Aleks Baltovski

31
19/08/2013 1 Aleks Baltovski – Design Manager Probuild Constructions (Australia) BIM ANNUAL SUMMIT 2013 A CASE STUDY: MONASH UNIVERSITY NEW HORIZONS PROJECT 26 August 2013 OVERVIEW > Monash University New Horizons Project BIM initiatives implemented Lessons Learnt & Feedback > Current capabilities > Future strategy > Closing comments

Transcript of Aleks Baltovski

Page 1: Aleks Baltovski

19/08/2013

1

Aleks Baltovski – Design ManagerProbuild Constructions (Australia)

BIM ANNUAL SUMMIT 2013A CASE STUDY:MONASH UNIVERSITY NEW HORIZONS PROJECT26 August 2013

OVERVIEW

> Monash University New Horizons Project BIM initiatives implemented Lessons Learnt & Feedback

> Current capabilities

> Future strategy

> Closing comments

Page 2: Aleks Baltovski

19/08/2013

2

PROBUILD HISTORY

› Privately owned organisation

› Founded in 1987 by Phil Mehrten

› Annual turnover = approx.$800m

› Target turnover by 2014 = $1b

› Servicing the following sectors:

› Retail- Colonial First State (Myer Bourke St)- GPT (Highpoint)- QIC (Eastland)

PROBUILD HISTORY

› Commercial- 717 Bourke St (MCCP)

- SE Water

› Government- Shrine Galleries of Remembrance

› Educational- Melbourne University

- Swinbourne University

- Melbourne Grammar School

Page 3: Aleks Baltovski

19/08/2013

3

PROBUILD HISTORY

› Research- Monash University New Horizons

› WBHO as major share holder (early 2000’s)

› Recent merge with Contexx & Monaco Hickey

PROJECT BACKGROUND

Page 4: Aleks Baltovski

19/08/2013

4

MONASH UNIVERSITY NEW HORIZONS PROJECT

CLIENT ACKNOWLEDGMENT

The New Horizons Centre at Monash University was funded by the Australian Federal Government through the Education Investment Fund.

PROJECT STAKEHOLDERS

PROJECT MANAGER

ARCHITECT

STRUCTURAL

BUILDING SERVICES

(MECH, ELECT & DRY FIRE)

HYDRAULIC & FIRE SERVICES

ESD/GREEN STAR

MANAGING CONTRACTOR

Page 5: Aleks Baltovski

19/08/2013

5

PROJECT STAKEHOLDERSSUBCONTRACTORS

MECHANICAL

ELECTRICAL

HYDRAULICS & CIVIL

DRY FIRE

WET FIRE

STRUCTURAL STEEL & FAÇADE

SHOP DRAWINGS

ELITE FIRE

MONASH UNIVERSITY NEW HORIZONS (MUNH)PROJECT DESCRIPTION

Monash University Clayton Campus

Collaborative research facility between Monash University and CSIRO. In particular it is the Faculty of Engineering, Faculty of Science and CSIRO.

Research on materials engineering including computational and physical modelling and simulation of manufactured products and technology for the bio-medical, aerospace and renewable energy industries.

Reinforces the importance of the Clayton Innovation Precinct as the most significant technology innovation hub in the southern hemisphere.

6-star Green Star Design rating under Education v1 rating tool achieved

6-star Green Star As-Built rating under Education v1 rating tool in progress

Managing Contractor building procurement without novation of consultant team

Page 6: Aleks Baltovski

19/08/2013

6

MONASH UNIVERSITY NEW HORIZONS (MUNH)

