Allduro | Waterproofing Material Suppliers Perth...

3
2012-06 Project Name PLANTER BOX WATERPROOFING Section 00000 Page 1 of 3 1 WATERPROOFING Planter Box Waterproofing (sheet membrane) 1.1 SUBMITTALS 1.1.1 Product Data: Include physical properties of the specified materials and explanations about product installation, including installation techniques, restrictions, limitations and manufacturer recommendations. 1.1.2 Warranty: Certification that all components of the waterproofing assembly are being supplied and warranted by a single manufacturer. Provide a specimen warranty from the manufacturer that includes all components of the waterproofing installation. 1.1.3 Shop Drawings: Include details for all assemblies. These should include details for walls, curbs, drains, penetrations, edges and expansion/control joints. Include installation details for waterproofing, flashing, fastening and insulation as applicable. 1.2 QUALITY ASSURANCE INSTALLER QUALIFICATIONS 1.2.1 The installer shall demonstrate its qualification to perform the work of this section by providing written evidence from the manufacturer. MANUFACTURER QUALIFICATIONS 1.2.2 Shall have a minimum of 30 years experience manufacturing waterproofing membrane systems. 1.2.3 Shall submit a current copy of their ISO 9002 manufacturing certification for the plant where materials will be manufactured and shipped from. Additionally, the sequential production log and the ISO 9002 production control record documents shall accompany the material shipment and made a permanent part of the job record and warranty file. 1.3 MOCK UP: 1.3.1 Provide a mock-up for evaluation of surface preparation techniques and application workmanship. 1.3.2 Do not proceed with remaining work until workmanship is approved by Architect. 1.4 PRE-INSTALLATION CONFERENCE 1.4.1 Convene no less than five days prior to commencing Work at a time and location to be determined. 1.4.2 All parties responsible for Work of this section shall be required to attend including the Architect, Builder, Contractor and any other trades affected by the waterproofing work. 1.4.3 All outstanding issues shall be noted in writing designating the responsible party for follow-up action and the timetable for completion. 1.4.4 Application of waterproofing system shall not take place until all outstanding issues are resolved SPECIFICATION

Transcript of Allduro | Waterproofing Material Suppliers Perth...

Page 1: Allduro | Waterproofing Material Suppliers Perth …allduro.com/wp-content/uploads/2013/04/30-Planter-Box...2013/04/30  · 1.12.6 Aquamat Jardin is a capillary mat specially designed

2012-06 Project Name

PLANTER BOX WATERPROOFING

Section 00000

Page 1 of 3

1 WATERPROOFING Planter Box Waterproofing (sheet membrane)

1.1 SUBMITTALS

1.1.1 Product Data: Include physical properties of the specified materials and explanations about product installation, including installation techniques, restrictions, limitations and manufacturer recommendations.

1.1.2 Warranty: Certification that all components of the waterproofing assembly are being supplied and warranted by a single manufacturer. Provide a specimen warranty from the manufacturer that includes all components of the waterproofing installation.

1.1.3 Shop Drawings: Include details for all assemblies. These should include details for walls, curbs, drains, penetrations, edges and expansion/control joints. Include installation details for waterproofing, flashing, fastening and insulation as applicable.

1.2 QUALITY ASSURANCE

INSTALLER QUALIFICATIONS

1.2.1 The installer shall demonstrate its qualification to perform the work of this section by providing written evidence from the manufacturer.

MANUFACTURER QUALIFICATIONS

1.2.2 Shall have a minimum of 30 years experience manufacturing waterproofing membrane systems.

1.2.3 Shall submit a current copy of their ISO 9002 manufacturing certification for the plant where materials will be manufactured and shipped from. Additionally, the sequential production log and the ISO 9002 production control record documents shall accompany the material shipment and made a permanent part of the job record and warranty file.

1.3 MOCK UP:

1.3.1 Provide a mock-up for evaluation of surface preparation techniques and application workmanship.

1.3.2 Do not proceed with remaining work until workmanship is approved by Architect.

1.4 PRE-INSTALLATION CONFERENCE

1.4.1 Convene no less than five days prior to commencing Work at a time and location to be determined.

1.4.2 All parties responsible for Work of this section shall be required to attend including the Architect, Builder, Contractor and any other trades affected by the waterproofing work.

1.4.3 All outstanding issues shall be noted in writing designating the responsible party for follow-up action and the timetable for completion.

1.4.4 Application of waterproofing system shall not take place until all outstanding issues are resolved

SPECIFICATION

Page 2: Allduro | Waterproofing Material Suppliers Perth …allduro.com/wp-content/uploads/2013/04/30-Planter-Box...2013/04/30  · 1.12.6 Aquamat Jardin is a capillary mat specially designed

2012-06 Project Name

PLANTER BOX WATERPROOFING

Section 00000

Page 2 of 3

1.5 DELIVERY, STORAGE, AND HANDLING

Deliver materials in original unopened containers of packaging clearly labelled with manufacturer's name, brand name and all identifying numbers.

1.6 QUALITY CONTROL

1.6.1 Inspection: At a minimum, inspections shall be required at start-up and at intervals of approximately 30 percent, 60 percent and 90 percent completion. A final inspection shall be required.

