orif applicable, the Goods and Services Tax (GST) number;
d) for corporations, the BN, or if this is not available, the GST number. If there is no BN or GSTnumber, the T2 Corporation Tax number must be shown.
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 3 of 27
4.5 Time Verification
4.5.1 Time charged and the accuracy of the Consultant’s time recording system may be verified by theCounty Project Representative before or after payment is made to the Consultant under the termsand conditions of the Contract. If verification is done after payment, the Consultant agrees torepay any overpayment immediately upon demand by the County.
4.6 Federal Goods and Services Tax (GST) Program
4.6.1 The Consultant’s GST number is ___________.
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 4 of 27
Annex 4 – Schedule location maps
(PAGE INTENTIONALLY LEFT BLANK)
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 5 of 27
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 6 of 27
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 7 of 27
DELETEABLE
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 8 of 27
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 9 of 27
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 10 of 27
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 11 of 27
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 12 of 27
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 13 of 27
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 14 of 27
ANNEX 5 – TOTAL SCHEDULE COST SUMMARY TABLE
Lump sums are only to include the items listed below for each type of work. The County acknowledges that there may be other costs associated with the project; additional items approved by the County Project Authority, necessary to complete the project will be managed using Extra Work Orders based on the Proponent’s unit rate schedule. All lump sum items will be paid based on a percentage completed not hourly fees.
All personnel on site are to be based local to the project area; costs associated with bringing in out of town staff shall not be included.
Digital drawing linework submissions are to be in the file type: Shape (ArcGIS) with the projection UTM NAD 83 Zone 11N.
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 15 of 27
SCHEDULE A – OVERLAY DETAILS AND LUMP SUM TABLES
1) PRELIMINARY ENGINEERING - Lump Sum to include:
Video log of the project
Topographical survey (asphalt extents and surface features)
Field inspections and assessment
Utility notification
Design review meeting
Geotechnical investigation (Deleteable)
2) DETAILED DESIGN - Lump Sum to include:
Preparation of detailed design drawings
Preparation of budget
Detailed design review meeting – 60%
Detailed design review meeting – pre-tender
3) TENDER PACKAGE PREPARATION - Lump Sum to include:
Bid item summary & cost estimate
Special provisions/review with the County
Completed tender package
Tender opening and bid package reviews
Tender award information & contract signing
4) CONTRACT ADMINISTRATION & PROJECT MANAGEMENT- Lump Sum to include:
Pre-construction meeting with the County & contractor(s)
Traffic Accommodation Strategy (TAS) & Environmental Construction Operations (ECO) Plan Review
Project update meetings (frequency to be determined)
Monthly progress payment certificates
5) CONSTRUCTION Survey - Lump Sum to include:
Base line
Centerline nails
Spotting for paint lines
*to follow Alberta Transportation frequencies
6) CONSTRUCTION Quality Assurance/Material Testing - Lump Sum by phase:
*to follow Alberta Transportation frequencies
7) CONSTRUCTION SUPERVISION - Lump Sum to include:
Project Manager – 1 hr/day, all construction days
Construction Supervisor - 10 hr/day, all construction days
Scale Person and Checker - 14 hr/day, paving construction days
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 16 of 27
8) POST CONSTRUCTION - Lump Sum to include:
Construction Completion Inspection with the County & Contractor
Final measurements and details, and on-Record survey
Video log of the project
Segregation Inspection
Final Inspection with the County & Contractor
1 Year Road Works Warranty
Submission of Finals and Summary Report
Digital Record drawings to include:
All CSP invert elevations
Edge of ACP including approaches
Sign locations and type
File type: Shape
Projection: UTM NAD 83 Zone 11 North
Schedule & Map A1 A2
A3 DELETEABLE
Project Code SR.LVR20 SR.VN20 SR.WW20 Type of Work Overlay Overlay Overlay Length (Km) 1.8 3.3 0.7
Lift 50mm 50mm 50mm Level Course 30mm 30mm 30mm
County Estimated Total Site Occ. (for Const. Super. evaluation purposes only)
9 17 4
County Estimated Paving Days (for Const. Super. evaluation purposes only)
3 6 1
1) PRELIMINARY ENGINEERING - Lump Sum
Geotechnical Investigation (Deleteable) 2) DETAILED DESIGN - Lump Sum
3) TENDER PACKAGE PREPARATION - Lump Sum
4) CONTRACT ADMINISTRATION - Lump Sum
5) CONSTRUCTION Survey - Lump Sum
6) CONSTRUCTION QA/MT - Lump Sum by phase
ACP
