Amendment C183 and Bunnings Planning Application PPA 2013-307 · 7.2.3 Traffic Growth 10 7.2.4...
Transcript of Amendment C183 and Bunnings Planning Application PPA 2013-307 · 7.2.3 Traffic Growth 10 7.2.4...
Amendment C183 and Bunnings Planning Application PPA 2013-307
Expert Traffic Evidence Statement CG150578
Prepared for Benalla Road Enterprises Pty Ltd
20 July 2015
Amendment C183 and Bunnings Planning Application PPA 2013-307
Expert Traffic Evidence Statement CG150578
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno ii
Document Information
Prepared for Benalla Road Enterprises Pty Ltd
Project Name Expert Traffic Evidence Statement
File Reference CG150578Panel001F02.docx
Job Reference CG150578
Date 20 July 2015
Contact Information
Cardno Victoria Pty Ltd
Trading as Cardno
ABN 47 106 610 913
Level 4
501 Swanston Street
Melbourne
Victoria 3000 Australia
Telephone: (03) 8415 7777
Facsimile: (03) 8415 7788
International: +61 3 8415 7777
www.cardno.com
Document Control
Version Date Author Author Initials
Reviewer Reviewer Initials
F02 20/07/15 Hilary Marshall Stephen Hunt
© Cardno. Copyright in the whole and every part of this document belongs to Cardno and may not be used, sold, transferred, copied or reproduced in whole or in part in any manner or form or in or on any media to any person other than by agreement with Cardno.
This document is produced by Cardno solely for the benefit and use by the client in accordance with the terms of the engagement. Cardno does not and shall not assume any responsibility or liability whatsoever to any third party arising out of any use or reliance by any third party on the content of this document.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno iii
Table of Contents
1 Planning Panels Victoria Guidelines 1
2 Introduction 3
3 Background 4
3.1 Planning Application 4
3.2 Delegate’s Report 4
4 Issues 5
4.1 Submissions 5
4.1.1 Fordyce Street 5
4.1.2 Proposed Access Arrangements and Traffic Impact 5
4.1.3 Adequacy of Car Parking 5
5 Proposed Development 6
5.1 General 6
5.2 Car Parking 6
5.3 Vehicular Access 6
5.4 Loading / Service Vehicle Access 6
6 Greater Shepparton Freight and Land Use Study 2013 7
6.1 Overview 7
6.2 Land Use 7
6.3 Issues 8
6.4 Relevant Findings 8
7 Midland Highway Traffic Impact Study 9
7.1 Overview 9
7.2 Issues Identified between Florence Street and Fordyce Street 9
7.2.1 Fordyce Street / Midland Highway Intersection 9
7.2.2 Florence Street / Midland Highway Intersection 9
7.2.3 Traffic Growth 10
7.2.4 Masters Development 10
7.2.5 Bunnings Development 10
7.3 Midland Highway Impact Study Conclusions 10
7.4 Discussion 11
7.4.1 Item 1 – Fordyce Street 11
7.4.2 Item 5 and 11 – Review of phasing / accidents at Midland Hwy / Florence Street 11
7.4.3 Item 8 – Formalise Eastbound Left Turn Lanes 11
7.4.4 Item 10 – Right Turn Lane on Florence Street and Bicycle Lanes 11
8 O’Brien Traffic Impact Assessment 12
8.1 Overview 12
8.2 Car Parking Assessment 12
8.2.1 Statutory Requirement 12
8.2.2 Empirical Assessment 12
8.3 Fordyce Street / Gilchrist Street Intersection 12
8.4 Bicycle Parking Assessment 13
8.5 Loading 13
8.6 Traffic Impact Assessment 13
8.6.1 Traffic Generation 13
8.6.2 Traffic Distribution 14
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno iv
8.6.3 Traffic Impact 14
9 Traffix Peer Review of OBT Assessment 15
9.1 Background 15
9.2 Traffic Surveys 15
9.3 Parking Assessment 15
9.4 Car Park Design Review 15
9.5 Bicycle Parking 15
9.6 Traffic Generation and Impact 16
9.7 Traffic Distribution 16
9.8 Traffic Impact 16
9.9 Pedestrian Connectivity 17
9.10 Alternative Access Design 17
10 Proposed Masters Development 18
10.1 Development 18
10.2 Access 18
10.3 Car Parking Assessment 18
10.4 Traffic Impact Analysis 19
10.4.1 Traffic Generation Rate 19
10.4.2 Traffic Distribution 19
10.4.3 Traffic Impact 19
11 Car Parking Considerations 20
11.1 Statutory Parking Demand 20
11.2 Bunnings Case Study Data 20
11.3 Adequacy of Parking 20
12 Traffic Considerations 21
12.1 Purpose of Analysis 21
12.2 Assumptions 21
12.3 Existing Conditions 21
12.3.1 Parameters 21
12.3.2 Analysis 22
12.4 Traffic Generation 22
12.5 Traffic Distribution 23
12.6 Growth 23
12.7 Traffic Volumes 23
12.7.1 Proposed Development Traffic Volumes 23
12.7.2 Masters Traffic Volumes 24
12.7.3 Future Traffic Volumes Post Development 24
12.8 Future Intersection Operating Conditions 25
12.8.1 Methodology 25
12.8.2 Post Development Scenarios Analysed 25
12.8.3 Scenario 1 Results 26
12.8.4 Scenario 2 Results 27
12.8.5 Scenario 3 Results 28
12.9 Traffic Impact Summary 28
12.10 Review of OBT U-Turn Analysis at Watson Street 29
12.10.1 Intersection Geometry 29
12.10.2 OBT Assumptions 30
12.10.3 Sensitivity Analysis 30
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno v
12.10.4 Summary 30
13 Response to Issues 31
13.1 Fordyce Street 31
13.1.1 Footpath Provision 31
13.1.2 Increased Traffic 31
13.1.3 Parking Restrictions 31
13.1.4 Fordyce Street / Gilchrist Street Intersection 31
13.2 Access Arrangements and Traffic Impact 31
13.2.1 Proposed Bunnings Access and Midland Highway / Florence Street 31
13.2.2 Request for Additional Intersection Analysis 32
13.3 Adequacy of Car Parking 32
14 Conclusions 33
Appendices
Appendix A Existing Conditions SIDRA Analysis – Saturday Midday Peak
Appendix B SIDRA Analysis Future Conditions Scenario 1
Appendix C SIDRA Analysis Future Conditions Scenario 2
Appendix D SIDRA Analysis Future Conditions Scenario 3
Appendix E SIDRA Analysis Future Conditions U-Turn Lane Capacity At Watson St
Tables
Table 5-1 Proposed Development Schedule 6
Table 7-1 VicRoads Crashstat Accident History Midland Highway / Florence Street Intersection 9
Table 7-2 Midland Highway Study Recommendations 10
Table 8-1 Proposed Bunnings Development Schedule 12
Table 9-1 Traffic Survey Comparison, Midland Highway west of Florence Street 15
Table 10-1 Proposed Masters Development Schedule 18
Table 10-2 Proposed Masters Development Schedule 18
Table 12-1 Rating of Degrees of Saturation 22
Table 12-2 Existing Conditions Intersection Analysis – Midland H’way / Florence St, Sat 30/11/2013 22
Table 12-3 Scenario 1 Future Conditions– Midland Highway / Florence Street, Saturday Peak Hour 26
Table 12-4 Scenario 1 Future Conditions – Midland Highway / Bunnings Access Saturday Peak Hour 26
Table 12-5 Scenario 2 Future Conditions– Midland Highway / Florence Street, Saturday Peak Hour 27
Table 12-6 Scenario 2 Future Conditions – Midland Highway / Bunnings Access, Saturday Peak Hour 27
Table 12-7 Scenario 3 Future Conditions– Midland Highway / Florence Street, Saturday Peak Hour 28
Table 12-8 Scenario 3 Future Conditions – Midland Highway / Bunnings Access Saturday Peak Hour 28
Figures
Figure 2-1 Locality Plan 3
Figure 6-1 Existing and Proposed Land Use in the Vicinity of the Site 7
Figure 6-2 Identified Network Issues 8
Figure 8-1 OBT Traffic Distribution 14
Figure 10-1 Masters Anticipated Traffic Distribution 19
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno vi
Figure 11-1 Peak Car Parking Demand 20
Figure 12-1 Bunnings Saturday Peak Traffic Generation Rates 23
Figure 12-2 Bunnings Only Peak Hour Traffic Volumes (vph) 24
Figure 12-3 Masters Only Peak Hour Traffic Volumes (vph) 24
Figure 12-4 Future Peak Hour Traffic Volumes - Existing + Growth + Masters + Bunnings (vph) 24
Figure 12-5 Midland Highway / Watson Street Intersection Geometry 29
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 1
1 Planning Panels Victoria Guidelines
The following report has been prepared In accordance with the Planning Panels Victoria Guide to Expert
Evidence. My qualifications, expertise and instructions to undertake this work are summarised below:-
Name:
Hilary Anne Marshall
Address:
Cardno
Level 4, 501 Swanston Street
Melbourne Vic 3000
Professional Qualifications:
> Bachelor of Engineering (Civil) Hons, 1999, RMIT University
> Bachelor of Business (Management), 1999, RMIT University
Professional Experience:
> Senior Engineer – Cardno Victoria 2011 – present
> Associate – Urban Crossroads Irvine, California USA 2004 – 2006
> Senior Engineer – Grogan Richards Pty Ltd 2002 – 2004
> Engineer – Grogan Richards Pty Ltd 1999 – 2001
Areas of Expertise:
> Car parking, traffic and transportation.