MONASH UNIVERSITY NEW HORIZONS (MUNH)PROJECT DESCRIPTION

Page 7: Aleks Baltovski

19/08/2013

7

MONASH UNIVERSITY NEW HORIZONS

MONASH UNIVERSITY NEW HORIZONS

Page 8: Aleks Baltovski

19/08/2013

8

MONASH UNIVERSITY NEW HORIZONS

MONASH UNIVERSITY NEW HORIZONS

Page 9: Aleks Baltovski

19/08/2013

9

MONASH UNIVERSITY NEW HORIZONS

MONASH UNIVERSITY NEW HORIZONS

Page 10: Aleks Baltovski

19/08/2013

10

MONASH UNIVESRITY‘CAVE’ CAPABILITIES

MONASH UNIVERSITY

Insert youtube video

Cave2 capability in collaboration with University of Illinois

Page 11: Aleks Baltovski

19/08/2013

11

BIM INITIATIVES IMPLEMENTED BYPROJECT STAKEHOLDERS

BIM INITIATIVES IMPLEMENTEDBY CLIENT & DESIGN TEAM

CLIENT

Not contractual requirement Encouraged by the Client

DESIGN TEAM

Design and documentation in Revit Well structured and detailed models Level of coordination (LOD200) Not all services were modelled Specifications and schedules

exported from Revit

Page 12: Aleks Baltovski

19/08/2013

12

USING ‘HOLLYWOOD’ BIM AT MUNHFLY-OVER MODEL

BIM INITIATIVES IMPLEMENTEDBY SUB-CONTRACTORS

SUB-CONTRACTORS

o Building Services and Structure trades took part in BIM process

o Combination of software packages used

o Consultants models utilised to move objects and coordinate services

o Mechanical Subcontractor (Allstaff) acted as lead trade

o Opportunity of the process established by Client and Design Team

Page 13: Aleks Baltovski

19/08/2013

13

BIM INITIATIVES IMPLEMENTEDBY PROBUILD

PROBUILD

o Shared role as BIM Manager (Navisworks)

o Established a BIM Implementation Plan to define:

Rules of engagement

Level of detail to be provided

Technology required

File format to be used

Segments to work on

Set targets and monitor progress

o Chair weekly coordination workshops

o Educated site staff how to use technology on site

USING BIM AT MUNHOUR BIM TOOL BOX

Page 14: Aleks Baltovski

19/08/2013

14

OUR UNDERSTANIDNING OF THEBIM PROJECT LIFE CYCLE

BIM COLLABORATION SPACE

Copyright: 20th Century Fox (Minority Report)Copyright:Warner Bros (Matrix)

Page 15: Aleks Baltovski

19/08/2013

15

BIM COLLABORATION SPACEMUNH PROJECT

USING BIM AT MUNHWEEKLY COORDINATION TIME LINE

Page 16: Aleks Baltovski

19/08/2013

16

USING BIM AT MUNHMODELLING PARAMETERS

USING BIM AT MUNHMODELLING PARAMETERS

Page 17: Aleks Baltovski

19/08/2013

17

USING BIM AT MUNH

USING BIM AT MUNHCLASH DETECTION

Page 18: Aleks Baltovski

19/08/2013

18

USING BIM AT MUNHCLASH DETECTION

USING BIM AT MUNHTRACKING PROGRESS

Page 19: Aleks Baltovski

19/08/2013

19

BIM INITIATIVES IMPLEMENTEDBY PROBUILD

Key uses for BIM process:

1. Visualisation of the building2. Clash detection3. Estimating4. Interrogation of documents5. RFI process and queries6. Design change management7. Setting out on site8. As-Built (untagged) model

AS-BUILT MODEL (UNTAGGED)PROVIDED TO CLIENT

Page 20: Aleks Baltovski

19/08/2013

20

THE BENEFITS OF BIM -OUR UNDERSTANDING

• BIM is a ‘Process’ not defined by a single word

• Much broader concept of BIM

• Exploring design and construction options

• Explore construction methods & sequencing options

THE BENEFITS OF BIM -OUR UNDERSTANDING

• Programming monitoring

• Improved understanding of deliverables:

