Ambre Energy IAS 15 Feb 08

download Ambre Energy IAS 15 Feb 08

of 33

Transcript of Ambre Energy IAS 15 Feb 08

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    1/33

    Felton Hybrid Energy Project

    Initial Advice Statement

    15 February 2008

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    2/33

    TableofContents

    1

    Introduction .............................................................................................................................................. 3

    1.1 Project Overview ............................... ........................................................... ........................................ 31.2 The Proponent ............................................................................ ........................................................... 31.3 Outline of Proposal .............................................................................. ................................................. 41.4 Purpose and Scope of Initial Advice Statement .................................................................................... 5

    2 Description of the Project ....................................................................................................................... 72.1 Project Location ..................................................... ........................................................... .................... 72.2 Background to the Project .......................................................... ........................................................... 72.3 Project Justification and Alternatives ................................................... ................................................. 92.4 Project Components ......................................................... ........................................................... ........ 102.5 Felton North Coal Mine .......................................................................................... ............................ 102.6 Coal Preparation ..................................................... ........................................................... .................. 142.7 Processing of Coal using the Hybrid Energy System ......................................................... ................. 152.8 Resources required .................................................................... .......................................................... 172.9 Timeframe for Project ...................................................... ........................................................... ........ 18

    3 Project Benefits and Costs .................................................................................................................. 193.1 Project Benefits ...................................................... ........................................................... .................. 193.2 Estimated Project Costs ............................... ........................................................... ............................ 19

    4 Existing Environment ............................................................................................................................ 204.1 Climate ......................................................... ........................................................... ............................ 204.2 Topography .......................................................................................... ............................................... 204.3 Soils and Land Use Suitability .................................................. .......................................................... 204.4 Remnant vegetation .......................................................... ........................................................... ........ 214.5 Surface water ..................................... ........................................................... ...................................... 224.6 Ground water ..................................... ........................................................... ...................................... 224.7 Air Quality ............................................................. ........................................................... .................. 224.8 Noise and Vibration ............................................... ........................................................... .................. 224.9 Existing ecosystems ................................................................... ......................................................... 22

    5 Measures to Control Potential Environmental Impacts ................................................................... 255.1 Air .................................................................................... ........................................................... ........ 255.2 CO2 Emissions ................................................................. ........................................................... ........ 255.3 Ground Water ......................................................... ........................................................... .................. 265.4 Surface water ..................................... ........................................................... ...................................... 265.5 Water Conservation .......................................................... ........................................................... ........ 275.6 Water Quality ...................................................................................... ................................................ 275.7 Hydrology ........................................................................ ........................................................... ........ 285.8 Land Management.................................................. ........................................................... .................. 285.9 Transport .............................................................................................. ............................................... 305.10 Flora and Fauna ...................................................... ........................................................... .................. 315.11 Native Title and Cultural Heritage ...................................................... ................................................ 315.12 Visual Amenity ................................................................ ........................................................... ........ 315.13 Environmental Management ....................................................................................................... ........ 325.14 Hazards and Risks .................................................. ........................................................... .................. 32

    6 Stakeholder Consultation..................................................................................................................... 33

    Ambre Energy Limited

    ACN 114 812 074

    Level 6 Grant Thornton House102 Adelaide StreetBrisbane QLD 4000Australia

    Tel: +61 (0)7 3009 9180Fax: +61 (0)7 3009 9181

    Ambre Energy Limited 2Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    3/33

    Ambre Energy Limited 3Initial Advice Statement Felton Hybrid Energy Project

    1 Introduction

    1.1 Project Overview

    Ambre Energy Limited is proposing to build and operate a world-class petrochemical plant

    producing synthetic crude oil and dimethyl ether1

    from coal, and co-generating electricity using anIntegrated Gas Combined Cycle (IGCC) system. The project will be designed to be ready for CO2capture and storage. The project is known as the Felton Hybrid Energy Project and is located nearFelton, 30km south west of Toowoomba; see Figure 1.1.

    Figure 1.1 - Felton Hybrid Energy Project location

    1.2 The Proponent

    The Project will be undertaken by a wholly owned subsidiary of Ambre Energy Limited, an unlistedAustralian public company based in Brisbane.

    Ambre Energy Limited was formed in June 2005 for the purpose of developing andcommercializing new technologies for the more effective use of coal as a source of energy, and to

    1 Dimethyl ether or DME is a simple non-toxic ether (chemical formula CH3OCH3) that is attracting world wide attentionas a potential clean diesel replacement and as a potential fuel for fuel cells.

    FFeellttoonn HHybbrriidd EEnneerr y PPrroo eecctt

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    4/33

    Ambre Energy Limited 4Initial Advice Statement Felton Hybrid Energy Project

    develop complementary coal mining projects. As of December 2007, it had over 160 shareholdersand had expended over $17 million developing its technologies and projects.

    The company has been developing its technologies since its inception, including the evaluation of anumber of potential sites and testing its proprietary Hybrid Energy System on coal, both in largescale laboratory trials and at its pilot plant facility in Utah, USA. Following this evaluation phase,the Felton Hybrid Energy Project was selected as the first project to be developed due to low miningcosts, the relatively high reactivity of the coal and the close proximity to infrastructure.

    Ambre Energy is committed to creating a project which is sustainable and which meets or exceedsthe expectations of local community and government stakeholders in the areas of environmental,safety and risk management.

    1.3 Outline of Proposal

    The Project will be developed in 3 stages:

    Stage 1

    Stage 1 of the Project will involve the development of two major components. First, a 12 milliontonnes per year (Mtpy) open cut coal mine and coal preparation plant will be developed with acapacity to produce 6 Mtpy of washed coal. Second, a petrochemical plant will process the washedcoal using Ambre Energys Hybrid Energy System (HES) to produce synthetic crude oil.

    This Stage 1 of the petrochemical plant will itself be developed in two successive stages. Stage 1Awill involve the construction of a cluster of retorts capable of pyrolysing2 3 Mtpy of washed coal to

    produce 3.6 million barrels per year (10,000 bbl/day) of synthetic crude oil. Synthetic gas (syngas)will also be produced by the retorts and by subsequent gasification of the spent coal ( char)

    discharged from the retorts. There is sufficient syngas produced to co-generate all electricityrequired for internal consumption (about 30MW) using gas engines. The object is to commissionStage 1A by the first quarter of 2010.

    Stage 1B will double the processing capacity of the HES plant to 6 Mtpy of washed coal, therebyproducing a total of 7.2 million barrels per year (20,000 bbl/day) of synthetic crude oil. A DMEpilot production plant will also be added. The syngas from the retorts and the char gasifiers will firstbe fed through the DME pilot plant to produce 100,000 tonnes of DME per year (300 tonnes perday). Tail gas from the pilot plant will then be used to generate electricity and steam for furtherinternal energy requirements. Stage 1B is scheduled to be commissioned by the third quarter of2011.

    During Stage 1, Ambre Energy will also investigate, and if viable implement, a land improvementand commercial forestation program covering the area of its mining leases to offset carbonemissions from its project and provide valuable soft and hard wood construction timber that mightotherwise be harvested and imported from ecologically vulnerable areas of natural forest in other

    parts of the world.

