Advancing Modular Construction
Damien Crough
Technical Leader
Schiavello Modular & Prefab Building Division
Founding Director & Board Chair
PrefabAUS
Advancing Modular Construction
Damien Crough – 13 years in
Modular Construction
PROJECT
Little Hero
ADDRESS
16-30 Russell Place,
Melbourne
MODULES
75
APARTMENTS
63
VALUE
$12m
PROJECT
Pegasus
ADDRESS
435-439 Whitehorse Rd,
Mitcham
MODULES
92
APARTMENTS
50
VALUE
$11.5m
PROJECT
The Nicholson
ADDRESS
14-20 Nicholson St,
East Coburg
MODULES
341
APARTMENTS
199
VALUE
$50m
PROJECT
Centvm
ADDRESS
100 Plenty Rd,
Preston
MODULES
219
APARTMENTS
109
VALUE
$21m
PROJECT
3:East
ADDRESS
37-39 Bosisto St,
Richmond
MODULES
63
APARTMENTS
57
VALUE
$13m
PROJECT
One9
ADDRESS
19 Hall St,
Moonee Ponds Vic
MODULES
36
APARTMENTS
34
VALUE
$4.5m
PROJECT
The Schaller Studio
OPERATOR
Art Series Hotels
ADDRESS
62 Lucan St,
Bendigo Vic
MODULES
66
ROOMS
128
VALUE
$14m
PROJECT
Elaine Terminal Station
ADDRESS
Lot 51, Government Rd,
Elaine VIC
MODULES
4
VALUE
$1.25m
PROJECT
Stella Apartments
ADDRESS
17 Malata Cres,
Success WA
MODULES
96
APARTMENTS
77
VALUE
$12.7m
PROJECT
Concorde South
ADDRESS
10 Forrest Circle,
South Hedland WA
MODULES
108
APARTMENTS
77
VALUE
$26m
PROJECT
Duffy Primary
ADDRESS
55 Burrinjuck Cres,
Duffy Act
MODULES
10
VALUE
$1.13m
Designing for Flexibility
Sustainability benefits
Case study example
What are the opportunities in Australia?
Designing for Flexibility
Sustainability benefits
• Minimal waste
• Recycle
• Re-use
16
Pod Model Structure
Base Frame Tray Frame
Shower Screen
Plumbing/Electrical
Service
Lining & Finish
Structure
Wall Floor Finish
Timber Backing
17
Services supports Incorporated
18
MEP
19
MEP Penetration
20
Modeling Workflow
• Adjust dimension based on
drawing and schedule:
• Width
• Height
• Length
• Finish thickness
• Substrate thickness
• Change door dimension
• Add features:
• Hob wall
• Opening
• Internal wall
• Add fixtures:
• Toilet
• Basin
• Shower
• Turn Placeholder
Wall into Frame
Step 1: Basic
adjustment
Step 2: Detailing Step 3: Framing
21
Modeling Workflow
• Group Fixtures into
their system
• Hot water
• Cold water
• Sanitary
• Run routing for each
system
• Run clash detection
to detect clashes
between elements
• Create penetrations
Step 4: Services Step 6: Penetration
• Adjust Frame
direction, spacing,
pipe location to avoid
clashes
• Add accessories
• Adjust timber backing
Step 5: Adjustment
Designing for Flexibility
Minimal Waste
• Small plumbing pipe offcuts
• Some packaging
Designing for Flexibility
Recycle & Re-use
• Punch outs for service
penetrations is the only waste
Designing for Flexibility
Case study example - Urbanest Student Accommodation
599 Swanston Street Melbourne
Urbanest Student Accommodation
599 Swanston Street Melbourne
Builder – ICON CO
423 Schiavello Bathroom Pods
Production rate of 10 pods per
day
Designing for Flexibility
599 Swanston Street - Urbanest Student Accommodation
Designing for Flexibility
599 Swanston Street - Urbanest Student Accommodation
Designing for Flexibility
Pod transport and lifting on site
Designing for Flexibility
https://www.youtube.com/watch?time_continue=40&v=Khz1bcg2xUQ
Illawarra Retirement Trust Apartments, 27A Stewart Street Wollongong
Builder – Infinity
Construction
138 Schiavello Bathroom
Pods
Production rate of 10 pods
per day
Designing for Flexibility
Illawarra Retirement Trust Wollongong
Designing for Flexibility
Builder – Infinity
Construction
91 Schiavello Bathroom
Pods
Production rate of 10 pods
per day
ParkRoyal Hotel Parramatta Extension
Designing for Flexibility
Parkroyal Hotel Parramatta
Designing for Flexibility
What are the opportunities in Australia?
Designing for Flexibility
Schiavello SPEC Structural System 10 - 35 levels
Schiavello Modular & Prefab Building Division
• SPEC – Single Pin Expansion Clamp - post tensioned steel column connection
Schiavello Modular & Prefab Building Division
• A prototype of the design has been constructed and erected as a demonstration of the
chosen building systems
• The system came together extremely quickly
Schiavello Modular & Prefab Building Division
• A prototype of the design has been constructed and erected as a demonstration of the
chosen building systems
• The system came together extremely quickly
Schiavello Modular & Prefab Building Division
185 Wharf Street Concept
Schiavello Modular & Prefab Building Division
Schiavello Modular & Prefab Building Division
Corrections – Stackable Modular Cell
Designing for Flexibility
Schiavello Manufacturing for Construction
Damien Crough
Technical Leader
Schiavello Modular & Prefab Building Division
Founding Director & Board Chair