7) CONSTRUCTION SUPERVISION - Lump Sum
8) POST CONSTRUCTION - Lump Sum
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 17 of 27
SCHEDULE B – GRADING/RECONSTRUCTION DETAILS AND LUMP SUM TABLES
1) PRELIMINARY ENGINEERING - Lump Sum to include:
Video log of the project
Topographical survey for site plan preparation
Field inspections and assessment
Utility notification
Environmental factors incl. "No-Go" area delineation, and biophysical assessment (as required)
Geotechnical investigation
Design review meeting
2) DETAILED DESIGN - Lump Sum to include:
Preparation of detailed design drawings
Individual Ownership Plans (IOPs) incl. legal survey w/ registration (as required)
Preparation of budget
Utility coordination
Crossing agreements (as required)
Detailed design review meeting – 60%
Detailed design review meeting – pre-tender
3) TENDER PACKAGE PREPARATION - Lump Sum to include:
Bid item summary & cost estimate
Special provisions/review with the County
Completed tender package
Tender opening and bid package reviews
Tender award information & contract signing
4) CONTRACT ADMINISTRATION & PROJECT MANAGEMENT - Lump Sum to include:
Pre-construction meeting with the County & contractor(s)
Traffic Accommodation Strategy (TAS) & Environmental Construction Operations (ECO) Plan Review
Project update meetings (frequency to be determined)
Monthly progress payment certificates
5) CONSTRUCTION Survey - Lump Sum to include:
Survey data files provided to the contractor (for machine control)
Clearing flagging
Work stakes / base line
Grade stakes - one set
Plug CSPs
Final grade stakes - 2 sets
Quantity measurements
*to follow Alberta Transportation frequencies
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 18 of 27
6) CONSTRUCTION Quality Assurance/Material Testing - Lump Sum by phase:
*to follow Alberta Transportation frequencies
7) CONSTRUCTION SUPERVISION - Lump Sum to include:
Project Manager – 1 hr/day, all construction days
Construction Supervisor - 10 hr/day, all construction days
Scale person and Checker - 14 hr/day, surfacing gravel construction days
8) POST CONSTRUCTION - Lump Sum to include:
Construction Completion Inspection with the County & Contractor
Final measurements and details
Borrow source locations and volume measurements (as required)
Video log of the project
Final Inspection with the County & Contractor
1 Year Road Works Warranty
Submission of Finals and Summary Report
Digital Record drawings to include:
All CSP invert elevations
Edge of Gravel including approaches
Sign locations and type
File type: Shape
Projection: UTM NAD 83 Zone 11 North
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 19 of 27
Schedule & Map B1 B2 B3 B4
Project Code CR.2001 CR.2013 CR.2023 CR.2005
Type of Work Grading/ Recon.
Grading/ Recon.
Grading/ Recon.
Grading/ Recon.
Length (Km) 3.2 3.2 3.2 3.2
New Road Structure 9m Top 8m Top 8m Top 9m Top
0.8m Structure
0.8m Structure
0.8m Structure
0.8m Structure
3.5:1 side slope
3.5:1 side slope
3.5:1 side slope
3.5:1 side slope
County Estimated Total Site Occ. (for Const. Super. evaluation purposes only)
16 16 16 16
County Estimated Gravel Surfacing days (for Const. Super. evaluation purposes
only) 4 4 4 4
1) PRELIMINARY ENGINEERING - LumpSum
2) DETAILED DESIGN - Lump Sum
3) TENDER PACKAGE PREPARATION -Lump Sum
4) CONTRACT ADMINISTRATION - LumpSum
5) CONSTRUCTION Survey - Lump Sum
6) CONSTRUCTION QA/MT - Lump Sumby phase
Grading
Gravel Surfacing
7) CONSTRUCTION SUPERVISION -Lump Sum
8) POST CONSTRUCTION - Lump Sum
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 20 of 27
SCHEDULE C – MUNICIPAL CURB & GUTTER DETAILS AND LUMP SUM TABLES
1) PRELIMINARY ENGINEERING - Lump Sum to include:
Video log of the project
Topographical survey for site plan preparation
Field inspections and assessment
Utility notification
Geotechnical investigation
Design review meeting
2) DETAILED DESIGN - Lump Sum to include:
Preparation of detailed design drawings
Preparation of budget
Utility coordination
Crossing agreements (as required)
Detailed design review meeting – 60%
Detailed design review meeting – pre-tender
Hydrovac – supervision and GPS location
3) TENDER PACKAGE PREPARATION - Lump Sum to include:
Bid item summary & cost estimate
Special provisions/review with the County
Completed tender package
Tender opening and bid package reviews
Tender award information & contract signing
4) CONTRACT ADMINISTRATION & PROJECT MANAGEMENT - Lump Sum to include:
Pre-construction meeting with the County & contractor(s)
Traffic Accommodation Strategy (TAS) & Environmental Construction Operations (ECO) Plan Review
Project update meetings (frequency to be determined)
Monthly progress payment certificates
5) CONSTRUCTION Survey - Lump Sum to include:
Survey data provided to the contractor (as required)
Work stakes / base line
Curb and gutter layout
Final grade stakes - 2 sets
Quantity measurements
*to follow Alberta Transportation frequencies
6) CONSTRUCTION Quality Assurance/Material Testing - Lump Sum by phase:
