Alabama 07 2016
-
Upload
construction-equipment-guide -
Category
Documents
-
view
214 -
download
1
description
Transcript of Alabama 07 2016
![Page 1: Alabama 07 2016](https://reader031.fdocuments.net/reader031/viewer/2022020522/579076cb1a28ab6874bad095/html5/thumbnails/1.jpg)
By Brenda RuggieroCEG CORRESPONDENT
A portion of Interstate 20/59 in Alabama is beingreconstructed to accommodate an increased flow oftraffic, which currently is the highest rate of trafficflow in the entire state. More than 160,000 vehiclestravel this area each day. This number is projectedto increase to more than 225,000 daily motorists by2035. Under the current conditions, the AlabamaDepartment of Transportation (ALDOT) reportedthat the existing bridge design is unable to safelyaccommodate traffic flow. The bridges were origi-nally built with a 50-year lifespan, and designed tocarry up to 80,000 vehicles per day.John Cooper, director of ALDOT, announced the
start of construction on the project through down-town Birmingham’s Central Business District onJuly 29, 2015.ALDOT’s construction plan has three phases, at
a total cost of more than $400 million. Throughoutthe early phases, access to and from downtownremained uninterrupted. ALDOT completed allwork on the new ramps leading into and out of thecity before closing off any existing access points.The contract for Phase One was awarded to
Brasfield & Gorrie for $7.4 million. It involveswidening roadways and elevating certain bridges inpreparation for the larger project.ALDOT began working with local elected offi-
cials, the Birmingham community, business leadersand others in 2011 to develop a comprehensive planto improve the route interchanges and replace thebridges on I-59/20. The approved plan will report-edly simplify access into and out of downtown, and ease theflow of commerce and traffic through Birmingham’s CentralBusiness District. Community input was sought throughoutthe planning and design process.The contract for Phase One was awarded to Brasfield &
Gorrie LLC for $7.4 million on July 22, 2015. It involveswidening roadways and elevating certain bridges in prepara-tion for the larger project. Work began on Aug. 26, 2015 andthe estimated completion date is May 12.The project covers .4 mi. (.6 km), and includes bridge
widening and approaches (grade, drain, base, pave, bridgeraising and highway lighting).According to ALDOT, the most challenging part of this
portion of the project has been managing traffic.To date, this phase of the project has included 5,000 cu.
yds. (3,822 cu m) of unspecified excavation, 275 cu. yds.(210 cu m) of Cl. B concrete, and 162 (123 cu m) of Cl. DSconcrete. Russo Corporation was subcontracted for drill shafts. At the start of this project, Brasfield Gorrie submitted a
value engineering proposal to change from steel piling todrill shafts, which was approved at a cost savings to this proj-ect.Phase Two involves redesigning and constructing the new
interchange ramps at I-65. There will be new ramps to 17thStreet and 6th Avenue North, as well as new ramps from11th Avenue North to the Interstate System. The project alsoinvolves construction between Arkadelphia Road and I-65along I-59/20. ALDOT issued a notice to proceed for this phase to
Granite Construction of Watsonville, Calif., on March 15 fora contract of more than $208 million.Throughout construction of Phase Two, access to and
from downtown will reportedly remain open. Granite willcomplete all work on the new I-65 ramps leading into andout of the city before access points are closed for PhaseThree.“Over the past 40 years, as traffic has skyrocketed
through the city of Birmingham, the junction of I-65 with I-59/20 has become labeled as Malfunction Junction,” saidDeJarvis Leonard, east central region engineer. “Phase Twois designed to address this problem. Regardless of whathappens with the long-term prospects of the central busi-ness district bridges, this work is necessary and will provide
Portion of Interstate 20/59 to Accommodate 160,000 Vehicles
ALABAMA STATE EDITION A Supplement to:
Your Alabama Connection • Rich Olivier, Atlanta, GA • 1-800-409-1479
“The Nation’s Best Read Construction Newspaper… Founded in 1957.”
