ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh,...

31
ACEC – Transportation Committee, March 28, 2018 ALTERNATIVE PROJECT DELIVERY Varuna Singh

Transcript of ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh,...

Page 1: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

ALTERNATIVE PROJECTDELIVERYVaruna Singh

Page 2: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 288 INHARRIS COUNTY

Page 3: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 288 in Harris County

▪ SEGMENT 1:

– 8 New Tolled Direct Connectors at SH 288 and Beltway 8

• Existing traffic uses frontage roads today to travel between these two facilities

• Both SH 288 general purpose lanes and managed toll lanes will be able to access new tolled DCs

– 4 New Managed Toll Lanes (2 in each direction)

Page 4: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 288 in Harris County

▪ SEGMENTS 2 & 3:

– 4 New Managed Toll Lanes (2 in each direction)

Page 5: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 288 in Harris County

▪ SEGMENT 4:

– Full Reconstruction of existing non-toll 8 Direct Connectors

• Both SH 288 general purpose and managed toll lanes can access non-toll DCs

– Full Reconstruction of Holly Hall St over SH 288

– 4 New Managed Toll Lanes (2 in each direction)

Page 6: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 288 in Harris County

▪ SEGMENT 5:

– 2 New Tolled Direct Connectors in/out of Texas Medical Center

– 4 New Managed Toll Lanes (2 in each direction)

Page 7: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 288 in Harris County

▪ SEGMENT 6:

– 4 New Tolled Managed Lanes (2 in each direction)

– Full Reconstruction of Southmore Blvd over SH 288

– 4 New Managed Toll Lanes (2 in each direction)

Page 8: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

▪ Owner: Texas Department of Transportation (TxDOT)

▪ Developer: Blueridge Transportation Group, LLC (BTG)

– ACS Infrastructure Development, Inc. – 21.6%

– InfraRed Capital Partners – 21.6%

– Shikun & Binui Concessions USA, Inc.– 21.6%

– Northleaf Capital Partners – 18%

– Clal Insurance – 12.1%

– Star America Infrastructure Partners – 5%

▪ Lead Contractor: Almeda-Genoa Constructors (A-GC)

– Dragados USA – 30%

– Pulice Construction, Inc. – 20%

– Shikun & Binui America Inc.– 50%

– Lead Design Engineering Firm: Stantec (formerly KBR)

– Operations &Maintenance: Roy Jorgensen Co.

SH 288 - Project Team Structure

Page 9: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 288 - Project Costs & Funding

Capital Costs Funding Sources

Design & Construction $802,340,050 CDA Developer1

$798,411,339

Utilities $1,066,007 TxDOT via Concession Payment2 $3,680,000

Right-of-Way $12,105,282 TxDOT via Category 12 $13,420,000

Sub-total $815,511,339 Sub-total $815,511,339

Change Orders $1,973,968 TxDOT via Category 3 (PROP12) $3,952,972

Hazardous Material Remediation $1,979,004

Sub-total $3,952,972

TOTAL $819,464,311 TOTAL $819,464,311

Note 1: Comprised of TIFIA Loan, Bonds and Equity

Note 2: Total Developer Concession Payment to TxDOT was $25.48M

Page 10: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

▪ March 4, 2016: Contract Executed

▪ May 9, 2016: Developer achieved Financial Close

▪ October 25, 2016: Notice to Proceed 2 Issued

• START of 1000 days/33 months completion deadline

▪ As of today, March 28, 2018: 519 of 1000 days elapsed

(52% of project time)

– Design: over 95% complete

– Construction: over 27% complete

▪ July 22, 2019: Substantial Completion

• END of 1000 days/33 months completion deadline, project opens to traffic

SH 288 in Harris County - Milestones

20

16

20

19

20

18

20

17

Page 11: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 288 Managed Lanes Project (P3 Concession CDA)

www.drive288.com

Page 12: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 CORRIDOR

Page 13: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 Corridor

Segment 1: 14 miles

Owner: TxDOT

Scope: 4 toll lanes from FM 1774 near

Pinehurst to FM 1774 near Todd Mission

(2 lanes in each direction)

Page 14: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 Corridor

Segment 1: 14 miles

Owner: TxDOT

Scope: 4 toll lanes from FM 1774 near

Pinehurst to FM 1774 near Todd Mission

(2 lanes in each direction)

Segment 2: 10 miles

Owner: TxDOT

Scope: 2 non-tolled lane configuration for

entire limits (1 lane in each direction)

Page 15: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 Corridor

Segment 3: 3 miles

▪ Owner: Montgomery County Toll Road

Authority

Adds 4 toll lanes within existing non-toll

frontage roads from Harris/Montgomery

County Line to FM 1774 in Pinehurst

Page 16: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 Corridor

Segment 3: 3 miles

▪ Owner: Montgomery County Toll Road

Authority

Adds 4 toll lanes within existing non-toll

frontage roads from Harris/Montgomery

County Line to FM 1774 in Pinehurst

Segment 4: 1.5 miles

▪ Owner: Harris County Toll Road Authority

Adds 6 toll lanes within existing non-toll

frontage roads from FM 2920 to

Harris/Montgomery County Line

Page 17: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 - Milestones

▪ October 4, 2017: Contract Execution (NTP1)

