AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and...

37
AFRICAN DEVELOPMENT BANK ETHIOPIA MEKELE-DALLOL AND SEMERA-AFDERA POWER SUPPLY FOR INDUSTRIAL DEVELOPMENT AND ACCESS SCALE-UP PROJECT (MDSAPIAP) APPRAISAL REPORT ONEC DEPARTMENT July 2016 Public Disclosure Authorized Public Disclosure Authorized

Transcript of AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and...

Page 1: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

AFRICAN DEVELOPMENT BANK

ETHIOPIA

MEKELE-DALLOL AND SEMERA-AFDERA POWER SUPPLY FOR INDUSTRIAL

DEVELOPMENT AND ACCESS SCALE-UP PROJECT (MDSAPIAP)

APPRAISAL REPORT

ONEC DEPARTMENT

July 2016

Publi

c D

iscl

osu

re A

uth

ori

zed

P

ubli

c D

iscl

osu

re A

uth

ori

zed

Page 2: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

Table of Contents

1. STRATEGIC THRUST & RATIONALE 1

1.1. Project linkages with country strategy and objectives ............................................... 1 1.2. Rationale for Bank’s involvement ............................................................................. 2 1.3. Donor Coordination ................................................................................................... 3

2. PROJECT DESCRIPTION 3 2.1 Project components .................................................................................................... 3 2.2 Technical solution retained and other alternatives explored ...................................... 4 2.3 Project type ................................................................................................................ 4 2.4 Project cost and financing arrangements ................................................................... 4

2.5 Project’s target area and population ........................................................................... 6 2.6 Participatory process for project identification, design & implementation ............... 6 2.7 Bank Group experience, lessons reflected in project design ..................................... 6

2.8 Key performance indicators ....................................................................................... 7

3. PROJECT FEASIBILITY 8 3.1 Economic and Financial Performance ....................................................................... 8

3.2 Environmental and Social Impacts ............................................................................ 8 3.2.1 Environment ............................................................................................................... 8 3.2.2 Climate Change .......................................................................................................... 9 3.2.3 Gender ...................................................................................................................... 10

3.2.4 Social........................................................................................................................ 10 3.2.5 Involuntary resettlement .......................................................................................... 11

3.2.6 Stakeholders ............................................................................................................. 11

4. IMPLEMENTATION 11 4.1 Implementation arrangements .................................................................................. 11 4.2 Procurement Arrangement ....................................................................................... 12

4.3 Financial Management ............................................................................................. 12 4.4 Monitoring and Evaluation ...................................................................................... 13

4.5 Governance .............................................................................................................. 15 4.6 Sustainability............................................................................................................ 15 4.7 Risk management ..................................................................................................... 16 4.8 Knowledge building ................................................................................................. 17

5. LEGAL INSTRUMENTS AND AUTHORITY 17 5.1 Conditions associated with Bank’s intervention ...................................................... 17

A. Condition Precedent to Entry into Force of the Loan Agreement ........................... 17 B. Conditions Precedent to First Disbursement of the Loan in Respect of Consultancy

Services for an amount not exceeding 3.35 million USD : ...................................... 18 C. Conditions Precedent to Subsequent Disbursement of the Loan ............................... 18

6. RECOMMENDATION 18

Appendix I: Comparative socioeconomic Indicator I Appendix II: Table of ADF Portfolio in the Country II

Appendix III: Table of Key Projects Financed By the Bank and other Development Partners

in the Country IV Appendix-IV: Project Location Map V

Appendix V: Justifiction For Financing More Than 50% Of Cost By AFDB VI

Page 3: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

Currency Equivalents

As of May2016

1 UA = 1.4173 USD

1 UA = 30.5843 ETB

1 USD = 21.5788 ETB

1 ETB = 100 (Ethiopian cents)

Financial Year for EEP

July 8th – July 7th

Weights and Measures

1 metric ton = 2204 pounds (lbs)

1 metre (m) = 3.28 feet (ft)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

1 kilovolt (kV) = 1000 volts

1 kilowatt (kW) = 1000 watts

1 megawatt (MW) = 1000 kW

1 gigawatt (GW) = 1000 MW

1 kilowatt hour (kWh) = 1000 watt hour

1 gigawatt hour (GWh) = 1000 kWh

Page 4: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

i

ABBREVIATIONS

ADB = African Development Bank Group

ADF = African Development Fund

AFD = Agence Française de Développement

BADEA = Arab Bank for Economic Development for Africa?

CAGR = Compounded Annual Growth Rate

CIDA = Canadian International Development Agency

CSP = Country Strategy Paper

CSO = Civil Society Organization

DC = Direct Current

DFID = Department for International Development

DSCR = Debt Service Coverage Ratio

EEPCO = Ethiopian Electric Power (Corporation)

EIB = European Investment Bank

EC = European Commission

EEA = Ethiopia Electric Agency

EEP = Ethiopia Electric Power

EEU = Ethiopia Electric Utility

ENPV = Economic Net Present Value

EMU = Environmental Monitoring Unit

EIRR = Economic Internal Rate of Return

ENPV = Economic Net Present Value

ESI = Electricity Supply Industry

ESIA = Environmental and Social Impact Assessment

ESMP Environmental and Social Management Plan

ETB = Ethiopian ETB

ETFO = Ethiopia Field Office

FE = Foreign Exchange

FIRR = Financial Internal Rate of Return

FNPV = Financial Net Present Value

FY = Financial Year

GoE = Government of Federal Democratic Republic of

Ethiopia

GEP = Generation Expansion Plan

GDP = Gross Domestic Product

GTP = Growth & Transformation Plan

GWh = Gigawatt hour

HV = High Voltage

HVTL = High Voltage Transmission Line

ICB = International Competitive Bidding

ICS = Interconnected System

IPP = Independent Power Producer

ISS = Integrated Safeguards System

IDA = International Development Association

JICA = Japanese International Co-operation Agency

KFW = Kreditanstalt fur Wiederanfbaw

km = Kilo meters

kV = Kilo volt

LC = Local Cost

Page 5: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

ii

LRMCS = Long Run Marginal Cost of Supply

LV = Low Voltage

MCM = Million Cubic Meters

MoFEC = Ministry of Finance & Economic Cooperation

MIS = Management Information System

MW = Megawatt

MV = Medium Voltage

NDF = Nordic Development Fund

NEPTP = Northern Ethiopia Power Transmission Project

NGO = Non-Governmental Organization

O&M = Operation and Maintenance

p.a. = Per Annum

PA = Project Area

PAPs = Project Affected Persons

PASDEP = Plan for Accelerated and Sustainable Development to

End Poverty

PCBs = Polychlorinated Biphenyls

PCR = Project Completion Report

PIT = Project Implementation Team

PPA = Power Purchase Agreement

PPER = Project Performance Evaluation Report

PSNP = Productive Safety Net Program

PSP = Private Sector Participation

QPR = Quarterly Progress Report

RAP = Resettlement Action Plan

SCS = Self Contained System

SIDA = Swedish International Development Agency

SMEs = Small and Medium Enterprises

SNNPR = Southern, Nations and Nationalities People’s Region

TPP = Thermal Power Plant

TVET = Technical, Vocational Education and Training

UA = Unit of Account

UEAP = Universal Electricity Access Program

UNDB = United Nations Development Business

UNECA = United Nations Economic Commission for Africa

USAID = United States Agency for International Development

USD = United States Dollars

VCT = Voluntary Counselling and Testing

TPP = Thermal Power Plant

Page 6: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

iii

Loan Information

Client’s information

BORROWER: The Government of the Federal Democratic Republic of Ethiopia (GoE)

EXECUTING AGENCY: The Ethiopian Electric Power (EEP)

Indicative Financing Plan

Sources of financing Amount

(USD million)

Instrument

ADB 104.61 Loan

ADF -

EEPCO/ GoE 17.91 Counterpart

contribution

Total project cost 122.52

ADB’s key financing information

Loan currency

United States Dollar (USD)

Interest type Fully Flexible Loan

Interest rate spread Funding margin+60 bps lending

spread

Commitment fee None

Other fees None

Repayment Semi-Annual

Tenor 20 Years

Grace period 5 Years

FIRR 14.38%

FNPV (@10%) US$ 64.52 million

EIRR 29.13%

ENPV (@12%) US$ 293.42 million

Timeframe - Main Milestones (expected)

Concept Note approval September 2015

Project approval July 2016

Effectiveness October 2016

Completion July 2019

Closing date December 2020

Last repayment July 2046

Page 7: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

iv

PROJECT SUMMARY

1.1 The Mekele-Dallol & Semera-Afdera Power Transmission Supply for Industrial Development

and Access Scale-up Project (MSPIAP) (with the associated Transmission lines, Substations and Rural

Electrification components) aims to improve the socio-economic development and livelihood of the

population of beneficiary regions through increased access to affordable & sustainable electricity

supply and improvement in service delivery. The two beneficiary regions are Tigray & Afar Regional

States of Ethiopia.

1.2 The Program’s main outcomes include (i) provision of adequate & reliable electricity supply

to industries and small businesses by adding 250 MVA capacity and making available 613 GWh/year

at Dallol (for potash companies Yara, Allana & Sercum Minerals) & 31.5 MVA at Afdera (small salt

extraction businesses); (i) increase in number of people with access to sustainable modern grid based

electricity supply; (iii) improvement in power utility revenue through increment in number of domestic,

commercial and industrial customers; and (iv) improved access in the provision of basic social services

such as schools, health centres safe water etc.. At output level, it will result in the construction of two

(2) 230 kV transmission lines and two (2) corresponding substations. The lines and substations to be

constructed will cover the following sections: (i) 130 km of 230 kV Mekele-Dallol transmission line

(ii) 175 km of 230 kV Semera-Afdera transmission line (iii) Construction of associated two new

substations at Dallo & Afdera, vi) Substation expansion on two existing Mekele & Semera 230 kV

substations (iv) Rural Electrification construction of MV and LV distribution networks (v) Consultancy

Services for project supervision and management and (vi) Technical Assistance and Capacity building

1.3 At completion in 2019, the project will benefit an estimated 36 rural towns/villages (estimated

102,000 people) directly in the beneficiary regions from improved access to electricity, basic social

services. The project will also support provision of adequate and reliable grid based power supply to

potash industries as well as other small business. The program will have a direct positive social benefit,

enabling improved education opportunities for women and school age children, improving access to

health services, creating productive/livelihood opportunities and employment through expanded service

and improved private sector activities.

2. NEEDS ASSESSMENT

2.1 The biggest challenge facing the Government of Ethiopia (GoE) is to mobilize the necessary

resources to meet the generation, transmission, distribution and rural electricity access scale-up

requirements,as these involve considerable investment costs. The Government has recently mobilized

resources for implementing three wind & hydroelectric generation projects; namely: Ashegoda Wind

project (120 MW) completed in 2012, Adama- I & II wind projects (204 MW) completed in 2015 with

financing from the French &Chinese Governments, Gibe-III hydropower plant(1870 MW), completed

end of 2015; Genale dawa-III hydropower plant (254 MW) to be completed in 2016 and Renaissance

dam (6,000 MW) to be completed in 2018, which are the latest development in EEP’s generation

expansion plan and are expected to provide an extra 8,124 MW to the system.

2.2 Implementation of this projectis therefore important to ensure that the generated power from

the power plants is transported to remotely located load centres. It will also solve the prevailing power

shortage due to in ability of the existing diesel power plants to satisfy rapidly growing demand in the

area as a result of the need to expand exploitation of large potash and salt resources in the area.

Providing electricity supply to large & small industries, urban & rural towns around Dallol and Afdera

with modern, cleaner and cheaper reliable power as opposed to diesel power, by extending the grid,

will stimulate economic activities that enhance job creation, improve access to basic services (schools,

health & social centres) and limit environmental degradation due to the utilization of fossil fuel. In

addition the proposed grid extension to the two towns will scale-up access to electricity in the Afar

Region from 55% to 75% by supplying to schools, health centres, social centres, etc. planned to be

connected.