    Stage 2

    Following the successful commissioning of Stage 1 of the project, a Stage 2 expansion will involvethe construction of:

    2 Pyrolysis of coal is the heating of the coal in the absence of oxygen, in this case at relatively low temperatures (less than600C). This process is also described as retorting because it is usually carried out in heating vessels of various types,commonly known as retorts.

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    5/33

    a larger char gasification plant capable of gasifying 4 Mtpy of char to provide sufficientsyngas to feed a 2 Mtpy DME Plant; and

    a 400 MW IGCC power plant utilising tail gas from the DME Plant.

    Stage 3

    Stage 3 of the project will involve:

    doubling the capacity of the open cut coal mine to 24 Mtpy;

    construction of a second 12 Mtpy coal preparation plant;

    doubling the production capacity of the petrochemical plant to 14.4 million bbl/yr ofsynthetic crude oil, 4 Mtpy of DME and 800 MW of exported power; and

    if commercially viable carbon capture and storage (CCS) facilities have been developed,stripping the CO2 from the syngas produced by the plant and disposing of it in thosefacilities. (If CCS facilities are developed at an earlier stage, CO2 stripping and disposal cancommence at that earlier stage.)

    1.4 Purpose and Scope of Initial Advice Statement

    The purpose of this Initial Advice Statement (IAS) is to provide sufficient information about thenature and scope of the Project so as to:

    Assist the Queensland Coordinator-General in making a decision on whether to declare the

    Project to be a significant project for which an Environmental Impact Statement (EIS) isrequired;

    Provide information to and facilitate consultation with governments, key stakeholders,landowners and the community;

    Allow the determination of the appropriate Environmental Impact Assessment Process andDevelopment Approval requirements; and

    Assist in the preparation of the draft Terms of Reference for the Projects EIS.

    This IAS addresses the technologies to be used, the potential of the coal resource, and the miningand processing practices that will be employed to economically enhance the values of the resourcein an environmentally acceptable manner.

    Issues that may be considered in determining that the Project warrants being declared a significantproject are:

    Complexity of local, State and Federal Government Requirements

    The Project will be examined under a variety of local, State and Federal laws and the permittingprocess will be complex.

    The conversion of coal to gas and hydrocarbons may generate considerable interest from the Federalas well as the State Government due to its strategic importance and potential environmental impacts.

    Ambre Energy Limited 5Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    6/33

    In addition there will need to be a cooperative decision making process between local and State andFederal Government Departments.

    Potential Environmental Effects

    The potential adverse impacts of the Project are:

    Possible disruption of groundwater aquifers in Hodgson Creek alluvials, the Walloonsandstone and the Tertiary basalts;

    Dust generated from mining processes;

    Odour generated from the processing of the coal;

    Greenhouse gas emissions;

    Social disruption to adjacent farming enterprises;

    Noise generated from mining and processing;

    Increased level of road traffic;

    Visual impact on a rural landscape; and

    Downgrading of agricultural land.

    Environmental and Planning Approvals

    The Project will need to comply with local, State and Federal legislation. The likely approvalsneeded for the Project include those required under the following legislation:

    Federal: Environment Protection and Biodiversity Conservation Act 1999

    State: State Development and Public Works Organisation Act 1971

    Mineral Resources Act 1989 Environmental Protection Act 1994 Petroleum and Gas (Production and Safety) Act 2004 Coal Mining Safety and Health Act 1999 Integrated Planning Act 1997 Water Act 2000 (for construction of a Referable Dam) Transport Infrastructure Act 1994 Vegetation Management Act 1999 Dangerous Goods Safety Management Act 2001

    Potential Effect on Relevant Infrastructure

    The Project will impact on local and State Government infrastructure such as roads, water supplyand hydrocarbon transport via pipeline. The potential impacts can be significant and Ambre Energyis of the opinion that it is important to have the Queensland Coordinator-Generals department asthe lead government agency to coordinate the permitting of the Project.

    The EIS for the Project will address these and other possible impacts. Already communityconsultation has commenced which has given Ambre Energy an indication of the issues that are ofconcern to the local community.

    Ambre Energy Limited 6Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    7/33

    2 Description of the Project

    2.1 Project Location

    The Project is located at Felton which lies in the Clarence-Moreton Basin in south-east Queenslandto the west of the Great Dividing Range. The basin extends from northern New South Walestrending northwest to Dalby in Queensland and from Toowoomba in the east to Millmerran in thewest. The Felton North deposit is approximately 30 km south west of Toowoomba and 10 km southeast of Pittsworth, see Figure 2.1.

    Figure 2.1 - Felton Hybrid Energy Project location plan

    2.2 Background to the Project

    The main focus of the Project is the large scale production of a combination of liquids and power

    from the proponents coal deposits at Felton North.

    The development of these coal deposits commenced in October 2006 when a wholly ownedsubsidiary of Ambre Energy, Eastern Mining Corporation Pty Ltd (EMC), applied for and wasgranted an exploration permit for coal (EPC 1076) over an area of 250 km in the Felton region. Atthe same time, EMC entered into a farm-in agreement with an adjoining EPC holder, MetallicaMinerals Limited, to earn a 75% interest in 180 km of their exploration permits (EPC 935 and EPC936). EMC has since acquired 100% ownership of these permits, and has further acquired EPC 1137and EPC 1138.

    During 2007, EMC conducted extensive core drilling programs on the site and identified a potentialdeposit of high ash coal (on average 50% ash content) in excess of 900 million tonnes of high

    volatile bituminous coal, an ideal source material for coal to liquids projects.

    Ambre Energy Limited 7Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    8/33

    Technologies

    The technologies to be used to exploit these deposits include a number of innovative processes suchas Ambre Energys proprietary Hybrid Energy System (HES) and a new production process fordimethyl ether (DME), as well as recognised processes such as those for power generation.

    At the heart of the HES is a continuous flow retort capable of pyrolysing coal in large quantities to produce hydrocarbon liquids aimed at the chemical and transport fuel market. The retortingtechnology for low temperature pyrolysis of coal was acquired by Ambre Energy via a joint venturewith U.S. based Oil-Tech, Inc.

    This technology allows relatively low cost removal of liquids from the coal feed and also produces asolid char. The char is still of sufficient quality to produce power and further transport fuels viagasification.

    Ambre Energy has demonstrated the retorting of coal using a pilot test facility in Utah, USA and hascarried out metallurgical test work and processing test work on the coal from the Felton North

    deposit. This test work, combined with exploration work and process option studies, has allowedAmbre Energy to develop a mine plan and processing facility concept that will maximise theeconomic returns from the Felton North resource.

    The development includes a plant to manufacture DME. DME has attracted much attention aroundthe world because of the versatility and environmental benefits of this next-generation liquid fuel.There are a number of large scale DME production plants currently under construction and plannedin the Middle East and China.

    Of particular interest is DMEs suitability as a fuel for compression ignition diesel engines,currently the most efficient engine technology available. Unlike diesel, gasoline or even ethanol,DME produces almost no particulates upon combustion; in other words, no smoke or soot. It

    contains no sulfur and produces very low NOx emissions. Prototype buses and heavy vehicles usingDME have been built in China and Japan, and by Volvo in Europe.

