Agile software development in an earned value world: a survival guide Jeffrey Kantor a , Kevin Long b , Jacek Becla c , FrossieEconomou a , Margaret Gelman d , Mario Juric e , Ron Lambert a , K. Simon Krughoff e , John D. Swinbank f , and XiuqinWu g a LSST Project Management Office, Tucson, AZ, U.S.A. b Longhorn Industries, U.S.A. c SLAC National Laboratory, Menlo Park, CA, U.S.A. d University of Illinois at Urbana-Champaign, U.S.A. e University of Washington, Seattle, WA, U.S.A. f Princeton University, Princeton, NJ, U.S.A. g Infrared Processing and Analysis Center, California Institute of Technology, Pasadena, CA, U.S.A. ABSTRACT Agile methodologies are current best practice in software development. They are favored for, among other reasons, preventing premature optimization by taking a somewhat short-term focus, and allowing frequent replans/reprioritizations of upcoming development work based on recent results and current backlog. At the same time, funding agencies prescribe earned value management accounting for large projects which, these days, inevitably include substantial software components. Earned Value approaches emphasize a more comprehensive and typically longer-range plan, and tend to characterize frequent replans and reprioritizations as indicative of problems. Here we describe the planning, execution and reporting framework used by the LSST Data Management team, that navigates these opposite tensions. Keywords: Project Management, Software Engineering, Agile Process, Earned Value 1. INTRODUCTION The Large Synoptic Survey Telescope (LSST) * project is a proposed large-aperture, wide-field, ground-based telescope that will survey half the sky every few nights in six optical bands. The 8.4-meter telescope will be located in the Andes mountains near La Serena, Chile. [1] The 3.2 Gpixel camera will take 6.4 GB images every 15 seconds, resulting in 15 TB of new raw image data per night. The focal plane consists of 189 science CCDs with 16 channels each to achieve a readout of all data in 2 seconds. After taking into account unusable nights, slew time, and other factors, this will produce 7 PB of new data each year to be processed. [2] The LSST Program is composed of four subsystem projects as well as an overall Program Management Office, Systems Engineering effort, and Commissioning project, each of which requires project management and control. The subsystem projects are: * http://lsst.org Modeling, Systems Engineering, and Project Management for Astronomy VII, edited by George Z. Angeli, Philippe Dierickx, Proc. of SPIE Vol. 9911, 99110N © 2016 SPIE · CCC code: 0277-786X/16/$18 · doi: 10.1117/12.2233380 Proc. of SPIE Vol. 9911 99110N-1 DownloadedFrom:http://proceedings.spiedigitallibrary.org/on11/11/2016TermsofUse:http://spiedigitallibrary.org/ss/termsofuse.aspx

Transcript of Agile software development in an earned value world: a ... · Agile software development in an ea...

Page 1: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

Agile software development in an earned value world: a survival guide

Jeffrey Kantora, Kevin Longb, Jacek Beclac, FrossieEconomoua, Margaret Gelmand, Mario Jurice, Ron

Lamberta, K. Simon Krughoffe, John D. Swinbankf, and XiuqinWug aLSST Project Management Office, Tucson, AZ, U.S.A.

bLonghorn Industries, U.S.A. cSLAC National Laboratory, Menlo Park, CA, U.S.A. dUniversity of Illinois at Urbana-Champaign, U.S.A.

eUniversity of Washington, Seattle, WA, U.S.A. fPrinceton University, Princeton, NJ, U.S.A.

gInfrared Processing and Analysis Center, California Institute of Technology, Pasadena, CA, U.S.A.

ABSTRACT Agile methodologies are current best practice in software development. They are favored for, among other reasons, preventing premature optimization by taking a somewhat short-term focus, and allowing frequent replans/reprioritizations of upcoming development work based on recent results and current backlog. At the same time, funding agencies prescribe earned value management accounting for large projects which, these days, inevitably include substantial software components. Earned Value approaches emphasize a more comprehensive and typically longer-range plan, and tend to characterize frequent replans and reprioritizations as indicative of problems. Here we describe the planning, execution and reporting framework used by the LSST Data Management team, that navigates these opposite tensions.

Keywords: Project Management, Software Engineering, Agile Process, Earned Value

1. INTRODUCTION

The Large Synoptic Survey Telescope (LSST)*project is a proposed large-aperture, wide-field, ground-based telescope that will survey half the sky every few nights in six optical bands. The 8.4-meter telescope will be located in the Andes mountains near La Serena, Chile.[1]The 3.2 Gpixel camera will take 6.4 GB images every 15 seconds, resulting in 15 TB of new raw image data per night. The focal plane consists of 189 science CCDs with 16 channels each to achieve a readout of all data in 2 seconds. After taking into account unusable nights, slew time, and other factors, this will produce 7 PB of new data each year to be processed.[2]

The LSST Program is composed of four subsystem projects as well as an overall Program Management Office, Systems Engineering effort, and Commissioning project, each of which requires project management and control. The subsystem projects are:

*http://lsst.org

Modeling, Systems Engineering, and Project Management for Astronomy VII, edited by George Z. Angeli, Philippe Dierickx, Proc. of SPIE Vol. 9911, 99110N

© 2016 SPIE · CCC code: 0277-786X/16/$18 · doi: 10.1117/12.2233380

Proc. of SPIE Vol. 9911 99110N-1

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 2: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

• Telescope and Site • Camera • Data Management • Education and Public Outreach

This paper focuses on the management and software development processes for the LSST Data Management System (DMS)[3] but software development in some other parts of the LSST project follow similar processes. Increasingly, “Big Science” astronomy and astro-physics projects are no longer treating the data management aspect as an afterthought to be done once the telescope is in place, and LSST definitely falls into this class. LSST features a large data management project by optical astronomy standards, processing and archiving over 70 petabyes of image data and producing over 20 petabytes of catalogs annually, and generating 2 million transient alerts per night. Over the 6-year construction and commissioning phase, the DM project is estimated to require 600,000 hours of engineering effort. In total, the DMS cost is approximately 60% hardware/system software and 40% labor.

LSST Data Management combines: large-scale, multi-year equipment, communications, and services procurements; off-the-shelf and customized middleware; custom scientific, algorithm-intense software; all integrated into a complex system. Managing the entire effort requires more formal mechanisms, and if, as LSST is, the project is funded by International and/or Federal entities, that includes the requirement to perform Earned Value Management (EVM)†. EVM requires significant up-front planning of the entire effort, to create a resource-loaded, scheduled baseline plan, against which progress is tracked and analyzed in terms of cost and schedule. EVM also discourages purely “level of effort” planning, where the plan only indicates a team working for some time period and deliverables are not specified.

Meanwhile, software development best practice is currently to employ an “agile process”‡, which typically implements iterations of short, intensive “sprints” to develop the software incrementally, and to address emerging requirements and iterative design. Agile process does not encourage long-term up front planning, rather it focuses on the near-term, with the longer-term aspects left “fuzzy” or level of effort against a prioritized backlog.

