Addendum 03 Narrative

47
CYNTERGY AEC LLC 1215 South Boulder Avenue, 4th Floor, Tulsa, OK 74119 Phone 918-877-6000 Fax 918-877-4000 www.cyntergyaec.com Addendum 03 Narrative Project Name: Cushing Vehicle Warehouse Project Location: GRDA – Cushing, OK This Addendum modifies previous Bid Documents, Specifications and Drawings as listed below. Bidders shall notify the Contracting Officer immediately with any discrepancies or errors found in these documents through the bid question system. Clarifications to Bid Questions 1. Bid Question: 1.1. Could not find information on the overhead door – is it insulated? Response: No, the overhead door will not be insulated. We have also added an OH door spec section to this addendum for reference. 2. Bid Substitution Question: 2.1. The Keystone block retaining wall system specified in the documents could be discontinued. Can a Dolese Trinity block wall system be used as a substitution? Response: Yes, the Dolese Trinity Segmental Block Wall System is an acceptable alternative to the Keystone block wall system. 3. Bid Question: 3.1. Sheet S001 "Design Criteria" #1 Says IBC 2006. One of the metal building manufactures has asked if this is correct. He said he can bid it this way, but his computer updates code automatically and says Cushing area is currently under IBC 2009. He just wants to make sure he is bidding the correct code you want. Response: The project should be under IBC 2009. 4. Bid Question: 4.1. Sheet C101 "Notes by symbols". Notes # 6,12,14,15 do not appear on the plan sheet. Please clarify? Response: Please omit Note 6 (OWS and drain excluded from project). Notes 12, 14 and 15 have been added to the plan sheet. See revised Sheet C101 included in this addendum. 5. Bid Question: 5.1. I know this is just a storage building, but is there any fire sprinkler, fire alarm or extinguishers required? Date: 07 August, 2015 To: Holly Moore, GRDA Director of Properties From: David Phelps, CAEC Project Manager Topic: Cushing Vehicle Warehouse Addendum 03 Narrative CC: Monica Fowler

Transcript of Addendum 03 Narrative

Page 1: Addendum 03 Narrative

CYNTERGY AEC L L C

1215 South Boulder Avenue, 4th Floor, Tulsa, OK 74119 Phone 918-877-6000 • Fax 918-877-4000

www.cyntergyaec.com

Addendum 03 Narrative Project Name: Cushing Vehicle Warehouse Project Location: GRDA – Cushing, OK

This Addendum modifies previous Bid Documents, Specifications and Drawings as listed below. Bidders shall notify the Contracting Officer immediately with any discrepancies or errors found in these documents through the bid question system.

Clarifications to Bid Questions

1. Bid Question:

1.1. Could not find information on the overhead door – is it insulated? Response: No, the overhead door will not be insulated. We have also added an OH door spec section to this addendum for reference.

2. Bid Substitution Question: 2.1. The Keystone block retaining wall system specified in the documents could be

discontinued. Can a Dolese Trinity block wall system be used as a substitution? Response: Yes, the Dolese Trinity Segmental Block Wall System is an acceptable alternative to the Keystone block wall system.

3. Bid Question: 3.1. Sheet S001 "Design Criteria" #1 Says IBC 2006. One of the metal building

manufactures has asked if this is correct. He said he can bid it this way, but his computer updates code automatically and says Cushing area is currently under IBC 2009. He just wants to make sure he is bidding the correct code you want.

Response: The project should be under IBC 2009.

4. Bid Question: 4.1. Sheet C101 "Notes by symbols". Notes # 6,12,14,15 do not appear on the plan sheet.

Please clarify? Response: Please omit Note 6 (OWS and drain excluded from project). Notes 12, 14 and 15 have been added to the plan sheet. See revised Sheet C101 included in this addendum.

5. Bid Question: 5.1. I know this is just a storage building, but is there any fire sprinkler, fire alarm or

extinguishers required?

Date: 07 August, 2015

To: Holly Moore, GRDA Director of Properties

From: David Phelps, CAEC Project Manager

Topic: Cushing Vehicle Warehouse Addendum 03 Narrative

CC: Monica Fowler

Page 2: Addendum 03 Narrative

Page 2 of 3

CYNTERGY AEC L L C

1215 South Boulder Avenue, 4th Floor, Tulsa, OK 74119 Phone 918-877-6000 • Fax 918-877-4000

www.cyntergyaec.com

Response: The building will not require a fire sprinkler system. It will require a fire detection/alarm system and a fire extingusher. Please refer to new FA101 drawing sheet and new Specification Section 283100 included in this addendum.

Document Changes and Clarifications Drawings

1. Sheet FA101:

• Sheet added to the set in its entirety in response to State Fire Marshal requirements. Per the rural water district and the Cushing Fire Department, no available fire hydrant water lines were found anywhere near the project site. Per State FM Code Directive 3013-8, option 2, a fire detection system will be installed.

2. Sheet C101:

• Detail 1 – Revised to add note symbols 12, 14, and 15 to plan. • Keynote 6 - Deleted. • Keynote 7 - Deleted. • Detail 1 – Revised to remove OWS and associated piping.

3. Sheet C102:

• Detail A-A – Revised to add separator fabric and adjust drainage material note. • Detail 1 – Revised to remove OWS and piping. • Revised callout note to remove “Seed” from grass note. Sod only.

4. Sheet C501:

• Detail 5 – deleted from sheet.

5. Sheet S101: • Detail 1 – revised to remove floor drain and adjust floor slab slopes.

6. Sheet A101: • Detail 1 – revised to remove floor drain and adjust floor slab slopes.

7. Sheet A102:

• Detail 1 – revised to remove floor drain and adjust floor slab slopes. 8. Sheet P101:

• Detail 1 – revised to remove floor drain and associated piping.

Page 3: Addendum 03 Narrative

Page 3 of 3

CYNTERGY AEC L L C

1215 South Boulder Avenue, 4th Floor, Tulsa, OK 74119 Phone 918-877-6000 • Fax 918-877-4000

www.cyntergyaec.com

Specifications

1. Section 000110: • Table of Contents – Added Section 083613 to TOC listing. • Table of Contents – Added Section 283100 to TOC listing.

2. Section 083613: • Added section 083613 – Overhead Doors in its entirety to project specifications.

3. Section 133419:

• Part 1.3, subparts A and A.1 – Quality Assurance – Revised language to relax requirements regarding MBMA and AISC.

4. Section 083613:

• Added section 283100 – Fire Detection and Alarm in its entirety to project specifications.

