AFC Schedules and Status

7
AFC Schedules and Status Tom Bradshaw John Cobb Wing Lau Matt Hills MICE MICO Meeting 12 th October 2011 Elwyn Baynham Mike Courthold Victoria Bayliss 1

description

AFC Schedules and Status. MICE MICO Meeting 12 th October 2011. Tom Bradshaw John Cobb Wing Lau Matt Hills. Elwyn Baynham Mike Courthold Victoria Bayliss. Introduction. Talk will cover Status of the project Work and spend: Schedule of work and spend this Financial Year - PowerPoint PPT Presentation

Transcript of AFC Schedules and Status

Page 1: AFC Schedules and Status

1

AFC Schedules and Status

Tom BradshawJohn CobbWing LauMatt Hills

MICE MICO Meeting12th October 2011

Elwyn BaynhamMike CourtholdVictoria Bayliss

Page 2: AFC Schedules and Status

2

Talk will cover

• Status of the project• Work and spend:

– Schedule of work and spend this Financial Year

– Schedule and spend estimates for next FY

– Forward look and spend requirements to completion

Introduction

Page 3: AFC Schedules and Status

3

Status of the project

Winding of AFC 1 and 2 are complete and look to be of very good quality – shown here with outer insulation prior to welding of bobbin outer (right)

•Most components are in hand and assembly is proceeding•Welding of covers on bobbin nearly complete

Page 4: AFC Schedules and Status

4

Recent Progress and Status

Parts look to be of good quality

Current lead assemblies

Suspension System

Page 5: AFC Schedules and Status

5

Critical areas

Schedule analysed at meetings to highlight critical path items – this has worked well – used this to get engineering support in the right areas

Critical path at the moment is the Outer Vacuum Can assembly which is proving complex and time consuming. WL spending some time with them to understand this

Some risk mitigated by testing cryocoolers prior to installation – this has been very valuable

Control system needs to be ready – trying to keep on top of this issue

Power supply specifications have been difficult to interpret in the context of operation with the AFC – we are keeping on top of this

Page 6: AFC Schedules and Status

6

Sche

dule

sModule/Activity Due DateAFC1 at RAL January 2012 Absorber integration and test +3mths elapsedAFC2 at RAL June 2012 – worst case trying to

improve on thisAbsorber integration and test <3mths

Task CommentsAcceptance tests Will be completed at RALField Mapping CERN personnelAbsorber integration

To fit in with hydrogen and hall scheduleRA

L ta

sks

2011

/12

RAL

task

s 20

12/1

3

Task Comments

Module 2 monitoring

Delivery as above

Acceptance tests #2

Will be completed at RAL

Field Mapping #2 CERN personnel

Absorber integration

To fit in with hydrogen and hall schedule

Page 7: AFC Schedules and Status

7

END