Aid Effectiveness - Moving up to the higher...

42
Partnership Group on Aid Effectiveness (PGAE) Aid Effectiveness - Moving up to the higher level Consultative Group Meeting Hanoi, December 6 - 7, 2007 i

Transcript of Aid Effectiveness - Moving up to the higher...

Page 1: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group on Aid Effectiveness (PGAE)

           

Aid Effectiveness - Moving up to the higher level

                  

Consultative Group Meeting Hanoi, December 6 - 7, 2007

i

Page 2: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Preface

  

This report presents the combined efforts of the Government and donors over the past year to put the principles of the Hanoi Core Statement (HCS) into action.  Substantial progress has  been made  on many  fronts:  from  the  legal  framework  to  government  systems;  from Ministry of Agriculture and Rural Development action plans to the one United Nations; from Six Banks  portfolio  review  to  the European Union Code  of Conduct;  and  the Like‐Minded Donors  Groups’  continuing  efforts,  all  Partnership  Group  on  Aid  Effectiveness  (PGAE) members continued  to support  the Government make ODA more effective  in Vietnam. This year  Civil  Society  Organizations were warmly welcomed  into  the  PGAE with  the  aim  of ensuring that the Government and donors were fully accountable to beneficiaries for the use of aid. Additionally  the  first  independent  exercise  under  the HCS Monitoring  and Evaluation Framework  was  undertaken  to  monitor  Government  and  donor  progress  in  HCS implementation.  

The conclusions from the final draft of the Independent Monitoring Report were clear. Government  commitment  and  leadership  has  been  strong  and  the  donors’  support  well aligned to putting the HCS into action. Substantial progress has been made but challenges for achieving the ambitious HCS targets still remain. Additional efforts with clear goals now need to be developed  for addressing  the  identified gaps  in Government Systems and accelerating their use by donors.  

The title of the PGAE Report this year is “Aid Effectiveness – Moving up to the higher level”. Taking this step will require the continued, strong leadership of the Government, and the full support of the donor community  in Vietnam. With this commitment the HCS can be successfully  implemented  by  the  year  2010.  Achieving  these  targets  will  be  an  important contribution to ensuring the sustainable development of Vietnam beyond 2010 – as it steps‐up to middle income country status.   

 

  

Ho Quang Minh Director General, FERD 

Ministry of Planning and Investment  

 

  

Laurent Msellati Manager, Portfolio and Operations, 

World Bank Office in Vietnam 

Co‐Chairs of the Partnership Group on Aid Effectiveness

Page 3: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Table of Contents

Chapter 1 Executive Summary........................................................................................................... 1

Chapter 2 Joint Work to Strengthen Government’s System .......................................................... 4 2.1 Development of the ODA Policy and Legal Framework ......................................... 4 2.2      Strengthening ODA Management Capacity ............................................................. 5 2.3      Five/Six Banks – JPPR V ............................................................................................... 5 2.4 The European Union ..................................................................................................... 7 2.5 The LMDG ...................................................................................................................... 9 2.6 United Nations ............................................................................................................. 11 2.7 Civil Society Organisations ........................................................................................ 13

Chapter 3 Implementation of the Hanoi Core Statement............................................................. 16 3.1  Contribution made by Thematic Groups..................................................................... 16 3.1.1 Procurement Thematic Group ................................................................................... 16 3.1.2  Public Finance Management Thematic Group......................................................... 17 3.1.3  EIA Thematic Group.................................................................................................... 18 3.1.4 SIA Thematic Group.................................................................................................... 19 3.2  ODA Project Management Unit .................................................................................... 21 3.3  Sector Pioneering: the HSC implementation in MARD............................................. 22 3.4  Monitoring and Evaluation ........................................................................................... 23 3.4.1  National Rollout of Monitoring and Evaluation System........................................ 23 3.4.2 Progress Assessment of the HCS implementation.................................................. 25

Chapter 4 Looking Ahead................................................................................................................. 29 4.1 The HSC mid‐term evaluation and survey .............................................................. 29 4.2 Independent Monitoring............................................................................................. 30 4.3 Why should the PGAE be renovated? ...................................................................... 31 4.4 How should the PGAE renovate itself? .................................................................... 32 4.5 How to mobilize resources to the HCS? ................................................................... 33

Appendix ‐ Summary Report of JPPR V ............................................................................................ 34  

Aid Effectiveness – Moving up to the higher level     

i

Page 4: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Acronyms

ADB  Asian Development Bank AFD  Agence Francaise Development AMT  Alignment Monitoring Tool AUSAID  Australian Agency for International Development  CIDA  Canadian International Development Agency CCBP  Comprehensive Capacity Building Programme CG CSO 

Consultative Group Civil Society Organizations 

DAC  OECD Development Assistance Committee DAD  Development Assistance Database DFID  Department for International Development of United Kingdom EC  European Commission EIA  Environmental Impact Assessment EU  European Union EVN  Electricity of Viet Nam GoV  GoV of Viet Nam GTZ  German Agency for Technical Cooperation HCS  Hanoi Core Statement IFAD  International Fund for Agricultural Development IMF  International Monetary Fund ISG  International Support Group (MARD) ISGE  International Support Group for Environment (MONRE) JBIC  Japan Bank for International Cooperation JICA  Japan International Cooperation Agency KfW  Kreditanstalt für Wiederaufbau LMDG  Like Minded Donor Group M&E  Monitoring and Evaluation MARD  Ministry of Agriculture and Rural Development MDG  Millennium Development Goal MDTF  Multi Donor Trust Fund MOC  Ministry of Construction MOET  Ministry of Education and Training MoF  Ministry of Finance MOFA  Ministry of Foreign Affairs MOH  Ministry of Health MONRE  Ministry of Natural Resources and Environment MOT  Ministry of Transport 

Aid Effectiveness – Moving up to the higher level     

ii

Page 5: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Aid Effectiveness – Moving up to the higher level     

iii

MPI  Ministry of Planning and Investment MTEF  Medium Term Expenditure Framework NAM  New Aid Modalities NGO  Non‐GoV Organisation ODA  Official Development Assistance OECD  Organization for Economic Cooperation and Development OOG  Office of GoV PBAs  Programme Based Approaches PD  Paris Declaration on Aid Effectiveness PEFA  Public Expenditure and Financial Accountability framework PER  Public Expenditure Review PFM  Public Finance Management PGAE  Partnership Group for Aid Effectiveness PMU  Project Management Unit IMTF  Inter‐Ministerial Task Force on ODA Problem Solving SBS  Sector Budget Support SBV  State Bank of Viet Nam SEDP  Socio Economic Development Plan SIA  Social Impact Assessment SWAp  Sector Wide Approach TG  Thematic Group of the Partnership Group on Aid Effectiveness TOR  Terms of Reference UNDP  United Nations Development Programme UNESCO  United Nations Educational, Scientific and Cultural Organization UNFPA  United Nations Population Fund UNODC  United Nations Office on Drugs and Crime VAMESP  Viet Nam Australia Monitoring and Evaluation Strengthening Project – Phase II V‐HAP  Viet Nam Harmonization Action Plan WB  World Bank 

Page 6: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Chapter 1  Executive Summary 

Remarkable socio‐economic development  in 2007. Growth hit a  ten year high of 8.5%  this year  continuing  Vietnam’s  dramatic  reductions  in  poverty  and  improvements  in  living standards. Export  volumes  increased  by  over  20%  and many  other  economic  targets were exceeded  including  the  contribution  of  the  service  sector  and  budget  revenues. Vietnam’s integration and  international standing was further  increased with Vietnam’s membership of the WTO and election as a non‐standing‐member of the UN Security Council.   The strong partnership between the Government of Vietnam and its development partners is, in part, responsible for these achievements bringing the prospect of middle income status sooner than expected. This partnership continued to strengthen and develop in 2007 focussing on  implementation  of  the  Paris Declaration  and  the Hanoi Core  Statement  (HCS).  This  is critical to ensure that the US$ 11 billion of ODA planned for 2006‐2010 is effectively used to support further growth and poverty reduction.  To ensure this target is met the Government this year completed a comprehensive set of ODA management and utilization policies and legal documents. These are detailed in Chapter 2.   HCS implementation was further supported by a number of initiatives. These all aimed to enhance aid effectiveness in Vietnam and are summarised below.  The Five Banks worked closely with the Government Inter‐Ministerial Task Force (IMTF) four ministries and HCMC to conduct the fifth Joint Portfolio Performance Review (JPPR V). This produced  twelve  “Fast  Track”  recommendations  for  review  by  the  Prime  Minister  on improvement of ODA performance.  The EU and  its member states  initiated activities to  improve their effectiveness at the policy level  through  the  PRSC  and  at  the  sectoral  level  in  education  and  health. The EU  Private Sector Working Group  also  broadened  its  activities  to  support  trade.  Importantly  the  EU developed a harmonization roadmap for implementation of HCS. This includes the “EU Code of Conduct on Complementarity and Division of Labour in Development Policy” a significant step on the way to rationalising support from the EU members and EC.  13  LMDG  donors  have  continued  to  support  strengthening  of  Government  systems  and implementation  of  the  HCS  through  the  Comprehensive  Capacity  Building  Programme (CCBP), funding PGAE activities and projects. They have also introduced new initiatives and approaches  such  as  common programmes  and projects.   The LMDG have  also  stated  their intention  to  focus  on  the  public  administration  reform,  anti‐corruption  and  public  finance management (PFM) in future.   An  important milestone  for  the Government  ‐ UN “One UN”  initiative  in Vietnam was  the signing  of  the  ‘One  Plan  –  One  Budget’  program  document.  This  is  a  legally  binding agreement between UNDP, UNICEF, UNFPA, UNV, UNAIDS, UNIFEM and the Government of  Vietnam  that  provides  the  basis  for  full  implementation  of  the  ‘One  UN’  initiative  in Vietnam.  

Aid Effectiveness – Moving up to the higher level     

1

Page 7: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

 International non‐governmental organizations (INGOs) and civil society organizations (CSOs) also demonstrated their interest in aid effectiveness and accountability through the setting up of Aid Monitoring Group  (AMG). The AMG will undertake  independent monitoring of aid and organize consultations on the effectiveness of aid delivery with beneficiary groups.   Thematic Groups (TGs) progress in 2007, continued to contribute to the achievement of the HCS.  The  Procurement  TG  supported  the  Government  to  strengthen  the  national procurement  system  and Procurement Law. The  thematic  groups  on ODA  on Budget  and Public Financial Management (PFM) have been dissolved and activities in this area have been organized around  the  joint preparation of  the Country Financial Accountability Assessment (CFAA)  Update.  This  is  expected  to  be  completed  by  the  end  of  2007.  The  TG  on  EIA completed the  joint study on EIA harmonization  leading to the development of the detailed working plan for the 2008‐2012 period. Similarly the TG on SIA completed its gap analysis on resettlement  policies,  and  developed  an  action  plan  to  achieve  the  HCS  targets  for resettlement. Guidelines for independent resettlement projects were also developed.   At  the  sectoral  level  the  Ministry  of  Agriculture  and  Rural  Development  (MARD)  has developed an action plan for meeting the HCS commitments with regards to ODA programs and projects under MARD management. The action plan  is expected  to be approved by  the beginning of 2008. The action plan will be used as a good practice model  for  replication  in other sectors and provinces.  Heading to the 3rd High Level Forum of Aid Effectiveness in Ghana. The HCS Independent Monitoring Team (IMT) report indicates that significant progress has been achieved. However a  lot of work remains to achieve the HCS targets. This conclusion  is similar to that found  in four   regional consultation meetings which were carried out from June to September 2007 in Mauritius, Ghana, Honduras and the Philippines on implementation of the Paris Declaration. These  reviews will help  frame  the OECD/DAC mid‐term  survey on  the  implementation of Paris  Declaration/Hanoi  Core  Statement  to  be  conducted  in  the  first  quarter  of  2008  and reported on at the 3rd High Level Forum on Aid Effectiveness in Accra, Ghana in September 2008.  Renovating  the PGAE  to achieve  faster progress  is a key  recommendation  to ensure HCS targets are met. As Vietnam develops so does its development assistance needs and the range of  aid  and  financing  instruments  broaden.    To  reflect  these  changes  the  PGAE  requires renovation to fulfil its mandate, and to set the priorities for and co‐ordinate aid effectiveness activities. To do  this  the PGAE now needs  to:  (i)  support  the Government put  in place  the strengthened  policies  and  regulatory  systems  required  to  manage  a  market  orientated, middle‐income  country;  (ii)  continue  the  improvement  of  public  finance  management  to increase aid predictability and  facilitate  the application of new aid modalities;  (iii) develop capacity  for  ODA  management  and  coordination,  particularly  at  sub‐national  levels;  (iv) improving ODA program/project performance; (v) take more advantage of complementarity and  labour  division  among  donors;  and  (vi)  scale  up  M&E  activities,  particularly  joint Government ‐ donor impact evaluations.  