Page 8: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

v

2.3 The Project Coordinator is already appointed. The submission of CVs of all Project

implementation Team including the procurement plan will be a condition for loan Negotiations. In order

to avoid the project stat-up delay, the advance contracting is already approved and procurement

documents for major components have already been received by the Bank. Procurement process is

expected to start soon. The Bank energy sector operation in the country so far has been very successful.

There is no energy project at risk. It can be concluded that the project preparedness is well advanced.

3. BANK’S ADDED VALUE

3.1 In support of the Government’s programs, the Bank has funded several projects in the

electricity sub-sector. These include (i) feasibility studies of hydropower projects, namely Alleltu,

Beles, Chemoga-Yeda and Halele-Werebesa (ii) Ethiopia-Sudan Power Interconnection Feasibility

Study (iii) Northern Ethiopia Power Transmission Project (iv) 230 kV Koka-Dire Dawa Power

Transmission, (v) Gilgel GibeI–Ghedo Transmission Project, (vi) 66 kV Transmission projects, (vii)

Gefersa Fitch, Debere Markos – Bitchena and Debre Markos Finoteselam Transmission(viii) Rural

electrification I, and (ix) Ethiopia-Djibouti Power Interconnection Project, to expand the transmission

system, increase rural electricity access and enable exchange of power with neighbouring countries.

These interventions have contributed to the development of Ethiopia’s hydropower resources, power

evacuation from the generating plants and expand rural electrification, which are vital for increasing

the population’s access to electricity. The Bank is currently financing: (i) the Ethiopia Rural

Electrification-II Project, which involves the electrification of 335 rural towns/villages, (ii) Electricity

Transmission System Improvement Project which involves construction of 943 km of 230 kV

transmission line and associated 21 high voltage substations expected to be completed in December

2016, and (iii) Ethiopia-Kenya Electricity Highway project which involves construction of 434 kms

500 kV HV DC transmission line with associated converter station expected to be completed in 2018.

3.2 The Bank considers the support of domestic infrastructure development and regional

integration, especially within the power sector, as a pillar of its strategy in the country which is aligned

with the New Deal on Energy for Africa and the high 5s. The Bank’s participation is vital for the

following reasons: (i) the financial support to EEP will strength the implementation of rural

electrification and transmission system improvement programs, that enables transmitting sufficient

power to customers (ii) the supply of electricity will contribute to the improvement of the standard of

living of the people (iii) create opportunities for effective utilization of energy resources (iv) the project

supports dialogue between the Bank and GoE on policy issues related to energy policy and regulatory

issues.

4. KNOWLEDGE MANAGEMENT

EEP has sufficient experience in the implementation of similar 230 kV and 400 kV transmission and

substation contracts and rural electrification projects. Implementation of this project will enhance the

knowledge (technical & project management) of the executing agency in managing the design and

project management/supervision of projects to be implemented in areas with extreme environmental

condition. The Bank continues to build capacity and strengthen knowledge and skills in EEP through

such types of projects. Bank’s Supervision Missions are key forums for dissemination and sharing of

experience and knowledge with implementing agency, contractors and regional administration to

improve sector coordination within government and financiers.

Page 9: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

vi

Country and Project Name: ETHIOPIA-Mekele – Dallol and Semera – Afdera Power Supply for Industrial Development and Access scale-up project

Purpose: The Project is intended to supply Electric Power to Potash Industries, Salt Mines extraction businesses & create Electricity Access scale-up

Results Chain Performance Indicators Means of

Verification

Risks/Mitigation Measures

Indicator (incl. CSI) Baseline

2015

Target 2020 IM

PA

CT

I

1. Improved living conditions

and Socio-economic

development of the

communities

1.1 Reduced number of

people living below the

poverty line

28.5 % 20.4 % -Government

Statistics and

Bulletins;

- Central Statistics

Agency,

-UNDP Human

Development

index

1.2 Increased % of access to

primary education (% are

female)

39% 80% (50% are

female)

OU

TC

OM

E

2. Increased electricity access

& rural electricity supply

3. Improved availability of

reliable and sustainable

electricity for private sector

industrial development

2.1 Increased % of access to

electricity (% are female)

2.2 Increased number of

domestic customers (Million)

55% (2104)

1.98

90% (50% are

female)

5.85

-EEP and EEU

annual reports;

-Utility records

-Project

Completion

Reports

- MoFEC annual

reports

Risk 1: Timely completion of private sector

potash industries

Mitigation: The private sector investors

received investment permits and are actively

mobilized on site.

Risk 2 : Availability of sufficient power

Mitigation: Ethiopia is currently building

about 6,000 MW generation

Risk3: Shortage of financing resources

Mitigation: Government support to

financing, transmission system and rural

electrifications components.

3.1 Increase in number of

large industrial customer

connections

37,903 111,976

3.2 Increase in large &

small industry Energy

Consumption, GWH/y

5,407

15,063

OU

TP

UT

S

Component A

Construction of high voltage

transmission lines

Component B

Construction high voltage

Substations

1.Length of high voltage

line constructed for Potash

industry, Salt mines and

supply of urban & rural

towns (km)

n.a 305

Project Quarterly

progress report &

Bank’s site

Supervisions

Risk 4: Project completion delay

Mitigation: Deployment of project

management & supervision consultant &

enforcement of the PIT staff

Risk 5: Cost overrun

Mitigation: Physical (5%) and price (5%)

contingencies built into the project costs, the

contract packaging will ensure that all

necessary construction guarantees and

insurances will be in place.

2. Length of MV & LV

distribution lines constructed

for rural towns/villages

around Potash and Salt

industry electricity access

(km)

n.a 0.4 kV, 481 Km

33KV, 1,524 Km

Page 10: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

vii

3. New high voltage

substations constructed for

Potash industry & rural

towns/villages electricity

access.

- Added Substation capacity

(MVA)

n.a

n.a

2

281

Risk 6: Financial viability of EEP (Low

tariff)

Mitigation: Implement cost reflective tariff

and expand export power to neighbouring

countries

4.Additional large industry

customers, No

n.a 3

5. Number of jobs created

during project

implementation (Semi-

skilled & unskilled)

-Temporary (% female)

-Permanent (% female)

n.a

n.a

4130 (35% fem)

2077 (35% fem)

Component C

Rural Electrification

4.Additional number of rural

towns connected

n.a 36

Risk 7: Scattered rural villages and public

institutions

Mitigation: Government plan to urbanize

rural villages and expanding electricity

access

5. Additional Rural

population benefited

- Connected households

(schools, health & social

centres, private businesses

and public institutions)

n.a

n.a

102,000 (45%

beneficiaries are

women)

20,400 (35

health & 43

educational

facilities )

Component D

Project Supervision and

Management

6. Supervision consultant

recruited

n.a 1

EA periodical &

Supervision

Mission Reports

Risk 8: Delays in recruitment of the

consultant

Mitigation: Consider using of Advance

contracting and timely no objection by the

Bank

Risk 9: Compensation & RAP

implementation delay

Mitigation: Make sure that the capacity &

skill mix of the team is adequate to manage

compensation and RAP implementation.

7. Delivered supervision

reports

- Project specific ESMP

developed and

implemented

n.a

n.a

12 Project

quarterly Reports

2 ESMP

Page 11: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

viii

Component E

Capacity Building

8. Number of staff trained

within the EEP and Ministry

9. Percentage of action points

of the Gender Audit

implemented.

n.a

n.a

35 (out of the

total 50% are

women)

75%

EEP & Energy

Ministry Reports

Risk 10: EEP Management may lack the

necessary commitment and capacity to

implement the action points of the Gender

Audit

Mitigation: Budget will be set aside for the

implementation of the Gender Audit action

plan and for the procurement of technical

assistance if needed.

KE

Y A

CT

IVIT

IES

CTIVITIES INPUTS (MUSD)

Components

Component A Transmission Lines

Component B Substations

Component C Rural Electrification

Component D Consultancy Services

Component E Capacity building & Feasibility

Study of Transmission Projects

Component F Distribution of advanced Cook

stove & Solar Panels (PV) including capacity

building

Component G Project Management, Audit,

Resettlement, Compensation and ESMF

Component A, USD 49.56 m

Component B, USD 29.70 m

Component C, USD 16.50 m

Component D, USD 3.35 m

Component E, USD 5.0 m

Component F, USD 0.5 m

Component G, USD 17.91 m

Total: USD 122.52 m

Page 12: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

ix

PROJECT IMPLEMENTATION SCHEDULE

Mekele – Dallol and Semera – Afdera Power Supply for Industrial Development and Access scale-up project

N

o Description

Year 2015 2016 2017 2018 2019 2020

Quart

ers 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 Concept Note approval

2 Project Approval

3 Effectiveness

Selection of Consultants

4 Bid Preparation

5 Bidding period

5 Evaluation, Contract

Award and Mobilization

6 Construction

7 Commissioning

8 Last Disbursement

Page 13: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE ADB GROUP TO

THE BOARD OF DIRECTORS ON A PROPOSED LOAN TO ETHIOPIA FOR MEKELE –

DALLOL AND SEMERA – AFDERA POWER SUPPLY FOR INDUSTRIAL DEVELOPMENT

AND ACCESS SCALE-UP PROJECT (MDSAPIAP)

Management submits the following Report and Recommendation on a proposed ADB loan of USD

104.61 million (UA 73.81 million) to finance the Mekele – Dallol and Semera – Afdera Power Supply

for Industrial Development and Access scale-up project (MDSAPIAP) in Ethiopia.

1. STRATEGIC THRUST & RATIONALE

1.1. Project linkages with country strategy and objectives

1.1.1 Ethiopia has made progress in all spheres of development and achieved a stable overall

macroeconomic performance and faster growth during the last ten years. The annual average real growth

rate of GDP of the country averaged 10.9% since 2004/05, placing it among the top performing economies

in the world. Growth has been broad-based and widespread and new jobs have been created in both the

public and private sectors, particularly through a boom in construction. All sectors have grown

significantly contributing to the overall growth registered in the country. On average, agriculture has grown

by 8.2%; industry by 14.4%; and services by 13.1% since 2004/05.

1.1.2 Its Growth and Transformation Plans (GTP I and II) outline equitable and inclusive development

and envisions the achievement of universal electricity access to its citizens by 2020. The GoE’s key

development objective, outlined in the just completed GTPI; (2011-15), and the new GTPII; (2016-2020)

is to achieve inclusive, accelerated and sustained economic growth and to eradicate poverty. Energy is one

of the nine priority sectors in the GTP. The sector is also underpinned through sound policy, legal and

strategic framework which includes the National Energy Policy (1994); new Energy Law, Proclamation

810/20131; Climate-Resilient Green Economy (CRGE) Strategy (2011) that outlines the green energy

development path and the 25 year Power Development Master Plan adopted in 2014, which describes the

national strategy and action plan for achieving the national electricity access and energy sector

development targets.

1.1.3 The 2016-2020 Country Strategy Paper (CSP) for Ethiopia was approved by the Bank’s Board of

Directors in March 2016. The CSP aligns with and facilitate attainment of GTP II objectives by continuing

to focus on: (i) Infrastructure development, especially energy, transport, and water and sanitations, and;

(ii) Promoting economic governance, with particular emphasis on facilitating effective and efficient

delivery of basic services and business enabling environment for private sector development. By aligning

with GTP II, the new CSP’s twin pillars are consistent with the objectives and core operational priorities

of the Ten Year Strategy (TYS) of the Bank and will contribute to the attainment of green growth and

climate resilience goals.

1.1.4 The Bank’s assistance strategy is part of the international donor community’s coordinated support

for the implementation of the Government’s Plan as articulated in Ethiopia’s Third Poverty Reduction

Strategy Paper, known as Growth and Transformation Plan (GTPI), covering the period under financial

years (FY) 2010/11 to 2014/15. A key objective set in the GTPI is to increase the country’s generating

capacity from 2,000 MW in 2010 to 10,000MW and electricity access from 41 % in 2010 to 75% by end

of 2015, particularly through the development of the country’s hydro power potential (estimated at over

45,000 MW but developed at less than 10% of this potential capacity to date) including other renewable

energy resources (wind, solar, geothermal.), electric power transmission and distribution infrastructure.