-- End of Addendum 03 Narrative --

Page 4: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 000110 08/07/2015 Page 1 of 2

TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 00 01 Project Title Page 00 01 07 Seals Page 00 01 10 Table of Contents BIDDING REQUIREMENTS Bidding Requirements (including Invitation to Bids, Instructions to Bidders, and Bid Forms) are issued by GRDA under separate cover and are not included in the Project Manual. CONTRACTING REQUIREMENTS Contracting Requirements (including Agreement, Bond, and Certificate Forms) are issued by GRDA un-der a separate cover and are not included in the Project Manual. DIVISION 01 - GENERAL REQUIREMENTS 011000 Summary 012500 Substitution Procedures 013300 Submittal Procedures 014000 Quality Requirements 017300 Execution 017419 Construction Waste Management And Disposal 017700 Closeout Procedures 017823 Operation And Maintenance Documentation 017839 Project Record Documents

DIVISION 03 033000 Cast-In-Place Concrete

DIVISION 08 083613 Overhead Doors – ADDM03 089116 Operable Wall Louvers DIVISION 13 133419 Metal Building Systems – ADDM03 DIVISION 22 220500 Common Work Results for Plumbing 220553 Identification for Plumbing Piping and Equipment 221700 Plumbing Insulation 221116 Domestic Water Piping 221119 Domestic Water Piping Specialties 221316 Sanitary Waste and Vent Piping 221319 Sanitary Waste Piping Specialties DIVISION 23 230500 Common Work Results for HVAC 230513 Common Motor Requirements for HVAC Equipment 230529 Hangers and Supports for HVAC Piping and Equipment 230553 Identification for HVAC Piping and Equipment 230593 Testing, Adjusting, and Balancing for HVAC

Page 5: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 000110 08/07/2015 Page 2 of 2

233113 Metal Ducts 233423 HVAC Power Ventilators 233713 Diffusers, Registers, and Grilles DIVISION 26 260500 Common Work Results for Electrical 260519 Low Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding for Electrical Systems 260529 Hangers and Supports for Electrical Systems 260533 Raceway and Boxes for Electrical Systems 260553 Identification for Electrical Systems 262416 Panelboards 262726 Wiring Devices 262813 Fuses 265100 Interior Lighting DIVISION 28 283100 Fire Detection and Alarm – ADDM03 DIVISION 31 311000 Site Clearing 312000 Earth Moving EXHIBITS 000000 Geotechnical Report

Page 6: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 083613 08/07/2015 Page 1 of 8

SECTION 083613 - SECTIONAL DOORS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes electrically operated sectional doors.

B. Related Requirements:

1. Section 055000 "Metal Fabrications" for miscellaneous steel supports.

1.2 ACTION SUBMITTALS

A. Product Data: For each type and size of sectional door and accessory.

B. Shop Drawings: For each installation and for special components not dimensioned or detailed in manufacturer's product data.

C. Samples: For each exposed product and for each color and texture specified.

1.3 INFORMATIONAL SUBMITTALS

A. Sample warranty.

1.4 CLOSEOUT SUBMITTALS

A. Maintenance data.

1.5 QUALITY ASSURANCE

A. Wood Sectional Door Manufacturer Qualifications: A qualified manufacturer that is certified for chain of custody by an FSC-accredited certification body.

B. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer for both installation and maintenance of units required for this Project.

1.6 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of sectional doors that fail in materials or workmanship within specified warranty period.

Page 7: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 083613 08/07/2015 Page 2 of 8

1. Warranty Period: Manufacturer standard number of years from date of Substantial Completion.

B. Special Finish Warranty: Manufacturer agrees to repair or replace components that show evidence of deterioration of factory-applied finishes within specified warranty period.

1. Warranty Period: Manufacturer standard number of years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. General Performance: Sectional doors shall comply with performance requirements specified without failure due to defective manufacture, fabrication, installation, or other defects in construction and without requiring temporary installation of reinforcing components.

B. Structural Performance, Exterior Doors: Capable of withstanding the design wind loads.

1. Design Wind Load: Uniform pressure (velocity pressure) of 20 lbf/sq. ft., acting inward and outward.

2. Testing: According to ASTM E 330.

2.2 DOOR ASSEMBLY

A. Steel Sectional Door: Sectional door formed with hinged sections and fabricated according to DASMA 102 unless otherwise indicated.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Amarr Garage Doors. b. Arm-R-Lite. c. C.H.I. Overhead Doors, Inc. d. Clopay Building Products. e. Fimbel Architectural Door Specialties. f. Haas Door. g. Martin Door Manufacturing. h. Overhead Door Corporation. i. Raynor. j. Wayne-Dalton Corp. k. Windsor Door.

B. Operation Cycles: Door components and operators capable of operating for not less than 10,000.

C. Air Infiltration: Maximum rate of 0.08 cfm/sq. ft. at 15 and 25 mph when tested according to ASTM E 283 or DASMA 105.

Page 8: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 083613 08/07/2015 Page 3 of 8

D. Steel Sections: Zinc-coated (galvanized) steel sheet with [G60] [G90] zinc coating.

1. Section Thickness: 1-3/8 inches. 2. Exterior-Face Surface: Ribbed. 3. Interior Facing Material: Zinc-coated (galvanized) steel sheet or manufacturer's standard

material.

E. Track Configuration: Provide track as recommended by manufacturer to suit loading required and clearances available.

F. Weatherseals: Fitted to bottom and top of door.

G. Windows: Approximately 24 by 11 inches, with curved corners, and spaced apart the approximate distance as indicated on Drawings; in one row(s) at height indicated on Drawings; installed with glazing of clear acrylic plastic.

H. Locking Devices: Equip door with slide bolt for padlock and chain lock keeper.

1. Locking Device Assembly: Cremone type, both jamb sides, locking bars, operable from inside with thumbturn outside with cylinder.

I. Electric Door Operator:

1. Usage Classification: Standard duty, up to 25 cycles per hour and up to 90 cycles per day.

2. Operator Type: Manufacturer's standard for door requirements. 3. Safety: Listed according to UL 325 by a qualified testing agency for commercial or

industrial use; moving parts of operator enclosed or guarded if exposed and mounted at 8 feet or lower.

4. Motor Exposure: Interior, clean, and dry. 5. Emergency Manual Operation: Chain type. 6. Obstruction-Detection Device: Automatic photoelectric sensor. 7. Control Station: Interior-side mounted. 8. Other Equipment: Portable, radio-control system.

J. Door Finish: 1. Baked-Enamel or Powder-Coat Finish: Color and gloss as selected by Architect from

manufacturer's full range. 2. Factory Prime Finish: Manufacturer's standard color.

2.3 STEEL DOOR SECTIONS

A. Exterior Section Faces and Frames: Zinc-coated (galvanized), cold-rolled, commercial steel (CS) sheet.

1. Roll horizontal meeting edges to a continuous, interlocking, keyed, rabbeted, shiplap, or tongue-in-groove weather-resistant seal, with a reinforcing flange return.

Page 9: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 083613 08/07/2015 Page 4 of 8

2. For insulated doors, provide sections with continuous thermal-break construction, separating the exterior and interior faces of door.

B. Section Ends and Intermediate Stiles: Enclose open ends of sections with channel end stiles formed from galvanized-steel sheet welded to door section. Provide intermediate stiles formed from galvanized-steel sheet, cut to door section profile, and welded in place. Space stiles not more than 48 inches apart.