Aid Effectiveness – Moving up to the higher level     

2

Page 8: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

The  PGAE  also  needs  to  redefine  its  remit  focusing  on  making  strategic  decisions  and supporting HCS  implementation  in  specific  sectors  and  areas. To do  this  requires  broader participation of Vietnamese government agencies and Civil Society Organisations  to ensure accountability. It also needs to support and be informed by other partnership groups in order to resolve the technical and sector issues that are slowing the implementation of the HCS.   To  implement  this  ambitious  agenda  requires  more  support  and  delegation  to  the Government‐led  Comprehensive  Capacity  Building  Programme  (CCBP),  TGs  and  sector partnership  groups.  This  will  allow  them  to  fulfil  their  important  tasks  ‐  assisting  the Government and donor‘s to deliver the aid effectiveness improvements that are at the core of the PGAE agenda.   Once  the principles of  the  renovation have been agreed by  the PGAE a  joint working  team will be established to develop a medium‐term program and budget for the 2008‐2010 period. This will be submitted to the PGAE for consultation and approval in early 2008.  

Aid Effectiveness – Moving up to the higher level     

3

Page 9: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Chapter 2  Joint Work to Strengthen Government’s System 

2.1 Development of the ODA Policy and Legal Framework  

In  2007  development  cooperation  between  Vietnam,  other  countries  and  international organizations continued to flourish, with  joint efforts focusing on the  implementation of the Paris Declaration  (PD) and Hanoi Core Statement  (HCS) on Aid Effectiveness. Reaching  the ambitious targets set out  in these documents requires  improvements  in the  legal framework to improve Vietnam’s own country systems. Legal reforms will also improve the effectiveness of  aid  delivery  by  streamlining  procedures  and  improving  the  alignment  of  support  to government priorities. 

To  support  development  and  eliminate  poverty  the Government  has  set  out  its  target  to disburse  US$  11  billion  of  ODA  in  2006‐2010  period.  In  order  to  achieve  this  target,  the Government has  introduced a  complete  set of ODA policies and  legal documents on ODA management and utilization, including: 

• ODA Strategic Framework for 2006‐2010 period and its Action Plan; and • Decree 131/2006/ND‐CP on ODA Management and Utilization. 

 Under the instructions of the Prime Minister, the Ministry of Planning and Investment (MPI), Ministry  of  Finance  (MOF)  and Ministry  of  Foreign  Affairs  (MOFA),  have  been working closely with  other  relevant  Vietnamese  agencies  and  donors  to  formulate  and  issue  their guiding circulars and decisions for implementation of Decree 131/2006/ND‐CP as follows:       

• Circular  04/2007/TT‐BKH  of  the Ministry  of  Planning  and  Investment  guiding  the implementation of Decree 131/2006/ND‐CP; 

• Circular  03/2007/TT‐BKH  of  the Ministry  of  Planning  and  Investment  guiding  the Organizational  Structures,  Functions  and  Responsibilities  of  ODA  Programs  and Project Management Units; 

• Decision  803/2007/QD‐BKH  of  the  Minister  of  Planning  and  Investment  on  the Reporting Mechanism for implementation of ODA programs and projects; 

• Decision  1248/2007/QD‐BKH of  the Minister of Planning  and  Investment  issuing  the ODA Monitoring and Evaluation Framework for 2006‐2010 period; 

• Circular 82/2007/TT‐BTC of the Ministry of Finance on Financial Management for ODA grant projects and programs;  

• Circular 108/2007/TT‐BTC of the Ministry of Finance on the Implementation of Decree 131/2006/ND‐CP on Financial Management for ODA projects and programs; 

• Circular  123/2007/TT‐BTC  of  the  Ministry  of  Finance  on  providing  guidance  on taxation applicable to ODA projects and programmes; 

These documents set out  the policies and  framework  for  the utilisation and mobilization of ODA.  They  decentralize  appraisal,  approval  and  implementation  of  ODA  programs  and projects and harmonise and simplify the procedures governing the utilization of ODA. 

It  is  recognised  that  inconsistencies  and potential  bottlenecks  still  remain  in  the new  legal framework. The Government and donors will continue to work on these issues. In particular other ODA‐related legal documents require improvement to simplify, decentralise and ensure 

Aid Effectiveness – Moving up to the higher level     

4

Page 10: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

consistency.  In  particular Decree  111/2006/ND‐CP  guiding  implementation  of  the  Law  on Procurement, Decree 112/2006/ND‐CP on management of  construction  investment,  etc. and the upcoming development of the Public Investment Law. 

Putting  the Government ODA  policies  and  legal  documents  into  practice  following  the issuance of  the above ODA policies and  legal documents was a major priority  in 2007. MPI with support from CCBP organized a series of ODA legal training workshops nation‐wide for Government  officials  at  all  levels  and  for  Vietnamese  program  officers working  in  donor agencies. These aimed at putting all the new ODA policies and legal documents into practice.  

2.2      Strengthening ODA Management Capacity   Capacity is required to effectively  implement the new, decentralised ODA policies and legal documents. The development of capacity for ODA management, especially at the provincial level,  is  a  priority. With  the  support  of  CCBP,  a  series  of  five‐day  Project Management Courses for more than 350 Government Officials and Project Management Units’ (PMU) Staff at national and local levels have been organized.  Along  with  support  from  international  and  national  consultants  under  CCBP,  many communication activities and a number of workshops have been held  to help  improve aid effectiveness,  reduce  transaction  costs  and  lighten  the  administrative  burden  of  ODA management in 2007. These include: (i) taking stock of international experience and reviewing Vietnam‘s experience in application of NAM; (ii) reviewing case studies in applying NAM in Vietnam;  (iii)  developing  training  materials  integrated  into  the  overall  CCBP  project management training; and (iv) developing a road map for the application of NAM in Vietnam from  2008‐2010.  The  results  of  this  work  were  broadly  disseminated  at  the  completion workshop, a PGAE Meeting in October and are now posted on the CCBP website. 

2.3      Five/Six Banks – JPPR V 

Achievements in 2007 

From the Five Banks to the Six Banks. The Development Banks welcomed a new and active member, the Export‐Import Bank of Korea (KEXIM). This is part of the Korean Government’s agency  for Economic Development Cooperation Fund  (EDCF)  that has made  a decision  to significantly increase support to Vietnam. 

Table 1: Yearly Commitment by EDCF to Vietnam (in million USD, * tentative) 

Year  2004  2005  2006  2007e 2008~10*

Commitment  21.0  19.5  26.0  243.4  800 

EDCF’s  support  is  based  on  a  ʺMid‐term  Rolling  Planʺ with  the Vietnamese Government based  on  the  2005  ʺCountry  Cooperation  Strategy  and  Program  for  Vietnamʺ.  These agreements  and  associated  technical  assistance  are  paving  the  way  for  future  EDCF investments. As EDCF wishes  to become an  ‘active and  integrated donor  in Vietnam’,  it  is taking measures  to  harmonize  and  align  its  support.  This  includes  joining  the  Five  Banks 

Aid Effectiveness – Moving up to the higher level     

5

Page 11: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Group  ‐ making  it  the  Six Banks Group  ‐  to  improve  its partnership with  the Vietnamese Government and other donors. 

Enhancing Portfolio Performance  –  JPPR V. The Fifth  Joint Portfolio Performance Review (JPPR V) aimed at identifying the bottlenecks in Vietnamese and donor systems and agreeing on  common  approaches  to  addressing  them.  It  reviewed  the  Five  Banks  activities  in  the following five portfolio: transport, energy, urban water/waste water, rural water supply and irrigation, and infrastructure in Ho Chi Minh City. The final multi‐agency workshop, held in Haiphong on May 23,  identified key actions on both sides. These actions could significantly improve performance and ensure achievement of the HCS targets on procurement, financial management and safeguards. 

A ‘Fast Track Action Plan’, derived from the JPPR V, was developed focusing on three areas1: • Accelerating  Project  Preparation,  Appraisal  and  Approval  including  common 

feasibility/design  procedures,  increased  preparation  funding  and  delegation  of approvals; 

• Accelerating  Project  Start‐up  including:  Delegation  to  implementing  agencies,  and starting implementation preparation early; and 

• Accelerating  Project  Implementation  including:  Removal/revision  of  cost  norms, accelerated payment processing and faster land clearance procedures. 

The JPPR V was organized in cooperation with the IMTF and reported to the Prime Minister as a jointly agreed input into the Government’s internal discussions on improving investment efficiency. In response the Prime Minister issued two directives 836 and 5103 requesting IMTF and  other ministries  to  take  concrete  steps  to  implement  key  fast  track  actions.  Intensive follow‐up  work  has  been  conducted.  This  has  focused  on:    common  feasibility  studies (including simplifying  ‘basic design’);  ‘advance actions’  to speed project start up; revision of cost  norms  in  construction  cost  estimates;  and  piloting  separately  funded  land acquisition/resettlement projects. 

Enhanced Systems  for Aid  Effectiveness. The  6 Banks  continued work  in  other  areas,  all aimed at strengthening government systems and their use by the Development Banks. Three focus areas for 6 Banks work were: 

• Adoption  of  the Aligned Monitoring  Tool  (AMT). On  July  30,  2007,  the Ministry  of Planning and Investment (MPI) issued the Decision 803. This decision mandates the use of the AMT for all ODA projects in Vietnam. In parallel the 6 Banks also agreed to use this reporting format. The AMT will reduce the reporting burden on government agencies and ensure  that  donors  and  government  have  access  to  the  same  information  to  evaluate project  performance.  The  AMT  tool  is  now  being  rolled  out  with  the  assistance  of VAMESP II and CCBP support. 

• Adoption of common Feasibility Study guidelines. The 6 Banks have also been working closely  with  MPI  and  more  recently  with  MoC,  to  develop  new  guidelines  for  the development  of  feasibility  studies  that  are  consistent with  both  international  standards and  government  regulations.  In‐principle  agreement  has  now  been  reached  on  the 

1 The detailed plan is presented in the full 6 Banks report to the CG, available separately. 

Aid Effectiveness – Moving up to the higher level     

6

Page 12: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

adoption of a common set of feasibility study guidelines acceptable to all. Importantly the definitions used in these common guidelines may be included in revisions to Decree 112. These are currently being submitted to the Prime Minister for approval. 

• Procurement, environmental and social impact assessment (EIA & SIA). In addition the 6 Banks have continued leading work in these areas, as co‐chairs of the Thematic Groups for Procurement, EIA, and SIA. Details are provided in Chapter 2 of this report. Work is also  being  supported  on  Financial  Management  and  improving  construction  sector transparency. The goal of this work  is to  improve Vietnamese  legislation and practice  to recognised International Standards. 

Looking ahead 

The 6 Banks recognize that much work remains to be done if the ambitious targets set out in the HCS are to be achieved and Development Banks aid  is to be more effective. Three main areas of work have been identified for future 6 Banks activities. 

• New approaches  to delivery. As Vietnam’s develops so does  its assistance needs. The 6 Banks  will  explore  with  the  Government  how  to  deliver  more  strategic  and  flexible financing  that  responds  to  the  demands  of  a  country  reaching middle  income  status. Options  for discussion  include  sub‐national  financing,  the  introduction of new  financial products  and  working  more  through  financial  intermediaries,  to  complement  more traditional stand‐alone project support. 

• Continued support for country system enhancement. The Hanoi Core statement cannot be  achieved  without  further  development  of  the  legislation  governing  procurement, financial management and safeguards. The 6 Banks will continue to support the thematic and  partnership  groups  in  these  areas.  In  particular  the  6  Banks  would  like  to  offer assistance  in  the development of  the Law on Public Investment,  to be undertaken  in  the coming year. 