So, the question this paper attempts to address is “How to marry these two in such a way as to get the benefit of both?” There have certainly been prior attempts to address this question, as a search of the web will attest, and the difficulty in making this “match” is well documented.[4] In LSST, a fundamental requirement is that the Agile – EVMS integrated process is fully EIA-7482 compliant. Sadly, many of the attempts to integrate coming from the Agile community re-invent the definition of EVM in ways that are fundamentally non-compliant, and as such are non-starters for LSST.

2. LSST DATA MANAGEMENT EVM PLANNING PROCESS

Since the DM software elements are a mix of off-the-shelf system software and adapted middleware, plus custom applications, each element has many interfaces to the other elements. In addition, the data quality requirements of LSST necessitate that some of the algorithms require some advancement over the current state of the art, and all of them require scalability to the LSST data volumes. Due to complexity of the system and to support EVM, a multi-level Work Breakdown structure has been created, as shown in Figure 1. Each institution in the DM team is typically responsible for 1 or more Level 2 WBS elements, and each institution has a Technical/Control Account Manager (T/CAM) responsible for planning, estimating, monitoring and EVM reporting for that Level 2 WBS element.

†Earned Value Management Systems ANSI/EIA-748-C Intent Guide, National Defense Industrial Association (NDIA) , April 29 2014 ‡https://en.wikipedia.org/wiki/Agile_software_development

Proc. of SPIE Vol. 9911 99110N-2

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 3: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

Applicati• Scie• Pipe standa• Data• Met• Obje Middlew• Port• Prov behave• Pres• Cust

shelInfrastruc

• Distr• Diffe alertingaccess • Off-t Softwa

The LSST Maoperations prequirementlevel designsdatabase, datools).

For these reaperformance2 WBS) mapsthe inter-deperform the process is ma

As the releagrained devepart of the p

on Layer (LDM-ntific Layer

elines constructerd “parts”, i.e. Aa Products repreadata extendab

ect-oriented, pyt

ware Layer (LDM-tability to clustervide standard see consistently (eserve performantom Software onf Software cture Layer (LDM

ributed Platformerent sites specig, data release p

the-shelf, Commre, Custom Inte

anagement andplans, plus LSSTts, the DM teams for the infrastata transfer, et

asons, the softe, and data quas the developmpendencies fowork. This pl

anaged.

se cycle proceelopment taskslan where the

151)

ed from reusableApplication Framesentations stanle without schemthon, C++ Custo

-152) rs, grid, other rvices so applica.g. provenance)

nce (<1% overhen top of Open So

M-129)

m alized for real-tiroduction, peta-

mercial Hardwaregration

Figure 1

d System EnginT project-level m has created tructure (hardwtc.), and the ap

tware is being ality increasingment work in tor critical pathan is captured

eeds, the T/CAs and very fineAgile Process

e, mework

dardized ma change m Software

ations

ad) ource, Off-the-

me -scale data

e &

: Data Managem

neering procesrisks and milea set of designware and syste

pplications (sof

developed viag over time. Ethat area into h scheduling, d in the LSST Pr

AM creates ane-grained deveis most appare

ment System Arc

ss shown in Figestones to crean documents coems software),ftware pipeline

a a series of prvery release cy1 to 3-month dand finally loroject Manage

n even more dlopment steps

ent, which will

chitecture and W

gure 2 flows date the DM Sysovering the DM, the middlewaes, algorithms,

rioritized, increycle, the T/CAdevelopment aads the activi

ement Control

detailed plan fs, the latter as be discussed i

WBS

down LSST syststem requiremM System as a are (software f, data structure

emental releasM of each majactivities. Theities with the System (PMCS

for each activishort as 2 – 20n a later sectio

tem requiremements. From th

whole, and sufor parallel proes, user interfa

ses, with functjor area of wo

e T/CAM then cresources ne

S), where the f

ity, adding mo0 days. It is in on below.[5]

ents and his set of bsystem

ocessing, aces and

tionality, rk (Level captures eded to full EVM

ore fine-this last

Proc. of SPIE Vol. 9911 99110N-3

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 4: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

A “Roadmapbe achieved WBS elemen

p”[6] has been din each releas

nt milestones o

Figure 2

developed whise and is depic

or KPM, matrixe

2: Data Managem

ch defines thected in Figuresed by increme

ment EVM Plann

e major milestos 3 and 4. Thental release cy

ning Process/Lev

ones and key pe granularity oycle of 3 – 6 mo

vels

performance mof the Roadmaonths.

metrics (KPM) p is Level 3 or

that will r greater

Proc. of SPIE Vol. 9911 99110N-4

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 5: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

Figure 3: LSST

Figu

Software Devel

ure 4: LDM-240

opment Roadm

DM Key Perform

ap Milestones(L

mance Metrics

LDM-240)

Proc. of SPIE Vol. 9911 99110N-5

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 6: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

ButlgBCW

LlemxolI I,....t eR:'k.1 333alIriny Pr:uwB SW.SIYLS\ 15.311.74 1.18.

.LJ WA!.Yn LlE 'h^.

/ Sind

U J Vein

a.1121Fr::'aF.anSm:::N4:eÓ Writ Wpm :abLSloiYOPo

.nM,15rkp

111

T.M'EIII

5

. E1

Ill

411 ' =I. F

IA;.r-11

II51 L 9

1 o 1 0241,0101or rill On

1 051:01011 051:020

Oa

1 o1rld m a

N 051:0Ea

\Mnt Mu__e9.kp1i-1ÍCreate Epic In LIRA

5 OÁ1E'1:M.9riLwrx. ,

2) Complete Resource Loading Workbook

EarnedBCWP

/IRA

tr1.,rrxa.Ramr.rwrnrraaia

ti/1) Status Stories in BRA Completed

6

\ 1ti.a4w.., lPW

2) Stories are loaded inPrimavera as activity teps

ti/3) Status is Integrated into Cobra at the Work Package leveland the basis for the Earned (BCWP) Calculation

What systems

WBSIWP

LucLmcm9102401.01

BudgetBOWS

55,460,5155.58,0535516,4605344553546p915102.3235365.365

$339445564.192

531.882

c:>costs 2)

into)ACWP)

i l-\n/Y

fDeltek Cobrai

9102401.02

rla4snmeeu

Nrru,r9nlavl

L02C.029102402.01

1/Accounting records all actual Monthly export of Actuals is loadedCobra and is the basis for Actuals

9102402.022_02G039102CO3.01.102c 0311

P'Sci.; 0 erdsA \

leal V3) Epics and resources are loaded into Primavera

4) Resource time-phasing is Baselinedin Cobra as the Budget )BCWS)

supply these numbers ? ??Cumulative ta Date

Earned Actuals SV CVBCWP ACWP

54,625,024 54.842,382 15835,2911 15217,35.15844,155 $935,625 1513,2981 15131,63015345.968 5341.531 5229.508 54,597598.188 5254.2551fflingErr

5381p45 5134,693 (7.6.4061 5244,9495102.323 55.340 $0 $933¢35238.919 5131.353 (586446) $14356'$1sl,ln $262.466 I$188,2641 (5112.2851560.023 5131.343 154.3651 1535330531.892 $10548 so 52133

3. ORGANIZATION

Tools

The LSST EVMS depicted in Figure 5 encompasses the processes and technical systems that integrate and quantitatively measure project cost and schedule performance against a project execution plan known as the Performance Measurement Baseline (PMB). Measuring and maintaining the PMB uses all of these tools in conjunction and under strict guidelines.