GTP-I had registered some progress in increasing the generation capacity from 2000 MW in 2010 to

1 New Energy proclamation has replaced the existed energy law in broader term and included both the electricity & energy

efficiency and conservation tasks. Proclaimed the establishment of the Ethiopian Energy Authority (EEA) under the

regulation of the Council of Ministers;

Page 14: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

2

4180 MW in 2015 and electricity access from 41 % in 2010 to 60 % in 2015 and the achieved results were

below the set target.

1.1.5 The GTP-II covering the period 2015/16 to 2019/20 has considered achievements made and

lessons learnt under the GTP-I implementation and will focus on sustained economic development with a

clear target of achieving improvement in the livelihoods of the population by promoting universal

electricity access program and maintaining sufficient, affordable & reliable supply of electricity by the end

of the period. As a result, there is going to be given significant emphasis on the energy sector.

1.1.6 The project is intended to: (i) provide sustainable power for the population of the North and North

Eastern parts of the country and potash mining industries, (ii) facilitate the implementation of the rural

electrification program and (iii) reduce high transmission losses and improve system efficiency, stability

and reliability. The project will thus result in increased economic activities and will enable Ethiopia to

further exploit its hydro & other renewable energy potential and enhance industrialization and commercial

business as well as improving the livelihoods of the rural population for sustained economic growth. As

such, the proposed project is in line with the Bank CSP 2016-20120 and the Government’s GTP-II

(2015/16-2019/20).

1.1.7 The project is aligned with the New Deal on Energy’s focus on supporting energy access and

in particular the need for the sector to add 130 million on-grid connections by 2025. This transmission

line and last mile connectivity project will not only contribute towards industrialization by providing

power for three industrial enterprises with related benefits for the economy but provide the conveniences

of modern energy access to over 100,000 people through the provision of household connections.

1.2. Rationale for Bank’s involvement

The intervention of the Bank has been requested and is justified in view of the following:

1.2.1 Ethiopia has made modest improvements during the last decade in access to electricity and basic

services according to the Ministry of Finance & Economic Development (MoFEC) annual report.2.The

country’s plan to meet its medium-term growth target of 10% and to increase the rate of the population

with access to electricity from 60% in 2016 to 90% by 2020 will be realised with a focus on grid based

rural electrification and off grid supply options and relying significantly on the development of adequate

transmission & distribution systems for power transfer to various parts of the country. This project will be

critical to meeting sufficient power transfer capacity to satisfy the growing industrial, commercial &

domestic demand (at initial stage 80 MW and will increase up to 200 MW by 2020) in the affected regions

and increase EEP’s revenue by USD 19 million at the initial stage from energy sales. This project will

support the Bank’s country strategy by providing support for improved access to infrastructure, enhanced

access to basic services and rural development through making available necessary power supply to meet

the growing demand.

A request from the Government of Ethiopia dated January 12, 2015 has been received by the Bank.

1.2.2 Most income generation schemes that communities are currently engaged other than agriculture

are traditional, uniform and meant mostly to meet daily needs. Some of the activities widely undertaken

include traditional informal salt mining, sell of fuel wood, gathering wild honey, etc. Hence the project

will transform the beneficiary regions by creating enabling environment to industries, small & medium

enterprises (SMES) to be engaged in exploitation of the abundant potash (estimated at l40 to l50 million

tons) and salt mines resources in the region which are currently suppressed due to lack of adequate and

sustainable power. In addition it will trigger inclusion of new salt extraction/iodizing industries (currently

30,000 tons/month salt is extracted by small private businesses) and commercial businesses, as well as the

expansion of basic infrastructure (health and education facilities notably) and job creation opportunities.

2 Population Access to Electricity (Service coverage) has been improved from 17% (2005) to 55% (2015)

Page 15: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

3

1.3. Donor Coordination

1.3.1 The Ministry of Finance and Economic Cooperation (MoFEC) is responsible for coordinating

donor financing within the sector. This is done through regular consultations between the GoE and the

Donors active in the energy sector through the Development Assistance Group (DAG). The DAG also

serves as a forum for donors to harmonize their strategies for intervention in all sectors including the energy

sector, and to share experiences from their respective areas of operation in the country to provide useful

lessons to the group for incorporation in future interventions. Furthermore, the DAG serves as the conduit

for development partners to assist the GoE in formulating policies as well as monitoring policy

implementation. The Bank’s country office in Ethiopia (ETFO) is playing a leading role in the DAG and

is currently serving as a Co-chair of the DAG Executive Committee. While there is no dedicated working

group for the energy sector, there is active sharing of information and harmonization of donors’ position

on key sector issues with a view to promoting long-term sector viability and growth on conducted

periodical Energy Sector Partners Group meetings.

1.3.2 The most active development partners (DPs) include: the World Bank, Japanese International

Cooperation Agency (JICA), French Development Agency (AfD), and European Investment Bank (EIB),

the Arab Bank for African Economic Development (BADEA), the Kuwait Fund, India, China, Italy and

the African Development Bank Group. The DPs are mainly involved in supporting (a) the Energy Access

projects aimed at helping the country establish a sustainable program for expanding the access to

electricity, and to improve the quality of electricity supply; (b) Energy project designed to increase the

efficiency and sustainability of Ethiopia's power sector; (c) the Universal Electricity Access Program

(UEAP); (d) Increase the hydro generation capacity and renewable energy mix (f) Urban distribution

system rehabilitation (g) Transmission and Substation rehabilitation & upgrading (h) Development of

geothermal power resources (for details see Appendix 3).

2. PROJECT DESCRIPTION

2.1 Project components

Table 2.1: Project Components

No Component Name Est. cost

(USD million)

Component description

A. Transmission Lines

Construction.

45.05

This component comprises of construction, on a turnkey basis,

the following two 230 kV transmission lines. (i) 130 km of 230

kV Mekele - Dallol line (ii) 175 km of 230 kV Semera-Afdera

transmission line

B Construction&

expansion of

substations.

27.00

This component comprises of extension of two substations at

Mekele & Semera and Construction of two new substations at

Dallol & Afdera, located in the north & North Eastern part of the

country.

C Rural Electrification

Access scale-up

15.00

This component comprises of construction of 1524 km of MV &

481 km of LV distribution lines, installation of distribution

transformers and connection of the rural & urban households

including energy meters.

D Project Supervision and

Management.

49.56

This component includes procurement of the consultancy

services for project management & s0u0pervision of the

construction contracts.

Page 16: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

4

E

Technical assistance &

capacity building

29.70

- This component includes procuring consultancy services for

undertaking of feasibility & ESIA/RAP studies & bidding

document preparation for identified power transmission

projects by EEP.

- Undertaking capacity building training program for EEP

staff involved in the project planning, design and

environmental (ESIA/RAP) studies.

- Provision of technical and capacity strengthening support in

the implementation of the Gender Audit action plan.

F Distribution of

advanced cook stoves

solar panels and energy

saving light bulbs

3.35

This component includes provision of energy saving stoves and

distribution of solar panels and energy saving light bulbs for

selected rural households & public utilities in Dallol & Afdera

area.

G EEP Project

Management and

Implementation of

ESMP, RAP and ESMF

5.00

This component, consists of EEP project design, management

and implementation of mitigation measures and compensation of

people affected by the project including the Rural Electrification

component ESMF implementation &. The Project has been

categorized in ADB environmental and social category I.

2.2 Technical solution retained and other alternatives explored

The Feasibility study selected the 230kV extensions based on the length of the lines and the maximum

required power transfer. The 230kV voltage level was considered based on the recommendation of

Ethiopian Power Systems Expansion Master Plan and technical-economic analysis study done by EEP

planning Department.

Table-2.2 Project alternatives considered and reasons for rejection

Alternative name Brief description Reasons for rejection

a) Using the existing

132 kV supply

option.

The feasibility study

considered extension of

existing 132 kV systems to

supply the demand.

The alternative option does not have adequate transfer capacity

to transmit the anticipated load of 200 MW and give technically

acceptable voltage at the receiving end. In addition the losses at

132 kV networks are considerably higher and leads to multiple

lines being strung in the future at potentially higher cost

compared to the construction of the 230 kV lines.

b) New generation Plant

capacity initially 80 MW

and will grow up to 200

MW

Construction of power

plants to service the local

demand and avoid

building long

transmission lines.

The option was discarded because even though initial cost of

diesel or thermal option is relatively low; it involves high

operation & maintenance costs which will result in high energy

costs to the users as compared to grid energy and notwithstanding

the environmental cost of the use of fossil fuels

2.3 Project type

2.3.1 The proposed project is an integrated project and includes transmission lines, substation &

rural electrification components. The two 230kV transmission lines are extended from existing 230

kV substations. The proposed new transmission lines will considerably expand the high voltage

transmission system and increase the power transfer capacity from the existing and future generating

sources to the major load centers in the country.

2.4 Project cost and financing arrangements

2.4.1 The project cost is estimated at USD 122.52 million (UA 86.45 million), comprising foreign

exchange costs (71%) of USD 86.67 million (UA 61.15 million) and local cost (29%) of USD 35.85

million (UA 25.30 million).The summary of the cost estimates by component, sources of financing

and by category of expenditure are shown in tables 2.2 below. Additionally, table 2.5 shows ADB and

Govt. financing which Govt.’s contribution is estimated to be USD 17.91 million (UA 12.64 million).

2.4.2 The Bank provides an ADB sovereign guaranteed loan amounting USD 104.61 million to

finance 85.4% of the total financial requirement of the proposed project. The remaining 14.6% (USD

17.91 million) of the project cost will be covered by the Government of Ethiopia. Detailed

Page 17: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

5

justification is provided in Appendix V for the relatively low counterpart fund for the proposed

project.

Table 2.3: Summary of Project Cost Estimates by Component

No. Component FC LC Total FC LC Total

In Million USD In Million UA

1 Mekele - Dallo

1.1 Transmission Line 17.68 4.42 22.10 12.47 3.12 15.59

1.2 Substation 12.80 3.20 16.00 9.03 2.26 11.29

Sub Total 30.48 7.62 38.10 21.51 5.38 6.88

2 Samara Afdera - - -

2.1 Transmission Line 18.36 4.59 22.95 12.95 3.24 16.19

2.2 Substation 9.90 1.10 11.00 6.99 0.78 7.76

Sub Total 28.26 5.69 33.95 19.94 4.01 23.95

3 Rural Electrification - - -

3.1 Medium and Low Voltage 12.00 3.00 15.00 8.47 2.12 10.58

Total for Transmission line 36.04 9.01 45.05 25.43 6.36 31.79

Total for Substation 22.70 4.30 27.00 16.02 3.03 19.05

Rural Electrification 12.00 3.00 15.00 8.47 2.12 10.58

Sub Total for TR, SS and RE 70.74 16.31 87.05 49.91 11.51 61.42

Price Contingency 5% 3.54 0.82 4.35 2.50 0.58 3.07

Physical Contingency 5% 3.54 0.82 4.35 2.50 0.58 3.07

Total Project Cost for Transmission,

Substation and Rural Electrification

77.81 17.94 95.76 54.90 12.66 67.56

4 Project Supervision and Management 3.35 - 3.35 2.36 - 2.36

5 Annual Audit - 0.10 0.10 - 0.07 0.07

6 Capacity Building Program 1.50 - 1.50 1.06 - 1.06

7 Feasibility Study for New transmission

line projects 3.50 - 3.50 2.47 - 2.47

8 EEP Project Management and design

Cost - 16.14 16.14 - 11.39 11.39

Total for Services 8.35 16.24 24.59 5.89 11.46 17.35

9 Compensation, Resettlement & ESMF - 1.67 1.67 - 1.18 1.18

10 Distribution of advanced cook stove &

Solar Panels (PV) including capacity

building

0.50 - 0.5 0.35 - 0.35

Total Project Cost 86.67 35.85 122.52 61.15 25.29 86.45

Table 2.4: Source of financing in million USD and UA

Source In Million USD

FC LC Total

ADB 86.67 17.94 104.61

Gov. Ethiopia 0 17.91 17.91

Total 86.67 35.85 122.52

Table 2.5 Financing expenditure schedule in million USD

Source

Year

2016 2017 2018 2019 2020 Total

In Million USD

ADB 1.0 30.88 36.37 25.9 10.46 104.61

Gov.

