Reference
Project name: Research project in Alzey,
Germany
Client: Wilhelm Faber GmbH
Contract value: 100,000.00 €
Project duration: 2003
Project description: Research project for testing alternative aeration and bottom liner
systems
Results achieved: • Design and conception of the test
• Construction of the test area
• Construction of the test windrow
• Scientific execution of the tests
Reference
Project name: Pilot project for the introduction of
an integrated waste management
system in Atlacomulco, Mexiko
Client: Secretaría de Ecología del Estado
de México
Contract value: approx. 460,000.00 €
Project duration: Since 2002
Project description: • Waste recycling
• Composting
• Residual waste treatment
Landfilling
Results achieved: • Conceptual design and introduction of the industrial plant as a pilot
project
• Implementation of the FABER-AMBRA® system for residual waste
treatment and composting
• Conceptual design and introduction of the separate waste
collection system
Reference
Project name: Mechanical-biological waste pre-
treatment
Client: Samae
(Public utility company Blumenau,
Brazil)
Contract value: approx. 300,000.00 R$/a
Project duration: Since 2002
Project description: • Introduction of a controlled waste landfill
• Implementation of the waste pre-treatment for 50,000 t/a
Results achieved: • Realization of a pilot operation for mechanical-biological waste
treatment
• Conceptual design and introduction of the industrial plant
• Implementation of the FABER-AMBRA® system
• Operation-accompanying consulting to ensure the quality standards
Reference
Project name: Mechanical waste treatment plant
Diekirch, Luxembourg
Client: Sidec, Luxembourg
Contract value: approx. 3,450,000.00 €
Project duration: 2001 – 2002
Project description: • Hall constructed out of steel with embankment walls, 2,600 m²
• Mounted surfaces 6,000 m²
Results achieved: • Construction of a plant for the mechanical waste treatment as the
prime contractor
• Comminution, metal separation, homogenization
• Construction of the required infrastructure such as access roads,
waste delivery place, drainage
Reference
Project name: Mechanical-biological waste
treatment, Phitsanulok, Thailand
Client: Municipal authorities of
Phitsanulok
Contract value: approx. 500,000.00 €
Project duration: Since the year 2000
Project description: Introduction of the FABER-AMBRA® system for the pre-treatment of
waste
Results achieved: • Realization of a pilot operation for mechanical-biological waste
treatment
• Conceptual design and introduction of the industrial plant
• Implementation of the FABER-AMBRA® system
Reference
Project name: Conversion of the landfill operation
Client: Municipal authorities of
São Sebastião
Contract value: approx. 1,000,000.00 €
Project duration: Since 2000
Project description: • Introduction of a controlled waste landfill
• PPP-cooperation project with the GTZ for the know-how transfer
• Implementation of the waste pre-treatment for 30,000 t/a
Results achieved: • Realization of a pilot operation for mechanical-biological waste
treatment
• Conceptual design and introduction of the industrial plant
• Implementation of the FABER-AMBRA® system
• Supply of the required equipment for the waste treatment
Reference
Project name: Introduction of the FABER-
AMBRA® system in Rio de
Janeiro, Brazil
Client:
Contract value: approx. 1,000,000.00 €
Project duration: 1999 – 2001
Project description: • Research project for the introduction of a mechanical-biological waste
treatment system in Brazil as a pilot project
• Scientific assistance by the technical University of Braunschweig and
the UFRJ, Rio de Janeiro
Results achieved: • Application, design and coordination of the project plan
• Supply of the required equipment for the waste treatment
• Construction of the test windrows
Reference
Project name: Waste pre-treatment on the landfill
of Meisenheim
Client: Local government authorities of
Bad Kreuznach
Contract value: approx. 1,100,000.00 €/a
Project duration: 1994 – 1999
Project description: • Operation of the plant for mechanical-biological waste pre-treatment
for a maximum of 53,000 t/a
Results achieved: • Separation of recyclable, bulky and hazardous materials
• Mechanical waste treatment
• Biological waste treatment
• Low-emission landfilling of the waste
Reference
Project name: Landfill of Meisenheim
Client: Local government authorities of
Bad Kreuznach
Contract value: approx. 5,000,000.00 €
Project duration: 1993 – 1994
Project description: • Construction of a hall made of steel (20 x 40 m) for the mechanical
treatment
• Surface preparation for the biological waste treatment
Results achieved: • Construction of the plant as the prime contractor
• Delivery of the engineering machinery
• Construction of the required infrastructure
• Winter security preparation for the new landfill area
Reference
Project name: Mechanical-biological waste
treatment, Cul de Sac, St. Martin
Client: Verde
Contract value: approx. 1,400,000.00 €
Project duration: Since 2006
Project description: • Introduction of the FABER-AMBRA® system on an existing landfill for
the pre-treatment of waste
• Quality security, training and support
Results achieved: • Implementation of the FABER-AMBRA® system
• Supply of the required equipment for the waste treatment
Reference
Project name: "Support to the Waste
Management to Commune of Villa
Alemana"
Client: Municipality of Villa Alemana
Contract value: ca. 484.400,00 €
Project duration: 12 months
Project description: • Development of a project of investigation applied (project pilot) for
Mecanichal-Biological Treatment (MBT) of waste.
• "Waste Management Integrated Plan for the Municipality of Villa
Alemana" and a proposal of integration of the neighboring
communes members from the Marga-Marga Association of
Municipalities: Limache, Olmué and Quilpue - V Region-Chile.
Results achieved: Urban Waste Management Integrated Plan
The systematic proposals of the Villa Alemana Urban Waste
Management Integrated Plan are summarized in the creation of public
policy for the municipal management of solid urban waste;
development and preparation of the population through environmental
education; enhancement and treatment of solid waste so that the
environmental and economic impacts are minimized and conditions
and training for the social integration of scavengers, through new ways
of working in cooperatives and into the municipal cleaning system.
MBT
The project consisted in 4 windrows construction and monitoring of
biological stabilization:
• Windrow 1, 3 and 4: mixed solid household waste;
• Windrow 2: organic green waste in order to generate a compost of
high quality
Reference
Project name: Mecanical-biological waste
treatment in Semarang,
Indonesien
Client: ITR PT. Iman Tatakerta Raharja
Contract value: approx. 1.900.000 €
Project duration: Since May 2011
Project description: • Introduction of the FABER-AMBRA® system for the pre-treatment of
municipal waste
• 350 t/d
• Quality assurance, training and support
Results achieved: • Implementation of the FABER-AMBRA® system
• Supply of the required equipment for the waste treatment
Reference
Project name: Pilot project for the introduction of
an integrated waste management
system in Karaganda, Kazakhstan
• Feasibility Study
• Project Development
• Quality Managament
Client: Kazakh Government
Contract value: approx. 1,100,000.00 €
Project duration: 2012/2013
Project description: • Feasibility Study for a region with 800,000 inhabitants
• Implementation
• Complete waste management of 800 t/d over 20 years
• Feasibility Study completed and tender ongoing
Results achieved: • Our project is the technical basis for a huge international
consultancy for the development of a new system to cover the
waste management costs by fees