A portion of Interstate 20/59 in Alabama is being reconstructed to accommodate an increased flow of traffic, which currently is thehighest rate of traffic flow in the entire state.
March 302016
Vol. XXIX • No. 7Mobile
Dothan
Auburn
Anniston
Gadsden
HuntsvilleFlorence
Decatur
BirminghamBessemer
Tuscaloosa
SelmaMontgomery
Phenix City
65
65
65
65
10
85
20
20
59
59
565
220
72
31
231
43
78
5
72
431
280
82
231
31
43
80
82
231
84
84
52
431
331
45
98
84
82
see ALDOT page 6
![Page 2: Alabama 07 2016](https://reader031.fdocuments.net/reader031/viewer/2022020522/579076cb1a28ab6874bad095/html5/thumbnails/2.jpg)
Page 2 • March 30, 2016 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide
DON’T CRAWL LIKE A CATTO START THE WORKDAYSTEP INTO THE INDUSTRY’S SAFEST COMPACT TRACK LOADER
SCHEDULE A DEMO TODAY:
$500
*Lease rates subject to JCB Finance approval. Based on 1,000 hours per year. Cash option price at $56,000 + tax. Offer expires May 31, 2016. Availability of eligible equipment may change without prior notice. Additional terms may apply. Contact JCB of Alabama for terms and agreement.
$675
O LIKE OUR 190T L LOADED WITH THE FOLLAND GET THE PROPER GEAR FROM JCB OF AL
ALK LIK WWALK LIKE A MAN WITH JCB
urpose bucket• General P• $675 per month plus applicable tax*• 60 month stated purchase option lease*
OWOADED WITH THE FOLL LOWING:AND GET THE PROPER GEAR FROM JCB OF AL
ALK LIKE A MAN WITH JCB
urpose bucket• $675 per month plus applicable tax*• 60 month stated purchase option lease*
OWING:ABAMAAND GET THE PROPER GEAR FROM JCB OF AL
ALK LIKE A MAN WITH JCB
OTHER SKID STEER MODELS A
190T
V STEER MODELS A AV
ABLEAILVVAIL
Contact JCB of Alabama for term apply. Offer expires May 31, 2016. Availability of eligible equipment may change without prior notice. Additional terms may
inance approval. Based on 1,000 hours per yearease rates subject to JCB F*L
• Plus a $500 Bass P• 7 ton Econoline trailer• PM kit• Chains / Binders / Straps• 48” pallet forks
. Contact JCB of Alabama for terms and agreement.Offer expires May 31, 2016. Availability of eligible equipment may change without prior notice. Additional terms may
. Cash option price at $56,000 pproval. Based on 1,000 hours per year r. Cash option price at $56,000 + tax.
ro Gift Card• Plus a $500 Bass P• 7 ton Econoline trailer
• Chains / Binders / Straps
.jcwwww.jcbofalabama.com
Offer expires May 31, 2016. Availability of eligible equipment may change without prior notice. Additional terms may. Cash option price at $56,000 + tax.
.jcbofalabama.com
SCHEDULE A DEMO TODAOTHER SKID STEER MODELS A
(888) 791-3173:YY: DEMO TODA AYV STEER MODELS A AV
4051
(888) 791-3173ABLEAILVVAIL
![Page 3: Alabama 07 2016](https://reader031.fdocuments.net/reader031/viewer/2022020522/579076cb1a28ab6874bad095/html5/thumbnails/3.jpg)
Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • March 30, 2016 • Page 3
1.800.239.2694www.cowin.com
Birmingham, AL205.841.6666
Madison, AL256.350.0006
Mobile, AL251.633.4020
Montgomery, AL334.262.6642
Oxford, AL256.832.5053
Pensacola, FL850.479.3004
Smart Works. ®
Since 1938 Cowin Equipment has been a family-owned business who has
made it their mission to serve and support Alabama’s road contractors. With
the new Intelligent Compaction and Density Direct Campaign, the industry’s
first-ever real-time density mapping technology, Cowin Equipment and Volvo
Construction Equipment are revolutionizing paving by eliminating guesswork,
improving quality and increasing productivity. Call your local Cowin Equipment
location for more information.