Ethiopia 0.5 5.12 6.15 4.35 1.79 17.91

Total 1.50 36.00 42.52 30.25 12.25 122.52

Page 18: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

6

2.5 Project’s target area and population

2.5.1 The project is located in the Northern and North Eastern part of the country in the Tigray & Afar

regional states traversing the Woredas Quiha, Enderta, Atsbi woneberta, Kileteawulalo in Tigray &

Kunoba, Berahale, Dallol, Afdera in Afar part of the target area; Afar region is an emerging region with

below national average level of development across all social and economic indicators and thus

implementation of the said project will significantly improve the socio-economic development and access

to the basic services of beneficiaries as well as the region.

2.5.2 The main project beneficiaries will therefore include (i) the power utility EEP (ii) rural & urban

households, industries, health & education facilities, commercial businesses and agriculture (irrigations)

which are currently without electricity supply (like Afdera woreda 36 primary & 1 Secondary schools and

6 health centers etc.….). Existing electricity consumers connected to the diesel generation supply will also

benefit from the supply and increased reliability of service as a result of the project.

2.6 Participatory process for project identification, design & implementation

2.6.1 Participation in identification was embedded in the government’s annual budget programming

process. In line with the National Energy Policy, which emphasizes the need for the development of

indigenous resources, Ethiopia has started to aggressively develop its immense hydro power & renewable

energy potential, both for internal consumption and export purposes. The energy generated at the remote

hydro sites has to be evacuated to the load centers through high voltage transmission network.

2.6.2 At design and preparation stage, views of the various stakeholders were captured through

meetings and workshops carried out as part of the ESIA, ESMP and RAP studies. The main objective was

to ensure all issues concerning the proposed project were covered. Consultations included stakeholders in

relevant government ministries, communities including women & project affected population (PAPs),

districts, national and international NGOs, civil society (SCO) and representatives of potash mining

companies. Awareness campaigns and participatory assessments such as discussions with local leaders,

public village meetings and interviews with focus groups were also held.

2.6.3 Results of the consultations have been incorporated into the project design. Issues were discussed

and consensus was reached on land acquisition procedures, compensation in terms of valuation and

timeliness for buildings and crops, the prospect of increased spread of HIV/AIDS and possibility of

connecting villages along the line, among other issues discussed.

2.6.4 Stakeholders participation modalities during project implementation will be through involvement

and follow-up on the compensation, RAP and ESMP activities, getting required periodical information

about the project progress and undertake a visit to construction sites to witness actual accomplishment.

2.7 Bank Group experience, lessons reflected in project design

2.7.1 The Bank Group has been a partner of the Ethiopian government in the development of the

electricity sub-sector for a long time. Since 1979, the Bank had provided financing for seven projects in

the sub-sector. The Bank has also been supporting Ethiopia’s effort to expand and exchange power with

its neighboring countries through financing the multinational projects. Support has been focused on

providing finance for the high voltage transmission lines, rural electrification and regional interconnection

projects of where the major ones are indicated in section 3.1 of the project summary. Currently there are

three ongoing projects under the Bank’s energy portfolio namely Rural Electrification-II project (RE-II),

Electricity Transmission System Improvement Project (ETSIP) and Ethiopia-Kenya Electricity Highway

with amount of financing close to UA 390 million. The interconnection project is expected to be completed

in 2018 and RE-II and ETSIP projects are progressing well and are expected to be completed by the end

of 2016. Each of the operations above ensured that the ESIA were properly handled.

Page 19: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

7

2.7.2 The Bank has 16 ongoing investment operations in Ethiopia with a total value of UA 1.138 billion

and the overall performance of the portfolio is highly satisfactory with an average Implementation Progress

(IP) rating of 3.1 and Development Objective (DO) of 3.50 as depicted in Appendix II. Some of the key

lessons learnt from the on-going projects under implementation in Ethiopia, as well as those supported by

other donors’, were taken into account in the formulation and design of the program. These include:

(i) Challenges have been faced on the on-going Rural Electrification program in connecting

rural households as per the plan due to scarcity of adequate energy meters and connection

accessories. In this project procurement of energy meters and connection accessories will

be packaged under the rural electrification component.

(ii) The lack of competent project management team coupled with frequent staff turnover has

in many occasions delayed project implementation. The project considered capacity

building of executing agency project implementation team, and the project will also hire an

experienced engineering consultancy firm for project management and supervision works.

(iii) There have been delays in submitting procurement plans, bidding documents, evaluation

reports and contracts execution. The Bank is continuously conducting training of

procurement experts & project management staff in the country to expedite procurement

process & project implementation.

(iv) As in the case with other similar projects, where construction works are located in dispersed

geographical areas, it is more cost effective and time saving to arrange them such that the

contractors do not have to move across the country to access the different sites. In this

project, proper procurement packaging (in lots) designed for transmission lines, substations

and rural electrification project components in conformance to the Bank procurement policy

and guidelines;

(v) Due consideration has not been given by implementing agencies to the follow-up and

monitoring of ESMP & RAP implementation. In the project implementation arrangement

adequate environmental & social experts are foreseen at the main project office and

construction sites level.

(vi) Repeated loan saving utilization request were received from Government which in turn has

caused project aging due to multiple extension of the disbursement deadline especially on

the Rural Electrification-II project. In this project it is attempted to establish more realistic

cost estimation of various components and required close follow-up for disbursement rate

as well as project implementation and take timely decision on utilization of significant

amount of saving.

2.8 Key performance indicators

2.8.1 The main deliverables of the project are: (i) construction of 305 km of 230kV single and double

circuit transmission lines: (ii) extension of two substations at Mekele & Sermera (iii) construction of two

new substations at Dallol (250 MVA ) & Afdera (31.5 MVA) (iv) construction of 1,524km of 33kV MV

and 481 km LV distribution lines with customer connection materials including energy meters; (v) creating

adequate electric power transmission capacity to industries and commercial businesses and electricity

access (vi) Beneficiary population in 39 rural and urban towns (102,000 ) and connected households

(20,400) (vii) full implementation of the ESIA and RAP measures (viii) Timely undertaking the feasibility

studies, ESIA, RAP and bidding documents preparation.

2.8.2 The project will allow the transfer of 200 MW to the north and north eastern parts of the country

towards Dallol, and 100 MW to the north eastern part of the country towards Afdera from the national grid.

Page 20: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

8

2.8.3 The progress during implementation will be monitored by the establishment of the Project

Implementation Team (PIT) which will ensure timely commencement of the works, regular disbursements,

timely submission of quarterly progress and environmental monitoring reports and annual audit reports.

3. PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.1.1 In order to determine the impact of the proposed investment, the Bank developed a financial and

economic model, based primarily on data from project technical feasibility studies prepared by EEP.

3.1.2 The financial and economic assessment of the project was undertaken over an operating period of

thirty five years starting in 2021. The investment will be carried out over four years (2017 to 2020). The

results of the analysis show that the project is financially sustainable and economically viable. Its financial

internal rate of return (FIRR) is estimated at 14.38% (real) while the financial net present value (FNPV)

discounted at a rate of 10% is equal to US$ 64.52 million. These figures were obtained on the basis of

weighted average tariff of US$ 0.06 per kWh charged across the different category of customers.

3.1.3 The main benefit for households being connected to the national grid is the supply of electricity

at a cheaper rate. The economic analysis of the proposed project was based on the willingness to pay of

the targeted population, estimated at around US$ 17 cents per kWh. The economic assessment of the

project results in an economic rate of return (EIRR) and economic net present value (ENPV) of 29.13%

and US$ 293.42 million (discounted at 12%, real).

3.1.4 The main financial and economic results are summarized in Table 3.1 below. The detailed

calculations and assumptions are presented in Annex B7.

Table 3.1: Main Financial and Economic Indicators

PARAMETERS VALUES

FIRR 14.38%

FNPV (@10%) US$ 64.52 million

EIRR 29.13%

ENPV (@12%) US$ 293.42 million

3.1.5 A sensitivity analysis was also performed against the key risk variables of the project to test the

robustness of its financial and economic cash flows. The identified key risks include an increase in

investment costs, an increase in operating costs, an increase of the energy generation costs and a reduction

in revenues, through a reduction of the end-user tariff. The results of the sensitivity analysis show that the

financial and economic results are robust under adverse conditions and also reveal that the metrics of the

project are more sensitive to a change in end –user tariffs and energy generation costs than to a change in

investment cost or operating and maintenance costs. Details of the financial and economic analysis, as well

as the sensitivity analysis, are provided in Annex B7.

3.2 Environmental and Social Impacts

3.2.1 Environment

3.2.1.1 Mekele-Dallol & Semera-Afdera Power Transmission project has been classified, as Category 1

in accordance with the AfDB’s Environmental and Social Assessment Procedures (ESAP) and the

Involuntary Resettlement policy. This classification is based on the voltage level of the lines, which is

230kV exceeding the Bank’s threshold of 110 kV and spanning on aggregate over 305km; and has a

potential impact of displacing more than 250 people in various settlements. This categorization is also

consistent with the Ethiopian Environmental Laws, Regulations and Ministry of Environment and

forestry,,Environmental Impact Assessment Procedural Guideline series 1, of November 2003, that

Page 21: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

9

requires the preparation of full Environmental and Social Impact Assessment (ESIA) and Resettlement

Action Plan (RAP) reports. The full ESIA & RAP reports are prepared end of November 2015 and

ESIA/RAP summary of the project was posted on the Bank’s Public Information Centre in March 2016,

with reference P-ET-FA0-011.

3.2.1.2 In general, the vegetation coverage of project area is low. Due to natural factors (disasters, agro

climatic change, etc.) have reduced the species diversity in the area. In the project areas, the dominant tree

species currently existing is Acacia. In the hot lowlands and dry-desert agro-climatic zones of the project

affected sites are characterized by dwarf shrub grass land, dry thorn bush land vegetation types which will

most likely be affected by the HV transmission line.

3.2.1.3 The diversity of wild animals in the study areas, as a whole, is low. However, according to the

information from the project site woreda agriculture office, some common wild animals currently existing

in the area might be affected and will potentially migrate to other locations. During the field assessment,

based on data sources obtained from the project affected areas, there were no unique bird species in the

areas, and therefore, there is no significant impacts on birds.

3.2.1.4 Extensive clearance of the way-leave can potentially create a specific biotope in areas with denser

vegetation hence may become hunting ground for carnivores. Furthermore, traffic impact may be expected

to occur during a short period at peak construction in the form of increased congestion on the main roads

passing through the project areas. All of these impacts are expected to be localized, short lived, and

reversible. Mitigation measures are included in detail in the ESMP. The project is also expected to result

in affecting 246 households through creation of the way-leaves for the transmission lines. All the

mitigation, monitoring and management measures proposed will be adopted by the EEP. The assessment

of the potential impacts are within the acceptable limits of the Ethiopian and African Development Bank’s

safeguard polices and guidelines.

3.2.1.5 An estimated USD 1.67 million will be made available in the project budget for ESMP

implementation and resettlement and compensation in accordance with AfDB policy on Involuntary

Resettlement taking into consideration country’s own involuntary resettlement policy.

3.2.2 Climate Change

3.2.2.1 The project categorized as climate change category- 2 and the there is no major direct climate risk

with regard to the project implementation. But will affect bushes and shrubs as a result of the formation of

right off ways (ROWs) and shall be cleared during the construction period, dust may arise due to the

construction works and traffic increase that causes dust pollution (air quality) and may sometimes result a

respiratory problem on some of the construction workforces and local communities living around and soil

erosion due to clearing of vegetation and excavation works. Some of the mitigation majors are; taking

proper route selection to minimize the ROW vegetation clearance, re-cultivating cleared areas with suitable

sediment binding grasses & trees, taking proper dust abatement measures (e.g. watering) where necessary,

and by using properly handled /maintained machineries.

