A G 2 0 0 0 H o r i z o n t a lI n s t a l l a t i o n
Step 1You’ll Need:
Installing an AG2000
Horizontally
Measure the horizontal straight pipe from pump. Ensure there is sufficient straight pipe to meet the
requirements of the meter (see note).
Important Note!
AG2000-400 22" min. AG2000-800 30" min.
AG2000-600 38" min.
AG2000-1000 48" min.
Tape Measure
Step 2You’ll Need:
Cut out a section of straight pipe, insuring there are at least two pipe diameters of straight pipe on the inlet side of the meter, and one pipe diameter of straight pipe on the outlet side of the meter.
Tape Measure
Welding Tools
Installing an AG2000
Horizontally
Step 2You’ll Need:
Cut out a section of straight pipe, ensuring there are at least two pipe diameters of straight pipe upstream of the meter, and one pipe diameter of straight pipe downstream of the meter.
Tape Measure
Welding Tools
Installing an AG2000
Horizontally
Step 3You’ll Need:
Weld the appropriate ANSI flanges on each open end of pipe, ensuring the flanges are parallel, and the flange bolt holes are aligned.
Allow the welds to cool to ambient temperature.
Tape Measure
Welding Tools
Level
Installing an AG2000
Horizontally
Step 3You’ll Need:
Weld the appropriate ANSI flanges on each open end of pipe, ensuring the flanges are parallel, and the flange bolt holes are aligned.
Allow the welds to cool to ambient temperature.
Important Note!
WARNING: DO NOT USE THE METER AS
A WELDING FORM.
THE HEAT AND/OR ELECTRICAL CURRENTS FROM THE WELDER
WILL DAMAGE THE METER AND VOID THE WARRANTY.
Tape Measure
Welding Tools
Level
Installing an AG2000
Horizontally
Step 4You’ll Need:
Install the meter, with the direction arrow on the side of the meter pointed down stream in the direction of the flow.
Flow Arrow
Wrench
Installing an AG2000
Horizontally
Step 4You’ll Need:
Install the equalization wires and tabs from the lug to the outside pipe flanges (not in direct contact with the meter) for proper electrical grounding.
Wrench
Wire Cutters
Screw Driver
Installing an AG2000
Horizontally
Tab on pipe flangeNOT
meter flangeTab on pipe flange
NOTmeter flange
Step 6You’ll Need:
Install the Weather Guard protective cap over the meter head. This is a force-fit, so measurable pressure will be required for a correct fit.
Hands
Installing an AG2000
Horizontally
Step 8You’ll Need:
Your meter is installed! Refer to the Seametrics AG2000 Instruction Manual
for additional information and instructions.
Important Note!
Congratulations!
Your properly installed AG2000will provide years
of low maintenanceoperation.