Density DirectRevolutionizing the Paving Industry
![Page 4: Alabama 07 2016](https://reader031.fdocuments.net/reader031/viewer/2022020522/579076cb1a28ab6874bad095/html5/thumbnails/4.jpg)
Page 4 • March 30, 2016 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • March 30, 2016 • Page 5
YOUR CHOICE OF A FREE PELICAN COOLER ORTWO PELICAN GUN CASES FOR EVERY PACKAGE PURCHASED
![Page 5: Alabama 07 2016](https://reader031.fdocuments.net/reader031/viewer/2022020522/579076cb1a28ab6874bad095/html5/thumbnails/5.jpg)
Page 4 • March 30, 2016 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • March 30, 2016 • Page 5
YOUR CHOICE OF A FREE PELICAN COOLER ORTWO PELICAN GUN CASES FOR EVERY PACKAGE PURCHASED
![Page 6: Alabama 07 2016](https://reader031.fdocuments.net/reader031/viewer/2022020522/579076cb1a28ab6874bad095/html5/thumbnails/6.jpg)
Page 6 • March 30, 2016 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide
Widening Three Bridges on Phase One Nears Completionsignificant improvements formotorists traveling along thisInterstate — the busiest stretch ofroadway in Alabama.”Work on Phase One — the
widening of three bridges and ele-vating two others along I-65 — isnearing completion. This phase
was necessary in order to avoidmajor traffic issues during con-struction of the later phases, and aprecursor for the work that will becompleted in Phase Two.Phase I was expected to last 130
working days from the time con-struction began. Phase II will lastapproximately 30 months and
Phase III, which will go out for bidby mid-2016, is projected to takeapproximately 12 to 14 monthsfrom start of construction. Work onPhase III will begin only after thenew ramps leading into and out ofdowntown have been completed aspart of Phase II.ALDOT will use a segmental
bridge design for the new bridgesdowntown. This design will allowfor faster construction time, andcut down on the noise and vibra-tions associated with the trafficflow once completed.This project is being paid for
through a combination of fundsfrom ALDOT, the Federal
Highway Administration, and theBirmingham MetropolitanPlanning Organization.
(This story also can be found
on Construction Equipment
Guide’s Web site at www.con-
structionequipmentguide.com.)
CEG
ALDOT from page 1
The Alabama State Department of Transportationreceived bids for transportation-related improve-ment projects.Following is a list of some of the projects let.
County: MadisonContract ID: 20150925005Project:Grade, drain, base, pave, bridges, signingand lighting.Location: On SR-53 (U.S. 231/Memorial Parkway)from just north of Whitesburg Drive to just south ofGolf Road.Contractors and Bid Amounts:
• Reed Contracting Services Inc., and Miller &Miller, Inc. — $53,882,864
• Dement Construction Company LLC —$72,379,062.