> Traffic advice and assessment of land uses and development proposals to planning authorities,
government agencies, corporations and developers (including residential, retail, commercial, industrial,
institutional and mixed use projects).
Expertise to Prepare this Report:
My training and experience including involvement with all forms of development over a number of years
qualifies me to comment on the traffic implications of the proposal.
Instructions which defined the scope of this report:
I have been requested by Norton Rose Fulbright, on behalf of Benalla Road Enterprises Pty Ltd, on 1st July
2015, to provide my expert opinion, in regards to Amendment C183 and a 96A planning application for a
Bunnings warehouse on the site addressed as 90 Benalla Road and 15-33 Fordyce Street, Shepparton. .
I have been requested to provide my opinion on the following issues:
1. Review the O’Brien Traffic TIA dated April 2015;
2. Review the Masters endorsed plans and Planning permit and the GTA Traffic and Transport Design
Review prepared in support of the application;
3. Have regard to the Midland Highway Archer Street to Florence Street, Shepparton Cumulative
Traffic Impact Study prepared by Traffic Works dated 1 June 2015;
4. Have regard to the Greater Shepparton Freight and Land Use Study 2013 Framework Plan by
submitters; and
5. Review and respond to the Traffic Engineering Peer Review prepared for Council by Traffix dated
January 2014 and their subsequent report addressing signalised access dated 17 June 2014;
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 2
I have also been asked to provide my opinion on access issues, traffic impacts and parking, with particular
regard to:
Access arrangements into the site from Benalla Road;
Access into the site from Fordyce Street, including truck access;
Rates of car parking, having regard to other trade supplies uses of similar size;
Traffic generation and distribution and the impact on Benalla Road and surrounding streets.
Facts, Matters and Assumptions Relied Upon:
> Site visit, Saturday 11th July 2015;
> O’Brien Traffic report titled ‘Impact Assessment, Proposed Bunnings Warehouse, 90 Benalla Road,
Shepparton’ dated April 2015;
> Development Plans of the Bunnings warehouse prepared by Michael Carr Architects
> Greater Shepparton City Council Delegates Report, regarding application number 2013-307;
> Draft Planning Permit and Conditions;
> Traffix Group Peer Review titled ‘Proposed Bunnings Development, 90 Benalla Road, Shepparton’ dated
January 2014;
> Traffix Group letter to Greater Shepparton City Council (Ref: 16504L9612), titled ‘Traffic Engineering
Assistance – Signalised Access’ dated 17th June 2014;
> Planning Scheme Amendment and 96A application;
> Submissions by various parties;
> ‘Midland Highway Cumulative Impact Study, Archer Street to Florence Street’ prepared by Trafficworks
for Council, dated 1st June 2015;
> Greater Shepparton Freight and Land Use Study 2013 prepared by Aecom for Shepparton City Council;
> Masters Permit Plans and Traffic Report prepared as a letter by GTA consultants (Ref:14M1516000)
addressed to Masters Home Improvement dated 19th
December 2013;
> Austroads Guide to Traffic Engineering Practice – Part 5: Intersections at Grade.
Identity of Persons Undertaking the Work:
Hilary Marshall of Cardno, assisted by Stuart Valentine also of Cardno who prepared the SIDRA analysis.
I have made all the inquiries that I believe are desirable and appropriate, and no matters of significance,
which I regard as relevant, have to my knowledge been withheld from the Tribunal.
Hilary Marshall
Senior Engineer
for Cardno
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 3
2 Introduction
The subject site is located on the southern side of Benalla Road (Midland Highway) in Shepparton,
approximately 150 metres west of Florence Street, as shown in Figure 2-1.
Figure 2-1 Locality Plan
It is proposed to rezone approximately 2 hectares of land at 15-33 Fordyce Street from General Residential
Zone to Commercial 2 Zone and remove the Development Plan Overlay (Schedule 1) from the land.
In conjunction with the rezoning application a 96A planning permit was lodged for land addressed as 90-94
Benalla Road and part of 15-33 Fordyce Street Shepparton for the purpose of a Bunnings warehouse
development.
This report has been prepared in accordance with the Planning Panels Victoria Guidelines. In the course of
preparing this assessment, I have inspected the subject site and surrounding road network, researched
relevant case study data, analysed relevant traffic volume data, reviewed the proposed development plans
and referred to the documents and plans outlined in Section 1.
I believe the description of the subject site and the surrounding road network has been adequately
addressed within the 96A Traffic Impact Assessment prepared by O’Brien Traffic and does not need to be
repeated in this review.
My opinions with respect to the proposed development are set out in the following report.
Subject site
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 4
3 Background
3.1 Planning Application
A Section 96A planning application was lodged in March 2013, for the development of a Bunnings
Warehouse and rezoning of part of the land from General Residential to Commercial 2, which includes the
removal of a Development Plan Overlay (Schedule 1). The Application was supported by a Traffic Impact
Assessment prepared by O’Brien Traffic (OBT).
Council issued a Request for Further Information (RFI), which amongst other things requested the applicant
to undertake surveys of the existing Bunnings store to determine the existing traffic split and to also
undertake a sensitivity analysis to determine the number of u-turns that could be accommodated at the
western median opening.
Council engaged Traffix Group to undertake a peer review of the OBT application. The Traffix report is
discussed in further detail in Section 9, but concluded insufficient detail had been provided to warrant the
granting of a permit.
It is understood that negotiations between OBT, VicRoads and Council continued regarding access to
Midland Highway.
Traffix were also commissioned by Council to develop a concept plan for access which was included in their
letter of 17th June 2014.
The agreed treatment involves a traffic signal that will stop the westbound lanes only to allow right turn from
Midland Highway into the site.
OBT prepared a revised TIA in April 2015, which includes a concept plan of the proposed access.
The Amendment and 96A application were advertised and a number of submissions received.
3.2 Delegate’s Report
A Delegate’s Report was prepared for the original application and was subsequently updated following
provision of further information and submissions. A summary of Key Issues was identified at the end of the
report with the following issue relevant to this assessment:
After consultation between VicRoads, the applicant and Council, a traffic resolution requiring traffic
lights on Benalla Road was agreed upon.
In conclusion the Delegate’s Report stated that:
“The proposed developments impact on road safety has been reviewed by the Council engineers, O’Brien
Traffic and VicRoads and subject to compliance with conditions of the permit found to achieve acceptable
traffic outcomes.”
“Therefore it is recommended that a permit issue, subject to the rezoning being approved.”
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 5
4 Issues
4.1 Submissions
A total of 15 submissions were made in regards to the proposed amendment and planning application. The
issues raised in submissions, relevant to my assessment have been summarised as follows:
4.1.1 Fordyce Street
No footpath on Fordyce Street;
Traffic impact on Fordyce Street;
Object to ‘No Standing’ signs being installed along Fordyce Street as they currently use the on street
parking in the vicinity of their site for staff parking;
Confusion and illegal movements at the Fordyce Street / Gilchrist intersection.
4.1.2 Proposed Access Arrangements and Traffic Impact
Concerns about proposed access arrangements;
Impact on existing road network;
Application report didn’t account for other approved developments;
Analysis doesn’t include Shepparton Marketplace / Midland Highway / Florence Street intersection;
Impact of new signal on above intersection;
Only point of access is Midland Highway and any change to the existing traffic signals is not
supported;
Phasing of new signal to be linked to existing Marketplace / Midland Highway / Florence Street
intersection;
Increased traffic congestion at the following intersections:
a. Gilchrist / Fordyce Street
b. Watson Street / Benalla Road
c. Fordyce Street / Benalla Road
d. Callister Road / Benalla Road
4.1.3 Adequacy of Car Parking
Car parking requirement less than Masters for a larger store;
Bunnings customers may park in Shepparton Marketplace car park;
Customers will use Shepparton Marketplace car park;
Requested permit condition:
No pedestrian or vehicular access to be provided between Bunnings and Shepparton Marketplace.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 6
5 Proposed Development
5.1 General
The proposed Bunnings warehouse development schedule as defined within the OBT Impact Assessment is
summarised in Table 5-1.
Table 5-1 Proposed Development Schedule
Use Area (sqm)
Warehouse 9921
Bulk Trade 2283
Plant Nursery 2925
Building and Landscape Supplies
1680
Timber Yard 2664
Total 19473
5.2 Car Parking
Car parking is proposed along the entire length of the site on the eastern side. A total car parking provision
of 417 spaces is proposed, comprising 404 standard bays, 9 disabled bays and 4 car plus trailer bays.
5.3 Vehicular Access
Access to the site is proposed as a new signalised intersection to Benalla Road allowing left and right turn in
and left turn out.