C. Reinforce bottom section with a continuous channel or angle conforming to bottom-section profile and allowing installation of astragal.

D. Reinforce sections with continuous horizontal and diagonal reinforcement, as required to stiffen door and for wind loading. Provide galvanized-steel bars, struts, trusses, or strip steel, formed to depth and bolted or welded in place. Ensure that reinforcement does not obstruct vision lites.

E. Provide reinforcement for hardware attachment.

F. Thermal Insulation: Insulate interior of steel sections with door manufacturer's standard CFC-free insulation, with maximum flame-spread and smoke-developed indexes of 75 and 450, respectively, according to ASTM E 84. Enclose insulation completely within steel sections and the interior facing material, with no exposed insulation.

2.4 TRACKS, SUPPORTS, AND ACCESSORIES

A. Tracks: Manufacturer's standard, galvanized-steel track system of configuration indicated, sized for door size and weight, designed for lift type indicated and clearances indicated on Drawings, Provide complete system including brackets, bracing, and reinforcement to ensure rigid support of ball-bearing roller guides for required door type, size, weight, and loading.

1. Track Reinforcement and Supports: Galvanized-steel members to support track without sag, sway, and vibration during opening and closing of doors. Slot vertical sections of track spaced 2 inches apart for door-drop safety device.

B. Weatherseals: Replaceable, adjustable, continuous, compressible weather-stripping gaskets of flexible vinyl, rubber, or neoprene fitted to bottom and top of sectional door unless otherwise indicated.

C. Windows: Manufacturer's standard window units of type, size, and in arrangement indicated. Provide removable stops of same material as door-section frames.

2.5 HARDWARE

A. General: Heavy-duty, corrosion-resistant hardware, with hot-dip galvanized, stainless-steel, or other corrosion-resistant fasteners, to suit door type.

B. Hinges: Heavy-duty, galvanized-steel hinges at each end stile and at each intermediate stile, according to manufacturer's written recommendations for door size. Attach hinges to door sections through stiles and rails.

Page 10: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 083613 08/07/2015 Page 5 of 8

C. Rollers: Heavy-duty rollers with steel ball-bearings in case-hardened steel races, mounted with varying projections to suit slope of track. Provide 3-inch- diameter roller tires for 3-inch- wide track and 2-inch- diameter roller tires for 2-inch- wide track.

D. Push/Pull Handles: Equip each push-up operated or emergency-operated door with galvanized-steel lifting handles on each side of door, finished to match door.

2.6 LOCKING DEVICES

A. Slide Bolt: Fabricate with side-locking bolts to engage through slots in tracks for locking by padlock, located on single-jamb side, operable from inside only.

B. Locking Device Assembly: Fabricate with cylinder lock, spring-loaded deadbolt, operating handle, cam plate, and adjustable locking bars to engage through slots in tracks.

1. Lock Cylinders: Cylinders standard with manufacturer and keyed to building keying system.

2. Keys: Three for each cylinder.

C. Chain Lock Keeper: Suitable for padlock.

D. Safety Interlock Switch: Equip power-operated doors with safety interlock switch to disengage power supply when door is locked.

2.7 COUNTERBALANCE MECHANISM

A. Torsion Spring: Counterbalance mechanism consisting of adjustable-tension torsion springs fabricated from steel-spring wire complying with ASTM A 229/A 229M, mounted on torsion shaft made of steel tube or solid steel. Provide springs designed for number of operation cycles indicated.

B. Cable Drums and Shaft for Doors: Cast-aluminum or gray-iron casting cable drums mounted on torsion shaft and grooved to receive door-lifting cables as door is raised. Mount counterbalance mechanism with manufacturer's standard ball-bearing brackets at each end of torsion shaft.

C. Cables: Galvanized-steel, multistrand, lifting cables.

D. Cable Safety Device: Include a spring-loaded steel or spring-loaded bronze cam mounted to bottom door roller assembly on each side and designed to automatically stop door if either lifting cable breaks.

E. Bracket: Provide anchor support bracket as required to connect stationary end of spring to the wall and to level the shaft and prevent sag.

F. Bumper: Provide spring bumper at each horizontal track to cushion door at end of opening operation.

Page 11: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 083613 08/07/2015 Page 6 of 8

2.8 ELECTRIC DOOR OPERATORS

A. General: Electric door operator assembly of size and capacity recommended and provided by door manufacturer for door and "operation cycles" requirement specified, with electric motor and factory-prewired motor controls, starter, gear-reduction unit, solenoid-operated brake, clutch, control stations, control devices, integral gearing for locking door, and accessories required for proper operation.

1. Manufacturers: Subject to compliance with requirements, provide products by the following:

a. Chamberlain Group, Inc. (The).

2. Comply with NFPA 70.

3. Control equipment complying with NEMA ICS 1, NEMA ICS 2, and NEMA ICS 6; with NFPA 70, Class 2 control circuit, maximum 24-V ac or dc.

B. Usage Classification: Electric operator and components capable of operating for not less than number of cycles per hour indicated for each door.

C. Door-Operator Type: Unit consisting of electric motor, gears, pulleys, belts, sprockets, chains, and controls needed to operate door and meet required usage classification.

D. Motors: Reversible-type motor with controller (disconnect switch) for motor exposure indicated.

1. Electrical Characteristics:

a. Phase: Single phase. b. Volts: 115 V. c. Hertz: 60.

2. Motor Size: Minimum size as indicated. If not indicated, large enough to start, accelerate, and operate door in either direction from any position, at a speed not less than 8 in./sec. and not more than 12 in./sec., without exceeding nameplate ratings or service factor.

E. Obstruction Detection Device: External entrapment protection consisting of indicated automatic safety sensor capable of protecting full width of door opening. Activation of device immediately stops and reverses downward door travel.

1. Photoelectric Sensor: Manufacturer's standard system designed to detect an obstruction in door opening without contact between door and obstruction.

a. Self-Monitoring Type: Designed to interface with door operator control circuit to detect damage to or disconnection of sensing device. When self-monitoring feature is activated, door closes only with sustained pressure on close button.

Page 12: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 083613 08/07/2015 Page 7 of 8

2. Electric Sensor Edge: Automatic safety sensor edge, located within astragal or weather stripping mounted to bottom section. Contact with sensor activates device. Connect to control circuit using manufacturer's standard take-up reel or self-coiling cable.

a. Self-Monitoring Type: Four-wire configured device designed to interface with door-operator control circuit to detect damage to or disconnection of sensor edge.

F. Control Station: Three-button control station in fixed location with momentary-contact push-button controls labeled "Open" and "Stop" and sustained- or constant-pressure, push-button control labeled "Close."

1. Interior-Mounted Units: Full-guarded, surface-mounted, heavy-duty type, with general-purpose NEMA ICS 6, Type 1 enclosure.

2. Exterior-Mounted Units: Full-guarded, standard-duty, surface-mounted, weatherproof type, NEMA ICS 6, Type 4 enclosure, key operated.