3.2.2.2 Implementation of the project will foster development in the beneficiary regions hydroelectric

production areas. This will allow for substitution of the current use of generators using diesel fuel, which

releases greenhouse gases into the atmosphere, with less polluting cheaper hydroelectric production and

by way of providing access to electricity to the rural Ethiopians, will reduce the burning of woods for fuel

consumption and thus reduction of environmental degradation due to reduction of cutting trees that caused

depleting of forests. Improvements in the establishment and functions of various social facilities in the

targeted sites, such as; education, health, water supply and other social service facilitates will contribute

much to the creation of public awareness and participation on environmental protection activities.

Page 22: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

10

3.2.3 Gender

3.2.3.1 The project is not expected to cause any major negative impacts on either women or men both

during construction and during implementation. However, it suffices to say that the most potentially

negative impacts of the project will emanate from relocation and destruction of property including food

crops whose incidences impact women more than men. Women bear the disproportionate burden of

constructing the tukuls (small cottages) and taking care of children. Traditionally women in rural areas

tend to rely more heavily than men on informal support networks. Interruption to these networks due to

relocation will potentially affect women more than men. Implementation of the resettlement action plan in

the project has included women as committee members and women interests will be highly considered.

Similarly, the scourge of HIV/AIDS impacts more on women and girls more than men and this will be

made worse by the influx of male workers into the project area. The project will embark on HIV/AIDS/STI

awareness and prevention programs geared towards women and girls especially students.

3.2.3.2 The availability of power supply would ease the burden of women in the project area. It will

facilitate the setting up of grinding/flour mills within their vicinities, thus reducing the costs of service. It

would also promote the use of improved technology for the preparation of food using electric appliances

for cooking and baking. Water pumps will function better because of power supply. Hence, construction

of the envisaged project will reduce portage burden on women, which benefits the female members of the

communities in particular. It would also enhance the social communication and interaction of women both

within and outside of the Zone of Influence (ZOI).

3.2.3.3 During project implementation, women just like men will have the opportunity for direct and

indirect jobs. It is expected that 30% of the semi-skilled and unskilled temporary jobs will be designated

to women. In addition women also benefited from the permanent employment opportunities by the

executing agency (EEP) in operation and maintenance of the constructed facilities and emerging private

companies and businesses as a result of the electrification program. It is planned under this project

provision of energy saving stoves using sustainable cooking fuels to 25,000 households in the Afdera and

Semera regions at a total cost of ETB 3.0 million. The initiative shall complement and draw synergies from

programs that are being funded by the Norwegian Government and UNDP with the involvement of NGOs.

The estimated total cost for the intervention is USD 200,000 covering educational and social mobilization

campaigns and training of both men and women in the technology to be carried out by the Directorate of

Alternative Technologies at Federal and Regional levels. During operation, benefits to women shall include

improvements to existing social infrastructures and services within reach such as health and secondary

education services; and availability of flourmills will reduce the labor input by women and girls, thus

freeing up time for other productive uses and girls will devote more time to their education.

3.2.4 Social

3.2.4.1 The construction phase of the transmission lines will take approximately 24 months, and during

that period, the project will create a number of employment and business opportunities associated with the

construction works. Over 90% of the rural population economy is cattle rearing and few agricultural based.

The project will therefore enhance the economies in the project area hence contributing towards poverty

alleviation through creation of jobs for local communities and supply of reliable and affordable electricity.

The power project is expected to generate as many as 800 temporary jobs in semi-skilled and unskilled

areas, thus the project has the potential to inject into the local economies an estimated ETB 79 million over

the construction period. An additional 77 people will be employed during operation to operate each of the

constructed 2 new substations and in the 2 new district offices to be opened in Dallol and Afdera for

customer services and an estimated of 3500 temporary & 2000 permanent jobs in potash mining companies

during construction & start potash mining. Since the power transmitted will be within the national grid,

project benefits should be seen in a national context since the project will facilitate economic growth in

the project area and nation through industrial growth in sectors such as manufacturing, agriculture and

services, resulting in more jobs being created hence increased incomes.

Page 23: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

11

3.2.4.2 During construction, several direct jobs will be created, including sub-contracting to local

transmission and substations contractors, supply of local materials, such as cement and reinforcement bars,

and casual labor for construction that could be sourced directly from the project area as well as contracts

for services such as security, bush clearing, digging and catering. Salaries, wages and fees to construction

workers and local sub-contractors will give a boost to the local economy. It is estimated that 15-20% of

project costs could be spent in the project area.

3.2.4.3 Although there are on-going awareness campaigns against the dangers of HIV/AIDS/STI and TB,

field workers such as those to be employed under this project may inevitably indulge in behaviors that may

put them at risk of contracting or spreading the diseases. The project, therefore, will put in place and made

provisions for implementing awareness and prevention campaigns for both contractor workers and the

communities in the project areas. A provisional sum has been included in the ESMP for HIV/AIDS and

STI awareness and prevention activities.

3.2.5 Involuntary resettlement

The project will result in affecting 246 households through creation of the way leave for the transmission

line, tower foundations, access roads and establishing sub-stations. Main types of the assets that are to be

affected are corrugated iron sheet (CIS) & small cottage houses, permanent loss of land etc.….The project

has set aside ETB 3,724,031 (equivalent of USD 178,524.73) for implementation of the resettlement action

plans (RAPs) for both lines (see Annex B8 for details). This will ensure that PAPs will be compensated

for all their losses at full replacement costs before start of the construction work for each particular

phase/section of the project and implemented in accordance with AfDB policy on Involuntary Resettlement

and Integrated Safeguards System (ISS) which became operational in July 2015. Implementation will be

done by EEP which has accumulated sufficient experience over the years in managing resettlement and

compensation actions.

3.2.6 Stakeholders

3.2.6.1 Stakeholder consultations were performed during project preparation and conceptualization

mainly through the ESIA and RAP exercises. Public Consultations were made with Zone, City, Woreda &

Kebele administrative officials and affected people, and selected communities at Berehalie Woreda.

Consultations and disclosure meetings were held with the affected community household members, elders

and chairpersons of the Kebele (Peasant) Associations. The outcome of consultation with main

stakeholders has shown that; (ii) they are supportive to the project; (iii) concerned raised have been taken

into account and the project design was informed accordingly.

3.2.6.2 All key agencies such as Ministry of Finance and Economy Cooperation (MoFEC), Ministry of

Environment and Forest (MoEF), Ministry of Water Irrigation and Electricity (MoWIE) and Ethiopian

Electric Power (EEP), Tigray & Afar Regional Governments will be served with copies of the respective

ESIAs. Zone and Woreda Administration offices will also be supplied with copies to be shared and

discussed with local leaders. The Bank also posted the Executive Summary of the ESIA and RAP its

website.

4. IMPLEMENTATION

4.1 Implementation arrangements

4.1.1 The GoE, through the Ministry of Finance and Economic Cooperation (MoFEC) will be the

borrower of the loan. Ethiopian Electric Power (EEP) will be the executing agency. The loan proceeds

will be transferred to EEP, a state institution established as per Council of Minsters rergulation

No.302/2013, as amended whose mandate is to implement the project by signing a subsidiary loan

agreement (on-lending) with the MoFEC on terms and conditions acceptable to the ADB.

Page 24: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

12

4.1.2 The day to day implementation of the project will be under the responsibility of a Project

Implementation Team (PIT). The PIT is headed by a Project Coordinator reporting to the Deputy

Executive Officer of Portfolio Management Office of EEP. The Project Coordinator is assisted by four

Site Managers. They will be located in Mekele, Dallol, Semera & Afdera. In addition a project

accountant, dedicated for the project and an Environmental & Social Officer to closely follow ESMP &

RAP implementation will also assist the project coordinator. Additional supervisors will also be

assigned as necessary. Project accounting and reporting in accordance with the Bank’s requirements

will be done at Project Coordination Office. In this regard, six appropriately qualified and experienced

accountants will be assigned by EEP (2 at the Project Coordination Office and 4 for each of the four

sub-sites).

4.1.3 Selection of the consultant for project supervision and management will be done prior to award

of the contract for construction.

4.1.4 The project implementing arrangements for the Mekele-Dallol & Semera-Afdera Project

including the Rural Electrification Component will comprise the overall Project Coordination Office

and four sub-offices at each of the project sites. EEP will submit the CVs of the Project Coordinator,

Site Managers and two accounting staff to be assigned at the project office for the Bank’s approval. The

establishment of the project implementation team at EEP, with qualifications and experience acceptable

to the Bank is one of the conditions for the Loan negotiation. The profiles of the project coordinator,

site managers and two accountants are given in technical annex B.3 implementation arrangement.

4.2 Procurement Arrangement

4.2.1 All Bank financed procurement contracts of goods, works and acquisition of consulting

services will be carried out in accordance with the Procurement Policy for Bank Group funded

operations, dated October 2015 and the provisions stipulated in the Financing Agreement.

4.2.2 Ethiopian Electric Power (EEP) through the procurement process to be undertaken by the

Procurement, Logistics and Warehouse Directorate, will be responsible for the procurement. The overall

project risk for procurement is moderate as the capacity of Procurement, Logistics and Warehouse

Directorate was assessed and found adequate to handle procurement with a recommendation to recruit

an additional procurement specialist to help the project. Advance Contracting (AC) procedures will be

followed with the objective of expediting important procurement processes. The project’s abbreviated

procurement plan was discussed and prepared during appraisal as part of the Procurement Technical

Annex and EEP team will prepare detailed Procurement Plan and submit prior to Loan negotiation.

Details of the procurement arrangements under the project are summarized in the Procurement

Technical Annex B5.

4.3 Financial Management

4.3.1 The Financial Management System of Ethiopian Electric Power (EEP) is adequate and capable of

recording accurate and complete transactions and delivering financial reports timely. The company uses

an automated financial reporting system, AGRESSO, which is specifically designed to meet the needs of

its operations. EEP has adequate and qualified staff to carry out the financial management responsibilities

of the project. As EEP is established as an autonomous public enterprise (Regulation No.302/2013), it is

responsible for the planning, budgeting, financial management, execution and monitoring of its projects.

EEP is financially autonomous and does not receive any budget allocation from the federal government.

Its budget is approved independently by the Board of Management. A detailed financial management

assessment is attached as technical annex B.4.

4.3.2 In line with the Paris Declaration on Aid Effectiveness and Accra Agenda for Action, the project

will make use of the Ethiopia’s Public financial management systems. The day to day management will be

as per the financial management policies and systems of EEP, as has been the case for previous projects

financed by the Bank. The Company will set up new account codes (as extended from the main chart of

Page 25: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

13

accounts of the company) to record and report the financial transactions of the project within its accounting

system. Bank financed projects executed by EEP so far have demonstrated timely preparation of financial

statements with annual audit reports submitted to the Bank within a reasonable period of time. The audits

for all ADF financed projects and other projects for previous years were carried out by Audit Services

Corporation. All project audit reports for the FY 2014/2015 were submitted in time and draft statements

of project accounts for the FY 2014/2015 are also timely submitted.

4.3.3 The former EEPCo’s Corporate account for the FY 2011/2012 audit was issued with an “except

for” opinion and the FY 2012/2013 audit report with ‘Adverse’ opinion with recommendations given on

the inaccuracy of debtors, treatment of project costs incurred and projects not yet materialized and

treatment of exchange rate losses in their construction projects. EEPCo’s 2013/2014 account is closed and

draft statement prepared but not audited as they are in the process of finalization of division of assets and

other properties which took longer period than expected. This is observed to be one of the critical risk areas

due to backlog of two years’ unaudited financial statements.

4.3.4 The project implementing arrangements for the Mekele-Dallol & Semera-Afdera project will

comprise the overall Project Coordination Office and four sub-offices at each of the project sites. Project

accounting and reporting in accordance with the Bank’s requirements will be done at Project Coordination

Office. In this regard, six appropriately qualified and experienced accountants will be assigned by EEP

(two at the Project Coordination Office and one each for the four sub-sites). EEP will submit the CVs of

the two accounting staffs to be assigned at the project coordination office to the project for the Bank’s

approval.

