ADO-PO section meeting Safety Sub Section Objectives for the coming months

6
08/28/22 ADO-PO section meeting Safety Sub Section Objectives for the coming months O. beltramello

description

ADO-PO section meeting Safety Sub Section Objectives for the coming months. O. beltramello. General Safety. LS1 safety supervision: Dimitar, Didier, Hugo, Sergey, Maryia, Natascia, Edward Daily safety supervision, PPSPS and WPA SLIMOS OPM, EOD - PowerPoint PPT Presentation

Transcript of ADO-PO section meeting Safety Sub Section Objectives for the coming months

Page 1: ADO-PO section meeting Safety Sub Section  Objectives for the coming months

04/20/23

ADO-PO section meeting

Safety Sub Section

Objectives for the coming months

O. beltramello

Page 2: ADO-PO section meeting Safety Sub Section  Objectives for the coming months

04/20/23 R. Vuillermet

General Safety

LS1 safety supervision: Dimitar, Didier, Hugo, Sergey, Maryia, Natascia, Edward

Daily safety supervision, PPSPS and WPASLIMOS OPM, EOD

Upgrade of the safety systems: Sergey, Didier

o Detector Safety System o New Flammable Gas detection systemo Upgrade of the centrale detection gas USA15o Maintenance of the safety systems:

Sniffers (Didier, Francesco, Gevorg, Fred, Cedric, Charles) Radiation Gate monitors Foam system .Fire detection, gas, etc..

Page 3: ADO-PO section meeting Safety Sub Section  Objectives for the coming months

04/20/23 R. Vuillermet

Radiation Protection

New RSO – Giancarlo New RPE – Alexandre

ALARA budgets for the end of LS1 and future: Irina, Natascia, Illona

All FLUKA dose calculations done by G. Mornacchi and C. Ursheler have been transferred.

The comparison with the dose measured at start of LS1 are on going.

We see a factor 2 maximum of difference between calculated and measured.

We will internalise the FLUKA doses calculations starting 1st July (FLUKA model update and new scenarios).

A technical student will be hired very soon (July).

Page 4: ADO-PO section meeting Safety Sub Section  Objectives for the coming months

04/20/23 R. Vuillermet

Radiation Protection

Remote Handling – Christos, Alexandre, Dimitar

We are currently setting up an organization in ADO-PO to prepare ourselves to future use of remote handling.

We are defining the requirements and tasks impacted. We are currently doing a survey of the market to determine which company is the most suitable for a collaboration (in close collaboration with CERN and especially EN department)The goal is to start a prototype in building 180 within a year with the case of IDEP dismounting.

Page 5: ADO-PO section meeting Safety Sub Section  Objectives for the coming months

04/20/23 R. Vuillermet

ATWPSS and EDUSAFE

ATWPSS – Christos, Alex, Mark, Dimitar, Vit

Upgrade development of the ATWPSS : Miniaturization + “helmet case”Integration of TETRA Adaptation of the system to the Fire Brigade needsDevelopment towards to EDUSAFE technologies

EDUSAFE – Christos, Lakshmi

EDUSAFE Network Coordinator Research program on Augmented Reality Technologies

Page 6: ADO-PO section meeting Safety Sub Section  Objectives for the coming months

04/20/23 R. Vuillermet

Visits

Public visits (Tiina) Organization of the visitsTraining of the guides

Open days (All team)

27-28-29-30 of September