*to follow Alberta Transportation frequencies
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 21 of 27
7) CONSTRUCTION SUPERVISION - Lump Sum to include:
Project Manager – 1 hr/day, all construction days
Construction Supervisor - 10 hr/day, all construction days
8) POST CONSTRUCTION - Lump Sum to include:
Construction Completion Inspection with the County & Contractor
Final measurements and details
Video log of the project
Segregation Inspection
Final Inspection with the County & Contractor
2 Year Road Works Warranty
Submission of Finals and Summary Report
Digital Record drawings to include:
All relevant pipe invert elevations
Edge of ACP or gravel including approaches, and back of curb
Sign locations and type
File type: Shape
Projection: UTM NAD 83 Zone 11 North
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 22 of 27
Schedule & Map C1 C2
Project Code CL.WG20 CL.WD20
Type of Work Muni. C&G Muni. C&G
Length (Km) 0.9 0.53
New Road Structure C&G both sides C&G both sides
Monosidewalk one side
Monosidewalk one side
80mm ACP 80mm ACP
300mm GBC 300mm GBC
Triaxle grid Triaxle grid
County Estimated Total Site Occ. (for Const. Super. evaluation purposes only)
21 12
1) PRELIMINARY ENGINEERING - Lump Sum
2) DETAILED DESIGN - Lump Sum
3) TENDER PACKAGE PREPARATION - Lump Sum
4) CONTRACT ADMINISTRATION - Lump Sum
5) CONSTRUCTION Survey - Lump Sum
6) CONSTRUCTION QA/MT - Lump Sum by phase
Grading
GBC
ACP
Concrete
7) CONSTRUCTION SUPERVISION - Lump Sum
8) POST CONSTRUCTION - Lump Sum
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 23 of 27
SCHEDULE D – BASE / PAVE DETAILS AND LUMP SUM TABLES
1) PRELIMINARY ENGINEERING - Lump Sum to include:
Video log of the project
Topographical survey for site plan preparation
Field inspections and assessment
Utility notification
Design review meeting
Geotechnical investigation (deletable)
2) DETAILED DESIGN - Lump Sum to include:
Preparation of detailed design drawings
Preparation of budget
Utility coordination
Crossing agreements (as required)
Detailed design review meeting – 60%
Detailed design review meeting – pre-tender
Hydrovac – supervision and GPS location
3) TENDER PACKAGE PREPARATION - Lump Sum to include:
Bid item summary & cost estimate
Special provisions/review with the County
Completed tender package
Tender opening and bid package reviews
Tender award information & contract signing
4) CONTRACT ADMINISTRATION & PROJECT MANAGEMENT - Lump Sum to include:
Pre-construction meeting with the County & contractor(s)
Traffic Accommodation Strategy (TAS) & Environmental Construction Operations (ECO) Plan Review
Project update meetings (frequency to be determined)
Monthly progress payment certificates
5) CONSTRUCTION Survey - Lump Sum to include:
Survey data provided to the contractor (as required)
Work stakes / base line
Grade stakes – 1 set
Final grade stakes - 2 sets
Quantity measurements
*to follow Alberta Transportation frequencies
6) CONSTRUCTION Quality Assurance/Material Testing - Lump Sum by phase:
*to follow Alberta Transportation frequencies
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 24 of 27
7) CONSTRUCTION SUPERVISION - Lump Sum to include:
Project Manager – 1 hr/day, all construction days
Construction Supervisor - 10 hr/day, all construction days
Scale Person and Checker - 14 hr/day, GBC and ACP construction days
8) POST CONSTRUCTION - Lump Sum to include:
Construction Completion Inspection with the County & Contractor
Final measurements and details
Video log of the project
Segregation Inspection
Final Inspection with the County & Contractor
1 Year Road Works Warranty
Submission of Finals and Summary Report
Digital Record drawings to include:
All relevant pipe invert elevations
Edge of ACP including approaches
Sign locations and type
File type: Shape
Projection: UTM NAD 83 Zone 11 North
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 25 of 27
Schedule & Map D1
Project Code NS.TR712
Type of Work Base / Pave
Length (Km) 4.9
New Road Structure 9m Top
120mm ACP
300mm GBC
4:1 Side Slope
Geogrid Biaxial - BX1200
County Estimated Total Site Occ. (for Const. Super. evaluation purposes only)
21
County Estimated GBC & ACP days (for Const. Super. evaluation purposes only)
14
1) PRELIMINARY ENGINEERING - Lump Sum
2) DETAILED DESIGN - Lump Sum
3) TENDER PACKAGE PREPARATION - Lump Sum
4) CONTRACT ADMINISTRATION - Lump Sum
5) CONSTRUCTION Survey - Lump Sum
6) CONSTRUCTION QA/MT - Lump Sum by phase
GBC
ACP
7) CONSTRUCTION SUPERVISION - Lump Sum
8) POST CONSTRUCTION - Lump Sum
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020
Page 26 of 27
End of Addendum Number 1
It is MANDATORY to return a signed copy of this Amendment in the RFP package submitted.
Signature Section for Confirmation of Receipt of Addendum No. 1 (Include in RFT Submittal)
_________________________ ________________________
Contractor’s Name (Print) Contractor’s Signature
_________________________ Date
Latest Revision: August 23, 2019 RFP # PS-2019-0024 – Civil Engineering Services for 2020