AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs...
Transcript of AFNHB : JALANDHAR PROJECT : As on 17 MAJOR ACTIVITIES ... · Internal plaster / final coat in DUs...
MAJOR ACTIVITIES UNDERTAKEN SINCE LAST WEB UPDATE
1. Following are the important actions undertaken/ completed since last update of 15 Jun 17. 2. Till 15 Jul 17, ten allottees have registered their DUs physical possession of six DUs have also been given to the allottees.
3. Minor defects observed by allottees while taking over DUs have since been rectified. 4. Seepage observed in a few DUs while testing plumbing lines have also been rectified. Internal plaster / final coat in DUs would be undertaken after the same have been declared fit for occupation by PMC.
5. Allottees desirous of getting their DUs registered are requested to visit site on Tuesdays or Fridays, after completing other formalities in consultation with the Advocate. Authorized signatory from AFNHB would be available to accompany allottees on Tuesdays and Fridays.
AFNHB : JALANDHAR PROJECT : As on 17 Jul 17
JAL VAYU VIHAR ENTRANCE
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
PANORAMIC VIEWS OF TOWERS
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
PICTURE TAKEN WITH DRONE CAMERA
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
INTERNAL VIEW OF DUs BLOCK A1/A2
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
A1 & A2 BLOCKS- (overall completion 99.75 %) Total Floors: - Stilt +9 Total Flats: - 106 (1350 SQ FT EACH) PROGRESS: Rectification of External painting, minor repairs/rectifications works of aluminium works in progress. External painting of Block A would be undertaken during Aug 2017.
INTERNAL VIEW OF BLOCK B 1
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
B1- BLOCKS (overall completion 99.75%) Total Floors: - Stilt +8 Total Flats: - 48 (931 SQ FT) PROGRESS: All works completed except final coat of external paint. Same has been planned during last week of Aug 2017.
COMMUNITY CENTRE
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
WORK COMPLETED
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
BASEMENT PARKING
Basement Parking- Progress 99.75%
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
LANDSCAPING
WORK COMPLETED
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
SWIMMING POOL
WORK COMPLETED
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
ROAD WORK
WORK COMPLETED
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
SUB STATION
WORK COMPLETED
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017
STREET LIGHTS
WORK COMPLETED
PROGRESS JALANDHAR PROJECT AS ON 17 Jul 2017