Design Basis Scoping Paper
Adli S. Khalaf Facilities Planning Department
Saudi Aramco
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 2/23
December 3, 2007 SAWEA WORKSHOP - 2007 2
Outline
Introduction
Definition
Purpose
Involved Organizations
DBSP Content
Examples
Development ProcessConclusions
Questions
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 3/23
December 3, 2007 SAWEA WORKSHOP - 2007 3
Six Phases of a Project
1. Enthusiasm
2. Disillusionment
3. Panic
4. Search for the Guilty
5. Punishment of the Innocent
6.Praise and Honor the Non-Participants
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 4/23
December 3, 2007 SAWEA WORKSHOP - 2007 4
Elements of Project Success
Understand Business Objectives
Strategy for Project GoalsRisk and Uncertainty
OBJECTIVES
The
Project
TEAM PROCESS
Customer Focus
Project Team
Contractor
Pre-Project Planning
Project Execution Plan
Controlling Cost/Schedule
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 5/23
December 3, 2007 SAWEA WORKSHOP - 2007 5
Definition
DBSP is a contract between the
signatories to further develop the
proposed project in a manner that
will ensure that the project’s statedBusiness Objective is achieved in a
cost effective manner.
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 6/23
December 3, 2007 SAWEA WORKSHOP - 2007 6
Purpose
The purpose of the DBSP is to:
Define the main elements of the project scopeof work (What will be built)
Define the limits of the project scope of work
Provide the design contractor definitiveinformation to independently develop the
project scope
Provide the Construction Agency the
information to effectively plan and execute theproject
Provide a cost estimate (+/-40%) for budgeting
purposes
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 7/23
December 3, 2007 SAWEA WORKSHOP - 2007 7
Involved Organizations
Planning Organization
Proponent or End User
Construction AgencyEnvironmental Protection
Organization
Estimating
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 8/23
December 3, 2007 SAWEA WORKSHOP - 2007 8
Planning OrganizationLeads the DBSP preparation effort
Clarifies the definition of the project’s Business
Case
Insures adequate justification for scope
elementsDescribes in broad terms the facilities to be
provided
Controls scope
Describes specific studies to be preformed
during Preliminary Design
Issues DBSP for review and approval
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 9/23
December 3, 2007 SAWEA WORKSHOP - 2007 9
Proponent
Provides supporting information
Reviews scope elements
Provides support to establishinterface points
Signs DBSP for endorsing project
scope
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 10/23
December 3, 2007 SAWEA WORKSHOP - 2007 10
Construction Agency
Reviews schedule
Reviews scope elements
Reviews constructabilityReviews study requirements
Signs DBSP for schedule considerations
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 11/23
December 3, 2007 SAWEA WORKSHOP - 2007 11
Environmental Protection
Organization
Reviews project’s environmental
implications
Signs DBSP for environmentalconsiderations
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 12/23
December 3, 2007 SAWEA WORKSHOP - 2007 12
Estimating
Prepares budgetary cost estimate
Estimate Accuracy is +/- 40%
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 13/23
December 3, 2007 SAWEA WORKSHOP - 2007 13
DBSP Content
Purpose of Facilities
Present Situation
Location Analysis
Interfaces
Design ObjectivesGeneral Project Design Basis
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 14/23
December 3, 2007 SAWEA WORKSHOP - 2007 14
DBSP Content (cont’d)
Description of Proposed Facilities
–Type of facility
–
Corresponding technical design basis –Specific facility attributes
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 15/23
December 3, 2007 SAWEA WORKSHOP - 2007 15
DBSP Content (cont’d)
Scope Evaluation to Date
Additional Study Requirements during
Preliminary Design
Constructability and Logistical Assessment
As-Built Drawing Assessment
Value Engineering StudyProject Schedule
Appendices
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 16/23
December 3, 2007 SAWEA WORKSHOP - 2007 16
What to Include in DBSP
What’s IN?Preliminary description of facility to be provided
Evaluation of existing conditions
Results of previous studies
Scope of Work of Project organized by discipline
Limits of scope of work for the Design Engineer
Design bases
Utility sources and interface pointsConceptual layout of equipment
Schematics and Process Flow Diagrams
List of major equipment
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 17/23
December 3, 2007 SAWEA WORKSHOP - 2007 17
What NOT to include in the DBSP
What’s OUT? Exact size of equipment
Type of valves, flow meters, levels, etc.
Name of manufacturer
Final layout, Sections, P&ID, etc.
Detailed design calculations
Detailed specifications
Project cost
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 18/23
December 3, 2007 SAWEA WORKSHOP - 2007 18
Example 1
Building- Location
- Site conditions
- Type of construction- Built-up Area
- Number of persons
- Sizing criteria- Preliminary layout
- Utility requirements
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 19/23
December 3, 2007 SAWEA WORKSHOP - 2007 19
Example 2
Sewage Treatment Plant
- Location
- Capacity
- Level of Treatment
- Treatment Process
- Treatment Facilities
- Design Criteria
- Electrical and Instrumentation
- Process Flow Diagram
- Conceptual Layout
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 20/23
December 3, 2007 SAWEA WORKSHOP - 2007 20
Example 3
Water Supply Network- Location
- Number of persons
- Water requirement- Piping material
- Preliminary pipe sizing
- Preliminary layout- Pumping and storage facilities
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 21/23
December 3, 2007 SAWEA WORKSHOP - 2007 21
Development Process
Issue Initial
Draft DBSP
Conduct ValueEngineering Study
(if required)
Issue Draft DBSP for
Review
Incorporate
DBSP
Comments
Complete
DBSP
Seek Approval
Of DBSP
Obtain Capital Budget
Cost Estimate
Design Basis Agreement
on Optimized Scope
Prepare DBSP Execution
Plan
DevelopProject
Scope
Assess Synergies of
Combining Projects
Y S
O
Initiate DBSP/
Assign Team Members
Y S
Modify Project Scope or
Recommend Cancellation
O
Business
Case Still
Valid
Modify Project Scope or
Recommend Cancellation
Approve
BusinessCase/Stud
y
8/15/2019 Adli Khalaf - Design Basis Scoping Paper
http://slidepdf.com/reader/full/adli-khalaf-design-basis-scoping-paper 22/23
December 3, 2007 SAWEA WORKSHOP - 2007 22
Conclusions
DBSP is a critical document in every projectcycle
DBSP requires proper and timely input from
involved organizations
A GOOD DBSP will put the project on track(scope, cost and schedule), and prevent future
issues and conflicts
A POOR DBSP will hinder the project designand execution phases, and negatively impact
the project cost and schedule