G. Emergency Manual Operation: Equip electrically powered door with capability for emergency manual operation. Design manual mechanism so required force for door operation does not exceed 25 lbf.

H. Emergency Operation Disconnect Device: Equip operator with hand-operated disconnect mechanism for automatically engaging manual operator and releasing brake for emergency manual operation while disconnecting motor without affecting timing of limit switch. Mount mechanism so it is accessible from floor level. Include interlock device to automatically prevent motor from operating when emergency operator is engaged.

I. Motor Removal: Design operator so motor may be removed without disturbing limit-switch adjustment and without affecting emergency manual operation.

J. Audible and Visual Signals: Audible alarm and visual indicator lights in compliance with regulatory requirements for accessibility.

K. Portable, Radio-Control System: Consisting of one of the following:

1. Three-channel universal coaxial receiver to open, close, and stop door. 2. Portable control device to open and stop door may be momentary-contact type; control to

close door shall be sustained- or constant-pressure type.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install sectional doors and operating equipment complete with necessary hardware, anchors, inserts, hangers, and equipment supports; according to manufacturer's written instructions and as specified.

B. Tracks: Provide sway bracing, diagonal bracing, and reinforcement as required for rigid installation of track and door-operating equipment.

Page 13: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 083613 08/07/2015 Page 8 of 8

C. Accessibility: Install sectional doors, switches, and controls along accessible routes in compliance with regulatory requirements for accessibility.

D. Power-Operated Doors: Install automatic garage doors openers according to UL 325.

E. Adjust hardware and moving parts to function smoothly so that doors operate easily, free of warp, twist, or distortion.

F. Touch-up Painting: Immediately after welding galvanized materials, clean welds and abraded galvanized surfaces and repair galvanizing to comply with ASTM A 780/A 780M.

3.2 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain sectional doors.

END OF SECTION 083613

Page 14: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 1 of 13

SECTION 133419 - METAL BUILDING SYSTEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Structural-steel framing. 2. Metal roof panels. 3. Metal wall panels. 4. Thermal insulation. 5. Doors and frames. 6. Accessories.

1.2 SUBMITTALS

A. Product Data: For each type of metal building system component.

B. Shop Drawings: For metal building system components. Include plans, elevations, sections, details, and attachments to other work.

C. Samples: For each type of exposed finish required.

D. Delegated-Design Submittal: For metal building systems indicated to comply with performance requirements and design criteria, including analysis data and calculations signed and sealed by the qualified professional engineer responsible for their preparation.

E. Welding certificates.

F. Metal Building System Certificates: For each type of metal building system, from manufacturer.

1. Letter of Design Certification: Signed and sealed by a qualified professional engineer. Include the following:

a. Name and location of Project. b. Order number. c. Name of manufacturer. d. Name of Contractor. e. Building dimensions including width, length, height, and roof slope. f. Indicate compliance with AISC standards for hot-rolled steel and AISI standards

for cold-rolled steel, including edition dates of each standard. g. Governing building code and year of edition. h. Design Loads: Include dead load, roof live load, collateral loads, roof snow load,

deflection, wind loads/speeds and exposure, seismic design category or effective peak velocity-related acceleration/peak acceleration, and auxiliary loads (cranes).

Page 15: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 2 of 13

i. Load Combinations: Indicate that loads were applied acting simultaneously with concentrated loads, according to governing building code.

j. Building-Use Category: Indicate category of building use and its effect on load importance factors.

k. AISC Certification for Category MB: Include statement that metal building system and components were designed and produced in an AISC-Certified Facility by an AISC-Certified Manufacturer.

G. Material test reports.

H. Source quality-control reports.

I. Field quality-control reports.

J. Maintenance data.

K. Warranties: Sample of special warranties.

1.3 QUALITY ASSURANCE

A. Manufacturer Qualifications: A qualified manufacturer and member of MBMA. (ADDM 03).

1. AISC Certification for Category MB: An AISC-Certified Manufacturer that designs and produces metal building systems and components in an AISC-Certified Facility or a minimum of five (5) years of experience in metal building systems fabrication and erection. (ADDM 03).

2. Engineering Responsibility: Preparation of Shop Drawings and comprehensive engineering analysis by a qualified professional engineer.

B. Erector Qualifications: An experienced erector who specializes in erecting and installing work similar in material, design, and extent to that indicated for this Project and who is acceptable to manufacturer.

C. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel." 2. AWS D1.3, "Structural Welding Code - Sheet Steel."

D. Structural Steel: Comply with AISC 360, "Specification for Structural Steel Buildings," for design requirements and allowable stresses.

E. Cold-Formed Steel: Comply with AISI's "North American Specification for the Design of Cold-Formed Steel Structural Members" for design requirements and allowable stresses.

1.4 WARRANTY

A. Special Warranty on Metal Panel Finishes: Manufacturer's standard form in which manufacturer agrees to repair finish or replace metal panels that show evidence of deterioration of factory-applied finishes within specified warranty period.

Page 16: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 3 of 13

1. Finish Warranty Period: 20 years from date of Substantial Completion.

B. Special Weathertightness Warranty for Standing-Seam Metal Roof Panels: Manufacturer's standard form in which manufacturer agrees to repair or replace standing-seam metal roof panel assemblies that leak or otherwise fail to remain weathertight within specified warranty period.

1. Warranty Period: 20 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Basis-of-Design Product: Subject to compliance with requirements, provide product indicated on Drawings by one of the following:

1. Mueller, Inc. 2. Whitney Manufacturing, Inc. 3. Steel Service Building Co.

2.2 METAL BUILDING SYSTEM PERFORMANCE

A. Delegated Design: Design metal building system, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.

B. Structural Performance: Metal building systems shall be designed according to procedures in MBMA's "Metal Building Systems Manual." 1. Design Loads: As required by MBMA's "Metal Building Systems Manual." and

ASCE/SEI 7. 2. Deflection Limits: Design metal building system assemblies to withstand design loads

with deflections no greater than the following:

a. Purlins and Rafters: Vertical deflection of 1/180 of the span. b. Girts: Horizontal deflection of 1/180 of the span. c. Metal Roof Panels: Vertical deflection of 1/180 of the span. d. Metal Wall Panels: Horizontal deflection of 1/180 of the span. e. Design secondary-framing system to accommodate deflection of primary framing

and construction tolerances, and to maintain clearances at openings.

3. Drift Limits: Engineer building structure to withstand design loads with drift limits no greater than the following:

a. Lateral Drift: Maximum of 1/200 of the building height.

4. Metal panel assemblies shall withstand the effects of gravity loads and loads and stresses within limits and under conditions indicated according to ASTM E 1592.

C. Seismic Performance: Metal building systems shall withstand the effects of earthquake motions determined according to ASCE/SEI 7.

Page 17: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 4 of 13

D. Thermal Movements: Allow for thermal movements resulting from the following maximum change (range) in ambient and surface temperatures by preventing buckling, opening of joints, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects. Base engineering calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss.