• JPPR V follow‐up. JPPR V achieved an unprecedented level of consensus on key areas for action  to  accelerate  aid  delivery  and  improve  effectiveness.  It  also  demonstrated  that agreed solutions can be  implemented  if both sides  take a  flexible approach,  for  instance, by  agreeing  to  introduce  specific measures  as  ‘pilots  for ODA’. Pilots  can demonstrate how  improved systems work  in practice,  leading  to government reforms  to  improve  the effectiveness  of  all  public  spending.  Consequently  the  6  Banks will  continue work  to implement the agreed JPPR V actions, including: support to pilot FS Guidelines; agreeing advance  actions;  improving  transparency  of  investment  procedures  and  reform  of  the construction  cost  norm  system.  All  these  activities  aim  at  supporting  the  long‐term development of Vietnamese government systems. 

2.4 The European Union 

Achievement in 2007 

The EU sectoral working groups continued to discuss and promote aid effectiveness. Besides providing  inputs  and  joint  analytical  work  to  the  VDR  (“Aiming  High”  in  2006,  “Social Protection”  in 2007) and to the PRSC policy dialogue, the EU Health Sector Working Group 

Aid Effectiveness – Moving up to the higher level     

7

Page 13: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

initiated and provided  support,  together with other development partners,  to  the  first ever Joint Annual Health  Sector  Review  2007.  This  provided  a  comprehensive mapping  of  the health sector and set out a clear vision for its reform. This review was used as an input for the annual planning  cycle of Ministry of Health.  It highlights  the  technical  and  financial gaps, where  donors  can  provide  support  in  the most  harmonized way.  This  is  one  step  further towards a sector programme in the health sector in Vietnam. 

As to the education sector group in which the EU plays a leading role, in December 2006 the first annual  dialogue  between  the Minister  of  Education, HE Mr Nguyen  Thien Nhan  and  the international donors active  in  the education sector was organized. The dialogue  focused on challenges  for  the  education  sector,  priorities  of MoET  and  improved ways  of working  to support the sector. It was followed by a full day retreat to review the activities of the ESG in 2006 and to discuss priorities and ways forward for 2007.  

Highlights of the EU higher Education Working Group include: • A Website on studying in Europe is up and running and has attracted many visitors; • 6 Weekly meetings where one EU member state makes a presentation on their activities 

in the (higher) education sector in Vietnam; • Preparations  for  the European Higher Education Fair  (Hanoi, HCMC 7‐12 December 

2007). 

In 2007 the EU Private Sector Development Working Group expanded its remit to include Trade Related Assistance. The group met  in March and again in October. The main purpose of the group remains threefold:  (i) to share information on programmes and projects with a view to creating synergies and opportunities for co‐operation; (ii) to update participants on incoming monitoring/evaluation missions  for co‐ordination purposes; and  (iii)  to generate options  for  policy  actions  under  the  Private  Sector Development  and  Global  Integration  areas  of  the  PRSC.  

The EU continued  to play an active role  in  the PGAE Thematic Groups,  in particular  in  the Thematic Group for Cost Norms. In line with the Action Plan 2007 on Cost Norms, EU and UN cost norms have been merged. The merged cost norms were sent to MPI for comment and their views are expected soon. In the future it will be important for other donors to adopt the same cost norms  to avoid  further distortions and  jointly move  towards  full alignment with Government cost norms by 2010. 

Finally, with  the MPI‐managed  Development  Assistance  Database  (DAD)  having  become fully operational, the design and content of the Blue Book underwent major changes in 2007. Published  in June 2007, the Blue Book has become more fact‐and‐figure based, based on the model of the EU Donor Atlas, and drawing information from the DAD. It reflects longer term trends in EU commitments and disbursements, and highlights key policy features such as the move towards new aid modalities, better division of labour and donor complementarily. 

Looking ahead 

The EU Harmonisation Roadmap continues  to guide EU activities aiming  to  implement  the Hanoi Core  Statement. On  1  July  2007, EU Ambassadors  approved  the  report on  activities carried out during the preceding year, and approved a set of future actions.  These activities 

Aid Effectiveness – Moving up to the higher level     

8

Page 14: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

have been  tailored  to  the circumstances of Vietnam and are  largely  inspired by  the new EU Development Policy  laid down  in  the “European Consensus on Development” of December 2005. Along with endorsing the commitment of the “Paris Declaration” and the “Hanoi Core Statement”,  it  adds  “four  additional  commitments”  (coordinated  capacity‐building programmes with  increased  use  of multi‐donor  arrangements;  channelling  50%  of  official ODA through government systems; no new parallel PMU’s; and reduction of uncoordinated missions by 50%). 

Furthermore,  on  15  May  2007,  EU  Ministers  adopted  a  landmark  new  instrument  for improved donor harmonisation and aid effectiveness namely  the “EU Code of Conduct on Complementarity  and  Division  of  Labour  in  Development  Policy”.  EU  Development Counsellors in Hanoi held a retreat on this issue in March 2007. This led to the inclusion into the Roadmap of the following principles and activities:  

• The GoV  should  be  invited  to  assume  leadership  and  encourage  the wider  donor community  to engage more  in a better division of  labor, geographically, thematically, but also on aid modalities. 

• Vietnam’s  graduation  adds  to  the  need  to  improve  dialogue,  complementarity  and division of labour, whenever relevant.  

• Division of labor and donor representation is already applied in different forms which should be  further discussed and developed, e. g.  in  the context of Targeted National and Sector Budget Support. The Code of Conduct of  the Donors participating  in  the targeted budget support programme for education will be assessed and might provide lessons  for  other  sector  approaches.  Further  joint  impact  assessments  of  targeted budget support are envisaged (P 135, education).  

• A lead donor approach  is followed for Public Financial Management (by NL), clearly going beyond coordination purposes, and may be replicated in other areas. 

• EU  PRES  and  EC  will  propose  to  PGAE  to  include  Division  of  Labor  and complementarity  in  the PGAE Workplan 2007 and  the Hanoi Core Statement Action Plan. This was proposed in a letter to the co‐chairs of the PGAE on 8th June 2007. 

2.5 The LMDG2 

Achievement in 2007 

Focus  on  alignment,  strengthening  of  core GoV  systems,  and  realising  the Hanoi Core Statement. LMDG action  in 2007  included promoting  innovation and new approaches and supporting the harmonisation agenda through common projects and programmes as well as funding PGAE activities. The LMDG was active through delegated co‐operation and through the individual and bilateral action of its members. The LMDG remains an important informal forum for exchange of information on harmonization and aid effectiveness issues.  

2  The  LMDG  is  an  ad‐hoc  grouping  of  13  bilateral  donors  (Australia,  Belgium, Canada, Denmark, Finland, Germany,  the Netherlands,  Ireland, New  Zealand, Norway,  Sweden,  Switzerland  and  the United Kingdom) who are drawn  together by  the  idea  that working  together  is more  effective  than working bilaterally.  

Aid Effectiveness – Moving up to the higher level     

9

Page 15: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

During the past twelve months, the LMDG, through its members DFID, New Zealand, Ireland and  Norway,  coordinated  the  donor  response  and  support  to  the  One  Plan  which  was launched  by  the  Government  of  Vietnam  and  the  six  participating  United  Nations organizations  in  June. This  innovative pilot  is being managed by a Tripartite National Task Force (TNTF) with representatives from GoV, donors and the UN.  

More  recently,  LMDG  members,  under  the  lead  of  DFID,  have  been  working  towards streamlining their inputs into the PRSC dialogue process. The group has been consulting with EU member states with a view to disseminating information on the PRSC, advancing the time table for action and focussing dialogue inputs though donor countries acting as the focal point for PRSC donors in thematic working groups.     

Denmark  organised  the  international  independent  monitoring  study  of  the  Hanoi  Core statement,  the  results  of  which  will  be  tentatively  discussed  at  the  Consultative  Group meeting of December 2007. The practices of three LMDG donors ‐Belgium, Denmark and the UK‐ were used as case studies for the report, the World Bank being the fourth case study.   

Support to the Harmonisation Action Plan (HAP). The LMDG is funding the Comprehensive Capacity Building Project  (CCBP)  in  conjunction with  the World Bank administered PHRD trust fund,  and the Public Procurement Training Project (PPTP).  

• The  four  components  of  the CCBP  contributed  to:  the  development  of  the  legal ODA framework (Decree 131 and its circulars; PMU circular); training of over 350 government officials at the national and  local  levels on the newly  issued  legal documents; the project management  training  in  eight  5‐day  project  management  courses  for  more  than  500 participants nation‐wide; the report on the application of new aid modalities; and support to the PGAE on aid effectiveness.  CIDA leads this component. 

• The LMDG  also  supports  the Public Procurement Training Project  (PPTP) managed by MPI.  Developing  training  curriculum,  training  certification,  training  of  trainers  and trainees, and enhancing the capacities of staff working in public procurement.  Denmark is the lead donor on this program.  

In  the  longer  term  the  LMDG  will  focus  on  Public  Administration  Reform Master  Plan support, Anti‐corruption and Public Financial Management:  

• PAR Master Plan Support. Together with UNDP, the LMDG will continue its support to the GoV’s PAR Master PLAN. The  formulation of a  second phase of  the UNDP/LMDG support  program  is  still  ongoing  and  will  address  improved  management  and coordination of the PAR support activities. Switzerland leads this activity.   

• Anti‐corruption.  Five  LMDG  members  are  working  together  in  a  program  aimed  at strengthening  the  GoV  Inspectorate.  Elaboration  of  laws,  capacity  building  and reinforcing  the  institutional  setup  of  the  Inspectorate  system  are  the main  goals.  The program  is  in  its  design  phase  the  implementation  phase  is  planned  to  start  in  2008. Sweden is the lead donor.  

• Public Financial Management. A number of LMDG members support a multi‐donor trust fund  for public  financial management  reform  in  the Ministry of Finance, with  technical 

Aid Effectiveness – Moving up to the higher level     

10

Page 16: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

assistance from the World Bank. A proposal for a second phase has been submitted to a group  of  eight  donors,  not  all  of  them  LMDG‐members.  The  Netherlands  leads  this activity.  

Looking ahead

Besides  its  ongoing  programmes  (CCBP  and  PPTP),  the  LMDG will  continue  to  promote innovation in a flexible manner through its dedicated fund, as well as increase the impact of its  actions.  The  aid  effectiveness  advisor  of  the  LMDG,  who  started  last  September,  is currently finalizing research proposals.   

2.6 United Nations 

Achievement in 2007 

One Plan/One Budget  ‐ One Plan 2006‐2010 was signed as a  legally binding programmatic document on 23 August between UNDP, UNICEF, UNFPA, UNV, UNAIDS, UNIFEM and the Government of Viet Nam. Before the signing ceremony in August, a special session of the Tripartite National  Task  Force  (TNTF) was  convened  to discuss  the One  Plan  on  12  June. Donors responded positively to the One Plan and are providing unearmarked funds through the One  Plan  Fund.  Eight  additional  agencies  plan  to  join  totalling  14  by December  2007: IFAD,  ILO, UNESCO, UNIDO, FAO, WHO, UNODC and UN‐Habitat. A  revised One Plan (One  Plan  2)  is  currently  being  developed  to  incorporate  the  contributions  of  the UNCT. UNHCR and IOM will not join the One Plan.  

The One Plan  is accompanied by a Results and Resources Framework  (One Budget), which highlights  the  resources  required  for  implementing  the One Plan  for  6 Agencies  combined over the 5 year time frame. The One Budget for One Plan I amounts to 218 million USD, and contains details  regarding  both  core  (73 million USD)  and non  core  resources  (145 million USD), as well as detailed resource requirements at the level of the 5 outcomes of the One Plan and  the  individual Outputs. The  funding gap  for  the  implementation of  the One Plan  is 88 million USD  for  the  six UN Agencies  signatory  to  one  Plan  1  as  per  June  2007.  The One Budget will change upon the integration of the results and resources of the incoming UNCT agencies.  

One Plan Fund  (OPF)  ‐ The draft ToR  for  the One Plan Fund was  finalized  in  June  2007. Several donors have signed the LoA and transferred their contribution to the One Plan Fund (Norway, UK, Netherlands, Luxemburg), while other donors have announced contributions and  it  is  anticipated  that  they will  sign  the LoA  in  the near  future  (Ireland, Canada, New Zealand).  