– Base & Option 1 Segment 1 + Segment 2

▪ Segment 1

– October 25, 2017: Limited NTP2 for ROW Clearing

– January 10, 2018: Limited Design NTP2

– March 15, 2018: Full NTP2 (Anticipated)

– July 10, 2020: Substantial Completion

• 1,010 days (33 months) after NTP1

2017

2019

2020

2018

Page 18: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 - Milestones

▪ Segment 2

– June 15, 2018: Limited Design NTP2 (Anticipated)

– October 15, 2018: Limited Construction NTP2 (Anticipated)

– January 15, 2019: Full NTP2 (Anticipated)

• Dependent on USACE Nationwide Permit

– March 20, 2022: Substantial Completion

• 1,160 days (38 months) after NTP2

2019

2020

2021

20

22

2018

Page 19: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 - Current Status

▪ Segment 1 is at 60% overall design for earthwork, drainage, retaining

walls, and bridges. Design for Segment 1 is anticipated to be completed

by July 2018.

▪ Design has started on several utility re-locations. All utility relocations are

anticipated to be completed by the end of 2018.

Page 20: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 at FM 1488 From South Looking North

Page 21: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 249 – Public Information

For information about the project, please contact the Public Information Team:

▪ Email: [email protected]

▪ Hotline: 1-866-TX-SH249

▪ Public Information Office located at

Landmark Building

18230 FM 1488, Magnolia, TX 77354

Page 22: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 99 GRAND PKWYSEGMENTS H&I

Page 23: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 99 Segments H&I

Design-Build SCOPE:

▪ Segments H and I-1 (37.5 miles)

• I-69/US 59 to I-10E

• New 2 to 4 toll lane facility

▪ Segment I-2A (8.7 miles)

• I-10E to FM 1405

• Existing 4-lane toll facility

• Upgrades to ITS and tolling equipment

▪ Segment I-2B (6.5 miles)

• FM 1405 to SH 146

• New 4 toll lane facility

TOTAL Length: 52.7 miles

Page 24: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 99 Segments H&I – Current Status

24

Design: 7% complete

Right-of-Way: (in addition to existing ROW in early construction areas below)

• Total Parcel Count to be acquired: 220

• Parcel Count currently available for construction: 6

• Parcel County not yet available for construction: 214

Utility Relocations:

• Approximately 60 utility owners involved

• Approximately 320 adjustments needed

Construction: early work areas

• Northern project limits: I-69/US 59 interchange to Loop 494(1.6 miles)

• Southern project limits: Cedar Bayou to SH 146 (3.3 miles)

Page 25: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 99 Segments H&I - Milestones

— June 30, 2017: Contract Executed

— October 27, 2018: NTP2 and H-West Option Issued

— August 2018: Start of Construction

— August 2019: Anticipated completion of design

— Late 2019: Anticipated access to all parcels for construction

— Mid 2020: Anticipated relocations of all utilities

— February 2022: Substantial Completion

• 1,674 days (56 months) after NTP1

2019

20

20

2021

2022

2018

2017

Page 26: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

SH 99 Segments H&I – Public Information

For information about the project, please contact the Public Information Team:

▪ Email: [email protected]

▪ Hotline: 1-877-553-7371

▪ Public Information Office located at:

Wachter Building

7560 FM 1960, Dayton, TX 77535

Page 27: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP)

Page 28: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

NHHIP OVERVIEW

10

69

10

45

45

610

45

69

610

69 59

59

▪ Environmental Impact Statement (EIS)

▪ Project divided into 3 Segments:

– Segment 1: Beltway 8 to I-610 (9 mi)

– Segment 2: I-610 to I-10 (3 mi)

– Segment 3: Downtown Loop System (12.3 mi)

▪ Goal: provide a safer facility with additional capacity for

projected demand by incorporating transit opportunities,

travel demand strategies, and flexible operations

▪ One “Proposed Recommended Alternative” per segment =

single corridor end to end (24 mi total)

Page 29: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

Segment 1 Segment 2 Segment 3

SEGMENT 3: PROPOSED RECOMMENDED ALTERNATIVE

29

Page 30: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

NHHIP - Milestones

— Summer 2017: Public Hearings Held

— Summer 2018: Issue Design-Build RFQ for Segment 3

— Fall 2018: Shortlist Design-Build Proposers for Segment 3

— Late 2018: Anticipated Record of Decision (all 3 segments)

— Early 2019: Issue Design-Build RFP for Segment 3

— Mid 2019: Receive Design-Build Proposals for Segment 3

— Late Summer 2019: Conditional Award Design-Build Segment 3

— Fall 2019 to Late 2019: Design-Build Contract Execution for Segment 3

— Spring 2020: Design and early construction

20

19

2020

2018

2017

Page 31: ALTERNATIVE PROJECT DELIVERYacechouston.org/wp-content/uploads/2012/02/Varuna-Singh...Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) 866-7040

ACEC – Transportation Committee, March 28, 2018

Houston District Resources & Questions

Quincy Allen, P.E.TxDOT Houston District Engineer

(713) 802-5001 / [email protected]

Raquelle LewisTxDOT Houston District PIO

(713) 802-5071 / [email protected]

Pat Henry, P.E.TxDOT Houston District Director for Advance Project Development

(713) 802-5241 / [email protected]

Varuna Singh, P.E.TxDOT Houston District Director for Alternative Project Delivery

(713) 866-7040 / [email protected]

NHHIP – www.ih45northandmore.com