The EVMS technical systems which are used to reach this goal include the following:

• CASNet – AURA Financial System • Primavera Project Planner (V8.3) - Schedule • Cobra (V5.1) - EVMS • Docushare – Document Control, Document Repository • Drupal – LSST Change Control Board Interface • Risk Register - Internally developed software used to manage risks and opportunities • eCAM – Internally developed software used as the T/CAM’s interface to all cost and schedule data • JIRA§ – Software project tracking with agile tooling for software teams

Figure 5 LSST PMCS tool set

Work Breakdown Structure

The LSST WBS is a product-oriented, hierarchical structure that identifies the hardware, software, services, and all other deliverables required to achieve the LSST Project. The LSST WBS is the primary structure for managing

§https://jira.lsstcorp.org/secure/Dashboard.jspa

Proc. of SPIE Vol. 9911 99110N-6

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 7: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

performance against the PMB and is the framework for defining and assigning work, developing schedules, estimating and budgeting, and controlling changes. The WBS elements that comprise LSST control accounts are defined at level 4 but in some cases details in the IMS are at a lower level.

The WBS dictionary is a narrative attached to the WBS that describes the scope, deliverables, and associated key milestones of each work element identified. The WBS dictionary defines each element to at least the control account level in terms of the content of the work to be performed.

The WBS has been added to JIRA as a custom field associated with Epics, Meta-Epics, and Milestones. This is a required field that ensures the element in JIRA is associated with the correct WBS in the PMCS tools.

Organizational Breakdown Structure

The LSST Organizational Breakdown Structure (OBS) shown in Figure 6 is a hierarchical structure that defines the Institutions/major contracts where the work will be planned and controlled. The OBS identifies the accountability, responsibility, management, and approvals of all authorized work scope. While the OBS is not directly called out in JIRA it is possible to infer the OBS based on the “Team” code that is assigned to an Epic.

Code Description1. LSST Construction Phase

1.01 LSST1.02 SLAC1.03 IPAC1.04 NCSA1.05 UW1.06 Princeton1.07 NOAO1.08 Adler1.09 UCD1.10 Arcadis1.11 UA1.12 (unassigned)1.13 RAL1.14 Purdue1.15 PFLOW1.16 REUNA

Figure 6 LSST OBS Structure

Proc. of SPIE Vol. 9911 99110N-7

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 8: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

OBS

1.01

1.02

1.03

1.04

Control Accounts

[

CA

As shown in Figure 7, a control account (aka cost account) is a management control point at which budgets (time-phased resource plans) and actual costs are summarized and compared to earned value for management control purposes. A control account is a natural management point for planning and control since it represents the work assigned to one responsible organizational entity for a single program WBS element. A control account manager maintains responsibility for an individual control account and all technical, cost, and schedule elements in work Packages below it.

Figure 7 Graphical Representation of Control Accounts.

Work Packages

LSST Work Packages are the intersection of the current cycle and a WBS element (whereas planning packages are the intersections of future cycles and WBS elements). Work Packages are defined at the level directly under the Control Account and specifies what work is planned, measures progress on that work, and computes the associated earned value. Actuals for LSST will be aggregated and loaded at the work package level. Once Epics from JIRA are imported into the IMS and are resource loaded they will be assigned to the current active Work Package for their assigned WBS. Many activities can be assigned to one Work Package which roll up to represent the total dollars and hours assigned to the Work Packages. If changes need to be made to the baseline resulting from rolling wave planning, a change request will be prepared and submitted for management review and approval. Work Packages are configured using the following criteria:

• Has a limited duration within a reasonably short time span • Has scheduled start and completion dates • Has resource requirement separated (e.g., labor, material, contracts) in a way that allows the EV reporting process to accurately measure progress • Has a budget or an assigned value expressed in hours and/or dollars • Reflects the way in which work is conducted and has meaningful work products • Has a one to one correlation to an accounting charge number in the LSST accounting system • Uses a single EV method

Control Accounts

Proc. of SPIE Vol. 9911 99110N-8

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 9: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

Planning Packages

LSST Planning Packages are defined at the level directly under the Control Account and specifies what work is planned. Planning Packages are reserved for future activities that cannot be clearly defined when the project baseline is set. Work that is beyond the current detailed planning period will reside in planning packages until they are converted to detailed work plans per a rolling wave process. The Planning Packages consist of a work scope, schedule, and time-phased budget normally at a higher level than individual Work Packages. Planning Packages do not require the detail found in Work Packages since, by definition, such details are not known. The Data Management Long Range Planning (DLP) project specifies the key milestones that are tied to planning packages in the IMS.

Technical/Control Account Managers (T/CAMs)

The LSST T/CAMs are responsible for the planning and management of the technical scope, schedule, and budget for assigned control accounts. They will provide timely input to the Project Manager in the formats described in this plan and will keep the project management staff informed of their work progress and issues or concerns, risk assessment, tracking methods, variance analysis, and estimate-to-complete/estimate-at-complete management processes.

Milestones

All significant development stages of each Planning Package are tracked through milestones. Each Planning Package has at least one milestone, used to mark the completion of a given Package. It is not uncommon to have multiple milestones per Package to track progress along the way. Each milestone has a description, and due date; it has no duration, and no resources assigned to it.

Critical Milestones are defined as Level 1 milestones (NSF reporting) and are watched and reported on monthly in the LSST monthly construction report. Level 2 milestones are coded to be managed at the project level, and Level 3 and 4 are watched at the WBS subsystem and T/CAM levels respectively.

Each activity within a Planning Package that involves a cross-team dependency is required to end with a milestone; this includes activities related to delivering software components, hardware, and services. Relationships between milestones, as well as between milestones and planning packages are captured in JIRA: milestones typically block planning packages, milestones can also relate to other milestones.

Figure 8 depicts the relationships between all of the PMCS Schedule, EVM, and JIRA Agile objects described in this section, including control accounts, work packages, planning packages, and milestones.