1. Temperature Change (Range): 120 deg F, ambient; 180 deg F , material surfaces.

E. Air Infiltration for Metal Roof Panels: Air leakage through assembly of not more than 0.06 cfm/sq. ft. of roof area when tested according to ASTM E 1680 at negative test-pressure difference of 1.57 lbf/sq. ft. .

F. Air Infiltration for Metal Wall Panels: Air leakage through assembly of not more than 0.06 cfm/sq. ft. of wall area when tested according to ASTM E 283 at static-air-pressure difference of 1.57 lbf/sq. ft. .

G. Water Penetration for Metal Roof Panels: No water penetration when tested according to ASTM E 1646 at test-pressure difference of 2.86 lbf/sq. ft. .

H. Water Penetration for Metal Wall Panels: No water penetration when tested according to ASTM E 331 at a wind-load design pressure of not less than 2.86 lbf/sq. ft. .

I. Wind-Uplift Resistance: Provide metal roof panel assemblies that comply with UL 580 for Class 60 .

J. Energy Performance: Provide roof panels with Solar Reflectance Index not less than 29 when calculated according to ASTM E 1980 based on testing identical products by a qualified testing agency.

2.3 STRUCTURAL-STEEL FRAMING

A. Primary Framing: Manufacturer's standard primary-framing system, designed to withstand required loads and specified requirements. Primary framing includes transverse frames; rafter, rake, and canopy beams; sidewall, intermediate, end-wall, and corner columns; and wind bracing.

1. General: Provide frames with attachment plates, bearing plates, and splice members. Factory drill for field-bolted assembly.

2. Frame Configuration: Single gable. 3. Exterior Column Type: Tapered depth. 4. Rafter Type: Uniform depth.

B. End-Wall Framing: Manufacturer's standard primary end-wall framing fabricated for field-bolted assembly.

C. Secondary Framing: Manufacturer's standard secondary framing, including purlins, girts, eave struts, flange bracing, base members, gable angles, clips, headers, jambs, and other miscellaneous structural members. Unless otherwise indicated, fabricate framing from either cold-formed, structural-steel sheet or roll-formed, metallic-coated steel sheet, prepainted with coil coating.

Page 18: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 5 of 13

D. Bolts: Provide plain-finish bolts for structural-framing components that are primed or finish painted. Provide zinc-plated or hot-dip galvanized bolts for structural-framing components that are galvanized.

E. Finish: Factory primed. Apply specified primer immediately after cleaning and pretreating.

2.4 METAL ROOF PANELS

A. Tapered-Rib-Profile, Lap-Seam Metal Roof Panels : Formed with raised, trapezoidal major ribs and intermediate stiffening ribs symmetrically spaced between major ribs; designed to be installed by lapping side edges of adjacent panels and mechanically attaching panels to supports using exposed fasteners in side laps.

1. Material: Zinc-coated (galvanized) 26 gage steel sheet.

a. Exterior Finish: Siliconized polyester. b. Color: As selected by Architect from manufacturer's full range .

2. Major-Rib Spacing: 12 inches o.c. 3. Panel Coverage: 36 inches. 4. Panel Height: 1.125 inches.

2.5 METAL WALL PANELS

A. Tapered-Rib-Profile, Exposed-Fastener Metal Wall Panels: Formed with raised, trapezoidal major ribs and intermediate stiffening ribs symmetrically spaced between major ribs; designed to be installed by lapping side edges of adjacent panels and mechanically attaching panels to supports using exposed fasteners in side laps.

1. Material: Zinc-coated (galvanized) steel sheet, 26 gage nominal thickness.

a. Exterior Finish: Siliconized polyester. b. Color: As selected by Architect from manufacturer's full range.

2. Major-Rib Spacing: 12 inches o.c. 3. Panel Coverage: 36 inches. 4. Panel Height: 1.125 inches.

2.6 THERMAL INSULATION

A. Faced Metal Building Insulation: ASTM C 991, Type II, glass-fiber-blanket insulation; 0.5-lb/cu. ft. density; 2-inch- wide, continuous, vapor-tight edge tabs; with a flame-spread index of 25 or less.

Page 19: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 6 of 13

2.7 DOORS AND FRAMES

A. Swinging Personnel Doors and Frames: Metal building system manufacturer's standard doors and frames; prepared and reinforced at strike and at hinges to receive factory- and field-applied hardware according to BHMA A156 Series.

1. Hardware:

a. Provide hardware for each door leaf, as follows:

1) Hinges: BHMA A156.1. Three antifriction-bearing, standard-weight, full-mortise, stainless-steel or bronze, template-type hinges; 4-1/2 by 4-1/2 inches, with nonremovable pin.

2) Lockset: BHMA A156.2. Mortise, with lever handle type. 3) Exit Device: BHMA A156.3. Touch- or push-bar type. 4) Threshold: BHMA A156.21. Extruded aluminum. 5) Silencers: Pneumatic rubber; three silencers on strike jambs of single door

frames and two silencers on heads of double door frames. 6) Closer: BHMA A156.4. Surface-applied, standard-duty hydraulic type. 7) Weather Stripping: Vinyl applied to head and jambs, with vinyl sweep at

sill.

B. Finishes for Personnel Doors and Frames:

1. Prime Finish: Factory-apply manufacturer's standard primer immediately after cleaning and pretreating.

2. Factory-Applied Paint Finish: Manufacturer's standard, complying with SDI A250.3 for performance and acceptance criteria.

a. Color and Gloss: As selected by Architect from manufacturer's full range .

2.8 ACCESSORIES

A. General: Provide accessories as standard with metal building system manufacturer and as specified. Fabricate and finish accessories at the factory to greatest extent possible, by manufacturer's standard procedures and processes. Comply with indicated profiles and with dimensional and structural requirements.

1. Form exposed sheet metal accessories that are without excessive oil-canning, buckling, and tool marks and that are true to line and levels indicated, with exposed edges folded back to form hems.

B. Roof Panel Accessories: Provide components required for a complete metal roof panel assembly including copings, fasciae, corner units, ridge closures, clips, sealants, gaskets, fillers, closure strips, and similar items. Match material and finish of metal roof panels unless otherwise indicated.

C. Wall Panel Accessories: Provide components required for a complete metal wall panel assembly including copings, fasciae, mullions, sills, corner units, clips, sealants, gaskets, fillers,

Page 20: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 7 of 13

closure strips, and similar items. Match material and finish of metal wall panels unless otherwise indicated.

D. Flashing and Trim: Formed from 0.022-inch nominal-thickness, metallic-coated steel sheet or aluminum-zinc alloy-coated steel sheet prepainted with coil coating; finished to match adjacent metal panels.

E. Gutters: Formed from 0.022-inch nominal-thickness, metallic-coated steel sheet or aluminum-zinc alloy-coated steel sheet prepainted with coil coating; finished to match roof fascia and rake trim. Match profile of gable trim, complete with end pieces, outlet tubes, and other special pieces as required. Fabricate in minimum 96-inch- long sections, sized according to SMACNA's "Architectural Sheet Metal Manual."

1. Gutter Supports: Fabricated from same material and finish as gutters. 2. Strainers: Bronze, copper, or aluminum wire ball type at outlets.

F. Downspouts: Formed from 0.022-inch nominal-thickness, zinc-coated (galvanized) steel sheet or aluminum-zinc alloy-coated steel sheet prepainted with coil coating; finished to match metal wall panels. Fabricate in minimum 10-foot- long sections, complete with formed elbows and offsets.

1. Mounting Straps: Fabricated from same material and finish as gutters.

G. Pipe Flashing: Premolded, EPDM pipe collar with flexible aluminum ring bonded to base.

2.9 FABRICATION

A. General: Design components and field connections required for erection to permit easy assembly.

1. Mark each piece and part of the assembly to correspond with previously prepared erection drawings, diagrams, and instruction manuals.

2. Fabricate structural framing to produce clean, smooth cuts and bends. Punch holes of proper size, shape, and location. Members shall be free of cracks, tears, and ruptures.

B. Tolerances: Comply with MBMA's "Metal Building Systems Manual" for fabrication and erection tolerances.

C. Primary Framing: Shop fabricate framing components to size and section, with baseplates, bearing plates, stiffeners, and other items required for erection welded into place. Cut, form, punch, drill, and weld framing for bolted field assembly.

D. Secondary Framing: Shop fabricate framing components to size and section by roll-forming or break-forming, with baseplates, bearing plates, stiffeners, and other plates required for erection welded into place. Cut, form, punch, drill, and weld secondary framing for bolted field connections to primary framing.

E. Metal Panels: Fabricate and finish metal panels at the factory to greatest extent possible, by manufacturer's standard procedures and processes, as necessary to fulfill indicated performance

Page 21: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 8 of 13

requirements. Comply with indicated profiles and with dimensional and structural requirements.

PART 3 - EXECUTION

3.1 ERECTION OF STRUCTURAL FRAMING

A. Erect metal building system according to manufacturer's written erection instructions and erection drawings.

B. Do not field cut, drill, or alter structural members without written approval from metal building system manufacturer's professional engineer.

C. Set structural framing accurately in locations and to elevations indicated, according to AISC specifications referenced in this Section. Maintain structural stability of frame during erection.

D. Base and Bearing Plates: Clean concrete- and masonry-bearing surfaces of bond-reducing materials, and roughen surfaces prior to setting plates. Clean bottom surface of plates.

1. Set plates for structural members on wedges, shims, or setting nuts as required. 2. Tighten anchor rods after supported members have been positioned and plumbed. Do not

remove wedges or shims but, if protruding, cut off flush with edge of plate before packing with grout.

3. Promptly pack grout solidly between bearing surfaces and plates so no voids remain. Neatly finish exposed surfaces; protect grout and allow to cure. Comply with manufacturer's written installation instructions for shrinkage-resistant grouts.

E. Align and adjust structural framing before permanently fastening. Before assembly, clean bearing surfaces and other surfaces that will be in permanent contact with framing. Perform necessary adjustments to compensate for discrepancies in elevations and alignment.

1. Level and plumb individual members of structure. 2. Make allowances for difference between temperature at time of erection and mean

temperature when structure will be completed and in service.

F. Primary Framing and End Walls: Erect framing level, plumb, rigid, secure, and true to line. Level baseplates to a true even plane with full bearing to supporting structures, set with double-nutted anchor bolts. Use grout to obtain uniform bearing and to maintain a level base-line elevation. Moist-cure grout for not less than seven days after placement.

1. Make field connections using high-strength bolts installed according to RCSC's "Specification for Structural Joints Using ASTM A 325 or A 490 Bolts" for bolt type and joint type specified.

a. Joint Type: Snug tightened or pretensioned.

G. Secondary Framing: Erect framing level, plumb, rigid, secure, and true to line. Field bolt secondary framing to clips attached to primary framing.

1. Provide rake or gable purlins with tight-fitting closure channels and fasciae.

Page 22: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 9 of 13

2. Locate and space wall girts to suit openings such as doors and windows. 3. Locate canopy framing as indicated. 4. Provide supplemental framing at entire perimeter of openings, including doors, windows,

louvers, ventilators, and other penetrations of roof and walls.

H. Bracing: Install bracing in roof and sidewalls where indicated on erection drawings.

1. Tighten rod and cable bracing to avoid sag. 2. Locate interior end-bay bracing only where indicated.

I. Framing for Openings: Provide shapes of proper design and size to reinforce openings and to carry loads and vibrations imposed, including equipment furnished under mechanical and electrical work. Securely attach to structural framing.

J. Erection Tolerances: Maintain erection tolerances of structural framing within AISC 303.

3.2 METAL PANEL INSTALLATION, GENERAL

A. General: Anchor metal panels and other components of the Work securely in place, with provisions for thermal and structural movement.

1. Field cut metal panels as required for doors, windows, and other openings. Cut openings as small as possible, neatly to size required, and without damage to adjacent metal panel finishes.

a. Field cutting of metal panels by torch is not permitted unless approved in writing by manufacturer.

2. Install metal panels perpendicular to structural supports unless otherwise indicated. 3. Flash and seal metal panels with weather closures at perimeter of openings and similar

elements. Fasten with self-tapping screws. 4. Locate and space fastenings in uniform vertical and horizontal alignment. 5. Locate metal panel splices over, but not attached to, structural supports with end laps in

alignment. 6. Lap metal flashing over metal panels to allow moisture to run over and off the material.

B. Lap-Seam Metal Panels: Install screw fasteners using power tools with controlled torque adjusted to compress EPDM washers tightly without damage to washers, screw threads, or metal panels. Install screws in predrilled holes.

1. Arrange and nest side-lap joints so prevailing winds blow over, not into, lapped joints. Lap ribbed or fluted sheets one full rib corrugation. Apply metal panels and associated items for neat and weathertight enclosure. Avoid "panel creep" or application not true to line.

C. Metal Protection: Where dissimilar metals contact each other or corrosive substrates, protect against galvanic action by painting contact surfaces with corrosion-resistant coating, by applying rubberized-asphalt underlayment to each contact surface, or by other permanent separation as recommended by metal roof panel manufacturer.

Page 23: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 10 of 13

D. Joint Sealers: Install gaskets, joint fillers, and sealants where indicated and where required for weatherproof performance of metal panel assemblies. Provide types of gaskets, fillers, and sealants recommended by metal panel manufacturer.

1. Seal metal panel end laps with double beads of tape or sealant the full width of panel. Seal side joints where recommended by metal panel manufacturer.

2. Prepare joints and apply sealants to comply with requirements in Division 07 Section "Joint Sealants."

3.3 METAL ROOF PANEL INSTALLATION

A. General: Provide metal roof panels of full length from eave to ridge unless otherwise indicated or restricted by shipping limitations.