A second two way vehicular access is proposed in the southwest corner of the site, providing fully directional
access to Fordyce Street approximately 50 metres south of Gilchrist Street.
5.4 Loading / Service Vehicle Access
A loading area is proposed to be located in the southwest portion of the site adjacent to Fordyce Street. The
loading area will be separated from the parking areas and general public access. The loading area will take
access to Fordyce Street, immediately north of Gilchrist Street.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 7
6 Greater Shepparton Freight and Land Use Study 2013
6.1 Overview
Aecom prepared the Greater Shepparton Freight and Land Use Study Framework Plan for Greater
Shepparton City Council dated 4th June 2013.
The purpose of the study was to identifying infrastructure needs and priorities primarily related to freight
movements through and around the City of Shepparton.
6.2 Land Use
The existing and proposed land uses within the vicinity of the subject site are shown in Figure 6-1.
Figure 6-1 Existing and Proposed Land Use in the Vicinity of the Site
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 8
As shown in the preceding figure, existing industrial land use is currently concentrated in the area north east
of the Shepparton town centre, including the area immediately north of the proposed Bunnings store.
Figure 6-1 also highlights (by the number 14) a large area of future residential growth south of the subject
site and west of Doyles Road.
6.3 Issues
The Framework Study identified a number of existing and potential issues. An excerpt of the Issues Map is
shown in Figure 6-2.
Figure 6-2 Identified Network Issues
Of relevance to this report is the identification of Florence Street, including its intersection with Midland
Highway, as having existing road network issues. It was noted that large vehicles such as B-Doubles
currently have trouble turning from Florence Street into Midland Highway. The report also stated that the
use of Florence Street, opposite the proposed Masters, as an informal truck stop was not appropriate.
6.4 Relevant Findings
The Framework Study stresses the importance of decreasing the reliance on Midland Highway as the
primary east west link though the Greater Shepparton area.
The Framework also identifies the Florence Street / Midland Highway intersection as needing an upgrade,
although no timing or priority was given as to what was required or when this should occur.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 9
7 Midland Highway Traffic Impact Study
7.1 Overview
Greater Shepparton City Council commissioned Trafficworks Pty Ltd to undertake an investigation of existing
and future operating conditions along Midland Highway between Archer Street and Florence Street. In
regards to future operating conditions Trafficworks were specifically asked to take the approved Masters
store and the proposed Bunnings relocation into account.
The report prepared by Trafficworks is titled ‘Midland Highway, Archer Street to Florence Street, Shepparton,
Cumulative Traffic Impact Study’ dated 1 June 2015.
7.2 Issues Identified between Florence Street and Fordyce Street
Of relevance to the road network abutting the subject site, the cumulative impact assessment identified the
following existing issues:
7.2.1 Fordyce Street / Midland Highway Intersection
“The southern service road connections to Fordyce Street produce a cross road intersection immediately
adjacent to the highway intersection. This creates an inherently unsafe layout that is inconsistent with the
other service road terminal treatments in this area. It is recommended that the eastern section of this service
road be terminated with a connection to the Benalla Road WBC (westbound carriageway) prior to the
Fordyce Street intersection, thereby matching the service road terminal treatments east of Zurcas Lane,
Watson Street and Callister Street.”
7.2.2 Florence Street / Midland Highway Intersection
“Florence Street: very short green times for the minor (north and south) legs resulting in extended queuing
into The Marketplace and insufficient time to clear trucks entering the highway from Florence Street. It is
suggested VicRoads also investigate timing improvements at this site.”
Trafficworks undertook a review of the VicRoads Crashstat database which details all reported accidents, up
to the end of 2013. I have verified the data collected by Trafficworks and agree that all accidents have been
included between the time periods, 2009 to 2013 inclusive. A summary of the accident history in the vicinity
of the site is shown in Table 7-1.
Table 7-1 VicRoads Crashstat Accident History Midland Highway / Florence Street Intersection
Location1
Year of Accident
Accident Code Type of accident Number of Vehicles Involved
Severity2
Midland Highway & Florence Street
2013 121 Right Through
Right turning vehicle hit by through vehicle
2 Other Injury
2013 121 Right Through
Right turning vehicle hit by through vehicle
2 Other Injury
2013 121 Right Through
Right turning vehicle hit by through vehicle
2 Other Injury
2012 121 Right Through
Right turning vehicle hit by through vehicle
2 Other Injury
2011 137 Left turn Sideswipe
Left turning vehicle hit by left turning vehicle
2 Other Injury
2011 121 Right Through
Right turning vehicle hit by through vehicle
3 Other Injury
1 The information in the preceding table has been sourced from VicRoads Crashstat database 2009-2013, data is currently updated to
the end of December 2013. Only accidents at the intersection have been included.
2 In terms of severity, accidents are classified as a fatality, serious injury, other injury or not injured.
Although no serious injuries or fatalities have occurred, the incidence of 6 accidents over the past 56 years
would have identified this intersection as a VicRoad Blackspot.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 10
7.2.3 Traffic Growth
The cumulative impact study referred to modelling that had been undertaken by Aecom for Midland Highway
that found:
“Highway volumes are approximately 6,500vpd in each direction at Archer Street, reducing to 5,500vpd at
Florence Street. These volumes are expected to increase by 8-10% over the next 10 years.”
7.2.4 Masters Development
The only concern raised by Trafficworks in regards to the Masters site was the potential for vehicles turning
right into the proposed Florence Street access to queue back to Midland Highway.
GTA included a SIDRA analysis of the proposed access to Masters on Florence Street, which indicated not
only the Masters development traffic but 10 years growth applied to existing through movements on Florence
Street. The results from this future analysis indicates 95th percentile peak queues of 2m during the Friday
PM peak and 5m during the midday Saturday peak. This level of queuing is equivalent to one vehicle or less
and in my opinion would be unlikely to queue back to the Midland Highway intersection on the basis of the
GTA analysis.
7.2.5 Bunnings Development
Trafficworks did not have the opportunity to review the OBT impact assessment for the proposed Bunnings
store; however they were able to review the proposed signalised access on Midland Highway. Trafficworks
stated that “the proposed left slip lane from the east can be considered minimal. There is scope for it to be
extended to store entering vehicle queues, which are likely to include car/trailer combinations, clear of the
westbound highway through traffic lane.”
The proposed intersection design shall be to the satisfaction of the Responsibly Authority (VicRoads) who
shall determine the appropriate lane lengths required for storage and appropriate deceleration.
7.3 Midland Highway Impact Study Conclusions
Trafficworks outlined a number of recommendations in Table 4 of their report with the following relevant to
the Bunnings proposal.
Table 7-2 Midland Highway Study Recommendations
Item Action Additional Description Responsible Priority
1 Review the service road connection to Fordyce Street
To remove the cross road layout and provide consistency of treatments
VicRoads and GSCC
Low
5 Investigate the five right through crashes at Florence Street
To develop appropriate countermeasure strategy
VicRoads High
8 Prohibit kerbside parallel parking wast of Callister Street intersection to Florence Street (north side) to:
Create a continuous bicycle lane;
Create left turn lanes at all intersections
GSCC
VicRoads and GSCC
High
High
10 Ancillary works for the Masters development to include a line marking scheme for Florence Street and bicycle lane treatment in Benalla Road
To address traffic congestion by providing a Type CHR right turn lane treatment in Florence Street at the car park entry.
Provide coloured pavements for the cycle lane crossings at the Benalla Road access points.
GSCC
GSCC
High
High
11 Investigate signal phasing improvements at Archer Street and Florence Street:
To reduce queuing in The Marketplace approach to Florence Street.
VicRoads High
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 11
7.4 Discussion
7.4.1 Item 1 – Fordyce Street
I agree with the suggested improvements at the Fordyce Street / Midland Highway intersection.
7.4.2 Item 5 and 11 – Review of phasing / accidents at Midland Hwy / Florence Street
I believe the recommendation to investigate the accidents at Florence Street / Midland Highway (Item 5)
would have to also include an investigation of the current phasing at this intersection (Item 11) and therefore
do not see these items as being independent of each other. I agree that given the number of accidents at
this intersection to date that a High priority rating should apply.
7.4.3 Item 8 – Formalise Eastbound Left Turn Lanes
I am not convinced it is necessary to remove all parking along the northern kerb of Benalla Road, however
the formalisation of a left turn lane from Benalla Road into Florence Street given the anticipated increase in
traffic due to the Masters development should in my opinion be included in the proposed modifications to this
intersection.
7.4.4 Item 10 – Right Turn Lane on Florence Street and Bicycle Lanes
As previously discussed the GTA analysis does not indicate that a CHR treatment is required adjacent to the
proposed car park entry to Masters on Florence Street.
I agree the bicycle lane should be as clear as possible past a potential conflict point with access into the
proposed Masters site.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 12
8 O’Brien Traffic Impact Assessment
8.1 Overview
I have been requested to review the OBT traffic assessment titled ‘Traffic Impact Assessment, Proposed
Bunnings Warehouse, 90 Benalla Road Shepparton’ dated April 2015. The report was prepared to
accompany the planning submission for the proposed Bunnings store.
It is understood that this report supersedes an earlier application report.