One Leader ‐ During a recent retreat of the UNCT (13‐14 September), the UNCT collectively concluded  that a One Leader  is  imperative as coherence at country  level  requires decisions from  a  UN‐wide  perspective.  As  there  is  no  enhanced  authority  and  accountability framework for the Resident Coordinator which allows for that at present, UNCT decided to develop  a  local  Memorandum  of  Understanding  for  RC  containing  among  others  the following principles:  

• One Leader has the authority to give guidance on One Plan  

Aid Effectiveness – Moving up to the higher level     

11

Page 17: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

• One Leader is the ultimate decision maker on the allocation of funds from OPF 

• One Leader acts as One Voice on behalf of UNCT as appropriate. 

A draft MoU will be circulated among UNCT shortly. As a complement to the MoU, a draft Code of Conduct for the UNCT is being developed.  

One UN House ‐ One UN House is an important component of the UN reform programme. Physical  co‐location  will  help  to  break  down  the  (communication  and  other)  barriers associated  with  physical  separation,  foster  a  sense  of  common  UN  identity,  and  lead  to considerable savings for  individual Agencies through the establishment of common support services  and  enable  the  achievement  of  programmatic  synergies  –  goals  that  are  clearly outlined  in  the  HCS.  The  technical  feasibility  of  an  eco‐friendly  UN  House  through refurbishment and expansion of the current UN Apartment Building has been established. An independent,  external  financial  analyst  will  undertake  a  financial  scenario  mapping  in November. A UN House Project Manager  is being recruited. The preliminary eco‐design by the Centre of Excellence, Faculty of Architecture, Chulalongkorn University  is ongoing with funding  from Norway. All UNCT  confirmed  their  support  for  a UN House  but  financial feasibility  remains a challenge. Total costs are expected  to be around 6‐8 million USD  if all UNCT  join.  In  addition  to  UN  contributions,  external  support  from  donors  and  the Government is essential.  

One Plan M&E Framework  ‐ A Monitoring  and Evaluation Framework  (MEF)  of  the One Plan  to measure development  impact has been prepared. The MEF will be reviewed by  the mission  of  the United Nations  Evaluation Group  (UNEG)  in November  2007  to  asses  the ‘evaluability’. The mission will also review a set of process benchmarks to measure progress in the achievement of the 5 ‘Ones’ in the One UN initiative. As part of establishing a baseline, an independent and external stakeholder (perception) review is planned late 2007, as well as a staff survey early 2008. 

Looking ahead 

In  2008  the  focus  will  be  on  the  implementation  of  the  One  Plan  2  (to  be  finalized  in December 2007) which will combine the development contributions of 14 UN Agencies in Viet Nam.  In  addition,  the  focus will  be  on  further  detailing  the One  Plan Management  Plan (OPMP) as an  internal management  tool on how UNCT will organize  itself  to better achieve the strategies and results  in  the One Plan 2006‐2010. As  the principal reform  tool  it outlines operational changes for enhanced effectiveness and coherence – ensuring that the One Plan is matched by an adequate management structure, human resources, and improved business practices  and  common  services.  OPMP  will  provide  details  on  the  current  situation  and changes  in  the  immediate  future,  i.e.  the period until early 2008; set out a strategy  for how management  structures,  resources  and practices  are  expected  to  be  in  2009 when One UN House  should  be  completed;  and  it  provides  pointers  to  the  future  beyond.  It  provides information on change processes, for example development of joint programme‐management groups with  staff  from  different  Agencies who  are  to  be  co‐located  in  the  immediate  or medium term future, and harmonisation of programme / project management guidelines.  

In addition, OPMP will outline the process for an external competency mapping based on a three‐tier process agreed by UNCT:  

Aid Effectiveness – Moving up to the higher level     

12

Page 18: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

What do we have: comprehensive mapping of available human resources in UNCT short term operational measures for better coherence and effectiveness; 

What  do we  need: matching  long  term  aspirations  for  a  changed UN with  adequate human resources (quantity and skill‐mix), noting that  in changed development context of Viet Nam achieving MIC‐status in 2010, the UN should adapt programmatically and operationally. 

How do we deliver as UNCT: timeframe/decisions.  

UN will also focus on the establishment of an eco‐friendly UN House in 2008, and review the operational  modalities  of  a  common  support  office  structure  and  the  inter‐agency collaborative  structures  that  would  lead  to  better  programmatic  synergies  (clustering, programme management groups etc).   

2.7 Civil Society Organisations 

Achievement in 2007 

As development actors, International NGOs  (INGO) and Civil Society Organisations  (CSOs) in  Vietnam  have  a  keen  interest  in  the  aid  effectiveness  agenda.  This  is  in  order  to  in strengthen development efforts in Vietnam and draw attention to the outcomes and impacts of  development  aid  across  the  country.  In  2007,  there  have  been  an  increasing  number  of initiatives  launched  by  INGOs  and  national  CSOs  to  enhance  the monitoring  of  aid  and strengthen the important role of CSOs in improving aid effectiveness. 

Launch of the Aid Monitoring Group (AMG) 

In June 2007, the Aid Monitoring Group (AMG) was initiated by a group of INGOs and CSOs that have been  involved  in aid  effectiveness activities and monitoring official development assistance (ODA) for several years.  

The  AMG  was  initiated  with  the  purpose  of  developing  and  carrying  out  independent monitoring of the  implementation of aid  in Vietnam. This will enhance the accountability of donors  and  government  to  citizens  in  Vietnam,  and  ensure  that  donor  strategies  and programmes reflect the priorities of the Vietnamese people ‐ particularly poor and vulnerable members of society. By enhancing coordination between INGOs and CSOs in the monitoring of aid, the AMG also seeks to strengthen the dialogue and interaction between development actors and donors in Vietnam. The AMG is organised on a voluntary basis and co‐chaired by the VUFO‐NGO Resource Centre  (NGO RC) and  the Vietnamese Centre  for Cooperation & Human Resource Development (C&D).  

In 2007, the AMG provided input for the Independent Monitoring Mission and organised the Consultation with NGOs on World Bank Conditionality. The AMG has also been preparing a national level study on aid.  

Training‐Workshop  on  building  the  capacity  of  civil  society  to  advocate  and  influence Multilateral Development Banks’ (MDB) Operations in Vietnam.  In July/August, the Rural Development Services Center (RDSC) organised a five‐day training workshop for Vietnamese NGOs (VNGOs) on MDB operations in Vietnam. Organised by RDSC with support from the 

Aid Effectiveness – Moving up to the higher level     

13

Page 19: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Bank  Information Centre  (BIC), more  than 20 organisations participated  in  the event, which lead  to  increased  awareness  of  i)  the  influence  and  ramifications  of ADB  and World Bank activities  in the development processes of Vietnam’s doi moi period, and ii) how to increase and  expand  the  advocacy  knowledge  and  skills  of VNGOs  towards  informed  engagement with the MDBs.  

Workshop on elective members and  the monitoring of aid for social programmes, policy, and the Law on Charitable Activities. In October, C&D and ActionAid Vietnam organised a two‐day  training  workshop  with  the  purpose  of  enhancing  knowledge  of  ODA  among Committee of Social Affairs members, National Assembly members and elective members of Peopleʹs Councils. The workshop also aimed to discuss ways to make aid more accountable, and included presentations and discussions on the concrete experiences and challenges faced by elective members involved in aid monitoring at the provincial level. 

National consultation on CSOs and aid effectiveness.   This workshop was held  in October as part of a global consultative process on aid effectiveness issues relating to civil society. This is  led by  the Advisory Group  on Civil  Society  and Aid Effectiveness  (AG),  created by  the OECD‐DAC.  The  purpose  of  the  consultation  was  to  raise  awareness  of  aid  monitoring among national civil society organisations (CSOs), and specifically to discuss the role of CSOs in enhancing aid effectiveness This will  inform  the submission  to  the High Level Forum on Aid Effectiveness  in Accra  in  2008. Facilitated by  the  regional Reality of Aid Network,  the consultation  was  organised  by  Vietnam  Union  of  Science  and  Technology  Association (VUSTA), with the support from the S‐CODE, the VUFO‐NGO Resource Centre, and UNDP. Some of the key findings from the consultation were:  

• The awareness and knowledge on AE, and particularly the Paris Declaration (PD) and the Hanoi Core Statement  (HCS),  is presently  fairly  low among national CSOs, and  there  is a need  for  awareness‐raising  and  information‐sharing  on  these  issues  for CSOs  to  take  an active role in relation to enhancing AE; 

• The role and capacity of CSOs in relation to the HCS needs to be addressed by GOV, donors and CSO,  similar  to  the  process  and  discussion  of  role  of CSOs  in  relation  to  the  Paris Declaration at the global level; 

• CSOs could play the role of monitoring the effectiveness of the implementation of ODA at the  commune  level  in  Vietnam,  as  well  as  monitor  funds  from  INGOs  and  other international organizations; 

• Donors  and  INGOs  should  consider  how  to  relate  to  and  involve  national CSOs  in  the design, implementation and monitoring of development programmes and project. 

The  national  consultation  provided  input  for  the  Civil  Society  Organisations  &  Aid Effectiveness Regional Workshop held in Hanoi between October 9 to 12.  

Looking ahead.  

As several activities have been  initiated  this year,  future plans  in  the areas of CSOs and aid effectiveness will be  further discussed and defined by  the end of 2007. At  the beginning of 2008, the different activities and processes will be taken into account, finalising plans for next year. Following are some general orientations that are being have already been discussed:  

Aid Effectiveness – Moving up to the higher level     

14

Page 20: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

In 2008, the Aid Monitoring Group (AMG) will continue to carry out analytical activities. In addition, the AMG will focus on: • Building capacity of  CSOs on aid effectiveness issues and the monitoring of aid; • Aid effectiveness of CSOs as development actors; • Aid monitoring at the sub‐national level; and • Linking up with regional and global processes and networks, including the Global Call for Action Against Poverty (GCAP), and the 2008 High Level Forum meeting in Accra. 

New activities are envisaged as follows: • Carry out national and sectoral studies on aid effectiveness in Vietnam, including studies of the implications and outcome of direct budget support modalities; 

• Analyse and enter into dialogue on the issue of CSOs and the Hanoi Core Statement; • Develop and pilot community aid monitoring models. 

CSO’s Recommendations to PGAE • Carry  out  consultation  with  the  AMG  and  CSOs  in  relation  to  studies  and  initiatives facilitated by the PGAE, including the next Independent Monitoring exercise. 

Aid Effectiveness – Moving up to the higher level     

15

Page 21: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Chapter 3  Implementation of the Hanoi Core Statement 

3.1  Contribution made by Thematic Groups 

After achieving “quick wins” in various aspects of HCS implementation during the year 2006, the thematic groups working in  areas of procurement, public financial management, EIA, SIA have continued making considerable progress in 2007. A summary of progress in each group is presented below, along with planned next steps for 2008. 

3.1.1 Procurement Thematic Group 

Achievements in the sector in 2007 

An Assessment of public procurement system  (Law on Procurement and Decree 111) was carried  out  using  the  OECD/DAC  Base  Line  Indicator  (BLI)  Assessment  Tool.  The independent  assessment  was  completed  in  February,  2007.  This  work  also  informed  the Development  Partners  recommendations  for  specific  modifications  required  in  the  Legal Framework  in  order  to  remove  identified  gaps. These were  communicated  to MPI  in  July 2007. These were  taken  into consideration  in  the proposals  for amending Decree 111 before submitting by MPI to the Prime Minister in September 2007.  Work  on  Harmonised  Standard  Procurement  Documents  also  made  good  progress  The Standard Bidding Documents for Goods were completed  in May 2007 and the Standard Bid Evaluation  Report  in  September.    Standard  Bidding Document  for  Civil Works,  Standard Request  for Proposals,  and  Standard Prequalification Document  for Civil Works  are under preparation. Standard procurement monitoring and reporting  formats were also adopted as part of Aligned Monitoring Tool (AMT) in June 2007. Support was also provided to upgrade the Procurement website and upgrading  the Procurement Bulletin  to  a Newspaper. This  is still ongoing and is scheduled for completion in February 2008.   LMDG Support was also provided for the procurement Capacity Building Program. Training modules  are  being  prepared  and  are  scheduled  for  completion  by  December  2007.  The Procurement Accreditation  / Certification  Scheme  also  started  early  2007. During  the  year thousands  of  procurement  personnel were  trained  on  procurement  regulations  and  skills using public and private institutions.  Finally  a  procurement  compliance  and  performance  measurement  system  using OECD/DAC/WB methodology was developed. Two pilots of its use have been completed and six oversight groups are currently under assessment. 

