Introduction

Page 3: Alcatel lucent bts offline & commissioning

The BTS commissioning & SW files are stored on the station unit module

(SUMA)

The Station unit module is the core of the BTS ,it is responsible for

• The O&M Functions such as Alarms reporting ,BTS Configuration,

internal Power Supply control & clock generation and distribution

• Transmission functions by connecting the BTS to the BSC through the

ABIS cable.

The ABIS can carry up to 32 time slots

• 0 to 30 are assigned to the TRES for normal traffic(voice and Data

services)

• 31 : is assigned to the OMU in the SUMA card for signaling (Control

information) between BSC & BTS such as Alarm reporting ,BTS

Master file Download, configuration files etc..

Page 4: Alcatel lucent bts offline & commissioning

LED Color Status Description

OML Yellow On BTS is supervised and connected to the BSC

Blinking BTS & BSC link is being established

Off Link disconnected.

ABIS Yellow On Abis 1 is connected and can serve TCH/Signaling

Blinking There are Alarms on the ABIS

Off Not configured or not used.

O&M Yellow On SUMA master file & configuration are present in the EPROM

Blinking In a transient state, SUMA is loading the BTS MSF & Configuration file from the BSC

Off Not used.

FAULT

RED On Fatal alarm on BTS Module (ANC,TRE etc ..)

Blinking Non-fatal alarm. Such as Faulty Fan unit

Off No alarm.

SUMA card led status indication

Page 5: Alcatel lucent bts offline & commissioning

Offline

Page 6: Alcatel lucent bts offline & commissioning

• Switch the BTS off by pushing down its DC C/BS

Page 7: Alcatel lucent bts offline & commissioning

• Unscrew the ABIS Cable

Page 8: Alcatel lucent bts offline & commissioning

• Open BTS SW and Type

User Name : commte

Password : bts2site

Page 9: Alcatel lucent bts offline & commissioning

• Go to Configuration Click On BTS Software Download

Page 10: Alcatel lucent bts offline & commissioning

• Press the folder icon to start choosing the BTS Files

Page 11: Alcatel lucent bts offline & commissioning

• Select Master File from the BTS SW folder

Page 12: Alcatel lucent bts offline & commissioning

• Select 0CPF File from the BTS SW folder

Page 13: Alcatel lucent bts offline & commissioning

• Wait for the BTS to download all the files ,During the SW

Download the Suma LED Status will be :

OML ,ABIS & O&M Flashing

last file to be downloaded is the OCPF 002 file after that the O&M

will be solid

Page 14: Alcatel lucent bts offline & commissioning

Commissioning

Page 15: Alcatel lucent bts offline & commissioning

• From Configuration choose BTS Commissioning

Page 16: Alcatel lucent bts offline & commissioning

• Click on Start Commissioning

Page 17: Alcatel lucent bts offline & commissioning

• Notice that the status of the commissioning changed from not

running to running

Page 18: Alcatel lucent bts offline & commissioning

• Edit Q1 address by clicking its start button

Page 19: Alcatel lucent bts offline & commissioning

• Edit Remote Inventory by clicking its start button and press

YES : if the update is already done in the Remote Inventory

panels

NO : if the update is not done in the Remote Inventory panels

Page 20: Alcatel lucent bts offline & commissioning

• Edit Sector Mapping by clicking its start button

Assign sector-ID to each combiner and then press ok

Page 21: Alcatel lucent bts offline & commissioning

• Edit Twin-Settings by clicking its start button

Choose the mode of each Twin-TRE , usually in our network

we leave at the default which is Dual TRE

Page 22: Alcatel lucent bts offline & commissioning

• Hardware check by clicking its start button

the Suma card will start to check the HW available inside

the BTS through the RI-Cable

Page 23: Alcatel lucent bts offline & commissioning

• INIT _ALL_SECT by clicking its start button

the SUMA card will power on all the combiners and TRES to

check their operation

Page 24: Alcatel lucent bts offline & commissioning

Choose End commissioning ,Stop commissioning window will appear

choose ok after moving all the modules in the selected module window

Wait for the BTS to restart itself SW and then connect the Abis cable.

Page 25: Alcatel lucent bts offline & commissioning

• Finally restart the BTS HW

the SUMA led status should be as following :

Abis & OML are solid

O&M Flashing as the BTS loading its data and RSLs from the BSC

Page 26: Alcatel lucent bts offline & commissioning

• The loading process will take 15 to 20 Minutes ,after that the

O&M Led will be solid and the SUMA will initialize the

BTS sectors (Combiners & TRES)

Page 27: Alcatel lucent bts offline & commissioning

• The BTS Terminal program will start to load the BTS Data

Take snapshots and check with OMC

Page 28: Alcatel lucent bts offline & commissioning

Thank You