All About Construction Cash Allowances v1.2

of 98 /98
All about Construction Cash Allowances Version 1.2

Embed Size (px)

description

A presentation on Construction Cash Allowances as typically implemented by the CCDC (Canadian Construction Documents Committee)

Transcript of All About Construction Cash Allowances v1.2

  • All about Construction Cash Allowances Version 1.2
  • By Peter Vander Klippe
  • What is a Construction Cash Allowance?
  • Cash Allowances are funds set aside for work that will be detailed later
  • Why should you care?
  • Why care #1: Cash Allowances are part of most CCDC* contracts
  • *CCDC = Canadian Construction Documents Committee
  • *Almost every construction contract in Canada is based on a CCDC contract
  • Why care #2: They allow you to tender sooner
  • Example: A retail project that was part of a larger program
  • The client was bundling the refrigeration installation
  • (So that they could get the best price)
  • But they needed to get started on the construction ASAP
  • So they included a refrigeration installation Cash Allowance
  • The amount was estimated based upon previous costs
  • After they received the pricing on the refrigeration installation bundles
  • The work was assigned to the contractor
  • With no additional mark up for overhead or profit*
  • *this wont work if your estimate is too low
  • Work started on site sooner then if we had to wait for the final price
  • Why care #3: They provide flexibility
  • You can use Cash Allowances to be more flexible
  • This works best for scope near the end of the project
  • Like landscaping, furniture, and security.
  • You can defer some decisions to later in the process
  • So if a deal is found on used furniture you can sod instead of seed the lawn
  • Or if you decide to use keys instead of swipe cards you can afford a patio
  • Or if you exceed your budget you can use some of the Cash Allowance
  • No patio or Sod
  • Staying within your budget
  • Things to watch out for when using Cash Allowances
  • Watch out for multiple specific Cash Allowances
  • This can limit your flexibility and run against approval thresholds
  • Example:
  • You have three Cash Allowances
  • $10,000 for security
  • $50,000 for landscaping
  • And $140,000 for refrigeration installation
  • For a total of $200,000
  • Contract is awarded, contractor starts work
  • And it turns out that it is going to take a lot more security work
  • To connect this system to the clients other buildings requires upgrading the existing system
  • The new security estimate is $25,000
  • But, thankfully concurrent to this,
  • The pricing came in for the refrigeration installation
  • And the layout was revised, reducing the number of cases
  • Which reduced the refrigeration installation to $125,000
  • So now we have:
  • $25,000 for security
  • The same $50,000 for landscaping
  • And $125,000 for refrigeration installation
  • For a grand total of $200,000
  • BUT
  • When you tell your contractor about this
  • He demands $2,250 extra in overhead and profit
  • He says that managing a security company is a lot more work
  • So he included a 20% markup in his bid for the security Cash Allowance
  • And only a 5% markup for the refrigeration installation Cash Allowance
  • So because we are shifting $15,000 from 5% to 20% markup, he wants his cut
  • And to make it worse
  • Your client lets you know that as the security costs has risen by 150%
  • He needs his CEO to sign off on the change
  • This could all be avoided
  • Make sure it is clear that there is only one Cash Allowance
  • Watch out for hidden Cash Allowances
  • It can get complicated if Cash Allowances are not clearly identified
  • Example
  • The mechanical sub- consultant ran out of time prior to tender
  • And instead of designing the reverse osmosis system
  • A drawing note was included that instructed the contractor to carry a $15,000 Cash Allowance
  • Possible outcome #1: Waste of funds
  • 2 bids are disqualified as they didnt include this Cash Allowance
  • One of these bids that was $45,000 lower then the awarded contractor
  • Possible outcome #2: Contractor claim
  • The contractor awarded the job missed this Cash Allowance in his estimate
  • (This often happens as missing something lowers your price)
  • So when the Supplemental Instruction is issued for the reverse osmosis system
  • The contractor submits a claim for the work at $17,345 + 10% markup
  • Possible outcome #3: Double dipping
  • The contractor technically did include the cash allowance in his price
  • But do to staffing changes at the contractors company
  • The new representative for the contractor submits the claim anyways
  • And the contract administrator isnt aware of this Cash Allowance
  • So the claim is approved
  • The contractor also invoices for 100% of his base work
  • And as the contractors invoice doesnt itemize the Cash Allowance
  • He is paid for both the Cash Allowance and the draw
  • Which gives the contractor $30,000 for $15,000 worth of work
  • Summary
  • Cash Allowances can be extremely useful*
  • *if used correctly