Gaps in the legal framework remain and need to be addressed, in particular:  

• In some cases local laws currently prevail over the procurement law. • Direct contracting for works and goods contracts below VND 1 billion is still allowed even 

when competition is possible. • The minimum  time allowed bidders  to complete expressions of  interest, prequalification 

and bidding documents is insufficient. 

Aid Effectiveness – Moving up to the higher level     

16

Page 22: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

• Bids are not opened at the stated time when there are fewer than three bids. This applies even under open bidding. Extension of bid opening/cancellation when fewer than 3 bids are received is also allowed. 

• There  is an urgent need  for harmonized standard procurement documents acceptable  to donors.  

• Use of  the merit point  system  for  evaluation  is  still  allowed. This  should be  limited  to procurement of complex Information Systems and textbooks. 

• There is lack of clarity between evaluation factors and qualification criteria.  • Bids cannot be recommended for award if they exceed the approved estimated price. 

Next steps and support requirement 

Based on these identified gaps the immediate priorities for future works are as follows: • Completion of Harmonized Standard Procurement Documents; • Further upgrading of the website and procurement newspaper; • Monitoring and measuring procurement compliance & performance; • Implementation of a procurement complaints mechanism; and • Introduction of annual procurement audits. 

The  TG  for  procurement  needs MPIʹs  support  for  the  proposal  to  the  Prime Minister  for Amendment of Decree 111. This is required in order to accelerate progress to allow the HCS targets to be met by 2010.  The group also needs to collaborate more with the PFM TG. 

3.1.2  Public Finance Management Thematic Group 

Achievements in the sector in 2007  The  thematic  groups  on  ODA  on  Budget  and  Public  Financial  Management  have  been dissolved and PFM  Issues are being dealt within  the Public Finance Partnership Group and around the preparation of the Country Financial Accountability Assessment (CFAA) Update under preparation and led by the World Bank.  The  CFAA  is  a  diagnosis  of  a  country’s  financial  management  environment  and  public financial management  system.  It  aims  to  help  the Government  and  development  partners assess and develop a common understanding of  the risk  that public  funds may be used  for unintended purposes;  identify  the key risks, capacity gaps and constraints  to progress; help the Government develop  strategies  for  reform; and assist  in program design  for  improving and  building  financial management  capacity  in  the  public  and  private  sectors.  The CFAA Update  is  being  jointly  undertaken  by  several  Donor  Partners  and  the  Government.  Its specific  objectives  are:  (i)  to  support  Vietnam’s  ongoing  program  to  strengthen  budget planning, execution, reporting, monitoring and accountability; (ii) to provide analytical inputs to  the public  financial management strengthening programs particularly at  the sub‐national levels  and  for  decentralization  developments  and  the  use  of  country  systems  for  all investment  financing;  (iii)  to  strengthen  capacity  to  conduct  public  financial  expenditure performance  and  fiduciary  risk  assessments  in  the  Ministry  of  Finance,  the  Ministry  of Planning  and  Investment,  in  selected  sector ministries  and  provinces;  and  (iv)  to  provide information and analysis for assessment of the degree to which reliance can be placed on the 

Aid Effectiveness – Moving up to the higher level     

17

Page 23: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

country’s  public  financial management  systems  and  for  fiduciary  risk  assessments  by  the Government, the World Bank and to other financiers and donors 

Gaps 

Progress since the last CFAA, remaining gaps and ways to address them will be identified as a result of CFAA update and other on‐going work. 

Next Steps and support requirement  The CFAA Update began in April 2007 and is planned to be completed by the end of 2007. A draft report is nearing completion, and was expected to be shared with donor partners in November 2007. 

3.1.3  EIA Thematic Group 

Achievements in the sector in 2007 

The TG for EIA engaged a team of consultants to conduct a study to: (i) update harmonisation progress between the Government’s and development partners’ requirements for EIA; and (ii) develop a detailed workplan for the TG for EIA for the period 2008‐2012, including suggested implementation arrangements. The consultants started  the  field work on 10  July, submitted the inception report on 27 July and the draft final report on 21 September. The TG will revise the  draft  final  report  incorporating  comments  from  the  TG  members,  organize  a  TG workshop, and finalize the final report by the end of 2007. 

Gaps 

The  gap  analysis  conducted  in  2006  and was  updated  under  the  on‐going  study.  Priority issues  for  harmonization  include:  (i)  criteria  for  EIA  screening;  (ii)  timing  of  EIA;  (iii) independence of consultants and appraisal authorities; (iv) scope and TOR for EIAs; (v) public consultation and  information disclosure;  (vi)  language used  in reports;  (vii) requirements of complex projects;  (viii) environmental management plans  (EMP),  (ix) post‐EIA enforcement, and (x) application of EIA. 

Next steps and support requirement 

The following priority areas are proposed for the workplan for the TG for EIA from 2008 to 2012 and the indicative budget required to complete the activities has been estimated. 

• Technical Sector Guidelines: updating of existing guidelines and/or development of new guidelines  to  address  the  Government’s  legislative  changes  and  enhance  harmonization with donor requirements. 

• Public  Consultation:  Identification  of  priorities  for  improving  capacity  in  public consultation and increasing harmonization with donor requirements through development of technical guidelines, decrees/circulars and capacity building activities. 

Aid Effectiveness – Moving up to the higher level     

18

Page 24: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

• EMPs and Post‐EIA Enforcement: Identification of regulatory  instruments, guidelines and capacity building requirements for enhancing capacity in EMPs and post‐EIA activities and improving harmonization with donor requirements. 

• Further  Legislative  Reform:  Identification  of  priorities  for  legislative  reform  to  support harmonization  efforts  including  review of  existing decrees  and  circulars, development of new decrees and circulars and revision of LEP. 

• Capacity Building:  Identification  of  capacity  building  activities  required  to  support  EIA harmonization efforts for MONRE, line agencies/ministries, DONREs, and districts. 

Activities proposed for 2008 include: • A review of Decree 80;  • A  review  and  preparation  of  technical  sector  guidelines  for  transport,  thermoelectricity, hydroelectricity, electricity transmission, and small‐scale rural infrastructure; 

• Development  of  regulations  on  public  participation  for  incorporation  into  legislative documents;  

• Training and awareness raising on public consultation in EIA; and • Development and maintenance of EIA information dissemination network. 

Importantly the TG for EIA needs financial and technical support from development partners to implement the proposed workplan to achieve the HCS target. 

3.1.4 SIA Thematic Group 

Achievements in the sector in 2007 

The TG for SIA engaged a team of consultants to conduct a study to: (i) compare and identify gaps  between  the  Government’s  and  donors’  resettlement  policies  and  regulations;  (ii) develop  an  action  plan  and  institutional  arrangements  for  achieving  the  targets  under  the HCS relating to resettlement; (iii) help the Government prepare leaflets and brochures on the harmonized  resettlement  policy;  and  (iv)  help  the  Government  prepare  guidelines  to implement separate resettlement projects. The consultants started the field work in mid‐July, and  submitted  the  draft  table  highlighting  the  differences  between  the Government’s  and donors’  resettlement policies and  the draft  leaflet on  the harmonized  resettlement policy  in September. The draft final report was submitted in November and it is expected that it will be finalized by December incorporating comments from the TG members. 

Gaps 

The following gaps were identified under the ongoing study: 

Non‐legal Land Users: Under the Government regulation, affected people (APs) who do not have user rights are not entitled to full compensation. 

Tenants:  Under  the  Government  regulation,  APs  who  rent  state‐owned  housing  are  not entitled to compensation if they do not accept to relocate to an available resettlement site, or may  receive only  small  cash  compensation; APs who  rent private housing may not  receive 

Aid Effectiveness – Moving up to the higher level     

19

Page 25: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

any assistance beyond a relocation allowance; and APs who rent land are not entitled to any compensation or assistance. 

Small and Non‐registered Business: APs who operate small and non‐registered business are not entitled to any compensation or assistance under the Government regulation. 

Compensation Rates: The Government uses  the rates established by  the Provincial People’s Committee (PPC). PPC rates are updated annually. It  is observed that PPC rates are usually well below actual market rates. 

Income Restoration: The Government regulation defines severely affected APs as those losing more than 30% of their productive assets, while it is 20% for the World Bank and 10% for the ADB. 

Vulnerable Groups and Ethnic Minorities: The Government regulation covers special needs of poor households, but does not explicitly recognize other vulnerable groups such as ethnic minorities. 

Monitoring:  The  Government  regulation  does  not  have  indicators  and  procedures  for independent monitoring. 

Next Steps and support requirement 

Based on  the gap analysis, a draft action plan  towards 2010 was developed. The proposed priority  actions  in  the  draft  action  plan  include:  (i)  development  of  project  classifications based  on  the  level  of  resettlement  impact;  (ii)  preparation  of  detailed  guidelines  for resettlement  impact  assessment;  (iii)  identification  of  compensation  unit  prices,  (iv) preparation  of  detailed  guidelines  for  livelihood  rehabilitation;  (v)  revision  of  eligibility criteria,  (vi)  development  of  a  policy  for  ethnic  minority  APs;  (vii)  strengthening  of monitoring and evaluation;  (viii) preparation of  resettlement plans before project appraisal; (ix)  strengthening  of  public  participation  and  information  disclosure;  and  (x)  policy dissemination and awareness raising. 

 

Aid Effectiveness – Moving up to the higher level     

20

Page 26: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

3.2  ODA Project Management Unit  Circular  03  on MPU:    Promoting  Decentralization  and  Accountability  –  Following  the issuance of Decree 131/2006/ND‐CP the Ministry of Planning and Investment issued Circular 03/2007/TT‐BKH  on  12  March,  2007  guiding  the  organizational  structure,  functions  and responsibilities of ODA program/project management units.  The Circular 03 defines the legal status  and  the  mandates  of  ODA  PMUs  as  well  as  their  inter‐relationship  with  other Government  agencies  in  the  State ODA management  system.   Attached  to  this Circular  is Appendices with  the  forms of Decision on Establishing  the Management Units of Technical Assistance/Investment Project.  Progress made since the last PGAE  Proposed Key Strategic Actions: 

From Last PGAE Status  Follow‐up 

Institutionalize  PMU‐related  legal framework.  Dissemination  and training  activities  on  Decree 131/2006/ND‐CP  and  its  guiding Circulars  and  related  regulations through  workshops,  meetings, media, internet;  

Five  training cources on ODA Strategic  Framewok,  Decree 131, Circular 04 and Cirular 03 on PMU were conducted from September  to  October  2007. About  400  participants  from the  line  agencies,  provinces, and  donor  communities were trainned.  

Continues  to  conduct the  training  program under  the  Project Management  Training to the PMUs and donor communities.  

Conduct  an  in‐depth  study  on “parallel”  PMUs  to  clarify  the validity  of  the  baseline  results, identify what practices need to be changed  and  encourage  the establishment  of  project management  structures  that sustainably  build  Government capacity; 

In‐depth  study  conducted under the CCBP. Study results have  been  incorporated  to establish Circular   03/2007/TT‐BKH of MPI on PMU  

No follow‐up  

Comprehensive  capacity building  on Project  Management  for  line agencies and PMUs staff through courses,  consultancy  workshops, media  and  possible  help  desks with CCBP support;  

Eigh  Project  Management training  cources  were conducted.  Target  goups  are staff  from  the  line  agencies, PMUs,  and  provincial departments  of  planning  and investment.  About  450 participants  from  the  North and  Central  regions  were trained  

Two  additional training  courses  are being  scheduled  in December  for  staff from  the  Southern region.  

 Difficulty Remains. In process of implementing Circular 03/2007/TT‐BKH, the Line Agencies have faced a number of difficulties with on‐going ODA programs/projects when the role and 

Aid Effectiveness – Moving up to the higher level     

21

Page 27: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

functions  of    “Program/Project  Owner”  is  required  to  be  clear‐cut  with  that  of  the  Line Agency or of  the PMU as  the model  that used  to exist  in  the past. Some Line Agencies  like MOT,  MARD  has  moved  faster  than  the  others  by  integrating  PMUs  with  their  new Program/Project Owners such as the Road/Railway Administration Authorities. Progress has been made also in HCMC while the other ministries (MOH, MoET) have been struggling with this transfer process due to the difficulties in defining the Program/Project Owners for PMUs.  To ensure  the Circular  to be effectively complied, one of  important elements  is  the support and the alignment of the donors to the Government systems on ODA PMUs.  