Construction detailing

Fire rating

Acoustic rating

• Just a tool – should not rely on it for everything

Page 21: Aleks Baltovski

19/08/2013

21

USING BIM AT MUNHPLANT ROOM COORDINATION

USING BIM AT MUNHRFI PROCESS & QUERIES

Page 22: Aleks Baltovski

19/08/2013

22

USING BIM AT MUNHDOCUMENTATION & MODEL INTERROGATION

WALL TYPE CODESSEARCH – MODEL & SPECIFICATION

USING BIM AT MUNHComplex Geometry - Sectioning

Page 23: Aleks Baltovski

19/08/2013

23

USING BIM AT MUNHComplex Geometry – Atria Skylights

USING BIM AT MUNHComplex Geometry – Raking Walls in Atria

Page 24: Aleks Baltovski

19/08/2013

24

USING BIM AT MUNHComplex Geometry – scaffolding in atria

MONASH UNIVESITY NEW HORIZONSLESSONS LEARNT & FEEDBACK

Page 25: Aleks Baltovski

19/08/2013

25

MONASH UNIVESITY NEW HORIZONSLessons Learnt

MONASH UNIVESITY NEW HORIZONS

CONTRACTOR & SUBBIES

• Exchange of information – earlier is always better

• Steel and Façade Shop Detailer Employed by Probuild as a sub-contractor

Engaged and involved earlier

• Earlier input by Managing Contractor and sub-contractors

• Client to have an understanding of what BIM is and be involved earlier

• All elements to be modelled

• More detail in models is always better

• Consider Mechanical sub-contractor to model the electrical services for the projects

Lessons Learnt

Page 26: Aleks Baltovski

19/08/2013

26

MONASH UNIVERSITY NEW HORIZONSLessons Learnt

CONSULTANTS

> Doubling up of models:

- Architect built their own structure model

- Model by Structural Engineer not used

> Insufficient time given to sub-consultants to update models

> Façade and structural steel model issued to Architect to review for information. Proposal rejected in lieu of reviewing 4000+ shop drawings

> No need to model item to huge level of detail

- A box with size, name parameters is OK

- If lucky a tag to a PDF file of Tech Data sheet would be ‘like super awesome’

FEEDBACK FROM SUB-CONTRACTORS

‘For a research facility such as MUNH, without BIM we would have struggled’.

‘The BIM process is recommended for all complex projects such as research and residential’

‘Hypothetically…if the project was delivered under traditional 2D process there may have been for example 100 issues to resolve. With BIM it has reduced this number to 25’.

Summary of the number of RFIs:

- Mechanical = 239 total- Electrical = 107 total- Hydraulics = 104 total- Wet Fire = 15 total- Dry Fire = 41 total

Page 27: Aleks Baltovski

19/08/2013

27

OUR CURRENT CAPABILITIES

OUR CURRENT CAPABILITIES

Pre-Construction phase

Estimating

Business Developments

Design Development

Design Interrogations

Explore options

Buildability & Logistics reviews

Construction phase

BIM Management role

BIM Implementation Plan

Weekly coordination workshops

Educate site staff on how to use technology

Page 28: Aleks Baltovski

19/08/2013

28

FUTURE STRATEGIES

FUTURE STRATEGIES

Organisational strategy

Our definition of BIM

Client expectations

Level of detail required

Project selection

Systems integration (QSE, Estimating, Design Management, Administration)

Collaboration with external parties

- ACONEX

- BIM Events & Lobby Groups

- Consultants

- Clients

Page 29: Aleks Baltovski

19/08/2013

29

CLOSING COMMENTS

BENEFITS OF BIMDoes the use of BIM make a difference?

Suddenly, a heated exchange took place between the King and the Moat Contractor.(The Far Side, Gary Larson)

Page 30: Aleks Baltovski

19/08/2013

30

BENEFITS OF BIMDoes the use of BIM make a difference?

CLOSING COMMENTS

CLOSING COMMENTS

Observations from BIM MEP AUS & BIM Summit 2012

- Progress overseas (Singapore, UK)

- Productivity ranking for Australia (ACIF)

- Target for BIM adoption (BEIIT)

Australia in the eyes of the World

Considered as a leader

Future opportunities

Current challenges in the industry – status

ROI – the need for measurability (McGraw Hill input)

Promote cooperation

Support industry initiatives such as BIM MEP AUS & BIM SUMMIT

BIM as part of the ESD movement (GBCA radar)

Page 31: Aleks Baltovski

19/08/2013

31

CLOSING COMMENTS

KEY ASPECTS TO REMEMBER:

Sharing Knowledge and Experiences – to maintain momentum of the BIM movement

Keep an open mind and be flexible when embarking on the BIM journey

Be bold and be brave and always look at the glass as half full

Embrace the spirit of Collaboration –use MUNH as an example

Thank you for your time