Airport DART Link The Council’s View Sean McGrath Senior Executive Engineer Fingal County Council

description

Airport DART Link The Council’s View. Sean McGrath Senior Executive Engineer Fingal County Council. Introduction. What is the Airport DART Link? 7km link from Clongriffin to Airport Trains to City Centre and Bray/Greystones Cost €300M or €200M or €150M Generate 9 MPPA in 2030. - PowerPoint PPT Presentation

Transcript of Airport DART Link The Council’s View

Page 1: Airport DART Link The Council’s View

Airport DART LinkThe Council’s View

• Sean McGrath• Senior Executive Engineer• Fingal County Council

Page 2: Airport DART Link The Council’s View

Introduction

• What is the Airport DART Link?• 7km link from Clongriffin to Airport• Trains to City Centre and

Bray/Greystones• Cost €300M or €200M or €150M• Generate 9 MPPA in 2030

Page 3: Airport DART Link The Council’s View

Indicative Route

Page 4: Airport DART Link The Council’s View

History

• 1994 - Dublin Transportation Initiative• Not included – open for future

evaluation• 1997 - A Platform for Change• Not included - low passenger numbers • 2011 – 2030 Vision• Not included – rejected at initial stage

Page 5: Airport DART Link The Council’s View

Reasons for Rejection

• Very low flows• No development potential (green

belt,airport)• No additional capacity in city centre

– Displaces Howth / Malahide or Maynooth services

• Does not serve Swords, MetroPark, Ballymun, Drumcondra, Parnell Square, O’Connell Street, St Stephen’s Green

Page 6: Airport DART Link The Council’s View

Metro North• Integrated with land use planning (joined up thinking)• 27,000 jobs or 16,000 jobs and 11,000 residential

units• Already approved• Serves: Airport, Swords, MetroPark, Ballymun, DCU,

Drumcondra, Mater Hospital, Parnell Square, O’Connell Street, Trinity College, St Stephen’s Green (14 stops)

• Serves airport employee catchment• Straight from city centre• Critically - new capacity in city centre

Page 7: Airport DART Link The Council’s View

NTA Passenger Numbers

• NTA model peak hour two-way flows:• DART:• 1,400 without Metro North• 500 with Metro North• Metro North:• 22,000• Metro North needs to be built anyway, so

DART is needless and wasteful duplication.

Page 8: Airport DART Link The Council’s View

Questions

• How are IE’s flows so much higher than NTA’s?

• There are currently 31 DART stations. How does adding one more station lead to a “50% increase in passenger numbers”?

• Are there any other suburban rail lines without any stations for a length of 7Km?

• Are there any airports within 10Km of their city centre?

Page 9: Airport DART Link The Council’s View

Conclusions

• Not integrated with land use

• Serves only one new station

• Does not serve current employment catchment

• NTA flow forecast are extremely low