8.2 Car Parking Assessment
8.2.1 Statutory Requirement
OBT assessed the statutory parking requirement adopting the land use of Trade Supplies and Restricted
Retail.
OBT applied the Trade Supplies rate to the entire site area and then added a further Restricted Retail rate to
25% of the floor area, as shown in Figure 8-1.
Table 8-1 Proposed Bunnings Development Schedule
Use Area (sqm) Rate Area / Number of Spaces
Trade Supplies 42850sqm 10% of site area 4285sqm
Restricted Retail 4868sqm 3 per 100sqm floor area 146 spaces
In order to determine the number of spaces that would be required within the 4,285sqm, OBT adopted a car
park area of 25sqm. An area of 25sqm equates to a parking bay 2.6m wide by 4.9m long with an allowance
of 4.71m of the aisle.
Cardno typically adopt an area of 29.38sqm which allows for a 2.6m bay by 4.9m long with an aisle of 6.4m.
Applying the two car bay areas to the 4,285sqm. results in a requirement of between 146 and 171 spaces.
As the Planning Scheme does not specify the methodology that should be adopted the OBT assumptions
are considered acceptable with the method resulting in a more conservative assessment of the car park
requirement.
The statutory parking requirement determined by OBT for the proposed Bunnings store was deemed to be
317 spaces.
I believe this is a reasonably conservative assessment of the Planning Scheme parking requirement.
8.2.2 Empirical Assessment
The OBT report states that Metropolitan Bunnings stores generate between 1.1 and 2.8 spaces per 100sqm,
with regional stores generating between 1.2 and 1.7 spaces per 100sqm.
The source of the data and size of the regional stores is not included.
The proposed parking provision of 417 spaces equates to a parking rate of 2.14 spaces per 100sqm. Based
on the preceding regional rates outlined by OBT the proposed provision appears to be appropriate.
8.3 Fordyce Street / Gilchrist Street Intersection
The OBT report outlines modifications to the Fordyce Street / Gilchrist Street intersection, including changes
to kerb alignment, linemarking and signage.
The proposed changes are supported and should be considered by Council regardless of whether the
Bunnings development proceeds or not.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 13
8.4 Bicycle Parking Assessment
I agree with the OBT assessment that a statutory requirement for 64 staff and 38 customer bicycle parking
spaces seems excessive.
In my opinion sustainable transport choices should be facilitated wherever possible. Although the number of
customers choosing to ride to the store is expected to be minimal it is still a feasible option given the access
from Fordyce Street and bike lanes on Midland Highway. Likewise, bicycle parking for staff should be
provided to encourage less dependence on private vehicles.
The OBT proposed parking provision of 6 spaces for staff in a secure location with an additional 6 spaces in
a visible location close to the entry seems a reasonable provision.
In the event that the supply was being exceeded on a regular basis, I think it would be reasonable to assume
that additional space could be found on site to provide additional bicycle parking.
8.5 Loading
The OBT report states that the statutory loading requirement is 207.4sqm and that the area provided
exceeds that requirement. The plans of the loading area indicate dimensions of 59.29 meters by 47.99
metres resulting in an area of 2,845sqm, well in excess of the Planning Scheme requirement.
The swept paths provided within the OBT report are unclear, with no indication of a scale or specifications of
the design vehicle used.
Therefore I have undertaken a review of swept path movements for a 26m B-Double vehicle which can
comfortably manoeuvre through the loading bay without reversing and can also access and egress the site
from Fordyce Street in a forwards direction. I am satisfied that the loading area is appropriate for the
proposed use.
8.6 Traffic Impact Assessment
8.6.1 Traffic Generation
OBT commissioned traffic surveys at the existing Bunnings store on Friday 28th February and Saturday 1
st
March 2014. The existing store has a floor area of 9,569sqm. The survey results are summarised as
follows:
Friday 3-4pm 317 trips = 3.3 vehicle movements per 100sqm
Saturday 11am-12pm 612 trips = 6.4 vehicle movements per 100sqm
OBT did not adopt the traffic generation rates found at the existing store. Instead they relied on anecdotal
evidence supplied by Bunnings that customers to the new Bunnings would be no more than 50% higher than
the existing patronage.
Based on the preceding information OBT assumed that customers would increase by 60%. The projected
traffic generation of the Bunnings warehouse was estimated as follows:
Friday 510 trips
Saturday 980 trips
Although OBT did not convert these numbers into traffic generation rates, I think it allows an easier
comparison.
Friday 510 trips = 2.62 vehicle movements per 100sqm
Saturday 980 trips = 5.03 vehicle movements per 100sqm
Although I agree in principle that the proposed Bunnings store is unlikely to continue generating at the same
rate per 100sqm of floor area as the existing store, especially given the close proximity of the proposed
Masters store, I have undertaken an independent traffic analysis as detailed in Section 12, using case study
data.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 14
8.6.2 Traffic Distribution
The anticipated traffic distribution adopted within the OBT report is based on traffic counts undertaken at the
existing Bunnings. The assumed distribution is shown in Figure 8-1.
Figure 8-1 OBT Traffic Distribution
The Freight and Land Use Study outlined a large area of future residential development south of the subject
site. New residential areas typically generate demand for home hardware and landscape type products and
as such could be assumed to be future customers of the proposed Bunnings store.
Furthermore there is a large area of existing residential development south of the subject site that would
have previously had to use Midland Highway to access the Bunnings. The provision of an access from
Fordyce Street would eliminate the need for these customers to use Midland Highway to access the site.
Therefore although I generally agree with the proposed distribution I think the 20% entering the southern
access on Fordyce Street would be likely to return the way they came, rather than having 6% of exiting
vehicles from Fordyce Street drive back to Midland Highway as proposed by OBT.
8.6.3 Traffic Impact
The OBT Assessment prepared in April 2015, does not include the results of their traffic analysis, which was
negotiated with Council and VicRoads prior to the preparation of their report. The report does state that:
“Benalla Road will operate satisfactorily when the Bunnings Warehouse opens and will continue to operate
satisfactorily even after 10 years of growth is applied to Benalla Road traffic. Fordyce Street will also
operate satisfactorily after the Bunnings Warehouse is developed.”
I have not been provided with a copy of the submission to VicRoads and Council or the SIDRA files of the
proposed access arrangement and therefore have undertaken an independent assessment of the traffic
conditions as detailed in Section 12.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 15
9 Traffix Peer Review of OBT Assessment
9.1 Background
Traffix Group was commissioned by Greater Shepparton City Council to undertake a Peer Review of the
OBT report submitted with the planning application for the Bunnings warehouse.
Traffix prepared a report titled ‘Proposed Bunnings Development, 90 Benalla Road, Shepparton’ dated
January 2014. A subsequent letter was also prepared by Traffix on the 17th June 2014 to address further
issues that had been raised, particularly in regards to the proposed new traffic signal on Midland Highway.
The Traffix Peer Review is based on the OBT Traffic Impact Assessment dated November 2013 (Ref 14787).
I have not seen a copy the OBT report prepared in November 2013, and as such have based my review of
the Traffix peer review in the context of the current OBT application report dated April 2015.
9.2 Traffic Surveys
Traffix highlighted that the OBT traffic surveys had been undertaken on the Melbourne Cup long weekend
and may not be representative of typical conditions.
I agree with Traffix that this was not an ideal time to undertake traffic surveys. I have compared the GTA
peak hour turning movements at Midland Highway / Florence Street undertaken a couple of weeks later on
Saturday 20th November 2013 to the OBT Saturday peak hour traffic movements at the Midland Highway /
Service Road entry undertaken on Saturday 2nd
November 2013.
The comparison is summarised in Table 9-1.
Table 9-1 Traffic Survey Comparison, Midland Highway west of Florence Street
Direction OBT Sat 2/11/2013 (Melbourne Cup Long Weekend)
GTA Sat 20/11/2013 Difference
Eastbound 1023 vph 1101 vph 78 vph (8%)
Westbound 901 vph 1120 vph 219 vph (24%)
Total 1924 vph 2221 vph 297 vph (15%)
As shown in the preceding table the difference is not significant in the eastbound direction, however the GTA
results were 219 vph or 24% higher in the westbound direction, which is significant for the purposes of
analysing the proposed Bunnings access.
On this basis I have adopted the GTA traffic survey results to determine eastbound and westbound
movements past the subject site.
9.3 Parking Assessment
Traffix are satisfied the proposed car parking supply exceeds the statutory requirement. Traffix also
prepared a car parking demand assessment based on case study data and stated that :
“We are satisfied that the proposed car parking provision of 408 car spaces is appropriate and will be
sufficient to accommodate the peak parking demands generated by the development without any adverse
off-site impacts.”
9.4 Car Park Design Review
Traffix undertook a design review of the proposed car park and access and were satisfied that the layout met
or exceeded the relevant requirements.
9.5 Bicycle Parking
Traffix agreed with OBT that the statutory requirements for bicycle parking for this type of use are excessive.
Traffix suggested that the parking requirement for restricted retail be applied to 25% of the floor area,
resulting in a requirement of 8 spaces for staff and 10 spaces for customers.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 16
As discussed in the previous section, I think OBT’s suggestion of 6 staff and 6 customer spaces is
reasonable. However the provision of an additional 2 secure staff spaces to increase the supply to 8 as
suggested by Traffix would not require a substantial increase to the area within the proposed building.
