All About Construction Cash Allowances v1.2
of 98
/98
-
Author
peter-vander-klippe -
Category
Engineering
-
view
200 -
download
5
Embed Size (px)
description
A presentation on Construction Cash Allowances as typically implemented by the CCDC (Canadian Construction Documents Committee)
Transcript of All About Construction Cash Allowances v1.2
- All about Construction Cash Allowances Version 1.2
- By Peter Vander Klippe
- What is a Construction Cash Allowance?
- Cash Allowances are funds set aside for work that will be detailed later
- Why should you care?
- Why care #1: Cash Allowances are part of most CCDC* contracts
- *CCDC = Canadian Construction Documents Committee
- *Almost every construction contract in Canada is based on a CCDC contract
- Why care #2: They allow you to tender sooner
- Example: A retail project that was part of a larger program
- The client was bundling the refrigeration installation
- (So that they could get the best price)
- But they needed to get started on the construction ASAP
- So they included a refrigeration installation Cash Allowance
- The amount was estimated based upon previous costs
- After they received the pricing on the refrigeration installation bundles
- The work was assigned to the contractor
- With no additional mark up for overhead or profit*
- *this wont work if your estimate is too low
- Work started on site sooner then if we had to wait for the final price
- Why care #3: They provide flexibility
- You can use Cash Allowances to be more flexible
- This works best for scope near the end of the project
- Like landscaping, furniture, and security.
- You can defer some decisions to later in the process
- So if a deal is found on used furniture you can sod instead of seed the lawn
- Or if you decide to use keys instead of swipe cards you can afford a patio
- Or if you exceed your budget you can use some of the Cash Allowance
- No patio or Sod
- Staying within your budget
- Things to watch out for when using Cash Allowances
- Watch out for multiple specific Cash Allowances
- This can limit your flexibility and run against approval thresholds
- Example:
- You have three Cash Allowances
- $10,000 for security
- $50,000 for landscaping
- And $140,000 for refrigeration installation
- For a total of $200,000
- Contract is awarded, contractor starts work
- And it turns out that it is going to take a lot more security work
- To connect this system to the clients other buildings requires upgrading the existing system
- The new security estimate is $25,000
- But, thankfully concurrent to this,
- The pricing came in for the refrigeration installation
- And the layout was revised, reducing the number of cases
- Which reduced the refrigeration installation to $125,000
- So now we have:
- $25,000 for security
- The same $50,000 for landscaping
- And $125,000 for refrigeration installation
- For a grand total of $200,000
- BUT
- When you tell your contractor about this
- He demands $2,250 extra in overhead and profit
- He says that managing a security company is a lot more work
- So he included a 20% markup in his bid for the security Cash Allowance
- And only a 5% markup for the refrigeration installation Cash Allowance
- So because we are shifting $15,000 from 5% to 20% markup, he wants his cut
- And to make it worse
- Your client lets you know that as the security costs has risen by 150%
- He needs his CEO to sign off on the change
- This could all be avoided
- Make sure it is clear that there is only one Cash Allowance
- Watch out for hidden Cash Allowances
- It can get complicated if Cash Allowances are not clearly identified
- Example
- The mechanical sub- consultant ran out of time prior to tender
- And instead of designing the reverse osmosis system
- A drawing note was included that instructed the contractor to carry a $15,000 Cash Allowance
- Possible outcome #1: Waste of funds
- 2 bids are disqualified as they didnt include this Cash Allowance
- One of these bids that was $45,000 lower then the awarded contractor
- Possible outcome #2: Contractor claim
- The contractor awarded the job missed this Cash Allowance in his estimate
- (This often happens as missing something lowers your price)
- So when the Supplemental Instruction is issued for the reverse osmosis system
- The contractor submits a claim for the work at $17,345 + 10% markup
- Possible outcome #3: Double dipping
- The contractor technically did include the cash allowance in his price
- But do to staffing changes at the contractors company
- The new representative for the contractor submits the claim anyways
- And the contract administrator isnt aware of this Cash Allowance
- So the claim is approved
- The contractor also invoices for 100% of his base work
- And as the contractors invoice doesnt itemize the Cash Allowance
- He is paid for both the Cash Allowance and the draw
- Which gives the contractor $30,000 for $15,000 worth of work
- Summary
- Cash Allowances can be extremely useful*
- *if used correctly