4.3.5 Disbursement Arrangements: EEP will utilize the Bank’s four disbursement methods explained

in the Disbursement Handbook. However, due to the project nature and arrangement, it will mainly use the

Direct Payment method. No Special account method is to be used unless it is agreed between the Bank and

the EEP due to certain circumstances to occur during the implementation period. The Bank’s Disbursement

Letter will be issued stipulating key disbursement procedures and practices.

4.3.6 Audit Arrangement: The project financial statements will be prepared within three months after

the closure of every financial year and presented to the auditors by 30 September and financial statements

will be audited by independent and competent audit firm competitively recruited. The audit is to be

conducted based on the Bank’s audit terms of reference in accordance with the International Standards for

Auditing (ISA). The complete audited project financial statements, including a management letter, will be

submitted to the Bank within six (6) months after the end of the fiscal year.

4.4 Monitoring and Evaluation

4.4.1 EEP’s performance is monitored through the preparation of periodic monthly and quarterly

reports for both senior management and the Board. There are established performance indicators and

budgets against which actual reporting is done and significant variances explained. The Bank requires

quarterly progress reports showing cash receipts by sources and expenditures by main expenditure

classifications together with physical progress reports linking financial information with physical progress

and highlighting issues that require attention. The sector indicators for power infrastructure projects, as

captured in the log frame, will be monitored using reports produced by MoWIE, EEP and the Ethiopia

Energy Authority (EEA).

4.4.2 The Project will be launched in the 1st quarter of 2017 and will be monitored through supervision

missions from the Bank’s headquarters, Regional Resource Centre and the Ethiopia country office (ETFO)

at least twice a year from 2017 through to 2019. The Bank supervision will also involve desk supervisions

including review of bi-annual progress and annual audit reports. The ETFO will also carry out field

supervisions twice a year or on a need basis. The coordination of the missions will be done by the MoFEC

in collaboration with the MoWIE.

Page 26: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

14

4.4.3 The PIT, assisted by the consultant, has the primary responsibility for monitoring project

implementation and fulfilling EEP’s reporting obligations to the Bank, including preparation and

submission of Quarterly Progress Reports (QPRs) and annual audit reports. These reports shall cover all

aspects of project implementation, including the status of progress, implementation of environmental and

social mitigation measures as well as status of fulfilment of the loan conditions. Moreover, EEP shall

maintain separate accounts that permit the identification of expenditures by category and financing source

for all components of the project.

4.4.4 The supervision consultants shall be required to prepare and submit to EEP and the Bank, final

commissioning reports at the completion of their assignments and assist the employer in Project

Completion Report (PCR) preparation. After the commissioning of the project, the EA will prepare the

PCR, which would serve as input in the preparation of the Bank’s own PCR.

4.4.5 During implementation, EEP’s Environmental, Health, Safety& Quality (EHS &Q) Office

assisted by the consultant will monitor the ESMP and will prepare and submit to the Bank quarterly

environmental reports. The EHS & Q Unit has been handling such tasks and is fully conversant with Bank

procedures. The Environmental Unit under the MoWIE will also be actively involved during the

monitoring phase.

4.4.6 Mid-Term Review (MTR): The Bank mid-term review of the project will be held not later than

18 months after the loan approval, which shall inform any adjustments to the project design to ensure that

project objectives are achieved.

4.4.7 Implementation Schedule and Supervision: The project will be implemented over a period of 24

months. On the assumption that the ADB loan is approved in July 2016, the project physical work

scheduled for completion by September 2018 with the commissioning of all sections of transmission lines,

substations and Rural Electrification component. The critical milestones for project implementation are

given below:

Table 4.2 Project Implementation milestones

No. Activity Responsible

Agency

Target Date

1 Loan Approval ADB July 2016

2 General Procurement Notice ADB/EEP June 2016

3 Loan Signed ADF/EEP September 2016

4 Effectiveness EEP October 2016

5 Recruitment of the Project Supervision

and Management Consultant

EEP/ADB July 2016

6 Bid document submitted to the Bank EEP May 2016

7 Review of bidding document and no

objection

ADB June 2016

8 Bidding EEP July -August y 2016

9 Evaluation, no objection EEP/ADB September-October 2016

10 Contract Signature for construction and

Mobilization

EEP/ADB

November 2016 to Jan.,

2017

11 Construction completion &

Commissioning

Contractors February 2019

12 Project Completion Report EEP/Consultant December 2019

4.4.8 All contractors for the line and substations will be mobilized at site in January 2017. Before

commencement of the construction work EEP will implement the environmental mitigation measures as

per the recommendation of ESIA report. The manufacturing, supply and installation of two sections of the

line and the substations will be undertaken in parallel and completed within 24 months from contract

commencement. The testing and commissioning of the transmission lines and substations is planned to

take place in January-February 2019, and the project will be operational by March 2019.

Page 27: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

15

4.5 Governance

4.5.1 EEP is managed by the Board of Directors consisting of 9 members from various Ministries and

Government organizations and the CEO of EEP. The Board holds monthly meetings and works closely

with the Management Committee of EEP with regard to the overall activities of the company. The internal

controls of the company are very effective in monitoring the utilization of its resources. Furthermore,

EEP’s financial statements are audited annually by the Audit Service Corporation (ASC), a governmental

entity which carries out annual audits for public and private organizations in the country. However

employing (contracting) other competent private audit firms is also possible under competitive selection.

At the project level, the project office will be required to maintain accounting and financial records that

will be audited in accordance with international accounting standards.

4.5.2 In general, the energy sector’s governance issues are well-articulated in Ethiopia. Currently, the

country has begun undergoing Civil Service Reform Programs to attain competitiveness and accountability

in all sectors including the energy sector. Furthermore, the Government has established an Anti-Corruption

and Ethics Commission with the objective of fighting corruption at all levels and enhancing transparency

and accountability. The commission is being strengthened through technical assistance programs from

some development partners.

4.6 Sustainability

4.6.1 Government Commitment: GoE has shown great commitment to implementing the project due

to the fact that the project will provide support to transmit sufficient power for industrial development and

electricity access scale-up so as to strengthen the national economy and livelihoods of the population.

4.6.2 Technical Sustainability: EEP has over the decades implemented similar projects and the staff

has gained considerable experience in the implementation of such projects and also has staff that is

experienced in the operation and maintenance of high voltage transmission lines, substations and

distribution network. In addition EEP has allocated significant amount of financing for the rehabilitation

and upgrading of the existing installations to get assurance of sustainability of the electricity supply.

Capacity building for EEP staff involved in engineering, operation & planning functions foreseen in the

project design.

4.6.3 Financial Sustainability: The tariff system in Ethiopia is still a cautious tariff regime. A uniform

tariff is charged with a lifeline tariff for the first block of 50kWh of consumption maintained since the last

tariff change in July 2006. Current tariffs average US¢0.0273/kWh across all consumer categories and

tariff levels this low cannot cover all non-power operating costs and purchased power costs and effectively

place the utility in a position whereby it has a strong financial disincentive to connect additional consumers.

If tariffs are not periodically adjusted to cover these costs, the financial situation of the electric utilities

will deteriorate resulting in decreasing service quality and impacting the sustainability of electricity

supply services. As a mitigation measure Government supports () in capital injection through financing

some of capital investments and granting debt restructuring to reduce the burden of loan repayments from

cash flows and foreign earnings from energy exports that commenced to Sudan and Djibouti generating

close to USD 100 million per annum and committed 400 MW to Kenya by 2018. In addition, EEP & EEU

appears to be working within the framework of achieving a selling price of electricity placed or suppressed

to a rate equivalent to US¢0.06/kWh depending on the prevailing exchange rate. Recently, EEP has

submitted a gradual cost recovery tariff adjustment proposal initially up to 50% increase adjustment

because the rate has fallen below the benchmark rate of at US¢0.06/kWh due to mostly foreign exchange

fluctuations and increase in operation expenses.

The request is under consideration by the EEA and final decision is expected after undergoing scrutiny in

the Council of Ministers and the parliament, and revised tariff expected to be implemented in the year

2017.

Page 28: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

16

4.6.4 Institutional Sustainability: The Sector undergone reform by restructuring of the monopolistic

former entity (EEPCo) into two independent entities mandated; EEP to the bulk generation, transmission

and substation operation and construction of new installations and EEU to be responsible for distribution

system operation, energy sales and customer services through commercialization and decentralization of

their operations to achieve efficiency & effectiveness.

4.6.5 Private sector participation: The public sector-led development strategy implemented over the

past decade, focusing on heavy investments in infrastructure, has sustained strong economic growth, which

reached an estimated 10.3% in 2013/14, which is over doubled of the Sub-Saharan Africa (SSA) average

growth rate. However, currently the government acknowledged that private sector involvement is crucial

to sustain the achievements so far made and continue the growth. The new energy policy allows local

private investment in generation facilities up to 25 MW (hydro, thermal and renewables) including

community organized cooperatives and similar entities. Over 25 MW, the policy allows local or foreign

investment in power projects.. The recent agreement with a private company to develop 2,000 MW

Corbetti geothermal power plant on IPP basis is also a demonstration of the Government’s intention

towards gradual opening of the power sector for private sector participation. The Bank also supported the

‘Roadmap to the Public Private Partnerships Framework in Ethiopia” study which was completed in 2014,

recommending government to issue a Public Private Partnerships (PPPs) policy statement.

4.7 Risk management

The major risks and mitigating measures during project implementation are outlined in the table below:

Table 4.3 Risk Management

Risk Description Rating Mitigation measures Starting potash

production

Delay in completion the

construction of private sector

potash industries

High The private sector investors received investment and

mining permits and are actively mobilized on site

and completed resources assessment and

verification.

Availability of sufficient

power

Inability to supply adequate

power to the industrial area and

rural towns

High Ethiopia is currently building about 6,000 MW

generation capacity which will be operational in

2018

Shortage of financing

resources

Insufficient fund for project

implementation

Medium Government support to financing (counterpart

funding) and commitment to implement,

transmission system and rural electrifications

components

Project completion delay Electricity supply infrastructure

projects implementation delay

High Deployment of project management and

supervision consultant ahead of start of the project &

re-enforcement of PIT.

Delays in recruitment of

the consultant

Procurement process execution

will take long time

Medium Consider using of Advance contracting and timely

no objection by the Bank

Lack commitment and

capacity to implement the

action points of the

Gender Audit

EEP Management may lack the

necessary commitment and

capacity to implement the

action points of the Gender

Audit

Low Budget will be set aside for the implementation of

the Gender Audit action plan and for the

procurement of technical assistance if needed.

Project cost overrun Project implementation cost

exceeding the allocated budget

Medium Physical (5%) and price (5%) contingencies built

into the project costs and the contract packaging

will ensure that all necessary construction guarantees

and insurances will be in place

Page 29: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

17

Risk Description Rating Mitigation measures Financial viability of EEP

(low tariff)

Tariff levels is below true costs

of producing, transmitting and

distributing electricity

(including financing costs)

Medium

- Government has been very supportive through

financing some of capital investments and granting

debt restructuring to reduce the burden of loan

repayments on EEP’s cash flows.

- Whilst EEP does not currently employ foreign

exchange hedging mechanisms, the impact of ETB

devaluation will be mitigated through foreign

earnings from energy exports that commenced to

Sudan and Djibouti by 2011 generating close to

USD 100 million per annum and committed 400

MW to Kenya by 2018. In addition, the process to

revise the existing tariff and gradual increase to $

0.06/kWh has started, and will also contribute

much for improvement in financial viability.

Timely implementation

of compensation & RAP

Resettlement and compensation

program may not be

implemented in a timely

manner owing to capacity

limitation and litigations which

might arise.

Medium Appraisal mission has critically examined the

implementation program, the skill mix composition

of the team implementing the agreed plan to ensure

that the team has adequate experience and

competence mix on resettlement and compensation

issues.