1. Install ridge caps as metal roof panel work proceeds. 2. Flash and seal metal roof panels with weather closures at eaves and rakes. Fasten with

self-tapping screws.

B. Lap-Seam Metal Roof Panels: Fasten metal roof panels to supports with exposed fasteners at each lapped joint, at location and spacing recommended by manufacturer.

1. Provide metal-backed sealing washers under heads of exposed fasteners bearing on weather side of metal roof panels.

2. Provide sealant tape at lapped joints of metal roof panels and between panels and protruding equipment, vents, and accessories.

3. Apply a continuous ribbon of sealant tape to weather-side surface of fastenings on end laps and on side laps of nesting-type metal panels, on side laps of ribbed or fluted metal panels, and elsewhere as needed to make metal panels weatherproof to driving rains.

4. At metal panel splices, nest panels with minimum 6-inch end lap, sealed with butyl-rubber sealant and fastened together by interlocking clamping plates.

3.4 METAL WALL PANEL INSTALLATION

A. General: Install metal wall panels in orientation, sizes, and locations indicated on Drawings. Install panels perpendicular to girts, extending full height of building, unless otherwise indicated. Anchor metal wall panels and other components of the Work securely in place, with provisions for thermal and structural movement.

1. Unless otherwise indicated, begin metal panel installation at corners with center of rib lined up with line of framing.

2. Shim or otherwise plumb substrates receiving metal wall panels. 3. When two rows of metal panels are required, lap panels 4 inches minimum. 4. When building height requires two rows of metal panels at gable ends, align lap of gable

panels over metal wall panels at eave height. 5. Rigidly fasten base end of metal wall panels and allow eave end free movement due to

thermal expansion and contraction. Predrill panels. 6. Flash and seal metal wall panels with weather closures at eaves, rakes, and at perimeter

of all openings. Fasten with self-tapping screws. 7. Install screw fasteners in predrilled holes.

Page 24: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 11 of 13

8. Install flashing and trim as metal wall panel work proceeds. 9. Apply elastomeric sealant continuously between metal base channel (sill angle) and

concrete, and elsewhere as indicated; or, if not indicated, as necessary for waterproofing. 10. Align bottom of metal wall panels and fasten with blind rivets, bolts, or self-drilling or

self-tapping screws. 11. Provide weatherproof escutcheons for pipe and conduit penetrating exterior walls.

B. Metal Wall Panels: Install metal wall panels on exterior side of girts. Attach metal wall panels to supports with fasteners as recommended by manufacturer.

3.5 METAL SOFFIT PANEL INSTALLATION

A. Provide metal soffit panels the full width of soffits. Install panels perpendicular to support framing.

B. Flash and seal metal soffit panels with weather closures where panels meet walls and at perimeter of all openings.

3.6 THERMAL INSULATION INSTALLATION

A. General: Install insulation concurrently with metal panel installation, in thickness indicated to cover entire surface, according to manufacturer's written instructions.

1. Set vapor-retarder-faced units with vapor retarder toward warm side of construction unless otherwise indicated. Do not obstruct ventilation spaces except for firestopping.

2. Tape joints and ruptures in vapor retarder, and seal each continuous area of insulation to the surrounding construction to ensure airtight installation.

3. Install factory-laminated, vapor-retarder-faced blankets straight and true in one-piece lengths, with both sets of facing tabs sealed, to provide a complete vapor retarder.

B. Blanket Roof Insulation: Comply with the following installation method:

1. Over-Framing Installation: Extend insulation and vapor retarder over and perpendicular to top flange of secondary framing. Hold in place by metal roof panels fastened to secondary framing.

2. Retainer Strips: Install retainer strips at each longitudinal insulation joint, straight and taut, nesting with secondary framing to hold insulation in place.

C. Blanket Wall Insulation: Extend insulation and vapor retarder over and perpendicular to top flange of secondary framing. Hold in place by metal wall panels fastened to secondary framing.

1. Retainer Strips: Install retainer strips at each longitudinal insulation joint, straight and taut, nesting with secondary framing to hold insulation in place.

3.7 DOOR AND FRAME INSTALLATION

A. General: Install doors and frames plumb, rigid, properly aligned, and securely fastened in place according to manufacturers' written instructions. Coordinate installation with wall flashings and

Page 25: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 12 of 13

other components. Seal perimeter of each door frame with elastomeric sealant used for metal wall panels.

B. Personnel Doors and Frames: Install doors and frames according to SDI A250.8.

C. Field Glazing: Comply with installation requirements in Division 08 Section "Glazing."

D. Door Hardware: Mount units at heights indicated in DHI's "Recommended Locations for Architectural Hardware for Standard Steel Doors and Frames."

1. Install surface-mounted items after finishes have been completed on substrates involved. 2. Set units level, plumb, and true to line and location. Adjust and reinforce attachment

substrates as necessary for proper installation and operation. 3. Drill and countersink units that are not factory prepared for anchorage fasteners. Space

fasteners and anchors according to industry standards. 4. Set thresholds for exterior doors in full bed of butyl-rubber sealant complying with

requirements specified in Division 07 Section "Joint Sealants."

3.8 ACCESSORY INSTALLATION

A. General: Install accessories with positive anchorage to building and weathertight mounting, and provide for thermal expansion. Coordinate installation with flashings and other components.

1. Install components required for a complete metal roof panel assembly, including trim, copings, ridge closures, seam covers, flashings, sealants, gaskets, fillers, closure strips, and similar items.

2. Install components for a complete metal wall panel assembly, including trim, copings, corners, seam covers, flashings, sealants, gaskets, fillers, closure strips, and similar items.

3. Where dissimilar metals contact each other or corrosive substrates, protect against galvanic action by painting contact surfaces with corrosion-resistant coating, by applying rubberized-asphalt underlayment to each contact surface, or by other permanent separation as recommended by manufacturer.

B. Flashing and Trim: Comply with performance requirements, manufacturer's written installation instructions, and SMACNA's "Architectural Sheet Metal Manual." Provide concealed fasteners where possible, and set units true to line and level as indicated. Install work with laps, joints, and seams that will be permanently watertight and weather resistant.

1. Install exposed flashing and trim that is without excessive oil-canning, buckling, and tool marks and that is true to line and levels indicated, with exposed edges folded back to form hems. Install sheet metal flashing and trim to fit substrates and to result in waterproof and weather-resistant performance.

2. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim. Space movement joints at a maximum of 10 feet with no joints allowed within 24 inches of corner or intersection. Where lapped or bayonet-type expansion provisions cannot be used or would not be sufficiently weather resistant and waterproof, form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with mastic sealant (concealed within joints).

Page 26: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 133419 08/07/2015 Page 13 of 13

C. Gutters: Join sections with riveted-and-soldered or lapped-and-sealed joints. Attach gutters to eave with gutter hangers spaced as required for gutter size, but not more than 36 inches o.c. using manufacturer's standard fasteners. Provide end closures and seal watertight with sealant. Provide for thermal expansion.