Proc. of SPIE Vol. 9911 99110N-9

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 10: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

Integrated M

The Integratreflecting thmeasuremenenables the interim even

The IMS is suthe IMS, PMPrimavera scprofiles in thmilestone co

Time Phased

The assignmeIMS is integrbudget in Cowork packag

Earned Value

Each establisassigned an Ebeen perform

Master Schedu

ted Master Sche interdependnt baseline (PMCritical Path Mts or deliverab

ubject to configMB, and technicheduling tool e PMB and the

ompletions.

d Budgets

ent of budgetsrated into Cob

obra is defined es.

e Techniques

shed work pacEVT of Percentmed, and what

F

4. PLA

le

chedule (IMS) dencies betwe

MB) used to trMethod that isbles.

guration contrical baseline a(P6). The timee schedule stat

s to scheduled bra and as par

as the Budget

kage will havet Complete as tt is remaining.

Figure 8 Field m

ANNING, SCH

is a networkeen tasks andack progress,

s used to iden

ol as part of thare kept synch-phased worktus drives the

activities in tht of the PMB at Completion

one correspothe stories assThe following

mapping across

HEDULING, AN

k of tasks linkd milestones. forecasts, andtify the progra

he baseline. Thhronized. The s

packages are iEV reporting a

he IMS produceit allows budg

n and is subdiv

nding Earned Vigned to the EEVTs are used

s the PMCS

ND BUDGETIN

ked from progThe IMS is th changes throam critical pat

e change contschedule is baidentified and against PV base

es a time phaseget performanided into cont

Value Techniqpic make it verby LSST:

NG

gram start thrhe foundationughout prograth, as well as d

rol process enaselined and sused to build t

ed on physical

ed budget plance to be measrol accounts, p

ue (EVT). Anyry easy to quan

rough programn of the perfoam execution. driving paths t

sures that elemtatus is postethe planned vapercent comp

n. The resourcesured . The Intplanning packa

y Epic from JIRAntify the work

m finish, ormance The IMS to major

ments of d in the

alue (PV) plete and

e loaded tegrated ges, and

A will be that has

Proc. of SPIE Vol. 9911 99110N-10

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 11: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

A – Level of Effort

This EVT assumes that when a work package starts, its progress will not deviate from the original budget spread. There are no limitations upon the applicability of this technique for measuring progress, but it is most suitable for only a small number of work packages that are by their nature unmeasurable. By definition, the value earned by an open work package using this EVT is equal to its to-date budget.

C - Percent Complete

Used to manually enter the completion status of the work package in percent each status period. When using method C the subordinate tasks in the schedule should have associated activity steps to help quantify the work performed.

K – Planning Package

This EVT results in always calculating an earned value of zero for the item. Use this EVT if one does not want the work package to earn any of its budget, regardless of its status.

Executing the Rolling Wave Plan

The estimated effort for future work exists in the time phased plan as 6-month cycle planning packages along with estimated DLP milestone completion dates. Planning packages were originally baselined from individually estimated via UML-based specifications. These planning Packages are converted to detailed work as planned in JIRA in the rolling wave process.

The Activities (epics) loaded into the IMS typically have durations on the order of 1 – 3 months. These Epics are estimated individually via developers though the Agile process. Each Epic is further detailed in steps (stories) of 2 – 20 days each. The development team T/CAMs plan each 6-month cycle in terms of Epics, Stories, Bugs, etc. in JIRA which doesn’t require CCB approval. The T/CAMs and individual developers only work within JIRA using the agile process during the cycle. This allows them real-time access to record progress and plan future work while data input into the PMCS is controlled by project controls (monthly for status and as needed for change control). Resource estimation and assignment to Epics is done outside of JIRA (in Excel) and is integrated into PMCS. The T/CAMs complete a spreadsheet to assign resources and hours to the specific Epic(s)/Activity(s) being imported for the upcoming cycle as shown in Figure 9.

Proc. of SPIE Vol. 9911 99110N-11

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 12: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

BEpc Dao[epua4

-, 1 I J K L M N

nowt* Wax, Bows]O 0 RS

spialsT U V W X

WBSs 3 4 5 6 7 8

- Freemon M Pie0omc4 S Ma er B G4A B Dams G Mal M Own' R Wllkrs A Gskrun M PNraiek D WW1 PL'SRILPlIfikL{i LSTJICSA LST445SA LSERNCSA LSSENCSA LSCNCSA LSTNCSA LSGICSA IAAANCSA LIENCSA

emJadn la witty p06 Oep14..i 160 708 320 0 0 168 160 025 07 01 01DM-

...eM1

DM -2209 Comlwc Event Processing 124384124

960

96 9663 62

96 025 07 01 01020 070201

OM -1109 055 Soawre 40 40 0 0 40 025 07 01 01DM -1120 Slate Dugam 4 24 24 0 02C 07 01 01Sso.1120)

0 qÁ.1121 Reactor Event Serncet 1) 8 8 0 0250702011 D1Á.1122 Wnte logic. handler that err. mots b logthat

torts8 8 0 025 07 01 03

2 DM -2210 Con6guraam Management Poppet) 4 144 72 7.2 025 07 02 043 DM -1270 VMeen Maelrocl relgd-1210) 6 756 0 0 1 025070204a 0M -1274 Server Room Rteeeh (014-1274)5 014-1273 OpenSteck Decso m ent Plan (014-1273)

0

2 526

115200

00 23 29

320

3

2902C 07 02 04025 07 02 04

6 DM -2211 Setup wen 00010000 b 5100. Wei o 10 0 0 0 10 0 025 07 04 057 0441212 Implamr+4 took to aulheuun ac NCSA 4 30 0 0 0 30 0 025 07 0104B OM -2213 Storage PMUx and Akgnmem 200 200 50 60 60 60 0 0 025 07 02 059 01.42214 Fie System Research and ProIotypeg 400 100 160 100 760 127 127 127 127 127 127 025 07 02 OS

20 0642115 Fie Mnagemem Technology 200 280 47 47 47 47 47 47 025 07 02 051 DM -2216 Undmstad (ä+FS between data centers 12 , 0 o 12 0 o o 025 07 02 05

22 0-2217 Update Sang Model 44 44 73 7.3 73 72 7.3 7.3 02C 07 02 0423 0641252 Bare Oats Cerro. RoquwrnKBB 36 36 15 18 0 0 0 0 02C 07 01 0524 0662239 De.Nop use ewes Re TOWS 20 40 61 32 32 0 0 0 0 025 07 03 0825 0642240 150 Work26 0642224 Wde,No, Network Work 20

4020

6133

61 673.3 33

6.7 61 6.7 025 07 01 0233 33 33 025070106

30 TtYls 130 748 194 289.2 240 180 40 80 132 52 1343.2 562 581 753 666 400 34731

02

7MBS 'A E, ID 100501ty Piane

LSST e4-15-08.0200701.03.0200.5-1123

LSST BL 15-06.02007.01.01 0M-1187

LOST BL 15-08 020 07 01.02 0M-1260

Y11er.0856 COrrenOntaion

OCS 60ddewae startwData Movement It werarcncd Stange

'Cobra 1BP I d43gBIBD Total

0901111

6LM20701APROC $26.058 37

KLM20701A000C $3,12096

8/LM20701APROC 323,93789

LSST OL I5 -06 02C 07.01.01 D44-2206 Deploy and test n0,,cr6 esnubeon for ngllly processing tesibed KLM20701 A PROC 341 ,302 40