Based on my observations of various Bunnings stores the suggested provision of 10 bicycle spaces for
customers seems excessive.
9.6 Traffic Generation and Impact
The proposed rates in the OBT report that Traffix reviewed suggested that the proposed Bunnings would
generate traffic at the following rates;
3 .0 trips per 100sqm on a Friday PM peak hour; and
5.5 trips per 100sqm on a Saturday midday peak hour.
Traffix then went onto list a number of case studies that indicated an average rate of
3.6 trips per 100sqm on a Friday PM peak hour; and
7.1 trips per 100sqm on a Saturday midday peak hour
Traffix acknowledged that they had not collected any of the data themselves and as such were unsure of the
areas used to determine the rates. Therefore Traffix did a comparison of raw traffic numbers, suggesting
that the generated traffic by the proposed Bunnings was higher than all the stores surveyed during the
weekday PM peak and all except the Nunawading store on the Saturday midday peak.
On this basis Traffix concluded that the traffic assessment was appropriately conservative, but suggested
that a case study of the existing Bunnings would provide a more accurate estimate.
I disagree that surveying the existing store would provide a more accurate assessment. Rarely in traffic
terms can you double the floor area of a use and expect it to continue generating at the same rate per
100sqm, particularly uses of this magnitude.
9.7 Traffic Distribution
Traffix suggested that the traffic distribution should be based on the existing Bunnings store. Although this is
a reasonable approach, it should be noted that the existing store takes access from Midland Highway only,
whereas the proposed development will provide an additional access to the south, feeding directly into a
large residential catchment.
It is anticipated that a large portion of customers living to the south west of the Bunnings store who would
have previously made their way to the Midland Highway and approached from the west would now use the
local road network to Fordyce Street instead.
As previously discussed I think the OBT distribution is reasonable.
Traffix also state that:
“Distribution of 20% of site-generated traffic to / from the south via the local residential street network is
substantial.”
It would be reasonable to assume that half of the 20% arrived / departed via Gilchrist Street with the
remaining 10% using Fordyce Street to the south. This level of traffic is equivalent to a peak of around 98
vehicle movements per hour on a Saturday.
Unfortunately survey data is not available at Fordyce Street / Gilchrist Street intersection to determine the
likely future traffic volumes. However based on observations and a review of land use in the area I would
expect existing traffic volumes to be relatively low and able to accommodate the additional traffic.
9.8 Traffic Impact
The traffic impact section of Traffix peer review is not considered relevant to this assessment as it was based
on superseded traffic generation rates for the Bunnings development, a superseded distribution and road
network assumptions that are no longer valid, such as the ability to undertake u-turns at Mitchell Street.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 17
9.9 Pedestrian Connectivity
I agree with the Traffix assessment that a pedestrian path should at least be provided from the entry to the
existing footpath along the southern service road along the Midland Highway frontage.
A pedestrian link between Shepparton Marketplace and the Bunnings store is considered reasonable,
however if this is not provided pedestrians still have the opportunity to visit both sites in a single trip by using
the footpath along the frontage of the site, which currently terminates at the western end of the Shepparton
Marketplace car park.
9.10 Alternative Access Design
I have reviewed the letter prepared by Traffix on 17th June 2014 regarding an alternative traffic signal design
which recommends a full traffic signal across Midland Highway allowing right turns out of the site.
It is my understanding that through negotiations with VicRoads and OBT that VicRoads’ preferred access
arrangement is the OBT design.
The only benefit of a fully signalised intersection at the Bunnings access is to facilitate right turns out of the
site. To accommodate right turns out, an additional phase would be required further reducing the time
allocated to through traffic on Midland Highway, which should have priority over all other movements.
In my opinion the full signalisation of the Bunnings access is not necessary, as traffic wishing to travel east
along Midland Highway can undertake a u-turn at the existing u-turn facility at the Midland Highway / Watson
Street intersection. I have analysed the capacity of the Watson Street u-turn lane against eastbound traffic
and are satisfied that the predicted u-turn traffic volume can be accommodated at this intersection.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 18
10 Proposed Masters Development
10.1 Development
Based on the development plan prepared by Leffler Simes Architects (Reference TP02 Rev E) dated
22/4/2014, it is anticipated that the Masters site will contain a Masters store, 2 Pad sites and a separate
tenancy as shown in Table 10-1. The areas contemplated in the GTA Traffic Assessment (prepared
19/12/2013) predate the areas shown on the Architects plan provided. Therefore I have also included the
previously proposed areas which relate to the GTA traffic assessment.
Table 10-1 Proposed Masters Development Schedule
Use Anticipated Use Area (sqm) Areas Adopted in GTA Application Report
Masters 13,655sqm GLFA 13,521sqm GLFA
Tenancy Restricted Retail 501sqm 530sqm
Pad Site 1 1,200sqm NA
Pad Site 2 1,668sqm NA
Pad Site 3 Service Station / Convenience Restaurant
NA 2,000sqm
120 seats
Based on the GTA assessment a parking supply of 428 spaces is proposed.
10.2 Access
Access to the Masters is proposed via new access points to Midland Highway, Florence Street and
Enterprise Drive.
Additional access points are proposed adjacent to the eastern boundary of the site onto Enterprise Drive with
egress provided via a left out only access onto Midland Highway.
10.3 Car Parking Assessment
For the purpose of determining the statutory parking requirement for the Masters store, GTA applied the
following rates to the various components of the overall store.
Table 10-2 Proposed Masters Development Schedule
Use Area / Number Rate 10% of Area Number of Spaces Required
Restricted Retail 8231sqm 3 spaces / 100sqm 246 spaces
Trade Supplies 2195sqm 10% of total site area 219.5sqm 14 spaces 1
Landscape Garden Supplies
1951sqm 10% of total site area 195.1sqm
Total Requirement for Masters
260 spaces
Service Station 2000sqm 10% of total site area 200sqm 7
Restricted Retail 530sqm 3 spaces / 100sqm 15
Convenience Restaurant
120 seats 0.3 spaces per patron 36
Total Other Uses Convenience Restaurant + Service Station; Or
Convenience Restaurant + Restricted Retail
43 spaces or
51 spaces
1 GTA has assumed a car space area of 29.38sqm based on a 2.6m x 4.9m space including the entire aisle
of 2.6m x 6.4m.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 19
10.4 Traffic Impact Analysis
10.4.1 Traffic Generation Rate
GTA outlined likely traffic generation rates for the proposed Masters as follows:
Friday 0.80 – 1.98 vehicle movements per 100sqm
Saturday 2.20 – 3.72 vehicle movements per 100sqm
The rates at the lower range were sourced from case study data collected at Masters in Box Hill, while the
upper rates were sourced from a case study undertaken at the existing Bunnings store in Shepparton.
It is noted that the traffic generation rates collected at Bunnings Shepparton are considerably lower than the
rates collected by OBT, which were 3.3 and 6.4 vehicle movements per 100sqm on Friday and Saturday
respectively.
Based on the range outlined above GTA adopted the average traffic generation rate as follows:
Friday 1.39 vehicle movements per 100sqm = 188 vehicle movements
Saturday 2.96 vehicle movements per 100sqm = 400 vehicle movements
In addition to the Masters site, an allowance for the restricted retail tenancy and Pad Site 3 were included,
with an additional 221 vehicle movements during the Friday PM peak and 226 vehicle movements during the
Saturday peak included.
10.4.2 Traffic Distribution
The GTA report did not discuss the assumed traffic distribution, but did include development only traffic
movements at each intersection including the Midland Highway / Florence Street intersection.
Based on the turning movements provided, GTA have adopted the distribution shown in Figure 10-1.
Figure 10-1 Masters Anticipated Traffic Distribution
As discussed above approximately one-third of traffic is related to the potential convenience restaurant which
would be located in the south east corner of the site with left out only access to Midland Highway.
The pad site has a significant effect on the overall traffic distribution specifically the 52% eastbound exit
movements along Midland Highway.
Given the permeability Florence Street offers to the north I think the assumed Masters distribution is
appropriate.
10.4.3 Traffic Impact
Although the GTA analysis indicates that the Masters will not have a detrimental impact on the existing
operating conditions of the Midland Highway / Florence Street intersection, it does not include the Bunnings
proposal and therefore does not address the issues raised in submission.
As previously stated I have undertaken a holistic analysis detailed in Section 12.
20%
12%
0% 0%
62%
36%
0%
0%
18%
52%
Proposed Masters Site
Midland Highway
Enterprise Drive
Flo
rence S
tre
et
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 20
11 Car Parking Considerations
11.1 Statutory Parking Demand
Based on the assessments made by OBT, GTA and Greater Shepparton City Council there seems to be no
clear consensus on the applicable planning scheme land use definitions that should apply to a Bunnings or a
Masters.
The methodology adopted by OBT is considered conservative as it applies the Trade Supplies parking rate
to the entire site and then applies the Restricted Retail rate to 25% of the floor area which has already been
included in the previous requirement for Trade Supplies, effectively double counting 25% of the floor area.
Furthermore the use of only 25sqm (rather than 29.38sqm) to calculate the number of spaces that would be
required by the 10% of site area, builds in further conservatism. The approach adopted by OBT is
considered reasonable. The statutory parking requirement determined by OBT for the proposed Bunnings
store was deemed to be 317 spaces.
11.2 Bunnings Case Study Data
A summary of case study data for Bunnings stores including data collected by Cardno and other consultants
and is shown in Figure 11-1.
Figure 11-1 Peak Car Parking Demand
The peak parking demands range from 1.2 to 2.5 spaces per 100sqm. The average demand as shown in
the preceding figure is 1.83 spaces per 100sqm.
The proposed parking provision is equivalent to 2.14 spaces per 100sqm. If the average rate is applied to
the application floor area of 19,473sqm it results in a demand of 356 spaces. The proposed parking
provision of 417 spaces exceeds the average demand by 61 spaces.
11.3 Adequacy of Parking
It is acknowledged that the case study data is based on conventional sized Bunnings stores and does not
include any stores as large as the proposal.
Car park demand is typically a function of the size of the facility, range of products available, catchment area
and the amount of competition. As highlighted within the OBT report relocating the Bunnings store
approximately 700 metres to the west will not change its current catchment area. Furthermore the addition
of a Masters on the same road within 200 metres will significantly increase the amount of competition in the
area. It is anticipated that the larger Bunnings will be able to provide a greater range of existing products
and increase display areas rather than introduce entirely new product lines that are not currently offered.
Based on the case study data and the preceding discussion the proposed parking rate of 2.14 spaces per
100sqm of floor area, equivalent to 417 spaces is considered satisfactory.
0
0.5
1
1.5
2
2.5
3
4,000 6,000 8,000 10,000 12,000 14,000 16,000
Park
ing
Rate
/ 1
00sq
m F
A
Floor Area (sqm) Peak Sat. Rate Average
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 21
12 Traffic Considerations
12.1 Purpose of Analysis
In light of the submissions outlined in Section 4.1, I have undertaken the following analysis to specifically
address the following concerns:
The application report did not account for other approved developments;
The analysis does not include Shepparton Marketplace / Midland Highway / Florence Street
intersection;
The impact of new signal on above intersection;
The only point of access is Midland Highway and any change to the existing traffic signals is not
supported;
The phasing of new signal should be linked to existing Marketplace / Midland Highway / Florence
Street intersection.
12.2 Assumptions
The following analysis is based on the following assumptions and information:
Existing traffic count data collected by GTA consultants at the intersection of Midland Highway /
Florence Street on Friday 29th and Saturday 30
th November 2013.
The GTA data results in higher through volumes on Midland Highway than the OBT traffic count and
as such has been used to factor up through volumes adjacent to the proposed Bunnings access.
Existing turning movements at the service road entry opposite the subject site have been sourced
from the OBT traffic assessment.
As demonstrated by the GTA traffic surveys, peak traffic volumes occur during the Saturday peak
period, including through movements on Midland Highway. The Saturday volumes are
approximately 31%higher than the peak on Friday. Therefore the following analysis is based on the
Saturday midday peak period.
A projected growth rate for Midland Highway of 8 to 10% over the next 10 years as outlined in
Trafficworks Cumulative Impact Assessment. Therefore a cumulative growth rate of 1% per annum
has been applied.
Site observations of existing operating conditions, including phasing and cycle times.
I have relied upon the data collected by GTA as I was unable to collect traffic volume data myself
due to the school holidays. The GTA data is higher than the OBT data and therefore considered
more conservative.
12.3 Existing Conditions
12.3.1 Parameters
The existing Saturday peak hour operating conditions of Midland Highway / Florence Street have been
analysed using the SIDRA Intersection program. The SIDRA computer package, originally developed by the
Australian Road Research Board, provides information about the capacity of an intersection in terms of a
range of parameters, as described below:
Degree of Saturation (D.O.S.) is the ratio of the volume of traffic observed making a particular movement
compared to the maximum capacity for that movement. Various values of degree of saturation and their
rating are shown in Table 12-1.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 22
Table 12-1 Rating of Degrees of Saturation
D.O.S. Rating
Up to 0.6 Excellent
0.6 to 0.7 Very Good
0.7 to 0.8 Good
0.8 to 0.9 Fair
0.9 to 1.0 Poor
Above 1.0 Very Poor
It is considered acceptable for some critical movements in an intersection to operate in the range of 0.9 to
1.0 during the high peak periods, reflecting actual conditions in a significant proportion of suburban
signalised intersections.
The 95th Percentile (95%ile) Queue represents the maximum queue length, in metres, that can be
expected in 95% of observed queue lengths in the peak hour; and
Average Delay is the delay time, in seconds, which can be expected over all vehicles making a particular
movement in the peak hour.
12.3.2 Analysis
The existing conditions of Midland Highway / Florence Street intersection have been analysed using
SIDRA6.1, with the results attached in Appendix A and summarised in the following table. The turning
movements counted by GTA in November 2013, were used for this analysis
Table 12-2 Existing Conditions Intersection Analysis – Midland H’way / Florence St, Sat 30/11/2013
Approach Movement Degree of Saturation 95th
%ile Queue (m) Average Delay (sec)
Marketplace (S) R 0.47 42 10
T 0.28 27 23
L 0.72 38 41
Midland Hwy (E) R 0.72 69 36
T 0.68 74 27
L 0.32 16 31
Florence St (N) R 0.63 65 32
T 0.63 65 27
L 0.25 16 31
Midland Hwy (W) R 0.34 48 14
T 0.34 49 9
L 0.75 71 22
Intersection 0.75
As shown in the preceding table the Midland Highway / Florence Street intersection is operating with ‘good’
conditions in the Saturday peak hour.
12.4 Traffic Generation
In order to determine the likely traffic generation of the proposed Bunnings warehouse, I have collated case
study data for Bunnings stores collected primarily by Cardno but also including information sourced from
other consultants. The Saturday peak hour traffic generation rates by floor area have been plotted, with the
results shown in Figure 12-1.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 23
Figure 12-1 Bunnings Saturday Peak Traffic Generation Rates
As shown in the preceding figure, the traffic generation rates range considerably from store to store. The
survey data outlined above ranges from 3.01 vehicle movements per 100sqm to 9.03 vehicle movements per
100sqm.
The size of Bunnings stores also varies from 7,434sqm to 15,851sqm. As previously discussed the
proposed Bunnings is considerably larger than any existing store Cardno are aware of.
In order to determine the likely traffic generation of the proposed store a line of best fit was applied to the
data, which indicates that on average the traffic generation decreases as floor area increases. The line of
best fit was projected to the proposed floor area of 19,473sqm, which indicates a rate only slightly higher
than the proposed rate of 5.03vm per 100sqm adopted by OBT. Based on the case study data the proposed
rate is considered appropriate.
12.5 Traffic Distribution
For the purpose of the following assessment I have adopted the OBT traffic distribution, which is generally
based on the traffic distribution of the existing Bunnings store. I have also adopted the proposed distribution
for the Masters site as determined by GTA and approved by Council.
12.6 Growth
A cumulative growth rate of 1% per annum has been applied to the through movements on Midland Highway
and also along Florence Street for a period of 12 years to bring the existing data (2013) up to 2015 and then
add 10 years growth, resulting in a design year of 2025.
12.7 Traffic Volumes
12.7.1 Proposed Development Traffic Volumes
The proposed Saturday peak hour traffic volumes for the Bunnings store (as per the OBT assessment) are
shown in Figure 12-2.
0
1
2
3
4
5
6
7
8
9
10
6,000 8,000 10,000 12,000 14,000 16,000 18,000 20,000
Movem
ents
/ 1
00 s
qm
Floor Area (sqm)
Peak Saturday Rate adopted by OBT (5.03vm/100sqm)
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 24
Figure 12-2 Bunnings Only Peak Hour Traffic Volumes (vph)
Of the 392 vehicle movements exiting the site, 82vph (21%) are anticipated to undertake a u-turn at the
Watson Street / Midland Highway intersection.
12.7.2 Masters Traffic Volumes
The anticipated traffic generation of the Masters site prepared by GTA consultants is shown in Figure 12-3.
Figure 12-3 Masters Only Peak Hour Traffic Volumes (vph)
12.7.3 Future Traffic Volumes Post Development
The total Post Development traffic volumes include, existing conditions + growth + Masters + Bunnings. The
total anticipated traffic volumes for the design year 2025 is shown in Figure 12-4.
Figure 12-4 Future Peak Hour Traffic Volumes - Existing + Growth + Masters + Bunnings (vph)
Midland Highway
Midland Highway
Midland Highway
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 25
12.8 Future Intersection Operating Conditions
12.8.1 Methodology
This assessment has been undertaken in SIDRA 6.1, making use of the network modelling capabilities
provided by this software package.
The networking capabilities in SIDRA account for additional considerations beyond a stand-alone
intersection assessment, such as the effect of upstream and downstream capacity constraints on the
performance of the intersection. Specifically, the two fundamental elements developed for and implemented
in the SIDRA Intersection software are:
The determination of the backward spread of congestion, as queues on downstream lanes block
upstream lanes; and
Application of capacity constraint to oversaturated upstream lanes for determining exit flow rates,
thus limiting the flows entering downstream lanes.