    Ambre Energy has claimed a stake in the development of this new clean fuel by funding a project atthe University of Utah to develop a reactor and catalysts for the production of DME from coal (aswell as biomass). The aim is to produce DME more simply and at a lower cost than will be

    produced at the plants currently being built in the Middle East and China.

    In addition to research into DME production, Ambre Energy has done test work on evaluating theliquids from the low temperature retort to produce a synthetic crude oil and a pitch product. Thelevel of processing of the liquids will be tailored to maximise the economic return of the Project andwill include a synthetic crude oil fraction and may contain a pitch fraction and extraction of

    chemical values from the liquids.

    Exploration

    Two drilling programs have successfully been completed over the Felton North deposit area. Thefirst drilling program was conducted in January 2007 with the second program following in July2007. The January drilling program consisted of 4 cored boreholes at Millmerran (40km south-westof Felton North) and 7 cored boreholes within the Felton North deposit area, totalling 795 metres ofHQ core. Figure 2.2 illustrates the typical drilling technology used during exploration at Felton

    North.

    The second drilling program was focussed solely on further defining the Felton North deposit area,and involved the completion of 6 chip boreholes and 9 cored boreholes, to produce 360m of core.

    Ambre Energy Limited 8Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    9/33

    Analysis of the two drilling programs indicates a low strip ratio resource with moderate ash, goodvolatiles and high hydrogen content. Modified Fischer Assay of the coal indicates high potentialliquid yields from the Felton North coal deposit compared to other coals in Australia. The geologyof the deposit appears to be structurally simple with coal seams dipping gently to the west.

    Since the beginning of November 2007, Ambre Energy has undertaken a third major drilling program to obtain detailed coal washabilty data, coal oxidation line data and other informationrequired for detailed mine design.

    Figure 2.2 - Exploration Drilling at Felton North looking west to Millmerran

    2.3 Project Justification and Alternatives

    There are a number of important strategic implications of the Project, such as:

    Development of a significant alternative source of crude oil and gas, with the potential toreduce importation of oil and thereby improve Australias balance of trade;

    Development of a relatively low cost coal-to-liquids and coal-to-gas process that canenhance the economic value of Queenslands coal deposits, particularly resources which arecurrently sub-economic or treated as waste, such as coal washing rejects;

    Maximising economic value from the Felton North coal deposit for the State of Queensland;

    Development of Australias first DME production facility and the opportunity for Australiato play a leading role in the adoption of DME as a next-generation fuel;

    Ambre Energy Limited 9Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    10/33

    Encouraging the establishment in the Darling Downs region of downstream petrochemicalindustries such as the manufacture of olefins and other products that require crude oil as afeedstock;

    Diversification of the employment opportunities and skill base of people living in regionalQueensland; and

    The potential to exploit the same technology and development concept in other areas withinAustralia.

    Ambre Energy is continuing to assess alternative projects in the USA in the event that the FeltonHybrid Energy Project is not able to proceed. In particular there are opportunities to use the HES toupgrade low quality Gulf Coast lignites as fuel for power stations.

    2.4 Project Components

    The Project will cover an area of approximately 25 km of land and will be comprised of a numberof components, as follows:

    Felton North Coal Mine with a production capacity of 24 Mtpy;

    Water pipeline to transport 10 ML/day of waste water up to 80 km from coal seam methaneproduction operations (located west of the Project site) to the Project site;

    Coal preparation plants capable of washing 24 Mtpy of raw coal to produce 12 Mtpy ofwashed coal;

    Clusters of retorts, each capable of retorting 1,000 tonnes per day of washed coal, with atotal retorting capacity of 12 Mtpy;

    Power generating combustion engines utilising retort gas as fuel to produce electricity forinternal needs (60 MW);

    Synthetic crude oil upgrading units capable of upgrading 40,000 barrels per day of syntheticcrude oil;

    Char (spent coal) gasification units capable of gasifying 8 Mtpy of char;

    DME production plant capable of producing 4 Mtpy of DME;

    IGCC power plants capable of producing a total of 800 MW of electricity.

    2.5 Felton North Coal Mine

    The Resource

    A measured, indicated and inferred resource of 900 million tonnes of coal has been identified at theFelton North deposit. It falls within EPC 935 and comprises Walloon Coal Measures, MarburgFormation sandstones and ridge capping Tertiary basalt flows. The Walloon Coal Measures consist

    of grey siltstones, commonly carbonaceous, and fine to medium grained soft grey lithic sandstones.

    Ambre Energy Limited 10Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    11/33

    Several carbonaceous zones are scattered within these sediments ranging in thickness from tens ofmetres to less than a metre. The carbonaceous zones are made up of mudstones (varying incarbonaceous content), carbonaceous shales, both clean and carbonaceous claystones and variouscoal grades. The sediments within these carbonaceous zones merge and coalesce laterally overrelatively short distances.

    The underlying Marburg Formation consists principally of cross-bedded medium to coarse quartzsandstones inter-bedded with grey shale and claystones. The Tertiary basalts were deposited as aseries of flows and exist as capping along remnant ridge lines. Figure 2.3 shows the drill holelocations of the 2007 exploration programs.

    Figure 2.3 - Borehole location Plan

    There are 9 seams within the Felton North deposit area, the G, H, T, K, MU, MM, ML, B and BBseams; see Figure 2.4.

    G seam

    H seam

    T seam

    K seam

    MU seam

    MM seam

    ML seam

    B seam

    1.9m

    8.5m

    14.5m

    0.7m

    4.0m

    4.7m

    2.9m

    4.3m

    5.5m

    2.0m

    4.0m

    5.0m

    0.7m

    Varying

    overburden

    G seam

    H seam

    T seam

    K seam

    MU seam

    MM seam

    ML seam

    B seam

    1.9m

    8.5m

    14.5m

    0.7m

    4.0m

    4.7m

    2.9m

    4.3m

    5.5m

    2.0m

    4.0m

    5.0m

    0.7m

    Varying

    overburden

    Figure 2.4 - Stratigraphy of the Felton North Deposit.

    Ambre Energy Limited 11Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    12/33

    All 9 seams vary in thickness and quality throughout the deposit. Figure 2.5 illustrates a typicalintersection of M seam.

    Figure 2.5 - Typical coal intersection at Felton North.

    Core recovered using HQ Diamond wire line technology.

    Mine layout and Infrastructure

    The Felton North Coal Mine will be a 24 million tonnes per year (Mtpy) open cut mining operationto be developed in two phases. During Stage 1 of the Project, a mine with a production capacity of12 Mtpy of run of mine coal will be constructed. Stage 3 of the Project will double the capacity ofthe mine to 24 Mtpy. The mine layout and infrastructure are shown on Figure 2.6. With further

    design and mine planning the layout may change but the plan basically depicts a realistic impressionof the various operational centres required to extract and process the resource.

    The mining operation will be based on the western side of Hodgson Creek where the coal will beextracted for crushing, washing and transport to the processing plant on the eastern side of HodgsonCreek. The waste product from the washing, predominantly bentonite clays, will be piped to claytreatment ponds on the western side of Hodgson Creek for settlement and the recovery of water.Recycling of water will be a high priority for the Project. Runoff from the stockpile area and

    processing plant site will be collected in sediment sumps for recycling to the clay treatment sumps.