LSS7 BL 1546.02C07.01.01 044.2207 Alert Prodrellpn SoNWa

LOST B1.15-012025.07.01.01 DM-2209 OCS Software

LOST BL 150602C0701.03.0OMTC-4000Á130 Pipeline Cantrlrctlon 7oo0d Scope Plerrörg R5.1

Genera Status I Reearces I Rdalkeshps 'Codes I Ndebodc I Steps I Peetbect 'AIMS Does I Expenses I SManary

KLM20701 A PROC

KLM20701 A PROC

KLM20707APROC

33,47520$411200

31,46100

F12015 FY2016 F120I=1=lBter-resk COlnMmcawt

I OCSMkqewaeslaltp1 Data Mopelrnrf h Iferercht+

0 OFPloy and te3tnetw

0 Aden Prpdxtgn SMA0 OCS SOewere

6-1.

siosidHelormio

Resarce B1 Neme

nelwOrk etiolation tor rlgMly proee5sngleabed

LSEN-NCSA LSENNCSASoOwaeEngneer - NCSA PeoowìezS 01A308wareEnOneer 16000

LSTNCSA LST-NCSA.Sr. TecMicienNCSA Freemon M OM Sr. remotion 16000

Cost

Figure 9 Resource planning sheet and resource assignment in the IMS

At least one month prior to the start of the release cycle the Project Controls Specialist exports the upcoming cycle plan to the PMCS. The planning package for the upcoming cycle is removed and the resources are distributed across the new Epics that have been planned in JIRA. In the end, Epics become resource-loaded activities in PMCS and Stories become Activity Steps which are used for performance measurement of the Epic. These Activity Steps are essentially sub-activities that in general can be done in any order and represent portions of the total activity effort for the resource(s) assigned to that activity. All Stories in an Epic have Story Points (~ 4 hours of work/SP), setting their weight of each Step to measure total progress on an activity.

Figure 10 shows the IMS as captured in PMCS prior to the 6-month rolling wave plan, and Figure 11 shows the state after incorporation of the 6-month rolling wave plan.

Proc. of SPIE Vol. 9911 99110N-12

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 13: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

Attivlly ID Activity Name FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 Fl

2015 -10 -01 2016 -10 -01 2017 -10 -01 2018 -10 -01 2019 -10 -01 2020 -10 -01 2021 -10 -01 2022 -10 -01 20ZST BL 16- 04.02C.03.06 Moving Object Pipelines (Day and Night4DMTC -1200 -900 Moving Object Pipeline R6.1 8 Moving Object Pipeline R6.1

DLP -294 Scalable intra -night tracklet linking o t Scalable infra -night tracklet linkingDLP -293 Fully functional NightMOPS rj, Fully functiopal NightMOPSDLP -292 Scalable orbit prediction code SScalable orgd prediction 'codeDMTC -1200 -910 Moving Object Pipeline R7.0 11 Moving Object Pipeline R7.0DMTC- 1200 -920 Moving Object Pipeline R7.1 I I Moving Object Pipeline Ry.1DLP -296 Scalable collapse tracklets rj Scalable collapse trackletsDMTC- 1300 -0400 Moving Object Pipeline R8.0 11 Moving Object Pipeline R8.0DLP -306 Link tracklets 2j Link t ¡ackletsDMTC- 1300 -0405 Moving Object Pipeline R8.1 I I Moving Object Pipeline R6.1DLP -295 Scalable orbit fitting code. t Scalable orit fitting code.DMTC- 1300 -0500 Moving Object Pipeline R9.0 Moving Object Pipeline R9.0

Moving Objgct Pipeline R9.1

DayMOPS far non - trailed objects

DMTC -1300 -0505 Moving Object Pipeline R9.1 I I

DLP -297 DayMOPS for non - trailed objects

DMTC -1300 -0600 Moving Object Pipeline R10.0 MovirD Object Pipeline R10.0DMTC- 1300 -0605 Moving Object Pipeline R10.1 I I Moving Object Pipeline R10.1DLP -298 DayMOPS including trailed objects DayMOPS including trail objectsOMTC -1300 -6400 Moving Object Pipeline Integration Review Moving Objgct Pipeline Ir¢egrction Review

LSS152Q14 DM Release,. . 7 ._

LYS ME Ma UST teplember 20114 Ma. end 'ones massLUTIII14.0152C CelfeevemfemMlemilnalee eon NOV

snit pawns:cm to mwr sumo. 2.... 21...15....,... ................... y yolsLOT =OUZO iy.1. MO. ayelf........... MOT. you ego.

ETOC42.0.0 ClOomMOITNONISO. al ONO O..UNTIKINOOLOynOnalloyo41.1 you SOS

Ls.

OrSTTs

051-unyyOr

ossomoo........

=i' OISOS VT SS 1.0.14

SI. ......10 .. ..... ass

SW [SS 0. SS. SS.0.1213 Lo3011y mood. 11. loy. yfol.DON 00. OXON NO150...11011tO Mo. CloYoboyolo...... VG. Ono. WI.

......... .... as . I OIL II 15 ten Icawessemennami

sooners momememensemmem tis Is sums elses

Ionce.* Own' ryOntalorryogo .. NY... .......OrIONOVZ O....O. COO ayroleST ........ .....S..... IIISS SS.

Y.° OLOON.ODOSNON9 ON No. Noy

WYNN y ylly. lo. Onyinoylefillool on sou To.olo sE ..... oNomoo o ov TooOaf Sy On Toys p, yoo4 oovowe y To. vo ...ow 00000 Oa SST SSTWO ...SO 0.1. AM NV OW 7.77ft TAT SST SST..... ST -SI 31:1 ST SS NY ST SSTS. 01. 11.0.14 ZISSONTO OLOVIOlos000.... VG.210... fie.o.ONO Se ABOVOitoODICOOlyggod 0.0.1.O15 NO-11olay rmftristivem as ism.. luminaOM TOWO-ONCoe OIL ONO arm

au au.. sue,.LW lalIONCOMOn011o ellos O..OtoloOlo ohomeollSomaillooloosoo ..... Y...VolOs Oysisloolossol lodoon...ho... you Nolf

....". rooloyaloo ... olOs 714.14

valocely ou wypoolomp IND.....NOOM o woe wooffrocamsse smommeromesami sawn. OTT S.. axesusome..... ....e.e.emenen ems EmanisMS CISSISCSO TS O. MO. SON

Ry.l000lny O. WOO MON.... 10. 0. ITS. noes.,,,,. asimmemeses. .,,,,,, ,,,,oftromeem pesemiem,motnniss. s ,,,,, ,,,,,,,,,0.........., woes awesme, emenanie,,,,, nose ma.,ouromoss. oress...e.m.........esenree-no.,... I.

orpeloyoum oulumuuruumurau alms. an,3rum. m u u u A umsuu unu a. elm. gem.mess -iimmemcmnomi es isms 250.14ONO ......,.-cc.......... n so>. ....e.g. ..,.,.....*..... S 'TS. "ST...,.. u..........n.r....... s ...... s...,=DN. ............. n '14+4, ',F.,yam..u um. Do....Nu ........................., ow 32.0e. waifortonsons evementranareemmewen a 1 in m.ems mamaant Inaba, amens meals

N..