• Eutaw Construction Company Inc. — $72,567,120.• Wiregrass Construction Company Inc. — $73,895,117
County: JeffersonContract ID: 20150925007Project: Improvements (grade, drain, base, resurface, sig-nal, culvert).Location: On CR-153 from 500 feet south of the I-59overpass to north of CR-2133 in Trussville.Contractors and Bid Amounts:
• Carcel & G. Construction LLC — $1,585,124• Chilton Contractors Inc. — $1,725,065• Veterans Landscaping Company Inc. — $2,268,528• Russo Corporation — $2,397,658
County: MobileContract ID: 20150925010Project: Bridge replacement and approaches.Location: On CR-23 (Padgett Switch Road) over CarlsCreek in Bayou La Batre.Contractors and Bid Amounts:
• McInnis Construction, LLC — $3,215,364• L & A Contracting Company — $3,305,092• Newell & Bush Inc. — $3,388,554• John G. Walton Construction Company Inc. —
$3,429,296• Gulf Equipment Corporation — $3,536,29• T.L. Wallace Construction Inc. — $3,553,135• Scott Bridge Company Inc. — $4,191,520
County: St. ClairContract ID: 20150925015Project: Bridge rehabilitation.Location: On CR-80 (Rivercrest Drive) over LoganMartin Lake northeast of Vincent.Contractors and Bid Amounts:
• Winston Contracting LLC — $899,878• Chase Plumbing & Mechanical Inc. — $1,356,200
County: JeffersonContract ID: 20150925037Project:Multi-use trail.Location: Trussville Greenway along the Cahaba River..Contractors and Bid Amounts:
• Walker Patton Company Inc. — $1,889,303• Veterans Landscaping Company Inc. — $2,100,821• Ikaros LLC — $2,200,000• Russo Corporation — $2,319,848
County: AutaugaContract ID: 20150925045Project: Planing, resurfacing and traffic stripe.Location: On I-65 south of the SR-3 (U.S. 31) interchange(MP186.00) to one mi. south of the CR-61 overpass (MP190.00).Contractors and Bid Amounts:
• Wiregrass Construction Company Inc. — $1,433,403• Midsouth Paving Inc. — $1,474,838
County: JeffersonContract ID: 20150925050Project: Pavement rehabilitation.Location: On SR-378 (Finley Boulevard) from thejunction of SR-5 (U.S. 78) to the intersection ofSR-3 (U.S. 31) in Birmingham.Contractors and Bid Amounts:
• Midsouth Paving Inc. — $2,572,038• Dunn Construction Company Inc. —
$3,151,370
County: EscambiaContract ID: 20150925033Project: Bridge replacement (grade, drain, base,pave and bridges).Location: On SR-41 (Conecuh River and Relief)in Riverview.Contractors and Bid Amounts:
• Tanner Inc. — $13,634,079• L & A Contracting Company — 13,900,364• Murphree Bridge Corporation and McInnis
Construction LLC JV — $13,967,513• Scott Bridge Company Inc. — $15,597,630• Anderson Columbia Company Inc. — $16,489,458
County: CullmanContract ID: 20150828050Project: Safety widening, planing, resurfacing and trafficstripe.Location: On SR-3 (U.S. 31) from the Blount County linein Garden City to north of the junction of Mills Street inHanceville.Contractors and Bid Amounts:
• Good Hope Contracting Company Inc. — $3,969,537• Wiregrass Construction Company Inc. — $4,524,651
County: EtowahContract ID: 20150828059Project: Bridge replacement.Location: On South 11th Street over Black Creek inGadsden.Contractors and Bid Amounts:
• Wright Brothers Construction Company Inc. —$1,977,543
• McInnis Construction LLC — $2,179,836• R. R. Dawson Bridge Company LLC — $2,368,870
Montgomery • Jefferson • Talladega • Calhoun • Russell • Walker • Lawrence • Dekalb • Morgan • St. Clair • Tuscaloosa • Morgan • Shelby• Bibb •Hale • Fayette • Marion • Winston • Cullman • Shelby • Chilton • Chambers • Covington • Baldwin • Clarke • Monroe • St. Clair• Chilton • Escambia• Montgomery • Jefferson • Russell • Fayette • Conecuh • Coffee • Geneva • Montgomery • Jefferson • Talladega •Bibb • Coffee • Calhoun • Russell • • Walker• Lawrence• Dekalb • Morgan • St. Clair • Tuscaloosa • Bibb• Hale • Fayette • Monroe •
Alabama…
‘The Yellowhammer State’ Highway Project Lettings
![Page 7: Alabama 07 2016](https://reader031.fdocuments.net/reader031/viewer/2022020522/579076cb1a28ab6874bad095/html5/thumbnails/7.jpg)
Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • March 30, 2016 • Page 7
![Page 8: Alabama 07 2016](https://reader031.fdocuments.net/reader031/viewer/2022020522/579076cb1a28ab6874bad095/html5/thumbnails/8.jpg)
Page 8 • March 30, 2016 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide