AJP Levens Building Demolition Statement
-
Upload
chris-findlay -
Category
Documents
-
view
229 -
download
0
Transcript of AJP Levens Building Demolition Statement
-
8/19/2019 AJP Levens Building Demolition Statement
1/10
EDGE HILL UNIVERSITY
LEVENS BUILDING
SINGLE STOREY SECTION
DEMOLITION STATEMENT
AJP Ref: 215-267
BY: The Alan Johnston Partnership LLP4th Floor1 Dale Street
Liverpool L2 2ET
Record of Approval
Originator Approved Date
M. B. Hysel M. B. Hysel 11 Dec 2015
-
8/19/2019 AJP Levens Building Demolition Statement
2/10
INTRODUCTION
The single storey section of the building knows as the Levens Building was the original building
constructed in 1994. The three storey section was added in 2002.
The single storey section is to be demolished to allow the construction of a new three storeyteaching block. The works to include the removal of the ground floor slab and foundations.
CONSTRUCTION
The single storey section is of traditional build with loadbearing masonry supporting a timber
trussed rafter pitched roof. The concrete ground floor slab is 175mm thick and mesh reinforced. It
would appear to be ground bearing. Although not established it is considered that the building has
traditional foundations bearing onto a medium clay at approximately 1.5 / 2.0 metres below existing
ground level.
The overall stability of the building is provided by the pattern of masonry crosswalls.
DEMOLITION
The demolition of this single storey building would not be considered to be particularly unusual.
There is no evidence of unusual construction procedures or components.
-
8/19/2019 AJP Levens Building Demolition Statement
3/10
For and behalf o f The Alan Johnston Partnership LLP
MARTIN B. HYSEL
Consultant
-
8/19/2019 AJP Levens Building Demolition Statement
4/10
APPENDIX A
PHOTOGRAPHS
-
8/19/2019 AJP Levens Building Demolition Statement
5/10
1
-
8/19/2019 AJP Levens Building Demolition Statement
6/10
-
8/19/2019 AJP Levens Building Demolition Statement
7/10
APPENDIX B
DRAWINGS
IT ISTHECONTRACTORS RESPONSIBILITYTO REPORT ANY
INCONSISTENCIESWITH THISDRAWING ANDTO REQUEST
CLARIFICATIONBEFORE PROCEEDING. DO NOTSCALEFROM THIS
IT ISTHECONTRACTORS RESPONSIBILITYTO REPORT ANY
INCONSISTENCIESWITH THISDRAWING ANDTO REQUEST
CLARIFICATIONBEFORE PROCEEDING. DO NOTSCALEFROM THIS
-
8/19/2019 AJP Levens Building Demolition Statement
8/10
CLARIFICATIONBEFORE PROCEEDING. DO NOT SCALEFROM THIS
DRAWING. ALL DIMENSIONSTO BECHECKEDONSITEPRIORTO
CONSTRUCTIONOR MANUFACTURE.
EDGE HILL UNIVERSITY
ST HELENS RD
ORMSKIRK
L39 4QP
CLARIFICATIONBEFORE PROCEEDING. DO NOT SCALEFROM THIS
DRAWING. ALL DIMENSIONSTO BECHECKEDONSITEPRIORTO
CONSTRUCTIONOR MANUFACTURE.
EDGE HILL UNIVERSITY
ST HELENS RD
ORMSKIRK
L39 4QP
FM
MATEC / LEVENS GROUND FLOOR
2100
01/10/2015
-
8/19/2019 AJP Levens Building Demolition Statement
9/10
e-mail [email protected]
tel. 0161 873 8770fax. 0161 873 8771
tel. 0141 572 2040fax. 0141 572 2041e-mail [email protected]
e-mail [email protected]
tel: 01704 531252fax: 01704 532833isdn: 01704 538544
Dwg. No.
Glasgow
Title
Scale Contract
Southport
Manchester
Rev
This drawing is copyright. It is sent to you in confidence. It must not becopied, used or disclosed to third parties without the express permission of
CHECKED
It is the Contractor's responsibility to report any inconsistencies on thisdrawing, or between drawings, to the Architect and to request clarification
NJSR. It remains our property and must be returned on request.
and instruction before proceeding.
REVISION DRAWN DATE
REV A AWJ 24/09/01
EXTERNAL WINDOWS TO STAIRWELL
AMENDED
REV B
EXTERNAL WINDOWS TO STAIRWELL RELOCATED
AWJ 11/10/01
CHANGES TO NOTES
REV C AWJ 17/10/01
REV D
LINTEL ABOVE FRONT DOOR AMENDED
17/10/01 AWJ
RWP RELOCATED
REV E AWJ 31/10/01
REV F
FRONT DOOR AMENDED TO PLANNING DRAWING
AWJ 05/11/01
19/11/01 AWJ
WINDOWS RELOCATED FOR EXPANSION JOINT
REV G
REV H
ADDITION OF LIFT SHAFT
AWJ 05/12/01
15/01/02 AWJ
PARAPET WALL AMENDED
REV J
REV K
SECONDARY FIRE ESCAPE ADDED
AWJ 04/02/02
13/06/02 AWJ
AS BUILT DRAWING
REV M
-
8/19/2019 AJP Levens Building Demolition Statement
10/10
e-mail [email protected]
tel. 0161 873 8770fax. 0161 873 8771
tel. 0141 572 2040fax. 0141 572 2041e-mail [email protected]
e-mail [email protected]
tel: 01704 531252fax: 01704 532833isdn: 01704 538544
Dwg. No.
Glasgow
Title
Scale Contract
Southport
Manchester
Rev
This drawing is copyright. It is sent to you in confidence. It must not becopied, used or disclosed to third parties without the express permission of
CHECKED
It is the Contractor's responsibility to report any inconsistencies on thisdrawing, or between drawings, to the Architect and to request clarification
NJSR. It remains our property and must be returned on request.
and instruction before proceeding.
REVISION DRAWN DATE
REV A AWJ 11/10/01
ADDITIONAL WINDOWS ADDED
WINDOWS OMITTED
REV B AWJ 17/10/01
AWJREV C
RWP RELOCATED
02/11/01
15/01/02
PARAPET WALL AMENDED
REV D AWJ
AWJREV E
SECONDARY FIRE ESCAPE ADDED
04/02/02
CHANGES MADE FOLLOWING DISCUSSION OF FIRE STRATEGY
15/02/02REV F AWJ
AWJREV G 13/06/02
AS BUILT DRAWING