LanTo,toSTUSTLWMITMTmetmyun

ooN.m

V.Ovs,,,,,,

ruu.Pony,........STS

".....°e"..^num.iii.ims

em0.11011

Yr.

yoy. eoSonNIO.O......OTo yy o o

a LSO Too.= MS. SOSSTAISSISKS.- ..... MSS

voloi I.LONONOW201.0.107losilam reOONooyel.

um up...* 4.ilmoot

imeme ese

ma siemens.

nooE.GoO NOVO LW

...........o....1

o .............. Gus.comm. 1

Remaining Leveler Efforl 0 Ansel Work 0 Mittel Remaining WorkI=1 Actual Level of Effort 0 Remaining Work Milestone

%Complete Me

(c)

Figure 10 DM PMCS Prior to 6-month rolling wave plan

Figure 11 Activities loaded from JIRA Epics

Proc. of SPIE Vol. 9911 99110N-13

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 14: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

5. PERFORMANCE/FORECAST MEASUREMENT, ANALYSIS

Once the Epics have been loaded into the baseline the team executes the work that has been planned. During the execution phase status is collected from JIRA and loaded into the PMCS. This method of collecting status is very efficient as developers can work in a tool (JIRA) that provides real time interaction and doesn’t require learning a new system like Primavera to record progress.

Performance Measurement

On at least a monthly basis (as a minimum) JIRA is updated with the status of the remaining and in-progress activities. This is the status that is loaded into the PMCS which includes:

• Actual start dates for activities begun during the status period (the day recorded in JIRA when the state changes to “In Progress”.

• Actual finish dates for activities completed during the status period (the day recorded in JIRA when the state changes to “Done”.

• Actual finish dates for milestones accomplished during the status period. • Physical percent complete of activities by collecting status of the associated stories on the Activity.

All of this information is recorded in JIRA and is used as the primary method for measuring the progress of software development work at LSST.

Every month, the Project Controls Specialist exports plan updates and status information from JIRA into the PMCS. When developers record progress in JIRA they set the status (Done, In Progress, To Do, etc.) on the stories assigned to an Epic. A Story is either Not Done or Done (0% – 100%), there are no partial completions recorded on stories for EV measurement. Each story that is marked complete will contribute to the total % Complete of the Activity. When these Stories and any additional that may be added during a cycle are all marked Done and the status is imported to PMCS, the Epic will show 100% complete. It is likely that a subset of stories may have not yet been planned for an In Progress Epic. In this case, a step is added in Primavera called “Remaining Stories” which is the delta of the estimated stories on the epic and the actual planned stories. This helps prevent case of having negative earned value and new stories are added to an Epic.

The mechanism for exporting status uses the standard Excel interface from JIRA as shown in Figure 12. The story export from JIRA is filtered to contain all issues that are assigned to an Epic and are of a type of Improvement, Story, or Bug. This data is then transferred to an Excel template which uses Vlookup functions to relate Epic and story data from JIRA with cost and schedule data from Primavera. This enables the tracking of performance to baseline dates and dollars solely in Excel.

The mechanism used to import the stories into the IMS employs an internally developed custom tool that allows importing activity steps into Primavera. Without this tool there is unfortunately no Primavera interface to import activity steps and it would be an arduous effort to manually load the steps each month. Once the steps have been imported EV is analyzed in the PMCS, and variances are calculated.

Proc. of SPIE Vol. 9911 99110N-14

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 15: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

*11RA Dashboards- PI0(ecls- Issues- Gant Gat Mlle- Scrum Standup Q o -=-FILTERS

New asno

Find filters

My Open Issues

Reported by Me

Recently mewed

All Issues

FAVORITE FRYERS

Epics Io. PUCS

Spies Tu PMCS All

Epics for PMCS Edited Save - Deuils *

O poem = DM AND esuetvpe = Epic AND WBS IS not EMPTY

1-100016a0 i

WBS Mk: Team Story Pointe Anionen he CnpliOn hue

® Email C} Snare

anmaleFull Content

XML

RSS (Issues)

RSS (Comments)Fnlc Link EPICN

02C.05.01 Summer Science do Xlugle Wu The epic will capture all the Java code 26IAttgtIS2016 User reraaamg in Firefly It does not Include Ne

Interface OWL to JS conversion effort

Summer Data Access2018 and

Database

U/HSSgned Advanced performance optimizations and tuning01 the shared scans. This includes

Reschedule user queues on a different

Firefly Word

react Excel (All Lelas(

51 Export *Tools

Excel (Current yields

FY1B ChansShareoplim On Dashboard

sic I--1

Columns

Rank

01

Oldal2

Epics Summer 2015

Simulations Epics

SOCS Dev Epics

SOCS Bev Stories

Slone for PMCS Res..

1SSPP02C.0501 Summer

2016SeleneUserInterlace

60 Xlugin Wu

02C.0502 Summer2016

SeleneUserInterlace

40 Xlugin Wu

02C.0501 Summer2016

SeleneUserInterlace

40 Xlugin Wu

wo poss oe pans DO

detecting slowquenes and nosing them to aslower lower pfodty scan scheduler and Imother would be laving the czar tell theworkers to more all tasks fora user query toa specific scheduler_ These require uniqueuser query ids_

Gantt Marl- Tracking

26/Aug/16 Bela version of 0 0Má081 01s1a1k6:

LOST web ul ready

We need to provide API access S all the table 26/Aug/16 Provide API fa 0 0M-4680 0lldally:displaying features to give user more control tabular data daptywhen using Frefly API to build customized web using FireflyUI

SUI will Cmtnue to work oath database team to 26/Aug/16 SUI will conbnueto 0 0M-4679 0I9la1jq:exercise all Ow APIs for data access . All known work with databaseissues should be waked out in S16 cycle team to erercae all

the APIs fa data

Was Activity ID Activity NamePhysical%

Complete Budgeted Total Cost5Eamed

( % comp 7 Total cost/

LSST.02C.04.01 0M -1974 Measurement - Calibration and Ingest 1CG% 59,380.95 59,350.95

LSST.02C.04.01 0M -1099 afw: :table - finish interface transition 100% $16,617.07 $16,617.07

LSST.03C.04.010M -1100 Measurement - Convert Old Algorithms 100% $31,951.49 $31,951.49

LSST.02C.04.01 DM -1101 Measurement - Finish Framework Overhaul 100% $23,87755 $23,677.55