It should be recognised that in networked SIDRA models, queue lengths in excess of the available storage
distance will be passed on to upstream traffic lanes. That is. queue blockage from a downstream
intersection can apply to intersections further upstream, affecting both queue length and capacity at the
upstream intersection. The model also considers the effects that signal coordination and platoon dispersion
have on the performance of the network.
12.8.2 Post Development Scenarios Analysed
The following post development scenarios were analysed:
1. Existing geometry at Midland Highway ./ Florence Street and existing phasing, and proposed
geometry at Bunnings access (as per OBT);
2. Proposed geometry at Midland Highway / Florence Street (as per Masters plan) with existing
phasing and proposed geometry at Bunnings access (as per OBT);
3. Proposed geometry Midland Highway ./ Florence Street (as per Masters plan) with modified phasing
to fully control right turns from Midland Highway east and west approaches and proposed geometry
at Bunnings access (as per OBT).
Although accident history only related to right turns into Shepparton Marketplace, it has been assumed with
the additional Masters traffic that it would be prudent to also fully control right turns from the east approach
into Florence Street.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 26
12.8.3 Scenario 1 Results
The results of the Post Development intersection analysis with the existing geometry at Midland Highway /
Florence Street and the existing phasing is attached as Appendix B and summarised in Table 12-3 and
Table 12-4.
Table 12-3 Scenario 1 Future Conditions– Midland Highway / Florence Street, Saturday Peak Hour
Approach Movement Degree of Saturation 95th
%ile Queue (m) Average Delay (sec)
Marketplace (S) R 0.76 82 21
T 0.26 27 22
L 0.87 42 49
Midland Hwy (E) R 0.64 64 32
T 0.88 132 37
L 0.72 38 36
Florence St (N) R 0.76 90 35
T 0.76 90 29
L 0.64 49 34
Midland Hwy (W) R 0.49 48 16
T 0.49 78 10
L 0.90 79 37
Intersection 0.90
Table 12-4 Scenario 1 Future Conditions – Midland Highway / Bunnings Access Saturday Peak Hour
Approach Movement Degree of Saturation 95th
%ile Queue (m) Average Delay (sec)
Bunnings (S) L 0.73 82 23
Midland Hwy (E) T 0.08 8 9
L 0.66 120 9
Midland Hwy (W) T 0.41 0 1
R 0.89 15 45
U 0.89 15 47
Intersection 0.89
If the existing phasing and intersection geometry is retained, the intersections are anticipated to operate with
‘Fair’ conditions during the Saturday peak hour.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 27
12.8.4 Scenario 2 Results
The results of the Post Development intersection analysis with the proposed modified geometry at Midland
Highway / Florence Street and the existing phasing is attached as Appendix C and summarised in Table 12-
3 and Table 12-6.
Table 12-5 Scenario 2 Future Conditions– Midland Highway / Florence Street, Saturday Peak Hour
Approach Movement Degree of Saturation 95th
%ile Queue (m) Average Delay (sec)
Marketplace (S) R 0.74 73 21
T 0.31 28 22
L 0.56 34 49
Midland Hwy (E) R 0.57 61 32
T 0.79 113 37
L 0.66 35 36
Florence St (N) R 0.31 15 35
T 0.35 32 29
L 0.80 58 34
Midland Hwy (W) R 0.15 17 16
T 0.38 56 10
L 0.83 84 37
Intersection 0.83
Table 12-6 Scenario 2 Future Conditions – Midland Highway / Bunnings Access, Saturday Peak Hour
Approach Movement Degree of Saturation 95th
%ile Queue (m) Average Delay (sec)
Bunnings (S) L 0.72 82 23
Midland Hwy (E) T 0.08 7 8
L 0.66 117 9
Midland Hwy (W) T 0.40 0 1
R 0.89 108 45
U 0.89 108 46
Intersection 0.89
If the intersection geometry is modified as proposed by Masters and the existing phasing is maintained the
intersection is anticipated to operate with ‘Fair’ conditions with slightly improved queues and delays on some
movements compared to Scenario 1.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 28
12.8.5 Scenario 3 Results
The results of the Post Development intersection analysis with the proposed modified geometry at Midland
Highway / Florence Street and changes to the phasing to include fully controlled right turns on both Midland
Highway approaches, is attached as Appendix D and summarised in Table 12-3 and Table 12-6.
Table 12-7 Scenario 3 Future Conditions– Midland Highway / Florence Street, Saturday Peak Hour
Approach Movement Degree of Saturation 95th
%ile Queue (m) Average Delay (sec)
Marketplace (S) R 0.73 74 19
T 0.36 30 27
L 0.67 36 39
Midland Hwy (E) R 0.64 64 32
T 0.88 132 37
L 0.55 35 37
Florence St (N) R 0.26 17 10
T 0.40 33 27
L 0.90 64 51
Midland Hwy (W) R 0.24 27 22
T 0.58 86 18
L 0.87 122 41
Intersection 0.90
Table 12-8 Scenario 3 Future Conditions – Midland Highway / Bunnings Access Saturday Peak Hour
Approach Movement Degree of Saturation 95th
%ile Queue (m) Average Delay (sec)
Bunnings (S) L 0.72 82 23
Midland Hwy (E) T 0.08 8 9
L 0.66 120 8
Midland Hwy (W) T 0.45 0 1
R 0.89 108 45
U 0.89 108 47
Intersection 0.89
If the Midland Highway / Florence Street intersection is modified and the phasing changed to fully controlled
right turns on both the east and west approaches of Midland Highway the intersection is still expected to
operate with ‘Fair’ conditions.
12.9 Traffic Impact Summary
Bunnings and Masters typically generate peak traffic activity on a Saturday, whilst the road network typically
experiences the highest levels of traffic activity during the PM commuter peak hour. The traffic surveys
collected in the vicinity of the site, indicate that the through volumes on Midland Highway are over 30%
higher during the Saturday peak hour than during the Friday PM peak hour. Furthermore Bunnings and
Masters typically only generate half as much traffic during the Friday PM peak hour than on a Saturday
midday peak. What this means from a traffic analysis point of view is that the queues and delays associated
with the Saturday analysis are anticipated to be far higher than at any other time of the week.
The analysis indicates that if no change were made to the existing intersection geometry or phasing as per
Scenario 1, then the proposed Bunnings access signals and Midland Highway / Florence Street intersection
would continue operating satisfactorily.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 29
The results of Scenario 2, which include the intersection improvements associated with the Masters site but
no change to the phasing are slightly better than Scenario 1, especially in terms of queue lengths on the
northern approach.
Scenario 3 includes the proposed intersection improvements as well as changing the existing phasing to
include fully controlled right turns on both the east and west approaches. The implementing of fully
controlled right turns should reduce the number of accidents involving right tuners entering Shepparton
Marketplace being hit by westbound through vehicles. Although the right turn from the eastern approach into
Florence Street does not have a history of accidents, it is considered reasonable given the expected
increase in traffic due to the Masters site. The disadvantage of fully controlled right turns from a traffic
analysis perspective is that it requires an additional phase to be implemented, which then decrease the
amount of green time available during each cycle.
The results of Scenario 3 indicate that the intersection will still operate satisfactorily with the fully controlled
right turns.
Based on the preceding analysis both the proposed Bunnings signals and the Midland Highway / Florence
Street intersection are expected to operate satisfactorily under all three scenarios analysed.
12.10 Review of OBT U-Turn Analysis at Watson Street
12.10.1 Intersection Geometry
I have been asked to undertake a review of the OBT analysis of increased u-turn traffic at the Midland
Highway / Watson Street intersection.
The Midland Highway / Watson Street intersection geometry is shown in Figure 12-5.
Figure 12-5 Midland Highway / Watson Street Intersection Geometry
As shown in the preceding figure, the Watson Street intersection is relatively complex, comprising two lanes
in each direction on Midland Highway, a u-turn lane on the eastern approach (approximately 60m in length),
a left turn deceleration lane into Watson Street, plus right and left turn out from Watson Street. A right turn
deceleration lane is provided on the west approach that provides access into Watson Street as well as right
turns into the service road, west of Watson Street.
Ideally the intersection should be analysed as a whole to determine the impact of additional u-turn traffic on
right turn movements out of Watson Street. However to my knowledge traffic volumes have not been
collected at this intersection.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 30
12.10.2 OBT Assumptions
OBT undertook an analysis of the capacity of the u-turn against eastbound traffic on Midland Highway. The
OBT analysis assumed the following:
Eastbound traffic on Midland Highway during Sat peak hour = 1533vph
U-turns generated by Bunnings = 104 vph
Assumed existing number of u-turns = 60 vph
Critical gap acceptance and follow-up headway of 7.0 seconds and 4.0 seconds, respectively
Commercial vehicle percentage assumed to be zero.
On the basis of these assumptions, OBT anticipated that the u-turn would operate satisfactorily, with a DOS
of 0.75, a 95th percentile queue of 23m and an average delay of 33 seconds.
This analysis does not take into account the additional traffic generated by the proposed Masters site.
Nevertheless the adopted gap and headway values are considered very conservative and will create
substantially more capacity if lower gap and headway values were adopted.
12.10.3 Sensitivity Analysis
In order to evaluate the OBT findings I have undertaken an analysis of the u-turn lane. Unfortunately as
previously stated I am unable to incorporate the existing turning movements at this intersection into the
analysis and have had to rely on the OBT assumption that there may be in the order of 60 existing u-turn
movements.
My analysis is based on the following assumptions:
Eastbound traffic on Midland Highway during Sat peak hour = 1725vph (Based on post development
traffic volumes including GTA existing volumes + growth + Masters + Bunnings);
U-turns generated by Bunnings = 104 vph
Assumed existing number of u-turns = 60 vph
Critical gap acceptance and follow-up headway of 5.0 seconds and 3.0 seconds, respectively, based
on the left turn criteria from Austroads Guide to Traffic Engineering Practice – Part 5: Intersections at
Grade;
Commercial vehicle percentage assumed to be 5% both on U-turn and Midland Highway through
volumes.
The results of this analysis are attached as Appendix E and indicate a DOS of 0.48, 95th percentile queue
length of 4m and an average delay of 1 second.
12.10.4 Summary
In summary although I have used higher traffic volumes and made an allowance for commercial vehicles, the
results of the analysis are better than the OBT results, clearly indicating that the adopted gap and headway
values are the determining factor in the analysis.
The assumption that vehicles will wait for a 7 second gap in oncoming traffic flow on a 60kph road seems
overly conservative.
Based on the my own investigation I am satisfied that the u-turn has sufficient capacity to accommodate the
anticipated u-turns from the proposed Bunnings.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 31
13 Response to Issues
As defined in Section 4, the submissions have been summarised into three main areas comprising Fordyce
Street, access arrangements and impact on surrounding road network, and adequacy of car parking. In view
of the preceding discussion and analysis my response to these issues is outlined as follows:
13.1 Fordyce Street
13.1.1 Footpath Provision
The Bunnings store has a limited frontage to Fordyce Street and is not expected to increase pedestrian
activity on Fordyce Street as pedestrians approaching from either Fordyce Street or Gilchrist Street can enter
the site via the southern access whilst all other pedestrians are expected to enter via the northern access
from Midland Highway.
The lack of a footpath along Fordyce Street is an existing issue that should be raised with Council.
13.1.2 Increased Traffic
Based on the OBT Traffic Assessment, it is anticipated that an additional 168 vehicle movements could be
expected on Fordyce Street south of the Bunnings access. If 20% arrive and depart from the south rather
than diverting 6% back to Midland Highway as proposed by OBT, then it could be expected that 196 vehicles
in the peak hour use the southern access to Fordyce Street.
Although not shown on the OBT distribution I think it would be reasonable to assume half of that traffic would
arrive and depart via Gilchrist Street with the remainder traveling south along Fordyce Street. Therefore a
maximum of 98 additional movements could be expected on Fordyce Street, south of Gilchrist Street and
Gilchrist Street in the Saturday peak hour.
Although the addition of 98 vehicle movements per hour is significant, it is anticipated that this level of traffic
activity can be comfortably absorbed by both Fordyce Street and Gilchrist Street. It should also be noted
that during the week anticipated Bunnings traffic volumes during the peak hour are in the order of half of the
Saturday peak.
13.1.3 Parking Restrictions
A submission was received stating that they object to ‘No Standing’ signs being installed along Fordyce
Street as they currently use the on street parking in the vicinity of their site.
It appears that No Standing signs are proposed on the western side of Fordyce Street immediately north of
Gilchrist Street as part of the improvements to the Fordyce Street / Gilchrist Street intersection.
Based on my review of the loading bay I believe the proposed No Standing restrictions are appropriate to
enable B-Double vehicles to egress from the proposed Bunnings loading bay.
13.1.4 Fordyce Street / Gilchrist Street Intersection
A submission was made stating that the current intersection of Fordyce Street / Gilchrist Street is confusing
and encourages illegal movements. I agree that the intersection is confusing and badly aligned. The
proposed changes described in the OBT Traffic Assessment that will be undertaken by Bunnings should
assist in defining priority and reducing the incidence of improper behaviour.
13.2 Access Arrangements and Traffic Impact
13.2.1 Proposed Bunnings Access and Midland Highway / Florence Street
I have undertaken a conservative analysis that takes into account the Bunnings development, the Masters
development, future growth on Midland Highway and coordination with the Midland Highway / Florence
Street intersection. The results of the analysis indicate that both intersections are expected to operate
satisfactorily.
Due to the close proximity of the proposed signals, the timing and phasing will be dictated by the Midland
Highway / Florence Street intersection. This level of coordination will ensure that priority to through
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 32
movements on Midland Highway is maintained. The proposed intersection will effectively operate in the
shadow of the adjacent intersection such that it will have minimal impact on the existing operating conditions
of Midland Highway.
13.2.2 Request for Additional Intersection Analysis
A submission was made requesting analysis of a number of additional intersections in the area. In my
opinion the analysis should be focused on the impact to Midland Highway adjacent to the site where the vast
majority of traffic is anticipated to access the site. This view is also presumably supported by VicRoads and
Council, who have not requested further intersections be analysed.
13.3 Adequacy of Car Parking
A parking provision of 417 spaces is proposed, which exceeds the Planning Scheme parking requirements
and is considered satisfactory.
The concern regarding Bunnings patrons parking in the adjacent Shepparton Marketplace car park does not
have merit in my opinion. It is understood that three separate access points will be provided to the Bunnings
store from the adjacent Bunnings car park, allowing convenient access from the majority of the car park.
In my opinion sufficient car parking has been provided such that future customers will not be reliant on
parking external to the site.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 33
14 Conclusions
Based on the preceding discussion it is concluded that;
The proposed parking supply of 417 spaces is considered satisfactory;
The proposed bicycle parking supply of 12 spaces, comprising 6 for staff and 6 for customers is
considered appropriate, noting that additional bicycle parking could be provided in the future if
required;
The proposed Bunnings store is anticipated to generate in the order of 510 trips during a Friday PM
peak hour and in the order of 980 trips during the Saturday midday peak hour;
The proposed traffic signal on Midland Highway has been analysed taking into consideration the
adjacent Midland Highway / Florence Street signalised intersection;
The intersection analysis was undertaken for the Saturday peak period, as it was noted that existing
traffic volumes are approximately 31% lower during the Friday PM peak than the Saturday peak
hour;
The SIDRA analysis took into account the proposed Masters store to be located on the north east
corner of Midland Highway / Florence Street, the proposed Bunnings store and its signalised
intersection to Midland Highway as well as the growth anticipated over the next 10 years;
The results of the analysis indicate that both the Midland Highway / Florence Street intersection and
the proposed intersection can operate satisfactorily, with or without the proposed intersection
modifications recommended by GTA and any change to the existing phasing;
A fully signalised intersection to service the Bunnings site as proposed by Traffix, is in my opinion
not required, as there will be sufficient capacity for vehicles to undertake a u-turn on Midland
Highway if they wish to travel east after visiting the Bunnings store;
Of the three scenarios modelled the best result was achieved with the proposed modification to the
Midland Highway / Florence Street intersection including a left turn slip lane and formalisation of the
right turn on the northern approach, as well as the creation of a left turn deceleration lane on the
western approach, with no change to the existing phasing,
The Scenario 3 analysis indicates that if the right turn from the western approach into Shepparton
Marketplace was fully controlled, which is aimed at reducing the likelihood of additional accidents at
the intersection, would continue to operate satisfactorily.
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 34
Expert Traffic Evidence Statement
APPENDIX
A EXISTING CONDITIONS SIDRA ANALYSIS – SATURDAY MIDDAY PEAK
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 35
Existing Conditions SIDRA Analysis – Saturday Midday Peak
INTERSECTION GEOMETRY
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 36
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 37
Expert Traffic Evidence Statement
APPENDIX
B SIDRA ANALYSIS FUTURE CONDITIONS SCENARIO 1
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 38
Scenario 1: Future Conditions SIDRA Analysis – Saturday Midday Peak
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 39
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 40
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 41
Expert Traffic Evidence Statement
APPENDIX
C SIDRA ANALYSIS FUTURE CONDITIONS SCENARIO 2
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 42
Scenario 2: Future Conditions SIDRA Analysis – Saturday Midday Peak
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 43
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 44
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 45
Expert Traffic Evidence Statement
APPENDIX
D SIDRA ANALYSIS FUTURE CONDITIONS SCENARIO 3
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 46
Scenario 3: Future Conditions SIDRA Analysis – Saturday Midday Peak
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 47
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 48
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 49
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 50
Expert Traffic Evidence Statement
APPENDIX
E SIDRA ANALYSIS FUTURE CONDITIONS U-TURN LANE CAPACITY AT WATSON ST
Amendment C183 and Bunnings Planning Application PPA 2013-307 Expert Traffic Evidence Statement
20 July 2015 ) Cardno 51
U-Turn Capacity at Watson Street Future Conditions SIDRA Analysis – Saturday Midday Peak