    The initial clay treatment pond will be constructed on the western side of Hodgson Creek behind aflood levee, which will protect the mining operation from floods and ensure that runoff from the

    mining operations does not enter Hodgson Creek. A similar levee will be constructed on the easternside of Hodgson Creek to protect the processing plant infrastructure and also to ensure runoff from

    Ambre Energy Limited 12Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    13/33

    the plant site does not enter Hodgson Creek. For planning purposes and until confirmation isobtained from hydrological studies of Hodgson Creek, the levees will be set back at least 100mfrom Hodgson Creek.

    The flood levee on the western side will form the base for the initial overburden dump and the outerslope will be stabilised with rock mulch and vegetation to provide an erosion resistant cover. Thisslope will remain as a permanent feature of the post mining landform while the eastern levee will beremoved during decommissioning of the plant site. Both levees will channel runoff to sedimentsumps for recycling water into the production dams, and smaller sediment sumps will be located atthe base of the outer slopes of the levees to collect runoff during construction of the levees.

    The mining operation will commence to the west of the initial clay treatment ponds and progress tothe west.

    Figure 2.6 - Open Cut Mine and Infrastructure layout plan

    Coal Handling

    Coal will be removed by shovel and truck with some selective removal of clay bands greater than300mm in thickness. The coal and small clay bands will be taken to a central coal preparation plantfor crushing and washing prior to transfer to the processing plant. The larger clay bands will betransported to the overburden dump located within the open cut mine perimeter.

    Tailings

    The clay bands liberated from the coal during the washing process will be pumped to the claytreatment ponds for settling to separate the clays from the water. This will involve stilling the waterin shallow ponds and passing the water through a series of ponds to facilitate the settling process.

    Clay Settlement Ponds

    When the clay ponds are nearing capacity, further ponds will be developed in the advancing minepits. This will involve constructing bunds in the pits to regulate storage and removal of water fromthe tailings. The westward advancing overburden dump will progressively cover the ponds that have

    Ambre Energy Limited 13Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    14/33

    been filled with tailings. The consolidation of the tailings at the toe of the dump will force waterfrom the ponds into the next series of clay ponds.

    2.6 Coal Preparation

    The run of mine coal is about 50% ash and needs to be washed to less than 30% ash. This is to bedone via 2 coal preparation plants. The first preparation plant will be constructed as part of Stage 1and will have a capacity to wash 12 Mtpy of run of mine coal to produce 6 Mtpy of washed coal.Stage 3 will include construction of a second plant of equal capacity.

    Waste from the plants will comprise rejects solids and waste water tailings (predominately watercontaining fine solids). The tailings will pumped to the clay treatment ponds, where the solids willsettle and the water will be recycled to the coal preparation plants. The reject solids will be stored ina waste pile and trucked to the mine waste area. The plants will be similar to many other coal

    preparation plants in Queensland, using predominantly dense media separation. The coalpreparation plant scheme is shown below in Figure 2.7.

    Figure 2.7 Coal Preparation Plant Scheme

    Ambre Energy Limited 14Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    15/33

    2.7 Processing of Coal using the Hybrid Energy System

    The petrochemical plant to process the washed coal will be sited approximately 0.5km to the east ofthe main mining area. The plant will be placed in a location that has previously been drilled anddetermined to contain no coal.

    The plant will be built in 3 stages. The proposed processing configuration maximises the use of theresource, producing power and a range of liquids that can replace imported crude oil and refined

    products. The coal processing scheme is shown below in Figure 2.8 and is described on thefollowing pages.

    Figure 2.8 Coal Processing Scheme

    Ambre Energy Limited 15Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    16/33

    Drying and Retorting

    The washed coal will be dried using a fluidised bed dryer. This unit will use the gas produced by thedownstream retorting and gasification processes as the energy source for the dryer. The dried coalwill then be fed into a cluster of retorts, each capable of processing 1,000 tonnes of coal per day.The retorts will be Ambre Energys patented design comprising a totally enclosed system operatingunder negative pressure. The retorts are indirectly heated using electric heating elements in aflowing bed of coal, and produces a vapour stream and a solid product.

    Liquids processing

    The vapour from the retort is condensed to produce liquids. The liquids will be further processed toremove solids and water to produce a synthetic crude oil suitable for the crude oil market. Furtherchemical values can be extracted from the liquids if economic conditions support this. The syntheticcrude oil will be sent via pipeline to Brisbane. Stage 1A will include a cluster of retorts with a total

    processing capacity of 3 Mtpy of coal to produce 3.6 million barrels per year of synthetic crude oil.

    A second cluster of retorts will be built as part of Stage 1B to increase production to 7.2 millionbarrels per year. Stage 3 will further increase production to 14.4 million barrels per year.

    Gas conditioning and co-generation of power

    The gas from the retort will be treated to remove hydrogen sulphide prior to being used as a fuel togenerate electricity for internal use via a gas engine based power station. The retort gas will also beused as the heat source for drying the incoming coal and to raise steam for process requirements.The hydrogen sulphide will be absorbed into caustic soda to make sodium hydrogen sulphide, a

    product used by base metal mines in Queensland and New South Wales as a flotation reagent.Consideration will also be given to the future stripping of carbon dioxide from the gas at this pointto take advantage of any viable CCS facilities that emerge.

    Gasification including DME production and IGCC power generation

    The solids from the retort are of sufficient quality to be gasified in a fluid bed or entrained flowgasifier system to produce a stream of syngas for DME production and co-generation of power in anIGCC power station. It is envisaged that Stage 1B of the Project will include a gasifier and a once-through 300 tonnes per day DME pilot plant. A number of plants have been built using coal to

    produce DME in other parts of the world. Ambre Energy is developing an optimised DME reactorthrough co-operative research with the University of Utah, which, if successful, will enhance theexisting process technology currently available for DME production.

    The tail gas from DME pilot plant will be combined with the retort gas to provide energy for power

    and steam requirements within the process plant. Any excess energy will be exported as electricityto the National Grid.

    After successful commissioning of the DME pilot plant, it is envisaged that during Stage 2 a largescale gasifier will be constructed to provide syngas for a 2 Mtpy DME plant and a 400 MW IGCC

    power station. Approximately 75 MW will be used internally and the balance will be exported.IGCC technology is well proven in similar power stations worldwide. Stage 3 will increase

    production to 4 Mtpy of DME and 800 MW of electricity.

    Oxygen Plant

    An air separation unit will be installed to provide the oxygen required for the gasification process.This unit will utilise proven technology from a recognised vendor of oxygen plants.

    Ambre Energy Limited 16Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    17/33

    Waste and Emissions Treatment

    The tailings from the coal preparation plant will be pumped to the clay treatment ponds. The wastewater from the other processing sections will be treated to a standard to allow addition of this waterto the tailings. Water from the clay treatment ponds will be recycled to the coal preparation plants.

    Air emissions will only be generated at 3 points in the process:

    Exhaust from the combustion of gas to dry the washed coal before it is fed into the retorts.The coal is dried at low temperature about 250C.