1.6.2 Warranty shall be issued upon approval of the installation.

1.6.3 A final inspection report from the Technical Representative, certifying that the waterproofing system has been satisfactorily installed according to the project specifications, approved details and good general waterproofing practice, shall be provided.

1.6.4 At all times, the contractor shall permit and facilitate access to the site by the manufacturer's representative.

1.7 SITE PROTECTION

1.7.1 During waterproofing work, exposed surfaces of finished surfaces shall be protected to prevent damage. Contractor shall assume full responsibility for any damage.

1.7.2 The Contractor shall provide for adequate protection of the installed membrane preventing damage that might arise from work performed by the other trades.

1.7.3 Apply drainage/ protection board/ insulation as soon as possible after membrane installation.

1.8 PROJECT CONDITIONS

Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer's absolute limits.

1.9 WARRANTY

The product manufacturer shall issue a written and signed document in the name of the owner, certifying the product will meet all the physical characteristic published by the manufacturer, for a period of [ ] years, starting from the date of completion of installation of membranes. No letter amending the manufacturer’s standard warranty will be accepted and the warranty certificate must reflect these requirements.

1.10 MANUFACTURERS/SUPPLIERS

1.10.1 Acceptable Manufacturer: SOPREMA Inc., Melbourne Victoria. Phone: (03) 99383887 Fax: (03) 99383899 Web www.soprema.ca.

1.10.2 Licensed / Registered agent: Allduro, which is located in Perth, Western Australia. Tel: (08) 94551658 Fax: (08) 94562079 Email: [email protected] Web www.allduro.com

SPECIFICATION

Page 3: Allduro | Waterproofing Material Suppliers Perth …allduro.com/wp-content/uploads/2013/04/30-Planter-Box...2013/04/30  · 1.12.6 Aquamat Jardin is a capillary mat specially designed

2012-06 Project Name

PLANTER BOX WATERPROOFING

Section 00000

Page 3 of 3

1.11 PRODUCTS

SopraGum Garden 4C, Soprasun 3.0 S, Sopradhere Primer, Sopradrain 10G, Aquamat Jardin, Microfab and Sopramastic

1.12 PRODUCTS DESCRIPTION

1.12.1 Soprasun 3.0 S is an APP modified thermo fusible waterproof membrane. 1.12.2 Sopragum Garden 4C is an APP modified thermo fusible waterproof membrane with a root

inhibitor incorporated. 1.12.3 Sopradhere is a quick dry APP membrane primer. 1.12.4 Sopramastic is a solvent based mastic containing SBS modified bitumen, fibres and mineral

fillers. 1.12.5 Sopradrain 10G is a high-strength drainage panel consisting of a polypropylene core with a

factory-laminated geo-textile for installation over waterproof membranes to provide drainage. 1.12.6 Aquamat Jardin is a capillary mat specially designed for green roof irrigation and water

retention in green roof assemblies. 1.12.7 Microfab is a non-chemical anti-root barrier.

1.13 SYSTEM

1.13.1 One layer of Sopragum Garden 4C cap sheet on one layer of Soprasun 3S base sheet. 1.13.2 In areas where the waterproofing membrane is exposed to UV apply one layer of Soprasun 4.0 F. 1.13.3 Sopradrain 10G is placed over waterproofing membrane and covered with Aquamat Jardin and

Microfab. 1.13.4 Growing medium is placed over system after reticulation is connected.

1.14 SUBSTRATE PREPARATION

1.14.1 GENERAL All surfaces should be sound, dry and free from but not limited to, dirt, dust, oil, grease, wax, tar, asphalt, mildew, mold, paint, foreign sealers, coatings, curing agents, loose particles, laitance or any other foreign matter that may impede with the bonding of the primer or membrane.

1.14.2 PRIMING The substrate is to be primed using Sopradhere primer at a rate of 4 to 6 m² per litre.

1.15 MEMBRANE APPLICATION

1.15.1 Horizontal Waterproofing – A layer of Soprasun 3.0S is to be fully bonded to the blinding slab with 100mm side laps and 150mm end laps fully sealed together with propane torch fusion. This is followed by a layer of Sopragum Garden 4C with 100mm side laps and 150mm end laps laid in a staggered pattern to the first layer and fully bonded with propane torch fusion to the base layer. This is the followed by a layer of Sopradrain 10G drainage cell, Aquamat Jardin, Microfab and selected soils.

1.15.2 Vertical Waterproofing – A layer of Soprasun 3.0S is to be fully bonded to the walls with 100mm side laps and 150mm end laps fully sealed together with propane torch fusion. This is followed by

a layer of Sopragum Garden 4C with 100mm side laps and 150mm end laps laid in a staggered pattern to the first layer and fully bonded with propane torch fusion to the base layer. This is the followed by a layer of Sopradrain 10G drainage cell and fibre cement board and selected soils.

The above installation technique is presented by Allduro a as a ‘general suggestion” for the installation of the Sopragum waterproof membrane system.

It remains the responsibility of the architect, engineer, builder and installation contractor to establish the correct method for any given application. The

installation and detailing of the membrane in its entirety should all be carried out in strict accordance with the manufacturers written instructions.

SPECIFICATION