3.3  Sector Pioneering: the HSC implementation in MARD 

More  than  two  years  have  passed  since  the  Prime  Minister  approved  the  Hanoi  Core Statement  (HCS). During  this  time numerous activities have been undertaken  to ensure  the HCS,  2010  targets  are  achieved, meeting  the  commitments made  at  the mid  ‐  term CG  for Vietnam  of  2005.  These  initially  focused  at  the  central  level  but  now  need  to  focus  on developing  the capacity of sector ministries who will  implement the HCS principles  in their projects  and  programmes.  In  order  to  accelerate  implementation  of  the HCS,  Vietnamese agencies have agreed the following approach: 

• MPI will support other ministries develop roadmaps  for HCS  implementation. These will reflect  the priorities  and needs of  the  sector. These  efforts must be  led by  the  respective ministries; 

• Focus  on  one  pilot  ministry  that  meets  the  requirements  of  a  ‘pioneer  in  HCS implementation’; and  

• Continue  support  for  HCS  implementation  in  ministries  and  sectors  that  have  been involved  in  the  thematic groups of PGAE  and CCBP  activities. For  example; Ministry of Finance, and Ministry of Natural Resources and Environment etc.. After drawing  lessons from these exercises these support activities can be replicated in other ministries and areas of support. 

To  take  this approach  forward MPI –  the government  coordinator  in HCS  implementation, recognizes  that  some  ministries  and  sectors  have  been  far  more  active  in  HCS implementation.  In particular  the Ministry of Agriculture and Rural Development  (MARD) has been outstanding. MARD has  already  achieved  significant  results  in  implementing  the HCS since 2005 and is now striving to identify its implementation approach over the coming years. Consequently in August 2007 the leader of MPI sent an official letter to propose MARD as a co‐implementer of the HCS. 

Under the direction of MARD’s leadership, International Cooperation Department (ICD) was appointed as  focal point  to conduct  the  implementation of HCS  led by a deputy director of ICD. This task force will identify with FERD MPI the targets for and the approach and specific action plan for implementation of this sector pilot. The taskforce has now completed the draft status  report,  defining  indicators,  priority  activities,  and  the  proposed  objectives  of implementing the HCS in MARD. 

Aid Effectiveness – Moving up to the higher level     

22

Page 28: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

This has now been  reviewed and  the action plan  for HCS  implementation submitted  to  the MARD leadership for approval.  

MARD’s Implementation plan for HCS  is a clear example of the active cooperation between two ministries, MARD and MPI, to achieve the HCS targets committed to by the government. These results came from working together at the highest level in each ministry, supported by close technical cooperation between FERD – MPI and ICD – MARD. 

3.4  Monitoring and Evaluation 

3.4.1  National Rollout of Monitoring and Evaluation System  During the life of the current 5‐year plan the Government has developed tools for monitoring donor commitments and disbursement as well as implementation processes and performance.  With the support of several donors, particularly the 6 Banks, AusAID, JICA, JBIC and UNDP the Ministry  of  Planning  and  Investment  now  has  systems  and  tools  in  place  for  national adoption to enable effective monitoring of ODA commitments, implementation and impact. 

As part of its commitment to aid effectiveness, articulated through the Hanoi Core Statement on Aid Effectiveness,  the Government of Vietnam has  institutionalised official development assistance (ODA) monitoring and evaluation. Following the issue of Decree 131/2006/ND‐CP by the Prime Minister in November 2006, the Government has issued: 

• Circular  04/2007/TT‐BKH  guiding  the  implementation  of  the  regulation  on management and utilisation of ODA; 

• Decision 803/2007/QĐ‐BKH for the monitoring report format to be used by ODA programs and projects; and 

• Decision  1248/2007/QĐ‐BKH  on  the  Framework  for Monitoring  and  Evaluation  of ODA Programs and Projects in 2006 – 2010 Period. 

The  overall  objectives  of  the  Framework  are  to  set  out  the  strategy  for  monitoring  and evaluation of ODA programs and projects. This  is  supported by an action plan  to develop, operate and improve the national system of monitoring and evaluation of ODA programs and projects.  This was  put  into  implementation  in  the Decision No.  94/2007/QĐ‐TTg  dated  27 June,  2007  of  the  Prime Minister.  The M&E  Framework  and  related  Action  Plan  can  be downloaded in Vietnamese and English at: www.mpi.gov.vn/tddg.

The monitoring  format  institutionalised  in Decision  803 was  developed with ODA  project managers and major donors, including the 5 Banks, over a 3‐year period, with support from the Vietnam Australia Monitoring  and  Evaluation  Strengthening  Project.    The  format was trialled  by more  than  40  PMUs  and  further  refined  before  being  institutionalised  by MPI.  Major  donors  have  already  aligned  with  the  format.    The  Foreign  Economic  Relations Department of MPI, which is the focal point for ODA monitoring, has recently established an email address  for electronic submission of monitoring reports – as required  in Chapter 6 of Decree  131/2006/ND‐CP  and  Circular  04/2007/TT‐BKH.  The  email  address  is: [email protected]

Aid Effectiveness – Moving up to the higher level     

23

Page 29: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

These  new  regulations  institutionalise  the  national  system  to  monitor  ODA  in  Vietnam enabling  PMUs,  sector  ministries,  donors  and  central  ministries  to  better  manage  for development results.  The formats monitor: 

• Disbursement  rate  –  variance  between  actual  and  planned  rate  of  disbursement  to contractors and investment activities. 

• Process – variance between actual and planned time taken to complete required processes for bidding, contract implementation, resettlement and environmental management. 

• Performance  –  variance  between  actual  and  planned  implementation  of  activities  and delivery of outputs.   Performance  indicators are project specific and entered by  the PMU and Project Owner. 

The  formats are supported by a range of  tools and resources  to enable project management units, project owners and line agencies to use them: 

• Aligned  monitoring  tool  (AMT)  –  is  an  Excel  tool  for  quarterly  monitoring  and performance reporting using the formats in Decision 803.  Major donors have aligned with these  formats,  so PMUs only need  to prepare one  report  for use by  the government and donor(s).    The  AMT  includes  harmonised  ODA  data  coding  that  has  been  adopted nationally –  including standard codes  for donors, countries, currencies, province, regions, and sectors.   

• Portfolio monitoring tool (PMT) – is an Access database that extracts data from the AMT to collate, analyse and benchmark performance of a line agency portfolio of investments.  A number of management indicators are programmed into the tool to allow quick assessment of variance from plan and benchmarked efficiency of implementation.  

• National monitoring manual – published in August 2007. The monitoring manual provides a  detailed  introduction  to  logical  frameworks,  practical  selection  of  indicators, measurement  of  performance  and  use  of  data  to  support management  for  development results . 

• Training handbook for teachers – published by MPI in May 2007, this is a training resource for  teachers  that  sets out a monitoring curriculum,  training  resources and exercises.   The handbook is available from the Foreign Economic Relations Department of MPI. 

• National M&E website – the national M&E website (www.mpi.gov.vn/tddg ) provides a focal point  for monitoring and evaluation  resources, news, communication, data exchange and international links for practitioners in Vietnam.  All the manuals, tools and other resources mentioned above can be downloaded from this site. 

These  regulations,  tools  and  other  resources  provide  guidance  and  support  for implementation of the monitoring system.   Already more than 40 PMUs are using the AMT and more than 10 line agencies are using the PMT.  Contact FERD/MPI to get in contact with these monitoring practitioners to learn from their experience.  In addition MPI and JBIC have signed a memorandum of understanding on joint evaluation.  The  3‐year  agreement  provides  for  both  parties  to  prepare  an  annual  “Implementation 

Aid Effectiveness – Moving up to the higher level     

24

Page 30: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                    Report 2007 

Aid Effectiveness – Moving up to the higher level     

25

Program  of  Joint  Evaluation”.    In  2007  the  Implementation  Program  includes  ex‐post evaluation of three projects executed by MOT: • National Highway No. 5 Improvement Project • National Highway No. 1 Bridge Rehabilitation Project • Hanoi – Chi Minh City Railway Bridge Rehabilitation Project 

The  joint  evaluations will be  conducted by  a  team of Vietnamese and  Japanese  evaluators, with counterparts  from MPI, MOF and MOT.   The methodologies used are  those set out  in Decree  131/2006/ND‐CP  and  Circular  04/2007/TT‐BKH  as well  as  the National  Evaluation Manual – published in May 2007.  The evaluation manual introduces 5 evaluation criteria, 4‐steps  for evaluation, questions and practical  selection of  indicators, evaluation  frameworks, methods for gathering data to measure indicators of performance and use of lessons learned to  support  management  for  development  results.  Meanwhile,  MPI  has  completed  3 evaluations  during  2007 with  support  from Vietnam Australia Monitoring  and  Evaluation Strengthening Project: 

• Baseline  evaluation  for  the  Second Ho Chi Minh City Water Environment  Improvement Project (JBIC, HCM City) 

• Mid‐term evaluation of the Road Network Improvement Project (World Bank, MOT) • Impact  evaluation  of  the Hanoi Water  Treatment  Project  (World  Bank, Hanoi  People’s Committee) 

Case  studies  from  these  and  other  evaluations  implemented  by MPI  are  available  at  the national M&E website: www.mpi.gov.vn/tddg   

With  support  from  UNDP  and  collaboration  from  many  donors,  the  Government  has implemented  a  system  to monitor donor  commitments  and disbursement  by donors  –  the Development Assistance Database (DAD). After completing the validation of historical ODA project  data  for  2001‐2005,  donors,  together with Government,  are  validating  the  data  for 2006‐2007 in DAD for the CG 2007. The updating and validating process will ensure that DAD provides  updated  donor  ODA  information  that  is  of  high  quality,  comprehensive  and transparent. The DAD database allows MPI  to analyse donor commitments by  location and sector and inform ODA strategies based on information provided by the donors. 

3.4.2 Progress Assessment of the HCS implementation  

In  June  2007,  the  PGAE  developed  an  Issues  Paper,  that  analysed  where  the  gaps  and challenges  lay  in achieving the agreed HCS targets. From this a set of strategic actions were identified  for  the  remaining  three years of HCS  implementation. The Paper  set out a more systematic and in‐depth approach to implementing the HCS. This builds on the “quick wins” of  2006  which  were  achieved  through  the  joint  efforts  of  the  GoV  and  donors.  The  key improvements are highlighted in this report (Chapter 1 and 2) and summarized in the Table 2 below. The next round of formal monitoring will be conducted through the HCS monitoring surveys scheduled for 2008, these activities are described in Section 4.1. 