    Exhaust from the combustion of syngas in the gas engines generating power for internaluse.

    Exhaust from the IGCC power plants.

    2.8 Resources required

    Water supply

    Project needs for mining and processing are approximately 5,000 ML/yr. It is proposed to build awater storage dam with a capacity of 10,000 ML.

    The water quality required for mining can be waste water from coal seam methane production, run-off from waste overburden dumps and plant area or recycled town waste water; whereas the

    processing plant will require water of reasonable quality for steam generation, which can beprovided by an onsite water treatment plant. Ambre Energy is currently negotiating an agreementwith a large coal seam methane producer to secure supply of 10ML per day (approximately 3,500ML per year) of waste water from their coal bed methane projects located less than 80 km fromFelton project.

    Other potential sources include:

    waste water produced by other coal seam methane producers;

    run off water from waste overburden dumps and the processing plant;

    recycled waste water from towns in the region;

    water entitlements purchased from landholders; and

    other government-controlled sources.

    Work force

    Stage 1 of Project development will require the following workforce:

    construction - 900 persons for 15 months;

    mining and coal handling - 120 persons ongoing;

    processing plant - 60 persons ongoing; and

    Ambre Energy Limited 17Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    18/33

    management and technical services - 20 persons ongoing.

    Accommodation for construction workers will be provided via a temporary camp. Ongoing workershave a number of attractive permanent accommodation options in surrounding towns. Where

    possible, personnel already living in the region will be invited to apply to fulfil positions available atthe Project.

    Transport

    Transport requirements are:

    a corridor for conveyor transport of coal across Hodgson Creek and return of solid waste tothe overburden dumps in the mining area;

    road access to transport infrastructure components to site the existing road corridor issuitable;

    as the Pittsworth to Felton road traverses the mining area, at some time in the future life ofthe Project, this road would require relocation to a mined and rehabilitated section of theProject area;

    road access to bring workers to site on a continuous roster, requiring transport at night;

    high voltage power transformers, power switch yards and high voltage power linesconnecting the site with the national grid and;

    pipelines for transporting water to site and synthetic crude oil and DME to markets (initiallyduring commissioning stage, synthetic crude oil and DME might be transported by rail androad transport).

    2.9 Timeframe for Project

    Ambre Energy is aiming to obtain all necessary mining leases and approvals for the Project in timeto allow commencement of construction of the Project during the first quarter of 2009. The object isto commission Stage 1A by the first quarter of 2010. The proposed commissioning timeframe forsubsequent stage is as follows:

    Stage 1B Third quarter 2011

    Stage 2 First quarter 2013

    Stage 3 Third quarter 2014

    This timeframe is subject to a number of contingencies, including the timing of governmentalapprovals, and access to sufficient capital at the relevant stages.

    Ambre Energy Limited 18Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    19/33

    3 Project Benefits and Costs

    3.1 Project Benefits

    The Felton Hybrid Energy Project will provide benefits to the local region as well as broader stateand national benefits.

    The key benefits include:

    Development of a significant alternative source of crude oil and gas, with the potential toreduce importation of oil and thereby improve Australias balance of trade;

    Development of a relatively low cost coal-to-liquids and coal-to-gas process that canenhance the economic value of Queenslands coal deposits, particularly currently sub-economic resources or waste coal such as coal washing rejects;

    Maximising economic value from the Felton North coal deposit for the State of Queensland;

    Development of Australias first DME production facility and the opportunity for Australiato play a leading role in the adoption of DME as a next-generation fuel;

    Encouraging the establishment in the Darling Downs region of downstream petrochemicalindustries such as the manufacture of olefins and other products that require crude oil as afeedstock;

    Diversification of the employment opportunities and skill base of people living in regionalQueensland; and

    The potential to exploit the same technology and development concept in other areas withinAustralia.

    Employment Opportunities

    Stage 1 of the Project will require the following workforce:

    construction - 900 persons for 15 months;

    mining and coal handling - 120 persons ongoing;

    processing plant - 60 persons ongoing; and

    management and technical services - 20 persons ongoing.

    3.2 Estimated Project Costs

    Preliminary estimates of capital costs for Stage 1A of the Project are in the order of $783 million.Ambre Energy plans to own and operate the mine, coal preparation plants and most of thecomponents of the petrochemical plant. Third parties will be invited to provide and operate theoxygen plant and power station.

    Ambre Energy Limited 19Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    20/33

    4 Existing Environment

    4.1 Climate

    The temperature and rainfall statistics for Pittsworth 15km north of Felton East, taken from theBureau of Meteorology web site, are listed in the following table:

    Statistic J F M A M J J A S O N D An

    Temperature 58 years of records 1909-1975

    Mean max (0C) 29.9 29.1 27.8 24.7 20.5 17.3 16.5 18.6 22.1 25.6 28.4 29.8 24.2

    Mean min (0C) 17.0 16.9 15.4 12.0 8.4 6.1 5.0 5.9 8.7 11.9 14.4 16.1 11.5

    Rainfall 120 years of records 1886-2007

    Mean (mm) 93.1 76.5 62.4 38.3 40.7 41.2 40.7 30.1 36.6 63.8 75.5 96.3 694.6

    Days 1mm 6.4 5.8 5.5 3.6 3.8 4.2 4.2 3.7 4.1 5.7 6.1 6.8 59.9

    Relative humidity 27 years 1938-1975

    Mean 9am (%) 65 70 69 66 69 74 70 65 61 57 54 59 65

    Table 4.1 Temperature and Rainfall Statistics for Pittsworth

    4.2 Topography

    The Project area includes the alluvial plains of Hodgson Creek rising to the low slopes of Walloonsandstones and finally to the steep slopes of the remnant basalt ridges and plateaus.

    The Central Darling Downs Land Management Manual produced by the Department of Natural

    Resources and Water has identified the following Land Resources Areas (LRA) in the Project site:

    Older Alluvial Plains: Broad level plains of basaltic alluvium with open grasslands;

    Basaltic Uplands: Undulating rises and rolling low hills rising to steep hills with coolibahopen woodlands; and

    Poplar Box Walloons: Undulating rises and low hills on Walloon sandstone with poplarbox open woodlands.

    This manual is restricted to the western side of Hodgson Creek and a soil survey will be conducted

    to extend this assessment to the east of Hodgson Creek and to qualify and quantify the soil types ofthe total project area to assist in mine and rehabilitation planning.

    4.3 Soils and Land Use Suitability

    While the soils in the Project area may not have been specifically surveyed, the Land ManagementManual lists the common and associated soils for the various LRAs mapped in the area.

    The common soils associated with the LRAs identified in the project area and their land usesuitability are listed in the Table 4.2.

    Ambre Energy Limited 20Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    21/33

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    22/33

    Lease Application area) and there has been a recording north west of the proposed mining area of arare plant, Digitaria porrecta, finger panic grass. With the prevailing drought conditions it is difficultto ascertain if these grasses still persist and vegetation surveys will be conducted to determine ifthese grasses are present.

    4.5 Surface water

    Hodgson Creek starts approximately 15 km south of Toowoomba and travels 30km before flowingsouthwest through the Project area where it is flanked by deep alluvial plains. Hodgson Creek thenflows southwest for a further 15km to join the North Branch of the Condamine River. Thecatchment at Balgownie (approx 2km downstream from Felton) is approximately 560 km2 with anannual discharge range of 333-154523Ml over an 18 year period. The hydrology of Hodgson Creekhas not been studied and no assessment has been made on the buffer zones that must be maintainedeither side of Hodgson Creek to ensure that properties upstream of the Project are not impactedadversely during flood events.

    4.6 Ground water

    The ground water sources in the Project area are the alluvial plains of Hodgson Creek, the Walloonsandstones, the Hutton (Marburg) sandstones and the basalts. All the groundwater resources in thearea have been allocated for use by landholders. The exploration activities have locatedgroundwater in the overburden above the coal measures which is not associated with the alluvial ofHodgson Creek. The quality of this water is suitable for stock but not for irrigation.

    4.7 Air Quality

    The region surrounding the Project site is rural with intensive cropping, cattle grazing, lot feeding ofcattle and intensive poultry farming. Emissions from these activities will be dust from cultivationand harvesting activities and odour from cattle lot feeding and poultry farming. The closest EPAmonitoring site is Toowoomba North which may not be applicable to this area, as the land-use onthe outskirts of Toowoomba may differ from the Felton area. Monitoring sites will be established atappropriate locations around the Project area.

    4.8 Noise and Vibration

    The agricultural practices in the Project area generate noise typical of a rural community and are

    generally accepted by the community. There are currently no industries in the area that generate thenoise and vibration associated with mining activities.

    4.9 Existing ecosystems

    Flora

    Figure 4.3 is a map showing existing ecosystems in the area of the proposed mining leases (the totalarea of which is outlined on the map). As indicated in section 4.4, remnant vegetation exists on

    basalt ridges. The remnant vegetation areas shaded green are not of concern, but the remnantvegetation area shaded pink is classified as endangered. The remainder of the landscape has beenintensively farmed.

    Ambre Energy Limited 22Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    23/33

    Fauna

    Typical of much of the Darling Downs, native fauna habitats have been greatly impacted byagricultural development in the Felton East area. Many natural habitats occur as remnants withinthis agricultural landscape, and some species of native fauna are able to exploit agricultural land tovarying degrees. Some species are however, locally restricted to, or highly dependent on theremnants of the natural landscape.

    Queensland Parks and Wildlife Service (EPA) records indicate the presence of the followingthreatened (rare, vulnerable or endangered) species within 25 km of Felton East, listed under the Nature Conservation Act 1992 (Queensland) and/or Environment Protection and BiodiversityConservation Act 1999 (Australia):

    Grey GoshawkMajor Mitchell's CockatooGlossy Black Cockatoo

    Painted HoneyeaterSwift ParrotLewin's RailPowerful OwlBlack-breasted Button-quailBulloak Jewel (butterfly)Spotted-tailed QuollBrush-tailed Rock-wallabyKoala (southeast Queensland)Long-legged Worm-skink.

    These species above are generally associated with native vegetation, and so the remnant natural

    habitats around Felton East are of possible significance to them.

    In contrast, however, a population of the Grassland Earless Dragon (Tympanocryptis pinguicolla)was discovered in recent years on the Darling Downs to the east of Pittsworth. This species had

    been considered extinct in Queensland until its rediscovery, and is now listed as Endangered(Nature Conservation Act 1992). All specimens are known from highly modified agricultural land,typically small holdings devoted to strip-farming of mixed crops, such as cotton, sorghum, maizeand sunflower interspersed with fallow land. Large areas of native and introduced grasses existingas headlands, and along drainage lines are a feature of the farmlands where the dragon exists (EPA,2008: www.epa.qld.gov.au). It is possible this species might also occur in the Felton East area.

    Ambre Energy Limited 23Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    24/33

    Figure 4.3 2003 Regional Ecosystem Mapwith Proposed Mining Lease Application Area

    Ambre Energy Limited 24Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    25/33

    5 Measures to Control Potential Environmental Impacts

    5.1 Air

    Impacts on air quality will be generated by the following activities:

    Dust from the mining operations and coal handling processes;

    Flue gas from the coal drying operation;

    Flue gas from the gas engines generating power for internal use;

    Flue gas from the IGCC power plant;

    Fugitive emissions including odours; and

    Greenhouse gas release from the coal reserves during mining and processing.

    Mitigation

    Dust generation will be managed by water sprays supplemented by commercially available dust

    suppressant agents and by forest plantations established as soon as practically possible within bufferzone around processing plant and mine.

    Flue gas from the drying process may contain particulate coal. This stream will be treated using abaghouse to ensure emissions are within allowable limits.

    Flue gas from the dryer, the gas engines and the power plant will contain standard combustion products, including NOx. Air emission modelling work, burner design and any post combustioncapture systems required, will be detailed during the design of the Project to ensure air emissionsare within acceptable limits.

    Odour has been identified by the project team as a source of community concern. The processes ofcoal drying at relatively low temperatures and combustion of the gas from gasification to makepower are not expected to generate odours. Given the community concern however, Ambre Energywill carry out test work to determine if odours will be present in any of the continuously operatingstreams.

    With the exception of the dryer, gas engines and power plant flue gases, all other gas and liquidstreams containing the product hydrocarbons are fully enclosed. However, fugitive emissions areoften the source of odour complaints from coal and hydrocarbon processing and these will becontrolled by the development of Standard Operating Procedures to ensure, among other things, thatthe air is evacuated and treated before maintenance is conducted.

    5.2 CO2 Emissions

    Based on test work completed to date and current design parameters, the Project will generate thefollowing CO2 emissions for each of the 3 main products:

    Synthetic Crude Oil 120kg of CO2 emission per bbl or 800kg CO2 emission per tonne ofcrude oil produced;

    DME 1,000 kg of CO2 emissions per tonne of DME;

    Power from IGCC power plant 500kg of CO2 emissions per MWhr of generated power.

    Ambre Energy Limited 25Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    26/33

    Mitigation

    The above figures can be significantly reduced by removing CO2 from retort gas and from tail gas before combusting it in the power plant. The process plant configuration can be tailored forproduction of high purity CO2 gas, which can be used by food manufacturers and by the oil industryfor Enhanced Oil Recovery. In addition to potential CO2 recovery and storage, Ambre Energy is

    planning to implement the following action to offset CO2 emissions:

    Planting of soft and hard wood plantations within the buffer zone around processing plantand mine, and on the waste dumps reclaimed after open cut coal mining;

    Planting of carbon sink forest plantations in Australia and in other countries;

    Application of Ambre Energys technology and process configurations, includingconcentration and capture of CO2, to other coal producing regions such as Indonesia, Chinaand India.

    5.3 Ground Water

    Initially mining will intersect ground water resources in the Walloon coal measure and mayintersect groundwater in the alluvials of Hodgson Creek. Eventually aquifers in the basalts may beintersected.

    Mitigation

    Groundwater studies will be conducted prior to mining operations commencing to quantify aquifersand to ascertain the impacts of mining on these aquifers. The water from these resources is fullyallocated to the farming community, and discussions will be held with the Department of NaturalResources and Water as to the process required to access these resources.

    Water extracted by the mining process will be used for such purposes as coal washing and dustsuppression.

    5.4 Surface water

    The disturbance from the mining operations will generate large amounts of sediment which has thepotential to flow into Hodgson Creek.

    Mitigation

    As surface water will be a valuable commodity, the emphasis will be on the harvesting of runoff forre-use rather than simply to still the runoff for sufficient time to allow the sediment to settle. Thefirst structures to be constructed will be the levees on both sides of Hodgson Creek to retain allrunoff from the construction and mine development sites.

    The levees will be located to leave a buffer zone of at least 200m between the levees toaccommodate flood flows in Hodgson Creek. The sizing of the buffer zones is to be validated by ahydrological study of the flow characteristics of Hodgson Creek. On the western side this levee willform the initial outer slope of the overburden dump which will progress to the west as the mineadvances. The runoff from the levee construction will be directed into sediment sumps. All runoff

    upslope from either levee will be directed into large sumps, constructed to allow access for portablerecycling pumps.

    Ambre Energy Limited 26Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    27/33

    Individual work areas with high sediment yield potential such as the coal preparation plants and coalstockpiles will be equipped with sediment sumps to remove coarse sediment before flowing to thelarger levee sumps. Graded banks and waterways will be constructed to direct runoff from unminedareas around the mining and processing operations. This water will be retained in separate dams andsumps for recycling.

    5.5 Water Conservation

    Water is required for the mining and coal washing processes as well as the processing of the coal toproduce gas and hydrocarbons. Water is a scarce resource on the Darling Downs and the Projectwill impact on the water resources.

    Mitigation

    Ambre Energy will design the mining and processing to maximise the re-cycling of water as well as

    water harvesting from the site. A further conservation measure will be to minimise evaporationlosses by designing the water supply dams to have the least surface area per storage volume. Awater storage dam with a capacity of 10,000 ML and a depth of about 12 metres will be built. Waterfrom smaller sediments dams will be pumped to this dam, or the smaller dams will be equipped withwater fill points to supply water to water trucks for dust suppression. Dust suppressants will also beused to improve the efficiency of the dust suppression water.

    The use of evaporation blankets on the main storage dams will also be investigated.

    5.6 Water Quality

    Mining activities will generate large quantities of sediment as will the diverting runoff water aroundthe operational areas. This sediment has the potential to impact on the quality of water and aquatichabitat in Hodgson Creek and other small steams flowing from the Project area.

    Mitigation

    Runoff from the mining activities will be managed through a series of sediment dams and thestringent requirement to maximise the recycling of water, a resource in short supply.

    Re-direction of runoff around the mining activities from Project controlled land also has the potential to generate large sediment loads from erosion of waterways and cultivated paddocks.

    Waterways and diversion banks will be designed and constructed using conservative design criteriato minimise water velocities, and waterways will be stabilised with grass cover or the placement ofrock mulch to minimise erosion.

    Management of land controlled by the Project and not required for mining activities will bedesigned to minimise runoff and thus erosion. The land acquired by the company will beamalgamated into manageable production units. Farming practices will maximise crop stubbleretention or pasture cover and minimum tillage will be practised. Alternatively, forest plantationoptions will be evaluated.

    Ambre Energy Limited 27Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    28/33

    5.7 Hydrology

    The incursion of the Project onto the flood plains of Hodgson Creek will cause changes to the flowcharacteristics during high flow conditions. This may cause raised water levels upstream from thelevees, affecting upstream farming practices on the alluvials and infrastructure such as pump

    installation.

    Mitigation

    A hydrological study will be commissioned to identify the changes in flood levels for various floodevents. This study will identify farming areas that may be affected and will provide a basis fordiscussions with upstream landholders. The study will validate the arbitrary 200m Hodgson Creekcorridor or recommend changes to reduce upstream effects.

    5.8 Land Management

    Overburden Characterisation

    As yet the overburden has not been characterised but initial observation of the Walloon sandstoneand the basalts indicates that these materials weather to form good agricultural soils. The miningtechniques will use truck placement of the overburden so that selective handling of overburden will

    be used to bury any material that may generate acid or undesirable levels of heavy metals that maybe mobilised by leachate from the dumps. The overburden strata will be analysed to identify stratathat requires selective handling and placement in the dumps.

    Select overburden will be used to rock mulch the outer slopes of the levee. This material will beeither basalt or Walloon sandstone or a combination. Initial wetting and drying tests on the Walloonsandstone indicate that this sandstone is resistant to breakdown by wetting and drying, an indicationof high silica cementing compounds. The sandstone is not as resistant to breaking as is the basalt butwill form an ideal rock to blend with basalt as it will provide both erosion resistance whilstweathering into a soil. The soil component is essential to ensure that runoff remains on the surfaceof the rock mulch rather than eroding the subsurface below the rock.

    Topsoil Management

    Before development commences on the site, a soil survey will be conducted to identify thesuitability classification of the various soil types as to their potential to produce the range of cropsthat have been grown in the past. One of the criteria used to determine the suitability class of a soil

    profile is the potential to store plant available water (easily extracted by plant roots) in the profile.

    The aim of the rehabilitation program is to return a landform on the mining areas with a similarproportion of suitability classes as existed pre mining. Thus returning the soil profile is an importantfirst step.

    During the mining operations more intense soil surveys will be conducted to plan topsoil strippingand storage operations. Topsoil and the subsoils to a depth indicated by the suitability classificationwill be stripped separately and replaced in the reverse order on the reshaped overburden dumps.Where possible the soil profiles will be directly replaced on reshaped spoil.

    On the processing plant site generally only the topsoil layer will be removed for storage andeventual return as the pavement for the product storage area will be placed directly on the subsoil.Where geotechnical stability is an issue the subsoils may be removed for eventual return before the

    topsoil is respread during the rehabilitation of the plant infrastructure site.

    Ambre Energy Limited 28Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    29/33

    Topsoil will be removed by scrapers and stockpiled separately from the subsoil, which will beremoved either by scrapers or by shovel and truck. When the overburden dump is sufficiently

    progressed to the west the subsoil and topsoil will be directly respread. Where topsoil and subsoilhas to be stored the sides of the topsoil dumps will be shaped to a 4:1 gradient and the dump surfacecultivated and planted with cereal/grass/legume mix to minimise erosion and to retain biologicalactivity in the soil.

    Overburden Removal and Landform Construction

    Overburden will be removed by a conventional shovel and truck operation with the initialoverburden being transported to an external dump that will form the levee approximately 100m westof Hodgson Creek. The height of the levee/dump will be determined by a life of mine overburden

    balance which will determine the surplus of overburden that has to be placed in external dumps.Initial indications are for a levee at RL 446m advancing to the west forming a plateau with thesurface draining to the west at approximately 0.5%. As the dump progresses over the initial claytreatment pond, new ponds will be progressively developed in the mined-out pits. At RL445 thedump will rise at a maximum 10% gradient to meet the smaller of two remnant basalt hills at

    RL495. The top of this hill will not be mined.

    At approximately 15m vertical intervals a 20m horizontal berm will be constructed between each10% slope. The resultant landform will have a maximum slopes length of 150-200m to minimise theerosion potential during the initial re-vegetation phase to stabilise the slopes. The runoff from thedump will be discharged to natural ground via unmined stable natural waterways or a constructedwaterway lined with rock mulch. During the mining operation all runoff will be directed intosediment sumps, including the clay treatment ponds.