Note: Risk rating (high, medium or low)

4.8 Knowledge building

4.8.1 The proposed project area is located in one of the hottest part of the country. The project

provides an opportunity to the staff of EEP in building transmission lines, associated substations and

distribution lines in difficult climatic areas. Therefore, during the construction of the transmission line

and the installation of the equipment, EEP’s staff will be trained on the job by the contractors and the

consultant. The Bank staff involved in the project will also gain access to the technology which could

be applied to other regional member states that intend to build similar projects.

4.8.2 The ESIA and the ESMP for the project conducted by EEP conform to international practices

on Health, Safety and Environment (HSE) standards. Implementation of the ESMP including the

monitoring system will allow the EEP to promote best international practice in operating transmission

system of such voltage level. EEP’s knowledge building resulting from the Bank’s intervention will

help GoE to attract more investment in the power generation & transmission sector. In turn the Bank

will also learn from the lessons learned from its planned supervision on how best to promote high HSE

standards.

5. LEGAL INSTRUMENTS AND AUTHORITY

The Project will be governed by a Loan Agreement between the Bank and the Federal Democratic

Republic of Ethiopia.

5.1 Conditions associated with Bank’s intervention

A. Condition Precedent to Entry into Force of the Loan Agreement

The Loan Agreement shall enter into force subject to fulfilment by the Borrower of the provisions of

Section 12.01 of the General Conditions Applicable to Loan and Guarantee Agreements of the Bank.

Page 30: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

18

B. Conditions Precedent to First Disbursement of the Loan in Respect of Consultancy Services

for an amount not exceeding 3.35 million USD :

The obligation of the Bank to make the first disbursement of the Loan shall be conditional upon:

i. the entry into force of the Loan Agreement ;and

ii. The first disbursements of the Loan for an amount not exceeding 3.35 million USD (the

“First Disbursements”) shall be made by the Bank to the Borrower and the Borrower

shall apply such First Disbursements, solely for the purpose of the payment of

consultancy services in connection with the Project Supervision & Management services

for the Project (the “Consultancy Services”);

C. Conditions Precedent to Subsequent Disbursement of the Loan

The obligation of the Bank to make the subsequent of the Loan shall be conditional upon submission

by the Borrower of evidence satisfactory to the Bank that the following conditions have been fulfilled:

i. an On-lending Agreement has been signed between the Borrower and EEP in which the

Borrower on –lending the loan to EEP, on terms and conditions acceptable to the Bank.The

Borrower has submitted to the Bank a Works and Compensation Schedule (the “Works

and Compensation Schedule”) detailing (A) each section of civil works under the Project

and (B) the time frame for compensation and resettlement of all project-affected persons

in respect of each section, in accordance with the RAP or an updated RAP.

ii. Have compensated and/or resettled in accordance with the RAP and the Works and

Compensation Schedule, all Project Affected Persons in respect of the civil works under

the first section or lot of the Project.

D. Other conditions:

iii. The Borrower shall, based on tariff review recommendations received from Ethiopian

Energy Authority, maintain electricity tariffs at levels that enable EEP to achieve a positive

operating margin”.

5.1.1 Undertakings: The Borrower shall ensure that:

(i) EEP recruits additional Environmental and Social experts to strengthen its environmental

and social team;

(ii) Fully implements the recommendations of the Environmental and Social Impact

Assessment (ESIA), Environmental and Social Management Plan (ESMP) and the

Resettlement Action Plan (RAP) of the project, and comprehensively reports to the Fund

on the said implementation on a quarterly basis;

(iii) EEP undertakes to revise the current tariffs up to the level of cost reflective tariffs the latest

by March 2017 to ensure its financial sustainability.

6. RECOMMENDATION

6.1 Management recommends that the Board of Directors approve the proposed ADB loan of USD

104.61 million (UA 73.81million) to the Federal Democratic Republic of Ethiopia for the purposes and

subject to the conditions stipulated in this report and the Loan Agreement.

Page 31: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

I

Appendix I: Comparative socio – economic Indicator3

3 Sources: AfDB Statistics Department Databases; last update :May 2014; For any given interval, the value refers to the most recent year available during the

period Note: n.a.: Not Applicable ; … : Data Not Available

Year Ethiopia Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2015 1 104 30 067 80 386 53 939Total Population (millions) 2015 99,4 1 184,5 5 945,0 1 401,5Urban Population (% of Total) 2015 19,4 39,7 47,0 80,7Population Density (per Km²) 2015 99,4 40,3 78,5 25,4GNI per Capita (US $) 2014 550 2 045 4 226 38 317Labor Force Participation * - Total (%) 2015 83,7 66,3 67,7 72,0Labor Force Participation ** - Female (%) 2015 78,3 56,5 53,0 64,5Gender -Related Dev elopment Index Value 2007-2013 0,853 0,801 0,506 0,792Human Dev elop. Index (Rank among 188 countries) 2014 174 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population) 2008-2013 36,8 39,6 17,0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2015 2,5 2,6 1,3 0,6Population Grow th Rate - Urban (%) 2015 4,9 3,6 2,6 0,8Population < 15 y ears (%) 2015 41,4 41,0 28,3 17,3Population >= 65 y ears (%) 2015 3,5 3,5 6,2 16,0Dependency Ratio (%) 2015 81,6 80,1 54,6 50,5Sex Ratio (per 100 female) 2015 99,6 100,1 102,8 97,4Female Population 15-49 y ears (% of total population) 2015 24,3 24,0 25,8 23,0Life Ex pectancy at Birth - Total (y ears) 2015 64,6 61,2 68,9 79,1Life Ex pectancy at Birth - Female (y ears) 2015 66,6 62,6 70,8 82,1Crude Birth Rate (per 1,000) 2015 31,9 34,8 21,0 11,6Crude Death Rate (per 1,000) 2015 7,2 9,3 7,7 8,8Infant Mortality Rate (per 1,000) 2015 41,4 52,2 35,2 5,8Child Mortality Rate (per 1,000) 2015 59,2 75,5 47,3 6,8Total Fertility Rate (per w oman) 2015 4,3 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2013 420,0 411,3 230,0 22,0Women Using Contraception (%) 2014 34,4 35,3 62,1 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 2,5 46,9 118,1 308,0Nurses and midw iv es (per 100,000 people) 2004-2012 25,3 133,4 202,9 857,4Births attended by Trained Health Personnel (%) 2009-2012 10,0 50,6 67,7 ...Access to Safe Water (% of Population) 2015 57,3 71,6 89,1 99,0Healthy life ex pectancy at birth (y ears) 2012 55,0 51,3 57 69Access to Sanitation (% of Population) 2015 28,0 39,4 60,8 96,3Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 1,2 3,8 1,2 ...Incidence of Tuberculosis (per 100,000) 2013 224,0 245,9 149,0 22,0Child Immunization Against Tuberculosis (%) 2013 71,0 84,1 90,0 ...Child Immunization Against Measles (%) 2013 62,0 76,0 82,7 93,9Underw eight Children (% of children under 5 y ears) 2005-2013 29,2 20,8 17,0 0,9Daily Calorie Supply per Capita 2011 2 105 2 621 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 3,1 2,7 3,1 7,3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 87,0 106,4 109,4 101,3 Primary School - Female 2011-2014 80,5 102,6 107,6 101,1 Secondary School - Total 2011-2014 28,9 54,6 69,0 100,2 Secondary School - Female 2011-2014 22,3 51,4 67,7 99,9Primary School Female Teaching Staff (% of Total) 2012-2014 36,7 45,1 58,1 81,6Adult literacy Rate - Total (%) 2006-2012 39,0 61,8 80,4 99,2Adult literacy Rate - Male (%) 2006-2012 49,1 70,7 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 28,9 53,4 75,2 99,0Percentage of GDP Spent on Education 2009-2012 4,7 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2013 15,1 8,6 11,9 9,4Agricultural Land (as % of land area) 2013 36,3 43,2 43,4 30,0Forest (As % of Land Area) 2013 12,4 23,3 28,0 34,5Per Capita CO2 Emissions (metric tons) 2012 0,1 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Ethiopia

november 2015

0

10

20

30

40

50

60

70

80

90

100

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Infant Mortality Rate( Per 1000 )

Ethiopia Africa

0

500

1000

1500

2000

250020

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

GNI Per Capita US $

Ethiopia Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Population Growth Rate (%)

Ethiopia A frica

01020304050607080

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Life Expectancy at Birth (years)

Ethiopia Africa

Page 32: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

II

Appendix II: Table of ADF Portfolio in the Country ETHIOPIA -ONGOING PORTFOLIO 15 MAY 2016

No Project

Loan/Grant Disbursement

IP DO PFI Status

Age

Approval

Date

Amount

(UA) Ratio Years.

PUBLIC SECTOR OPERATIONS

AGRICULTURE SECTOR 58,482,000

1 Drought Resilience and

Sustainable Livelihoods I 19-Dec-12 30,000,000 10.64% 2 3 PPP 3.4

2 Drought Resilience and

Sustainable Livelihoods II 26-Nov-

14 28,482,000 3.20% NR NR

NON-

PP/NON PPP 1.5

TRANSPORT SECTOR 316,770,000

3

Mombassa-Nairobi-

Addis Road Corridor –

Agere Mariam -Yabelo

Road Project (Phase II)

1-Jul-09 85,000,000 84.83% 3.77 4 NON-

PP/NON PPP 6.9

4

Mombassa-Nairobi-

Addis Road Corridor-

Hawassa-Agere Mariam

Road Project (Phase III)

30-Nov-11 105,000,000 40.16% 3 3 NON-

PP/NON PPP 4.5

5 Bedele-Metu Road

Upgrading 10-Nov-11 41,060,000 62.71% 3 3

NON-

PP/NON PPP 4.5

6

Modjo- Hawassa

Highway Road Project

Phase I 6-Nov-13 84,080,000 17.78% NR NR

NON-

PP/NON PPP 2.5

Modjo- Hawassa

Highway Road Project

Phase I* 6-Nov-13 1,630,000 2.21% NR NR

NON-

PP/NON PPP 2.5

ENERGY SECTOR 388,950,000

7 Rural Electrification II

Project 20-Dec-06 87,200,000 82.35% 3.82 3.5

NON-

PP/NON PPP 9.4

8

Electricity Transmission

Systems Improvement

Project 6-Dec-10 93,750,000 86.28% 3.85 4

NON-

PP/NON PPP 5.4

Electricity Transmission

Systems Improvement

Project* 6-Dec-10 58,000,000 96.83% 3.85 4

NON-

PP/NON PPP 5.4

9

Ethiopia-Kenya

Electricity Highway

Project 19-Sep-12 150,000,000 15.05% 3 3

NON-

PP/NON PPP 3.7

WATER SECTOR 120,027,122

10

Support to the One

Water Sanitation and

Hygiene National Water

Program

8-Sep-14 60,000,000 29.69% 3 3 NON-

PP/NON PPP 1.7

Support to the One

Water Sanitation and

Hygiene National Water

Program*

8-Sep-14 6,015,073 37.86% 3 3 NON-

PP/NON PPP 1.7

11

Four Towns Water and

Sanitation Improvement

Program 13-Jan-16 54,012,049 NR NR

NON-

PP/NON PPP 0.3

MULTI - SECTOR 186,143,000 0

12 Basic Services

Transformation Program 17-Dec-15 180,000,000 NR NR

NON-

PP/NON PPP 0.4

13 Institutional Support

project for PPPs* 26-May-15 1,173,000 10.73% NR NR

NON-

PP/NON PPP 1.0

14

Ethiopia-Africa Trade

insurance-RMC

Membership Program

Insurance agency

23-Sep-15 4,970,000 0.6

PUBLIC SECTOR 1,070,372,122

Page 33: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

III

ETHIOPIA -ONGOING PORTFOLIO 15 MAY 2016

No Project

Loan/Grant Disbursement

IP DO PFI Status

Age

Approval

Date

Amount

(UA) Ratio Years.

