AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

30
AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD Analysis and Design of a Mild Reinforced One way slab with Post Tensioned Beams Jeffrey L. Rothermel Jr. The Pennsylvania State University Department of Architectural Engineering Structural Option

description

AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD. Analysis and Design of a Mild Reinforced One way slab with Post Tensioned Beams. Jeffrey L. Rothermel Jr. The Pennsylvania State University Department of Architectural Engineering Structural Option. - PowerPoint PPT Presentation

Transcript of AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

Page 1: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009

U.S. Pharmacopeia Headquarters Consolidation

Rockville, MD

Analysis and Design of a Mild ReinforcedOne way slab with Post Tensioned Beams

Jeffrey L. Rothermel Jr.The Pennsylvania State University

Department of Architectural EngineeringStructural Option

Page 2: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

Discussion Topics

• Background Information

• Existing Structure

• Design Goals

• Project Stages and Process

• Structural Design

• Mechanical Ductwork Redesign

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Page 3: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

U.S. Pharmacopeia Headquarters

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

• Owner: U.S. Pharmacopeia• Architect: Hellmuth, Obata + Kassabaum (HOK)• Structural: Cagley & Associates Inc.• MEP: R.G. Vanderweil Engineers• Construction: DPR Construction Inc.

• 6 stories - 91’• 191,000 ft2 of new office and lab space• New 19,000 ft2 conference center• Houses chemical and biological labs• $69 million

Page 4: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

U.S. Pharmacopeia Headquarters

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

• Showcase laboratory spaces• Large open office plans• Kitchenettes for employees at every floor• Curtain wall, metal paneling, and beige split face CMU• Conical auditorium with curtain wall skin• Enclosed outdoor plaza space

Page 5: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

Existing Conditions

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

• Two way mild reinforced concrete flat slab with drop panels

• 22’x22’ column grid

• 14’ floor-to-floor heights (Typ.)

• Reinforced concrete moment frames

• Steel framed conference center

• Truncated, conical concrete auditorium

Photo courtesy of HOK Inc.

Photo courtesy of HOK Inc.Photo courtesy of HOK Inc.

Page 6: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Page 7: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

Design Goals

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

• Lower floor-to-floor heights from 14’ to 13’

• Increase column grid from 22’ to 44’

• Eliminate moment frames

• Reduce ductwork sizes

• Maintain existing ceiling height

Page 8: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

Design Stages

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

• Investigate 3 alternatives

• Choose optimum system

• Design chosen floor system

• Design matching lateral system

• Resize ductwork mains

Page 9: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Possible Solutions

Staggered Steel Truss systemTaken From AISC Design Guide 14: Staggered Steel Truss Framing

Two way post tensioned slab

One way slab with post tensioned beams

Page 10: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Structural Depth DesignDesign Process

1. Lay out beams2. Design slab system3. Design post tensioned beams

1. Size2. Tendon quantity3. Drape

4. Column check5. Design shear walls

1. Shear reinforcement2. Flexural reinforcement3. Coupling beams

Page 11: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

One way slab with PT beam design

New Beam Layout

Page 12: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

One way slab with PT beam designSlab Design

• One way reinforcing

• 7” slab typ.

• 7-1/2” slab at 250 psf loading

• #5 bars T&B

• #5@ 24” for shrinkage and temperature parallel to beams

Page 13: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

One way slab with PT beam design

Designed with RAM Conceptper ACI 318-02

• Spans extended to 44’• Shallow wide beams • Existing column size kept (24”x24”)• F’

c = 6000 psi• Class T Transitional• T-Beam properties• #6 Bottom at ρmin= 0.004• #5 Top with no minimum reinforcement• 0.6f’

ci compression limit (18.4.1(a))• 7.5√f’

c ≤ft ≤ 12√f’c tensile stress limit (18.3.3)

Page 14: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

One way slab with PT beam designDesign Process

1. Size the beams2. Add tendons3. Check stresses4. Adjust profile5. Schedule

Page 15: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

One way slab with PT beam design

• Interior beams typically 48”x14”

• Edge beams typically 30”,32”x14”

• 40-60 tendons interior typically

• 30-40 tendons in edge typically

Page 16: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

One way slab with PT beam design

Transfer Girders

• 16-30” deep at transfers• 48-56” wide at transfers• Same depth as existing transfers• 20-50% more post tensioning

Page 17: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

One way slab with PT beam design

Load Balancing Load Balancing (% DL)Span 1 2 3 4 5 6 7

Floor Col Line              First A 73 87 81 73 69 72

 

  B 78 97 92 71 76 91  C 80 95 94 74 80 67  D 75

 77 67 100 83

  E 72 75 64 97 85  F 78 94 90 72 76 93  G 91 87 88 86 69 72 77

Second A 76 90 83 75 70 74

 

  B 91 110 99 76 69 69  C 86 110 94 72 66 65  D 67

 88 69 89 95

  E 69 85 64 92 99  F 97 88 98 79 73 74  G 76 95 95 93 60 77 83

Third A 71 87 83 76 71 78

 

  B 73 72 77 70 64 76  C 77 95 82 75 70 81  D 50

 72 70 110 81

  E 68 70 65 110 80  F 93 87 74 66 64 74  G 99 100 78 82 39 69 93

Fourth B -2 90 88 85 76 73 75  C 38 110 91 90 85 85 32  D 16 78

 65 64 100 69

  E 16 75 64 60 100 75  F 40 64 86 74 70 64 75  G 67 87 95 86 100 88 81

Penthouse B -57 65 82 93 78 110 80  C 19 82 98 100 90 89 88  D 34 86

 95 61 100 45

  E 27 95 93 59 100 42  F 62 89 96 92 89 96 100  G 58 90 100 93 84 100 78

• Balance % of dead load• Target balance 60-90%

• Target met in most beams• A few beams overbalanced• Some underbalanced

Page 18: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

One way slab with PT beam designExisting Column Properties• Checked using PCA Column• Moments from RAM Concept at column

• Interior columns sufficient• Exterior columns require increased rebar

• Required for increased moment• 8#9 12#9

Page 19: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Shear Wall Design

Existing reinforced concrete moment frames

Page 20: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Shear Wall Design

Page 21: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Shear Wall Design

Taken From ASCE 7-05

Load Determination

• Method 2 per ASCE 7-05

• 4 wind cases investigated

• Seismic loads using Equivalent Lateral Force Method

• 18” trial thickness

• 1.6W vs. 1.0E

Page 22: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Shear Wall DesignShear reinforcement as required per Sec. 11.9

• Each wall/segment designed for shear and flexure separately

• Minimum shear reinforcing used• None needed for shear strength

• #4s H,V @18” Typ.

• Moment controlled reinforcing designs

• #8s Vert. for flexure

Page 23: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Shear Wall DesignDeflections in SAP

• 8” Membrane• Self mass included• 24” mesh• Full I values for all members• F’

c = 3000 psi

• Wind limitation H/400• Seismic limitation 0.02hxn

Page 24: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Shear Wall DesignCoupled shear wall design

SAP • Member self weight included• 8” Membrane• Coupling beams extend into wall face

• 2’ Rigid end offset• 48” deep beams

• Coupling beams as deep beams per Sec. 21.9.7• Designed per Sec. 10.7• Shear reinforcement per Sec. 11.7

Page 25: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Mechanical Ductwork design

Design Goals

• Keep loss under .25” WC/100’

• Keep fpm flow under 2500 in mains over occupied spaces

• Reduce height and increase width

Page 26: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

First Floor

Mechanical Ductwork Redesign

Page 27: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Mechanical Ductwork Redesign

• Vertical mains shrunk 8-20” per side

• Maximum horizontal run that travels under beams is 20”

• Minimum ceiling height is 8’10”

• Average ceiling height can be +10’6”

Page 28: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Façade SavingsFloor sf curtain wall sf split face CMU sf metal panel

4th 758 - -3rd 758 - 562nd 204 604 561st 204 604 56

Total 1924 1208 168$/sf 65.65 62.72 34.04

Savings $4,309.92 $3,933.80 $1,158.72Total Savings $9,402.44    

Cost of New DuctworkTotal Weight x 1.15* x Cost (installed) ($/lb) = Total Cost

42,263.2 x 1.15 x 6.79 = $330,012             

Cost of Existing DuctworkTotal Weight x 1.15* x Cost (installed) ($/lb) = Total Cost

53,749.2 x 1.15 x 6.79 = $419,700                     Savings From Changes $89,688             *15% added for brackets and supports

Some Quick Costs• Savings on façade and ductwork• More expense on structure

Page 29: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Project Summary

• Post tensioned beam system provides optimal performance

• Wide shallow beams incorporate desired attributes into floors

• 48”x14” for most interior beams and 30”x14” for most exterior

• 8” shear walls designed for moment

• Mechanical ductwork redesigned to obtain project goals

• Savings on façade and mechanical ducts, more cost in structure

• All goals reasonably attained

Page 30: AE Senior Thesis 2009 U.S. Pharmacopeia Headquarters Consolidation Rockville, MD

AE Senior Thesis 2009|U.S. Pharmacopeia Headquarters|Jeffrey L. Rothermel Jr.|Structural Option

Questions/Comments