Page 31: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                                Report 2007 

Aid Effectiveness – Moving up to the higher level     

Table 2  Progress and Initiatives in implementing HCS till the end of 2007 

HCS Target Indicators  Benchmark ’05  Targets for 2010  Important progress till the end of 2007 

Ownership          

1. Five Year Socio‐Economic Development Plan (SEDP) targets achieved 

SEDP developed and approved  

SEDP targets achieved 

ON TRACK: SEDP ʹs targets are being achieved under the framework of annual national plan ‐ M&E Framework for National SEDP (Decision 555/2007/QĐ‐BKH) 

Alignment          

2. Donor assistance strategies are aligned to the SEDP and related to national, regional, provincial and sector strategies 

100% of donors aligned 

100% 

ON TRACK: ODA strategic framework approved by the Vietnamese Government ‐ Donors through Partnership Groups continue to support SEDP at national and sectoral levels (e.g., health and education) 

3. Donor strengthen GoV capacity by avoiding parallel PMUs 

111 parallel PMUs  0  No progress reported 

4. GoV integrates capacity building objectives in the SEDP and related national regional, provincial and sector plans and leads comprehensive CB programmes with coordinated donor support 

84% of aid for CB delivered through GoV‐led / coordinated programmes 

100%  Progress to be identified during the 2008 survey 

5. Donor progressively rely on the GoV’s procurement system once mutually agreed standards have been attained 

32% of aid flow and 23% of donors using GoV procurement systems 

50% 50% 

ON TRACK: Assessment of Vietnamʹs Procurement Systems using BIS and APPI when Decree 111 was revised 

6a. Donors progressively rely on the Government of Vietnam’s public financial management and accounting systems strengthened once mutually agreed standards have been attained 

27% of aid flows and 6% of donors using GoV PFM system 

50% 50% 

ON TRACK: CFAA Update, PFM reforms ‐ MTEF, TABMIS under implementation 

26 

Page 32: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness    Report 2007 

Aid Effectiveness – Moving up to the higher level     

Targets for HCS Target Indicators  Benchmark ’05  Important progress till the end of 2007 2010 

6b. GoV publishes timely, transparent and reliable reports on budget planning and execution 

27.7% of GoV budget accounted for and audited 

50%  Audited report on budget planning and execution was published 

7. Donor enhance the predictability of future aid  

69% of aid disbursed according to agreed schedules 

75% Efforts are made among the Government and donors to increase the disbursement rate in ODA programmes and projects 

8a. GoV and donors improve environmental safeguards (EIA) 

9% of EIA used GoV system ‐ 61.7% with additional safeguards 

30%  EIA TG Workplan on hamonization the EIA procedures between the Government and donors 

8b. GoV and donors improve social safeguards (SIA) 

0.4% of SIA used GoV system ‐ 78.3% with additional safeguards 

30% New decree (supplementing Decree 197/2004/NĐ‐CP) being preparedSIA TG Workplan  

Harmonization and Simplification          

9. Fewer, better core diagnostic (CFAA, PER, CPAR, etc.) and country analytical reviews of Vietnam’s development needs  

80% used CDW 32% of CAW shared 

100% 75% 

ON TRACK: VDR, Vietnam Environmental Monitor, Joint CAW on Alternative Aid Modalities for Health Sector,...  ‐ DAD, SBS Website ‐ ODA Evaluation survey by VAMESP II 

10. Common project cycle management tools agreed and used throughout the project/programme cycle (planning, design, implementation, M&E and reporting) 

Donors using common project/programme cycle tools ‐ no data 

50% 

ON TRACK:  ‐Common FS format ‐ Common reporting format AMT legalized ‐ Decision 803/2007/QĐ‐BKH ‐ M&E framework in ODA programmes and projects with action plans ‐ Decision 1028/2007/QĐ‐BKH ‐ One UN reform 

27 

Page 33: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness    Report 2007 

Aid Effectiveness – Moving up to the higher level     

28 

HCS Target Indicators  Benchmark ’05  Targets for 2010  Important progress till the end of 2007 

11. GoV and donors increasingly use programme based approaches 

34% of aid is national or sector programme based 

75% ON TRACK: Decree 131/2006/NĐ‐CP recognizes PBAs ‐ NAM studies by CCBP ‐ Donors support GoV NTPs, SWAPs 

12. Decentralization and delegation of authority to the country level is maximized for each donor  

60% of aid interventions that are managed at the country level 

75% ON TRACK:   ‐ Delegated cooperation among the donors  ‐ EU donor complementarity and division of labour 

Managing for Results          

13. Results framework developed and used to assess the performance of the SEDP and sector programmes 

Based on OECD/DAC scoring ‐ no data  3 

ON TRACK: Results framework for national SEDP (Decision 555/2007/QĐ‐BKH) ‐ Result frameworks for ARD and NRE sectors 

Mutual Accountability          

14. Periodic mutual assessment of progress in implementing agreed commitments on aid effectiveness 

No  Annual Assessments 

ON TRACK: Regular GoV/donors dialogues within PGAE and PGAE reports to CGs ‐ DFID, AusAiD, Belgium shared HCS action plans ‐ Independent monitoring mission in 2007 

 

Page 34: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

Chapter 4  Looking Ahead 

4.1 The HSC mid‐term evaluation and survey  As agreed in the HCS M&E framework, formal HCS monitoring is to be conducted every 2 years to review progress  in  implementing  the HCS. Next year  this exercise will be undertaken  jointly with  the monitoring  of  the  Paris Declaration  planned  to  be  conducted  in  1st Quarter,  2008  as decision at the meeting of the OECD‐DAC Working Party on Aid Effectiveness (WP‐EFF) held in late November, 2007  to report   monitoring results  in 3rd High Level Forum  in Accra  (Ghana)  in September 2008. The harmonised survey is scheduled for the first quarter of 2008.  It will have 3 main objectives: 

• To track progress in implementing the Hanoi Core Statement based on the 14 agreed indicators against the benchmarks of 2005; 

• To  take  stock of progress  in  implementing  the Paris Declaration  (in preparation  for  the  third high level forum to be held in Accra next year);  

• To  review GoV  and donors’  successes  and  challenges,  stimulate  broad discussion  and  reach agreement on specific, future actions to improve aid effectiveness. 

Based on the lessons learned from the baseline surveys in 2006 and as suggested by the JV‐PDM, the  coming  HCS/PD  monitoring  surveys  is  to  be  organized  through  the  PGAE.  The  PGAE Coordinator will  act  as  the National Coordinator  and  one  or more Donor Focal Points will  be nominated. Further support will be provided by CCBP. The 2008 survey will compose of donor surveys and GoV surveys using the same methodology as 2006 to ensure consistency. (A separate survey of selected GoV agencies will be conducted later to serve the monitoring needs of the HCS. This will be conducted  later). Learning  form  the 2006 survey  three  improvements  to  the survey process will be introduced: 

• Improving  the  clarity  of  the  definitions  of  PD  and  HCS  indicators  and  provide  firmer instructions based on the comments of donors and GoV agencies who participated in the 2006 surveys, the PGAE Issues Paper (6/2007) and JV‐PDM survey  instruments (whilst maintaining consistency with the 2006 data);  

• Developing  a  web‐based  IT  tool  to  operationalize  the  survey  process  in  order  to  broaden dialogue,  facilitate  responses,  speed‐up  data  collection  and  analysis  and  generate  country reports and communicate findings faster;  

• Improve  the  survey  process  through  better  integration  of  the  qualitative  and  quantitative dimensions of the survey. Donors’ responses will be verified and supplemented through results of  the GoV  survey  and  other data  sources,  consultation with CSO’s  and  linkages with other processes  (e.g.,  JV  on  Procurement,  JV  on Managing  for Development Results,  Independent Monitoring). Special studies will also be undertaken if needed. 

 

Aid Effectiveness – Moving up to the higher level    

29

Page 35: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

 Table 3 presents the tentative 2008 survey plan with milestones and responsibilities parties:  

Table 3: Tentative 2008 survey plan with milestones and responsibilities  

Milestones  Activities  Responsible 

Dec 2007 Formation  of  the  2008  Survey  Management  Group including nomination of Donors Focal Point(s) 

PGAE 

Dec 2007 

Revision of survey  instruments  including definitions and guidance, GoV and  donors questionnaires,. Development of  tools  to  operationalize  the  survey  process  and communicate findings 

CCBP 

15 Jan 2008 Launch  the  2008  Survey  with  lunch  ,  meeting  with participating donors and CSOs 

PGAE with CCBP support  

Jan 08 – Mar 08 Conducting the 2008 Survey: including donor  responses, collecting data from key GoV agencies  

PGAE with CCBP support  

Mar 08 Consolidating  responses,  generating  Vietnam  country worksheet 

CCBP 

15 Apr 2008 Submitting  the  results  of  the  Survey  to  the  OECD  for analysis after consulting PGAE members 

Nat’l Coordinator 

Apr – May 08  Conducting the survey of selected GoV agencies  CCBP 

June 08  HCS Monitoring Results for PGAE report to mid‐CG 08  PGAE 

Apr – Sep 08 Data  verification  for  the  Vietnam’s  country  chapter  in communication with Working Party on Aid Effectiveness looking ahead to the Accra event 

PGAE with CCBP support  

2‐4 Sep 2008  The Accra High‐Level Forum on Aid Effectiveness  Nat’l Coordinator 

Sep – Nov 08 HCS  Data  verification  with  results  from  GoV  survey, PGAE TGs outputs, additional studies 

PGAE with CCBP support  

Dec 2008 HCS  Monitoring  Results  with  findings  and recommendations for PGAE report to CG 2008 

PGAE 

 

4.2   Independent Monitoring The HCS sets out 28 Partnership Commitments and 14 targets to be achieved by 2010.  To monitor progress all HCS signatories agreed  that  the Government of Vietnam  (GoV) and donors should periodically  review  their  progress  against  these  commitments  through  an  Independent Monitoring process.  The first review is currently being finalised.  The assessment was carried out by an Independent Monitoring Team (IMT), using a methodology agreed with a Management Board established by the Partnership Group on Aid Effectiveness to oversee  the  process.    It  offers  an  overview  of  HCS  implementation  to  date,  plus  detailed 

Aid Effectiveness – Moving up to the higher level    

30

Page 36: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

examination  of  three  thematic  areas:  (i)  country  leadership  and  donor  alignment  behind  the national development agenda;  (ii) use of country systems for ODA delivery; and  (iii) organising HCS  implementation.    These  themes  were  explored  through  case  studies  of  three  sectors  – education,  transport  and  rural water  and  sanitation.   The  IMT  also  conducted  reviews  of  four donors  (Belgium,  Danida,  DFID  and  the World  Bank) who  participated  in  the  exercise  on  a voluntary basis.   Under  the  HCS,  the  Independent  Monitoring  process  is  intended  to  support  mutual accountability.   The IMT  is called upon to make  judgments on the quality of effort by both GoV and  donors  to  implement  the HCS,  and  to  point  out  any  shortcomings.    It will  be  up  to  the government  and  donors  to  review  these  findings  and  collectively make  judgements  on  their usefulness and what steps should be taken to address them. 

4.3  Why should the PGAE be renovated?  The PGAE was set up three years ago as a government‐donor platform with the mandate to guide and coordinate aid effectiveness activities. Since then it has taken on an ambitious agenda. Firstly agreeing the Vietnam Harmonization Action Plan (V‐HAP) and developing programs such as the CCBP to support its implementation. This was followed by Vietnam becoming the first country to localise  the Paris Declaration with Government and donors  jointly committing  to  the principles and  targets  of Hanoi Core  Statement.  By  implementing work  on  the  “quick wins”  as well  as initiating  longer  term  work  on  government  systems  the  PGAE  has  made  a  tremendous contribution  to  the  aid  effectiveness  agenda.  All  concerned  should  be  congratulated  on  the PGAE’s achievements and by backing their joint HCS commitments with action.   During  the  lifetime  of  the  PGAE  Vietnam  has  maintained  its  remarkable  development  and poverty reduction record. It is now expected to become a middle‐income country by the year 2010, several years ahead of previous estimates. With WTO accession Vietnam  is also  internationally recognised  as  integrated  into  the global  economy  and moving  rapidly  to  full market  economy status.  Further  evidence  of  Vietnam’s  increasing  level  of  international  stature was  the  recent election of Vietnam as a Non‐standing Member of the UN Security Council.  

An example of how this progress affects development assistance occurred in October 2007 when the World Bank announced that Vietnam’s development progress and increasing creditworthiness had made  it  eligible  to  access  International  Bank  for Reconstruction  and Development  (IBRD) financing ‐ available to middle income countries. Other donors will also be considering changing their  aid  policies  to  Vietnam  as  Vietnam  approaches  middle‐income  country  status.  These transition issues now to be discussed as part of the PGAE agenda. 

In addition, four regional consultation meetings which were carried out from June to September 2007  in Mauritius, Ghana, Honduras  and  the Philippines  on Paris Declaration  implementation have affirmed that although progress has been made more effort was required in all areas. From donor  behaviour  change  to  stronger  application  of  new  aid  modalities;  increasing  aid predictability  and  supporting  capacity  development;  improving  aid  coordination  and 

Aid Effectiveness – Moving up to the higher level    

31

Page 37: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

strengthening  monitoring  and  evaluation  of  PD  implementation.  The  report  of  Independent Monitoring Team (IMT) recognises a similar trend  in Vietnam. It recognizes significant progress and  achievement  on  the  implementation of  the HCS, but  also  recommends  that  to  achieve  the HCS targets, the PGAE should renovate itself.  In Vietnam, some donors and groups of donors have already responded actively. For instance the EU  and  its member  states  have  adopted  “The  EU Code  of Conduct  on Complementarity  and Division  of  Labour  in  Development  Policy”.  This  is  based  on  the  principle  that  donor complementarity  is of paramount  importance  to  increasing aid effectiveness. Thus  it  is expected that donor complementarity and division of labour will be an important part of the future PGAE agenda. 