LSST.02C.04.01 DM -1107 afw- Footprint Improvements 100% $44,799.06 $44,799.06

LSST.02C.04.01 DM -1109 Measurement - MultiFIt Plugln Framework 0% $15,066.95 $0.03

LSST.02C.04.01 DM -1904 Continued footprint Improvements 12.50% $63,50750 $10,438.44

LSST.02C.04.01 DMTC- 3300-0190 Application Framework DRP Scope Planningo55.1 100% - -" $1,410.40

Total $730,010.99 5138,474.98

%Comp

$ Earned/Total Cost 51.11%

Y,L% ßE10Sne,14 Ism R.xI- %=IDA111®®0f1

nwn

,mcNO, 'swan

m 0, 0414442,241.4®

n,.aa mma 1 02C OM PS, Emma. 11 4105 SI 40E4 WOO

image 2wmlle SOO, 10,0 4000u e. MOO 4000

mn. o.+o«.an i,xm aaamn

m.w.. 590.097

»mlMeal 01511Pma,lm un,..:rl

own. I amwwalwa.issa.Ild.I

Insegess wl40444a4.. n...4.a a nww nnma s,mri

I .mu f-1 Iw ©_

1-a1..14 a 10...5 ,0/01/2014 Ions o

1.3 112 3

01 042.1Stall

111

Figure 12 JIRA Interface to Export Status

EV is analyzed in Deltek Cobra, which integrates directly with Primavera. This integration establishes a many to one relationship between activities in the IMS to a single work package in Cobra. The EV for a Work package is calculated in Cobra by determining the earned amount for each activity in relation to its budget and % complete. The sample data in Figure 13 shows the flow from Primavera budget (top) and status to the integration in Cobra

Figure 13 IMS to EVMS tie out

Proc. of SPIE Vol. 9911 99110N-15

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 16: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

While Earned Value is very effective over the long term it does have some “lags” inherent in the system.

• 1 week to 1-month lag between updates in JIRA and in PMCS • 1+ month lag between PMCS updates and monthly reports • EV is “skewed” by late invoicing, requiring estimated actuals

We do have the ability to assess performance earlier outside of the EV tools by looking at trends in JIRA-based on Epics and Stories directly.

• Estimated Story Points vs. Planned Story Points • Planned Story Points vs. Completed Story Points

6. REPORTING

Performance metrics generated from PMCS and JIRA are used in conjunction to assess performance, and ultimately to report to stakeholders on the health of the project. An orderly process is used to collect, review, report, and use the data generated by the system and is repeated monthly. This monthly reporting cycle is based on the accounting month which ends on the last day of each calendar month. These project status reports contain the following information:

• Budget summary • CPI/SPI Trending • Status of key milestones • Progress narrative • Baseline change control log • EVMS data • Variance explanations (when required) Electronic systems have been developed at LSST to serve this reporting and analysis data directly from the Cobra and Primavera databases in a system that allows drilling from a high WBS level all the way to the activity and activity step level to facilitate simplified analysis and reporting.

The data generated from the PMCS are available in a web application known as eCAM, or electronic T/CAM Notebook, which is shown in Figure 14. eCAM facilitates this monthly analysis and reporting by showing all current period, cumulative, and at complete EVMS data for all WBS/CA/WPs for the entire project. Status indicators exist in eCAM to not only highlight costs that have tripped variance thresholds, but also date indicator lights to highlight the following situations;

• Red: Today’s date >= forecast start/finish date and Today’s date >= BL start/finish date

• Yellow: Forecast start/finish date > BL start /finish date and today’s date < BL Start/ BL Finish

• Green; Forecast start/finish date <= BL start /finish date and today’s date < BL Start/ BL Finish

eCAM will highlight all control accounts and work packages that have tripped the variance reporting threshold. T/CAMs are directed to populate an Explanation and corrective action at the control account level at a minimum. It is encouraged that this data is captured at the work package level and aggregated to the parent control account. Past narratives are evaluated each month to address issues that aren’t being resolved.

Proc. of SPIE Vol. 9911 99110N-16

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 17: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

Only Show Variances Hide WBS Summary Hide Completed Expand All

L^i EV Summary SV CV Selected Work Package: KLM20401A.PROC EVT: PctCamplete CAM: SwinbankJ

WBS / WP

-BudgetBCWS

Current PeriodEarned Actuals SV CVBCWP ACWP

SPI CPI Budget EarnedBCWS BCWP

Cumulative to DateActuals SV CVACWP

SPI

Narrative R - uiredAt Complete

CPI BAC EAC % %Spent Complete

1 $70,168 $35,688 $123,809 ($34,479) ($88,121) 0.51 0.29 $782,330 $511,436 $503,884 ($270,894) $7,552 0.65 1.01 $15,362,042 $15,263,820 3% 3%1.02C $70,168 $35,688 $123,809 ($34,479) ($88,121) 0.51 0.29 $782,330 $511,436 $503,884 ($270,894) $7,552 0.65 1.01 $15,362,042 $15,263,820 3% n3%1.02C.04 $70,168 $35,688 $123,809 ($34,479) ($88,121) 0.51 0.29 $782,330 $511,436 $503,884 ($270,894) $7,552 0.65 1.01 $15,362,042 $15,263,820 3% 3%

04.00 $50,855 $21,028 $47,306 ($29,827) ($26,278) 0.41 0.44 $296,620 $263,427 $225,405 ($33,193) $38,022 0.89 1.17 $1,953,129 $1,873,603 12% 13%V1.02C.04.01 $0 $0 $22,682 $0 ($22,682) 0.00 0.00 $226,611 $138,482 $91,511 ($88,129) $46,970 0.61 1.51 $3,303,487 $3,243,856 3% 4%

KLM20401A.PP $0 $0 $0 $0 $0 0.00 0.00 $0 $0 $0 $0 $0 0.00 0.00 $3,076,876 $3,076,876 % %

2,682) 0.00 0 ,:. - ($88,1291.02C.04.02 $0 $0 $0 $0 $0 0.00 0.00 $0 $0 $0 $0 $0 0.00 0.00 $2,527,545 $2,527,545 0% %

1.02C.04.03 $0 $0 $0 $0 $0 0.00 0.00 $1,410 $1,409 $0 ($11 $1,409 1.00 0.00 $3,172,316 $3,170,907 0% o%1.1.020.04.04 $0 $0 $0 $0 $0 0.00 0.00 $0 $0 $0 $0 $0 0.00 0.00 $1,068,861 $1,068,861 0% o%11.1.02C.04.05 $0 $0 $0 $0 $0 0.00 0.00 $0 $0 $0 $0 $0 0.00 0.00 $183,413 $183,413 0% 0% VI 1.02C.04.06 $19,313 $14,660 $53,821 ($4,653) ($39,161) 0.76 0.27 $257,690 $108,118 $186,967 ($78,849) 0.42 0.58 $3,153,291 $3,195,635 6% 3%

_^E] Schedule Details Selected Work Package: KLM20401A.PROC

ID ResourceDescription

BaselineStart

BaselineFinish

Forecast/Actual Forecast/ActualStart Finish

TotalFloat

PlannedCost

Planned Target RemainingHours Duration Duration

LSSE- PRINCETON - Sr. Software Engineer- PRINCETON DM Sr. Software Engineer 0

('1M -1107 -afw - Footprint Improvements 11- Dec -14 29- Dec -14 020- Jan -15 A 31- Jan -15 A 1 00.0 $44,799 166 11 11 ^LSC- PRINCETON - Scientist- PRINCETON DM Scientist 0

LSC- PRINCETON - Scientist- PRINCETON DM Sr. Scientist 0LSSE- PRINCETON - Sr. Software Engineer - PRINCETON DM Sr. Software Engineer 0

nM -1109 - Measurement - MultiFit Plugin Framework 30- Dec -14 16- Feb -15 01- Jul -15 .14- Aug -15 0.0 -19 $15,067 126 33 33LSEN -UCD - Software Engineer - UCD DM Software Engineer 0

LSSE- PRINCETON - Sr. Software Engineer - PRINCETON DM Sr. Software Engineer 0DM -1904 -Continued footprint improvements 02- Mar -15 29- May -15 024- Mar -15 A o28- Sep -15 12.5 -19 $83,508 296 64 63

LSC- PRINCETON - Scientist- PRINCETON DM Scientist 0LSC- PRINCETON - Scientist- PRINCETON DM Sr. Scientist 0 C

DMTC - 2300 -0190 - Application Framework DRP Scope 30- Jan -15 26- Feb -15 *02- Feb -15 A 27- Feb -15 A 100.0 $1,410 5 20 V20

Project I LSST ME 15 -06 `1 CAM Swinbank J V WBS Leve

n Near Term Responsibilities Procurement* Milestones

sl 1- LSST May 2015 Month End Baselii tvI

Total: $2,048 138,474

Figure 14 eCAM showing JIRA Epics assigned to a Work Package

Outside of eCAM, JIRA performance can be measured and reported directly from the JIRA excel exports, as shown in Figure 15. By pivoting this data information can be grouped by any of the code fields used in JIRA and Primavera.

Figure 15 JIRA Excel Report

Typical Analysis:

• We consider overall work rate to be relatively constant over a 6-month cycle, since we do not have large staffing changes during the cycle

• Progress should be roughly linear with time (but see reporting comment below) • The SP Variance % of Completed/Planned is 37% which is ~4% slow versus expectation of 33% at 2/3 date, i.e.

we are behind by 4% of total planned work • Our experience is that we under-report progress until the last month, due to “conservative” assessments of

completion, and having only done unit tests which don’t expose all problems • We will both add SP in the last 2 months and complete them at a higher rate • Based on the above, I expect us to slip 15% of S15 SP

WBS CAM Key Epic Name COMPLETED Stories Planned

Stories Complete

Remaining SP

Sum of SP % Variance Completed / Target

Planned 20/5002C.07.03 Gelman M DM-1273 Plan OpenStack v1 Deployment To Do 67 47 20 30%

02C.07.03 Total 67 47 20 30%02C.07.03.08 Gelman M DM-2239 Develop use cases for TOWG To Do 9 1.5 7 82%

02C.07.03.08 Total 9 1.5 7 82%02C.07.04 #N/A DM-2225 LOE - S15 (sys admin) In Progress 178 178 0 0%

02C.07.04 Total 178 178 0 0%02C.07.04.05 Gelman M DM-1268 Upgrade Rack KVMs In Progress 11 6 5 45%

DM-2211 Setup qserv prototype for qserv team To Do 4 4 0 0%DM-2218 Base Data Center Requirements Done 15 13.5 1 7%

02C.07.04.05 Total 30 23.5 6 24%02C.07.04.06 Gelman M DM-2224 Wide-Area Network Work To Do 15 13 2 13%

02C.07.04.06 Total 15 13 2 13%Grand Total 2491 1685.5 806 37%

Proc. of SPIE Vol. 9911 99110N-17

Downloaded From: http://proceedings.spiedigitallibrary.org/ on 11/11/2016 Terms of Use: http://spiedigitallibrary.org/ss/termsofuse.aspx

Page 18: Agile software development in an earned value world: a ... · Agile software development in an ea rned value world: a survival guide Jeffrey Kantor a, Kevin Long b, Jacek Becla c,

7. CONCLUSION AND NEXT STEPS

The LSST EVMS and Agile integration provide a means to develop software using current best practice Agile methods while preserving the planning, performance monitoring/analysis, and reporting rigor required by EVM. By allowing the near-term rolling wave plan to be developed and executed in an Agile manner, but within the context of the overall EV process, a marriage of the two worlds is achieved.

While the process is now fully integrated, there are a number of steps where the exchange of data between the various tools in the EVMS is still somewhat manual, via data export and import, and a number of areas where additional reports and notifications would be useful. Future work in the system will be directed at improving the level of automation and support for additional analytical reports and notification.

8. ACKNOWLEDGMENTS

This material is based upon work supported in part by the National Science Foundation through Cooperative Support Agreement (CSA) Award No. AST–1227061 under Governing Cooperative Agreement 1258333 managed by the Association of Universities for Research in Astronomy (AURA), and the Department of Energy under Contract No. DE–AC02–76SF00515 with the SLAC National Accelerator Laboratory. Additional LSST funding comes from private donations, grants to universities, and in-kind support from LSSTC Institutional Members.

We thank Victor Krabbendam and Tim Jenness, AURA/LSST for reviewing the draft manuscript.

9. REFERENCES

[1] Kahn, S., “Final design of the Large Synoptic Survey Telescope,” in [Ground-Based and Airborne Telescopes IV], Hall, H. J., Gilmozzi, R., and Marshall, H. K., eds., Proc. SPIE 9906, in press (2016).

[2 ] Kurita, N., Kahn, S., Stubbs, C., Ritz, S., Nordby, M., Riot, V., “Large Synoptic Survey Telescope camera design and construction”, in [Advances in Optical and Mechanical Technologies for Telescopes and Instrumentation], 2016, 9912, in press

[3] Juric, M. et al., “The LSST Data Management System,” in [Astronomical Data Analysis Software & Systems XXV], Lorente, N. P. F. and Shortridge, K., eds., ASP Conf. Ser. in press, arXiv:1512.07914, ASP, San Francisco (2016)

[4] Boehm B., Turner, R. , “Management challenges to implementing agile processes in traditional development organizations”, IEEE Software Volume:22 Issue:5 (2005).

[5] Becla, J., et al, “LSST DM Project Management Tools Overview”, LDM-472

[6] Kantor, J., et al, “Data Management Releases”, LDM-240

Proc. of SPIE Vol. 9911 99110N-18