Alaskan Way Viaduct Replacement Program Update Joint Transportation Committee May 14, 2014 Cam Gilmour Deputy Secretary Lynn Peterson Secretary of Transportation Todd Trepanier AWV Program Administrator

Transcript of Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... ·...

Page 1: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

Alaskan Way Viaduct

Replacement Program Update

Joint Transportation Committee

May 14, 2014

Cam Gilmour Deputy Secretary

Lynn Peterson Secretary of Transportation

Todd Trepanier AWV Program Administrator

Page 2: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

• SR 99 Tunnel Project update

– STP’s schedule and repair

plan

– Change order process

– Disadvantaged Business

Enterprise

• Program updates:

– Construction at north and

south end of tunnel

Overview

2

Page 3: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

Seattle Tunnel Partners’ Repair Timeline

3

• Late May 2014: Begin building the access pit’s underground walls.

• June 16, 2014: STP / Hitachi Zosen will submit the seal system repair

and bearing replacement plan to WSDOT.

• Late July through September 2014: Excavate the pit.

• October 2014: Remove the machine’s cutterhead and begin repairing

damage to the seal system and main bearing.

• November 2014: STP / Hitachi Zosen will submit a full report of

machine repairs to WSDOT.

• February 2015: Test machine to ensure it is ready to tunnel beneath

downtown.

• Late March 2015: Resume tunneling.

Page 4: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Today, Above Ground

4

Conceptual

Page 5: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan - Today, Below Ground

5

Conceptual

Page 6: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Injecting Grout

Conceptual

6

Page 7: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Relocating Utilities

Conceptual

7

Page 8: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Relocating Utilities

Conceptual

8

Page 9: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Injecting Grout

Conceptual

9

Page 10: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Installing Secant Piles

Conceptual

10

Page 11: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Completing Access Pit

11

Conceptual

Page 12: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Removing Ground Water

12

Conceptual

Page 13: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Tunneling into the Access Pit

13

Conceptual

Page 14: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Installing the Crane

14

Conceptual

Page 15: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

STP’s Repair Plan – Repairing the Machine

15

Conceptual

Page 16: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

Change Order Overview

16

• Change orders are the formal mechanism WSDOT uses to make changes

to its construction contracts.

• Requests can be submitted by a contractor to WSDOT or initiated by

WSDOT.

• Contractor-submitted change order process:

– Contractor provides change notice.

– Contractor submits change order request with more details and cost

estimate.

– WSDOT reviews to determine if contractor is entitled to a change

order per the contract.

– If WSDOT determines the contractor is entitled to a change order:

• Pending change order: ongoing discussions about cost, time and

scope.

• Executed change order: after agreement upon the changes is

reached. Once executed, a change order revises the contract to

include the new terms.

Page 17: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

Disadvantaged Business Enterprise

17

Finalized Conciliation Agreement with FHWA

• Agreement contains steps both agencies agreed are necessary to improve DBE

participation on AWV Replacement Program.

• Outlines resources that both WSDOT and STP must dedicate to program.

• Stipulates oversight role of WSDOT in enforcing STP activities related to DBE

participation.

• Includes reporting mechanisms that will remain in place through life of project.

Executed Change Order with STP

• Tunnel contractor now contractually required to award $96 million in paid work to

certified DBE firms.

• With executed change order, WSDOT withdrew earlier finding against the firm for

breach of contract.

• Should STP fail to comply with the terms or conditions of the change order, WSDOT

may either reinstate the finding or implement other appropriate contract actions.

AWV DBE Program Administrator

• WSDOT hired Bobby Forch, formerly of SDOT, to oversee program.

Page 18: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

South Portal Operations Building Construction

18

Page 19: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

North Portal Receiving Pit Construction

19

Page 20: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

North Access Construction

20

Page 21: Alaskan Way Viaduct Replacement Program Updateleg.wa.gov/JTC/Meetings/Documents/Agendas/2014... · Seattle Tunnel Partners’ Repair Timeline 3 • Late May 2014: Begin building the

For more information on the

Alaskan Way Viaduct Replacement

Program,

please contact:

Todd Trepanier

Program Administrator

206-805-2843 or

[email protected]

www.alaskanwayviaduct.org