PUBLIC SECTOR OPERATIONS

TOTAL

PRIVATE SECTOR OPERATIONS

15 Deba-Midroc Cement

Factory 16-Apr-09 39,882,752 100% 3.09 4

NON-

PP/NON PPP 7.1

16 Ethiopian Air Lines 23-Mar-11 27,998,968 96.68% 3.77 4 NON-

PP/NON PPP 5.2

PRIVATE SECTOR

TOTAL 67,881,720

TOTAL INVESTMENT

OPERATIONS 1,138,253,842

TRUST FUNDS

17 Assela Wind Farm SREP

PPG 28-Jun-12 1,206,418 21.02% 3.75 NR

NON-

PP/NON PPP 3.9

18 Africa Bamboo 5-Dec-14

532,550

6.61% NR NR

NON-

PP/NON PPP 1.4

19 AWF/NEPAD Baro

Akobo Sobat 2-May-13 2,060,000 28.00% 3 3

NON-

PP/NON PPP 3.0

20

Capacity Building for

Financial Inclusion in

Ethiopia (M-Birr) 26-Feb-15 230,247 40.68% NR

NON-

PP/NON PPP 0.1

21

Support to Institutional

Strengthening in Gender

Mainstreaming for

Infrastructure Sector

1-Apr-15 230,925 30% NR NON-

PP/NON PPP 1.1

22

ClimDev Fund for

Adaptation to Climate

Change in Ethiopia Jun-15 795,580 8% NR

NON-

PP/NON PPP 0.4

23

Marketing and Service

Chain Support for Total

Sanitation in Arba

Minch

11-Jun-15 973,536 NR NON-

PP/NON PPP 0.9

TOTAL TRUST FUNDS 6,029,256

TOTAL PORTFOLIO 1,144,283,098

* Grant components

Page 34: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

IV

Appendix III: Table of Key Projects Financed By the Bank and other Development Partners in

the Country Project/Framework Development

Partner

Amount of

finance x1,000

Sector Contribution

Rural Electrification-I AfDB UA

34,230

Creating electricity access to 36 rural Woreda towns in seven

administrative Regions, to improve the livelihood of rural population

and economic development in the country,

Rural Electrification II AfDB UA

87,200

Creating electricity access to rural population to 335 towns and

villages in Amhara, Oromiya and Southern regions to improve the

livelihood of rural population and economic development in the

country

Ethiopia-Djibouti

Interconnection project

(Construction of 283 km 230 kV

line)

AfDB UA

59,400

Multinational power Transmission Interconnection, to enable

countries to exchange (export/import) electric power for mutual

economic benefit and reduction the fossil fuel generation by

importing/exporting clean energy

Electricity Transmission System

Improvement

project(Construction of 943 km

230 kV lines & 21 subsations)

AfDB UA

151,750

Improve access to electricity for the rural population, improve

transmission capacity and reliability of power supply to businesses and

manufacturing firms in urban areas through the reduction of system

losses and frequency of outages

Ethipia-Kenya Electricity

Highway project (Construction

of 1045 km, 500 kV HV DC

line)

AfDB UA

150,000

Multinational power Transmission Interconnection, to enable

countries to exchange (export/import) electric power for mutual

economic benefit and reduction the fossil fuel generation by

importing/exporting clean energy

Sululita-Bahir Dar-D.markos-

Sululta 400kV Transmission

line

China Exim

Bank

Improving the power transfer capacity & relaibility of high voltage

transmission network

Generation (Amertin Neshi

Hydro Electric power project,

100 MW)

China Exim

Bank

USD

117,000.00

Increasing the Country’s hydro generation capacity, to satisfy the

growing energy supply demand throughout the country

Generation (Gilgel Gibe II

Hydro Electric power project,

420 MW)

Govt. Italy &

EIB

EUR

270,000

(220,000,

50,000)

Increasing the Country’s hydro generation capacity, to satisfy the

growing energy supply demand throughout the country

Ethiopia-Sudan Interconnection

project

World Bank USD

41,000

Multinational power Transmission Interconnection, to enable

countries to exchange (export/import) electric power for mutual

economic benefit and reduction the fossil fuel generation by

importing/exporting clean energy

Addis Ababa distribution

rehabilitation project

World Bank Distribution network (rehabilitation & upgrading) to improve network

power distribution capacity, reliability and quality of electricity supply

to customers

Rural Electrification (EAREP I

& II)

World Bank USD

180,800

Electrification of 265 towns through grid expansion and additional

villages through mini off grid system and development of productive

use of energy

Transmission & Substations

Rehabilitation & Upgrading

project

World Bank USD

90,000.00

Rehabilitation & upgrading of the existing transmission lines &

substations in Addis Ababa area & other regions to enhance their

capacity in order to improve the power supply situation

Rural Electrification Kuwait USD

35,000.00

Electrification of 27 towns, improvement of 4 substations and

construction of 3 transmission lines in Afar Region to create access to

electricity & improve the livelihood of rural population

Rural Electrification BADEA-I USD

3,600.00

Electrification of 44 towns in two regions, Amhara and SNNP region

to create access to electricity &improve the livelihood of rural

population

Transmission (132 kV line and

substation for SAWLA-Key

Afer)

BADEA &

OPEC

USD

29,000.00

(9,000.0 &

20,000.00)

Constructing the 132 KV transmission line and associated substations

to improve power supply to Urban and Rural areas in southern part of

the country

Rural Electrification India USD

65,000.00

Electrification of 27 towns in Hagare-Mariam Mega area to create

access to electricity & improve the livelihood of rural population

Page 35: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

V

Appendix-iv: Project Location Map

Page 36: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

VI

APPENDIX V – JUSTIFICTION FOR FINANCING MORE THAN 50% OF COST BY ADB

1. Introduction: GOE made a request for this financing plan during appraisal of the program.

This appendix provides the justification for waiver for the Bank financing more than 50% of the

proposed operation financing as indicated in the financing plan depicted in the table below.

2. Country Commitment to Overall Development: Ethiopia has experienced strong economic

growth, averaging 10.8% since 2005, underpinned by public-sector-led development. Real gross

domestic product (GDP) is estimated to have grown by 10.2% in fiscal year 2014/15. The agriculture,

services and industry sectors accounted for 38.8%, 46.6% and 15.2% of real GDP, respectively. Public

investments are expected to continue driving growth in the short and medium term with huge

investments in infrastructure and the development of industrial parks, prioritized to ease bottlenecks to

structural transformation, which will still have to take shape with industry playing a significant role in

the economy.

The country has made significant headway in achieving most of the MDG targets owing to the

Government’s commitment to development. Poverty level declined from 45% in 1995/96 to 29.6% in

2010/11. Under five mortality dropped from 123 in 2005 to 88 in 2010. HIV/AIDs prevalence drop to

1.3% below the MDG target of 2.5%. Primary school net enrolment increased from 68% in 2005 to 95%

in 2013. In 2014/15, access to electricity supply reached 60% nationally, from a national average of

16% in 2004/5.

3. Financing allocated by Sector Targeted by the Bank: Ethiopia has made significant

improvement in basic social services over the years. This has been supported by progress in long-term

institution building, provision of physical infrastructure and gradual improvements in governance. With

the government’s consistent implementation of its poverty-reduction strategy, pro-poor spending

continues to rise (73% of total public expenditure in 2014/15). As a result, poverty in Ethiopia has

declined at an annual average of 1.94% since 1995. The population share of persons living below the

national poverty line fell from a baseline of 48% in 1990 to 45.5% in 1996 and 29.6% in 2011, and is

estimated to have further declined to 23.4% in 2015, which is below the MDG target of 24%. This trend

has continued under the government’s commitment in the GTP-I. The 2012/13 approved federal

government budget indicates the commitment of Government in implementing the GTP, which engulfs

the target sectors of the Bank (energy, roads, basic services and governance). The commitment in the

energy sector is even stronger, as reflected in the EEPs budget of 2012/13 below, which is one of the

Banks target sector:

Budgetary Allocation Budget 2012/13

Share for power Sector Total

Own

source

Generation Projects (20) 30,878.2 1,249.8 4.1%

Upgrading projects (1) 98.2 98.2 100.0%

Generation studies 10.6 10.6 100.0%

Transmission Projects (15) 10,605.2 188.0 1.7%

Transmission line studies 53.8 7.8 14.5%

Distribution 2,214.6 1952.0 88.1%

Universal Electricity Access 2,414.6 1000.0 41.4%

Institutional strengthening 1,311 715 53.8%

Total 53,405.2 4,220.3 7.9%

Source

Total Amount

Million US$

% Total

Million US$

ADB 104.61 85.4%

GoE 17.91 14.6%

Total 122.52 100%

Page 37: AFRICAN DEVELOPMENT BANK · AFRICAN DEVELOPMENT BANK ... TVET = Technical, Vocational Education and Training ... 175 km of 230 kV Semera-Afdera transmission line (iii) Construction

VII

4 Ethiopia has started exploiting its huge hydropower potential for domestic needs and export of

power to the Eastern African region and beyond. The generation capacity in the national grid will be

increased from the current 4,180 MW in 2015 and to 17,347 MW in 2020. To evacuate the power

generated, the transmission and distribution systems will also be rehabilitated and expanded. The

national access to electricity will grow from the current level of 60 percent to 90 percent in 2020. EEP,

a State owned and vertically integrated utility responsible for the construction and operation of

generation plants, transmission & substation networks as well as bulk sell of sale of electricity in the

country, is expected to operate on dual objectives - undertaking such huge development oriented

programs and operating on financial sustainability with strict adherence to the performance benchmarks.

None the less, the utility was incapable of raising tariff since 2006, which is threatening its financial

sustainability. The major sources of finance for EEP were multilateral development banks, bilateral

financing, retained earnings and government equity. End user payments contributed to about 2 percent

of EEP’s sources of financing. The external sources were 65 percent concessional and 35 percent non-

concessional. All these were happening under the strong government guarantee and custody and all

these reflect government’s commitment and ownership.

5. Budget and Debt Situation: Ethiopia’s budget has been steadily growing and it has now

proclaimed to reach US$ 11 billion in 2015/16 financial year from US$5 billion in 2005/6. In 2014/15,

the fiscal deficit amounted to 2.0% of GDP compared to 2.6% in 2013/14. The tax-revenue-to-GDP

ratio improved to 13.4% in 2014/15 from 12.7% % in the previous year, but this remains well below

the sub-Saharan Africa average of about 20%. The growth in exports slowed down during the last 3

years, roving around US$ 3.0 - 3.25 billion in the last three years, showing contraction as a percent of

GDP, while import bill increased by about 20% in 2013/14. The trade balance is hence further

deteriorated as a percentage of GDP and by nominal value. The external debt increased from

USD 11.2 billion in 2011/12 to USD 19 billion in 2014/15, up from 12.1% of GDP in 2009/10 to 26.2%

in 2014/15. In 2014, Ethiopia accessed the EURBOND and borrowed USD 1 billion from the

international financial market. Ethiopia’s 2014/15 Federal budget law shows an allocation of 4.6% of

the federal budget to debt servicing. Ethiopia’s debt is steadily growing, despite still remaining at

moderate level in terms of debt stress.

5. Conclusion: The GoE has demonstrated commitment through its achievements and spending

in critical sectors such as in Energy & road. The HV transmission network expansion and rural

electricity access scale-up program shall not be seen in isolation from the national power sector

development for which Government’s contribution is estimated at 50% of the estimated financing need

of USD 29.3 Billion for the GTP-II (2016-2020). The financing under the program enhances the

achievement of the sector goals and builds on the Bank’s earlier contribution to the development of the

energy sector in Ethiopia. Furthermore, Ethiopia is still an ADF country only and eligible to access the

ADB resources based on the new Credit Policy approved in 2014 (Diversifying the Bank’s Products to

Provide Eligible ADF-Only Countries Access to the ADB Sovereign Window). Requiring an ADF

country to comply with counterpart financing level of ADB countries (refer 2.1.2, (ii) of the Policy on

Expenditure Eligible for Bank Group Financing) more than 50% of program financing is a burden to

the country.