Vietnam’s development partners are proud to have assisted in its remarkable transition. They also fully recognise the efforts made by the government to continually  improve the mobilisation and utilization  of  development  agencies’  support.  In  the  future  these  efforts must  recognise  that Vietnam’s  development  needs  and  options  are  changing  rapidly.  It  is  in  this  spirit  of mutual commitment  to  improving  the  quality  and  appropriateness  of development  assistance  that  the renovation of the PGAE will be undertaken.  

4.4  How should the PGAE renovate itself? 

The renovation of the PGAE will not alter its focus on achieving the PD and HCS targets Instead the  PGAE  has  taken  this  opportunity  to  review  past  successes,  remaining  challenges  and  the changing development context. This has led to identification of six immediate PGAE priorities:  

(i) supporting  the  Government  to  continue  economic  and  social  reforms  and  further strengthen  country  systems  and  policies  to meet  the  demands  of  a middle‐income, market orientated country; 

(ii) Stimulate  the  improvement  of  public  financial  management  and  increasing  aid predictability to promote the application of new aid modalities;  

(iii) Increased  support  for  capacity  development  including  ODA  management  and coordination capacity, particularly at sub‐national levels;  

(iv) Improving  ODA  program/project  performance  through  harmonization  and simplification of procedures between the Government and donors; 

(v) Taking more advantage of donor complementarity and division of labour; and  

(vi) Scaling up M&E activities in ODA programmes and projects to monitor the progress of PD  and  HCS  implementation.  This  will  include  joint  impact  evaluations  between Government  and  donors  based  on  the  Governments’  M&E  framework  for  ODA programmes and projects in the 2006‐2010 period. 

Aid Effectiveness – Moving up to the higher level    

32

Page 38: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

The PGAE needs to renovate its working arrangement to ensure:  

(i) Broader participation of the relevant Vietnamese agencies;  

(ii) Engagement  of  international  support  groups  and  partnership  groups  in  the  PGAE agenda;  

(iii) Facilitating CSO’s to contribute to greater aid effectiveness. 

It is proposed that in future PGAE meetings should be organized every quarter. They will focus on strategic direction, policy and resourcing  issues. The PGAE will continue to be supported by thematic  and  sectoral working groups, but with  clearer delegated mandates defined by  the  six priorities shown above. 

Once the renovation plan has been adopted by the PGAE, a joint working team will be established to develop  the medium‐term program  for  2008‐2010. This will  then be  circulated  to  the PGAE consultation and approval in early 2008. 

4.5  How to mobilize resources to the HCS?  The work  above will  require  resources.  So  far  the TG’s  and  other  activities have  relied  on  the efforts and funds of individuals, agencies and the CCBP, often on an ad‐hoc and voluntary basis. An  additional  issue  noted  in  the  final  draft  IMT  report  is  that many  of  the  individuals  and agencies  who  committed  time  and  support  to  the  HCS  have  moved  on  and  have  not  been replaced. In addition the CCBP will be drawing to a close next year.   It is critical for the achievement of the HCS that these additional resources are now committed to ensure that the renovated PGAE and its working groups have the resources required to fulfil their mandates. Resources are required  to develop government systems, and help  line ministries and donors  put  the  HCS  principles  into  action.  The  CCBP  remains  the  best  placed  vehicle  for supporting these activities.  The  PGAE  therefore  recommends  that  the  CCBP  and  TG  budgets  and work  programmes  be revised to extend their mandates, resources and duration – to ensure comprehensive achievement of  the  HCS  targets.  To  take  this  forward  the  joint  working  team  established  to  develop  the medium‐term program for 2008‐2010 will develop a detailed budget estimate for further support. This will be circulated in early 2008, for adoption and financing by the PGAE members. 

Aid Effectiveness – Moving up to the higher level    

33

Page 39: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

Appendix ‐ Summary Report of JPPR V 

 The Fifth  Joint Portfolio Performance Review  (JPPR V) aimed  to  improve  the delivery of aid  in Vietnam.   It was carried out  jointly with close working between  the ODA Inter‐Ministerial Task Force  of  the Government  (IMTF)  and  the  Five Development  Banks we  represent  representing around  80  percent  of  the  total  ODA  commitments  to  Vietnam.    Given  the  importance  of infrastructure projects in our portfolio the JPPR V focused on reviews of transport; energy; urban water/waste water;  irrigation  and  rural water  supply;  and  infrastructure  in Ho Chi Minh City. This JPPR is a remarkable example of our joint efforts to improve the effectiveness of aid delivery in Vietnam and further strengthen our relationship.  Five Banks’ Portfolio:  Current Status. The analysis of the overall performance of the Five Banks’ portfolio shows that Vietnam is using its ODA resources well.  Programs and projects co‐financed by  the  Five  Banks  uniformly  achieve  their  development  objectives  and  the  outcomes  are satisfactory and sustainable.  Slow implementation and increasing undisbursed balances remains a major source of concern.   By  the end of December 2006,  the active portfolio of  the Five Banks amounted to approximately US$13 billion. Annual disbursement, including program lending was around US$1.2 billion (about 9.2 percent of the total portfolio).  This slow implementation pace is the core concern of  the IMTF and Five Banks.   The efficient and timely  implementation of ODA programs  and  projects  is  not  only  necessary  to  support  the  attainment  of  annual  economic development  targets and  improving  living  conditions  for  the poor, but  is also key  to attracting increased levels of ODA and FDI funding.  Recommendations  to  Improve  Implementation  Performance.  The  Government  and  Donor Community have  committed  themselves  to  significantly  improving  the  rate of  implementation, but not at the cost of quality and sustainability.  For that reason, the JPPR was designed to focus on key areas  for  improvement and  the production of concrete  recommendations. The  three key areas identified for attention were: 

1. Simplify and increase consistency in the Government systems.  One coherent and consistent set of ODA management decrees and its implementation circular with other ODA related legal documents  in procurement,  financial management  and MoC  guiding  regulations.  In  future joint work on the Law on Public Investment was recommended.   

2. Accelerate  preparation,  appraisal  and  approval  ‐  three  recommendations.  (i)  simplify  the project  detailed  outline  and  include  the  preparation  timetable  and  budget   Second,  (ii)  adopt  the  jointly  developed  common  feasibility  study  guidelines  to  streamline appraisal;  (iii)  adopt  a  “one‐stop  appraisal”  process  based  on  line  agency  approval  of  the Feasibility Study. Combined  these measures would  reduce preparation  time by around one year. 

 

Aid Effectiveness – Moving up to the higher level    

34

Page 40: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

3. Agree  and  provide  guidance  on  treatment  of  ODA  under  the  Procurement  Law.  Procurement  remains  the most  important bottleneck.  It was  recommended  to  revise Decree 111/2006/ND‐CP guiding implementation of Procurement Law to reduce the gap between the Government and donors’ systems. 

We  recognize  that many  of  these  issues  also  affect Government  investment  programs. We  are jointly committed to improving performance and accelerating Vietnam’s development.  

JPPR Fast Track Actions  

Challenges  ODA Fast Track Actions  Who/How 

A.  Accelerate Project Preparation, Appraisal and Approval 

1.  Misalignment between Government and Five Banks procedures 

1. Streamline approval process and supporting document: 

• Harmonize Project Detailed Outline (GoV) and Project Concept Note (5 Banks) 

• Institutionalize Guidelines for the preparation of the Feasibility Study/Project Investment Document 

• Synchronize GoV and 5 Banks approval process:  (a) upstream approval of the ODA Requesting List by Prime Minister; and (b) approval of Feasibility Study by Line Agency prior to Negotiations 

MPI / PGAE New Guiding Circular on Decree 131/2006/ND‐CP 

2.  Inadequate funding of preparation stage, including for resettlement activities 

 

2.  Include in Project Detailed Outline Approval by the PM project preparation timetable and funds, including Government Counterpart Funds, Preparation and Technical Assistance Grants and other Project Preparation Facilities. 

MPI / PGAE New Guiding Circular on Decree 131/2006/ND‐CP 

3.  Inconsistent framework for public investment management 

3. Delink for ODA Programs and Projects the requirement of Basic Design from the approval of the Feasibility Study 

MPI/MOC/PGAE New Decision 

4.  Cumbersome and heavily centralized approval procedures of Program / Sector Loan 

4. Base the approval of Program/Sector Loan on general program frameworks 

  Allow delegated management of final list of sub‐projects 

  Consider applying these retro‐actively for on‐going project 

MPI / PGAE New Guiding Circular on Decree 131/2006/ND‐CP 

B.  Accelerate Project Start‐up 

5.  Still limited empowerment of project entities in project preparation and start‐up 

5. Identify the Project Owner for all Five Banks’ projects 

  Ensure that maximum delegation of power is institutionalized in line with Decree 131 – Circular 

LA / 5 Banks Special Correspondence 

Aid Effectiveness – Moving up to the higher level    

35

Page 41: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

Challenges  ODA Fast Track Actions  Who/How 

03 

6.  Disconnect between preparation and implementation teams within the Line Agencies and limited empowerment of decentralized entities in project preparation 

6. Early establishment of the PMU by the Project Owner 

• Same PMU(s) for preparation and implementation • Early appointment of Project Director and Key Staff • Adequate budget provided for PMU operation (or 

continuation in the case of repeater project)  

MPI / PGAE New Decision 

7.  Widespread adoption of a sequential approach, rather than parallel approach, to implementation in particular in the early stages 

7. Advance Action   Allow procurement (primarily for consultant 

services, technical assistance and key packages), resettlement and other key project start‐up activities to commence after Government approval of Feasibility Study and formal commitment of Donor 

 

MPI / PGAE New Decision 

8.  Long delays in procurement planning and processes because or remaining gaps between new procurement law and related decrees and donor guidelines 

8. Identify clearly remaining differences between Government and Donor regulations 

• Provide clear guidance/training during the project launch to Project Owners, as well as auditors and inspectors, on how to deal with major inconsistencies 

• Ensure awareness that in case of conflicts between Government and Donor regulations the agreed procedures in the legal agreement prevail 

 

MPI / PGAE New Decision 

C.  Accelerate Project Implementation 

9.  Excessive reliance on Construction Cost Norms for the preparation of cost estimates in the procurement process (as per Art. 37 and 38 “a successful bidder must have a winning price that does not exceed the approved estimated price of the procurement package”) 

 

9. Use Article 3.3 of the Procurement Law for ODA programs and projects to:  

• Reform the cost norms system through establishing a system whereby costs are controlled at the overall project level rather than for individual packages (this would allow reallocations within the project 

• allow winning bids to exceed the approved estimated price of the procurement package (exception to Articles 37 and 38); 

• Higher bid prices should not be a valid reason for rejecting bids 

• Allow procurement with variable costs (consider price adjustments clause in contracts) 

MPI / PGAE Revise Procurement Law (N. 61) and Implementation Decree (N. 111) In the meantime, issue a new Decision applicable to ODA Projects in accordance with Article 3 

Aid Effectiveness – Moving up to the higher level    

36

Page 42: Aid Effectiveness - Moving up to the higher leveleeas.europa.eu/archives/delegations/vietnam/documents/eu...World Bank Office in Vietnam Co‐Chairs of the Partnership Group on Aid

Partnership Group for Aid Effectiveness                            Report 2007 

Challenges  ODA Fast Track Actions  Who/How 

 

10. Long delays in the selection of national consultants as government consultancy rates are well below the market 

10.   Remove/Revise the restrictions on consultancy rates on ODA Programs and Projects so that market rates can be paid for high quality consultant services 

MOF / 5 Banks New Decision 

11.  Long delays in internal payment processing at various levels, and in particular for the preparation of final accounts which requires a large volume of supporting documents 

11.  Accelerate payments: • Remove non essential expenditure checks (ex. 

National Treasurer Office) • Enforce business standard • Relax the requirements in order to speed‐up the 

liquidation of completed contracts or contracts close to completion 

• Lump sum items should be treated in line with the payment conditions specified in the contracts 

 

MOF / 5 Banks New Decision 

12. Slow clearance and compensation processes 

12.  Pilot the establishment of a separately funded land acquisition/resettlement project, implemented in accordance with guidelines that would meet the Five Banks’ due diligence requirements 

 

LA / 5 Banks Pilot basis 

 

Aid Effectiveness – Moving up to the higher level    

37