    Revegetation

    As the soil profile is respread, care will be taken to reduce compaction from the spreading

    equipment by ripping, and to blend the subsoil with the reshaped spoil surface. Topsoil will then berespread and further ripping will remove compaction and blend the topsoil with the subsoil duringthe seeding process.

    The initial surface treatment will be to control initial erosion by ripping and planting high rates ofcereal cover crops as well as grasses and deep rooted legumes. Fertilizer will also be applied.Depending on the season it may be necessary to hay mulch the surface, immediately after seeding,to both minimise erosion as well as provide shade to reduce water loss from the surface, which willextend the germination period. The aim is to produce a vegetative cover of at least 70% projectedleaf cover, to effectively control erosion as well as to build up the organic carbon in the soil thatwould have been lost during storage.

    This vegetative cover will remain for several years after which time cropping trials will beimplemented. These trials will ascertain the suitability of the various rehabilitated landforms tomaintain acceptable erosion losses during fallow period with reduced standing stubble cover afterthe crops have been harvested.

    Trees will be introduced in some areas only after the slopes have been stabilised with a vegetativecover. This will involve using seedlings and may require initial irrigation depending on the rainfall

    patterns. Experimentation will also be done with direct seeding on areas where rip lines pondrainfall runoff generated from adjacent tracks and flat areas. These tracks that generate runoff aregenerally constructed on the berms.

    The acquisition of farming properties can lead to sub standard management of this land withattendant decline in productivity and weed management and an increase in erosion. This will be aconcern for local landholders who have farmed in this local area, sometimes for generations.

    Ambre Energy Limited 29Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    30/33

    Secondly the development of the Project has the potential to produce rehabilitated landforms withmuch lower land suitability criteria than the present criteria.

    Mitigation

    Land management will involve:

    the farming or commercial forestation of the land acquired by the Project until required bythe mining operations;

    the rehabilitation of the mined land to appropriate land suitability classes;

    the farming or commercial forestation of the rehabilitated land;

    the decommissioning of the final mine voids, infrastructure and processing facilities and thereturn of pre mine land suitability to this land; and

    the disposal of the land after decommissioning of the Project.

    These issues will be addressed and strategies developed well before construction to ensure that landacquired by the Project is managed with conservation farming or forestry practices, and the return ofappropriate land suitability classes will be an integral part of the rehabilitation and decommissioning

    program. The rehabilitation program outlined in section 5.8, in particular the topsoil and subsoilmanagement, will ensure that the rehabilitated landform provide a similar proportion of landsuitability classes as now exist.

    5.9 Transport

    The transport requirements of the Project will involve the following:

    daily commuting of workers, both construction and permanents with 24 hour operation forpermanent workers;

    delivery of construction materials which may include large components requiring escorts;and

    the movement of large quantities of hydrocarbon liquids and possibly gas from thepetrochemical plant for export or use in a coastal refinery.

    Mitigation

    The project team will investigate all these issues to ensure that these traffic movements do not causeunnecessary damage to local or regional roads, and that other options are investigated including railor pipeline transport of product.

    Risk assessment will be conducted on the various options, including the commuting of permanentworkers. The final selection of the transport options will be driven by firstly, risk assessments andsecondly, economics.

    Ambre Energy Limited 30Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    31/33

    5.10 Flora and Fauna

    The remnant native vegetation, predominantly Eucalyptus coolabah and Eucalyptus orgadophila,will be removed except for the areas of hill tops that will not be mined because of the depth to coal

    being too great. A smaller area of Queensland blue grass will also be removed by mining. At this

    stage the habitat value of these communities for the native fauna of the area is not known.

    Mitigation

    The rehabilitation programme will develop landforms with the same or better suitability classes sothat the re-introduction of these tree species will be incorporated into the programme. Further,where hill tops have already been cleared for pasture, a program to re-introduce native tree specieswill be investigated and implemented. Techniques will involve both direct seeding and the use oftube stock.

    A fauna survey will identify the importance of the vegetated areas as fauna habitats, and the re-establishment of these native tree areas will be linked by tree corridors to similar vegetation

    communities adjacent to the project area to facilitate the movement of fauna into the rehabilitatedareas.

    5.11 Native Title and Cultural Heritage

    The land in the Project is freehold and as such Native Title has been extinguished. The bed ofHodgson Creek would appear to be open to claim as the freehold blocks do not abut in the centre ofthe creek, but a Native Title Search conducted on the 20 August 2007 has identified that there is no

    Native Title on this land. Hodgson Creek was included in the area claimed by the Western WakkaWakka People on 27 January 1999. This claim has been finalised so that Hodgson Creek is notunder claim.

    A cultural heritage survey has not been conducted on the Project area.

    Mitigation

    Hodgson Creek will be protected by a buffer zone of approximately 200m. A cultural heritagesurvey will be conducted over the Project area leading to the development of a Cultural HeritageManagement Plan, depending on the results of the survey.

    5.12 Visual Amenity

    Due to the topography, the Project site is highly visible from the adjacent public roads and presentsa vista of cultivated paddocks extending up to vegetated hill tops. Due to the small rural populationthere is a limited amount of domestic lighting resulting in a clear night sky. This landscape will be

    progressively removed while the activities associated with mining and the work areas will beilluminated continuously.

    Mitigation

    The progressive loss of the vista will be partially offset by the construction and rehabilitation of themain levee on the western side of Hodgson Creek which will be approximately 30m in height andwill partially hide the mining operations. Very little else can be done to hide the mining activities

    from the PittsworthFelton road, although planting of trees may have some effect. The processing

    Ambre Energy Limited 31Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    32/33

    areas will be landscaped and lights will be subject targeted and time limited to minimise annoyanceto offsite dwellings.

    5.13 Environmental Management

    The strategies and techniques to mitigate environmental impacts will be incorporated in anEnvironmental Management System (EMS) to the ISO 14001 standard which will operate from thestart of construction. Separate EMSs will operate for the mining and coal preparation operation onthe Mining Leases, west of Hodgson Creek and the petrochemical processing facility on theindustrial site, east of Hodgson Creek.

    5.14 Hazards and Risks

    In addition to the potential hazards already identified as being associated with an open cut miningoperation, such as personnel safety, environmental damage, vibration, noise, dust, etc., there are also

    potential hazards associated with the production, storage and transportation of hydrocarbon fuels.

    Mitigation

    There are well established procedures for dealing with hydrocarbon fuels and these will beidentified in detail in the EIS.

    Ambre Energy Limited 32Initial Advice Statement Felton Hybrid Energy Project

  • 8/14/2019 Ambre Energy IAS 15 Feb 08

    33/33

    6 Stakeholder Consultation

    Ambre Energy has started a consultative process with relevant interested parties. A key aspect ofthis process is discussions with landowners and community members directly affected by theProject to identify any areas of concern. This process will continue and includes identification of allstakeholders, discussion with Local, State and Federal Government representatives, communication

    plans and consultation and negotiation on measures required to address compliance and communityconcerns.