D. Downspouts: Join sections with 1-1/2-inch telescoping joints. Provide fasteners designed to hold downspouts securely 1 inch away from walls; locate fasteners at top and bottom and at approximately 60 inches o.c. in between.

1. Provide elbows at base of downspouts to direct water away from building. 2. Tie downspouts to underground drainage system indicated.

E. Pipe Flashing: Form flashing around pipe penetration and metal roof panels. Fasten and seal to panel as recommended by manufacturer.

3.9 FIELD QUALITY CONTROL

A. Tests and Inspections:

1. High-Strength, Field-Bolted Connections: Connections shall be tested and inspected during installation according to RCSC's "Specification for Structural Joints Using ASTM A 325 or A 490 Bolts."

2. Welded Connections: In addition to visual inspection, field-welded connections shall be tested and inspected according to AWS D1.1/D1.1M and the following inspection procedures, at inspector's option:

a. Liquid Penetrant Inspection: ASTM E 165. b. Magnetic Particle Inspection: ASTM E 709; performed on root pass and on

finished weld. Cracks or zones of incomplete fusion or penetration will not be accepted.

c. Ultrasonic Inspection: ASTM E 164. d. Radiographic Inspection: ASTM E 94.

B. Product will be considered defective if it does not pass tests and inspections.

C. Prepare test and inspection reports.

END OF SECTION 133419

Page 27: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 1 of 13

SECTION 283100 – FIRE DETECTION AND ALARM

PART 1 - GENERAL

1.1 SUMMARY – (FIVE ZONE CONVENTIONAL CONTROL/COMMUNICATOR PANEL)

A. This section includes the furnishing, installation, and connection of the fire alarm equipment required to form a complete coordinated conventional control system that is ready for operation. It shall include, but not be limited to, alarm initiating devices, alarm notification appliances, control panel, auxiliary control devices, annunciators, power supplies, Ethernet and/or digital alarm communications to central stations and wiring as shown on the drawings and specified herein.

B. The fire alarm system shall comply with requirements of NFPA Standard No. 72 for protected premises signaling systems except as modified and supplemented by this specification. The system field wiring shall be supervised either electrically or by software-directed polling of field devices.

C. The fire alarm system shall be manufactured by an ISO 9001 certified company and meet the requirements of BS EN9001: ANSI/ASQC Q9001-1994.

D. The Fire Alarm Control Unit (FACU) and peripheral devices shall be manufactured 100% by a single U.S. manufacturer (or division thereof).

E. The system and its components shall be Underwriters Laboratories, Inc. listed under the appropriate UL testing standard as listed herein for fire alarm applications and shall be installed in compliance with the UL listing.

F. The installing company shall employ NICET (minimum Level III Fire Alarm Technology) technicians on site to guide the final check-out and to ensure the systems integrity.

1.2 SCOPE

A. A new conventional control system shall be installed in accordance with the specifications and drawings.

B. Basic Performance: 1. The FACU shall meet requirements of UL ANSI 864 Ninth Edition 2. Initiation Device Circuits (IDC) shall be wired Style B (Class B) 3. Per NFPA 72. 4. Notification Appliance Circuits (NAC) shall be wired Style Y (Class B) Per NFPA 72. 5. All circuits shall be power-limited, per UL864 requirements. 6. A single ground or open on any initiating device circuit or notification appliance circuit

shall not cause system malfunction, loss of operating power or the ability to report an alarm.

C. Basic System Functional Operation:

Page 28: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 2 of 13

When a fire alarm condition is detected and reported by one of the system initiating devices, the following functions shall immediately occur:

1. The system Alarm LED on the FACU shall flash. 2. A local sounder with the control panel shall sound. 3. A backlit 80-character LCD display on the FACU shall indicate all information

associated with the fire alarm condition, including the type of alarm point and its location within the protected premises.

4. In response to a fire alarm condition, the system will process all control programming and activate all system outputs (notification appliances and/or relays) associated with the point(s) in alarm. Additionally, the system shall send events to a central alarm supervising/monitoring station via either dial-up over PSTN or Internet or Intranet via PSDN or virtual private network.

1.3 SUBMITTALS

A. General: 1. Submit fire alarm information to the State Fire Marshal prior to submitting to the

Architect/Engineer. 2. Two copies of all submittals shall be submitted to the Architect/Engineer for review after

approval has been given by the State Fire Marshal. 3. All references to manufacturer's model numbers and other pertinent information herein is

intended to establish minimum standards of performance, function and quality. Equivalent compatible UL-listed equipment from other manufacturers may be substituted for the specified equipment as long as the minimum standards are met.

4. For equipment other than that specified, the contractor shall supply proof that such substitute equipment equals or exceeds the features, functions, performance, and quality of the specified equipment.

B. Shop Drawings: 1. Sufficient information, clearly presented, shall be included to determine compliance with

drawings and specifications. 2. Include manufacturer's name(s), model numbers, ratings, power requirements, equipment

layout, device arrangement, complete wiring point-to-point diagrams, and conduit layouts.

3. Show annunciator layout, configurations, and terminations.

C. Manuals: 1. Submit simultaneously with the shop drawings, complete operating and maintenance

manuals listing the manufacturer's name(s), including technical data sheets. 2. Wiring diagrams shall indicate internal wiring for each device and the interconnections

between the items of equipment. 3. Provide a clear and concise description of operation that gives, in detail, the information

required to properly operate the equipment and system.

1.4 GUARANTY

A. All work performed and all material and equipment furnished under contract shall be free from defects and shall remain so for a period of at least one (1) year from the date of acceptance.

Page 29: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 3 of 13

1.5 POST CONTRACT MAINTENANCE

A. Complete maintenance and repair service for the fire alarm system shall be available from a factory trained authorized representative of the manufacturer of the major equipment for a period of five (5) years after expiration of the guaranty.

1.6 APPLICABLE PUBLICATIONS

The publications listed below form a part of this specification.

A. National Fire Protection Association (NFPA) - USA No. 70 National Electrical Code No. 72 National Fire Alarm Code No. 101 Life Safety Code

B. Underwriters Laboratories Inc. (UL) - USA No. 38 Manually Actuated Signaling Boxes No. 217 Smoke Detectors, Single and Multiple Station No. 228 Door Closers–Holders for Fire Protective Signaling Systems No. 268 Smoke Detectors for Fire Protective Signaling Systems No. 268A Smoke Detectors for Duct Applications No. 346 Waterflow Indicators for Fire Protective Signaling Systems No. 464 Audible Signaling Appliances No. 521 Heat Detectors for Fire Protective Signaling Systems No. 864 Control Units for Fire Protective Signaling Systems No. 1481 Power Supplies for Fire Protective Signaling Systems No. 1638 Visual Signaling Appliances No. 1971 Visual Signaling Appliances No. 2017 General-Purpose Signaling Devices and Systems CAN/ULC S524-01 Standard for Installation of Fire Alarm Systems

1. The FACU shall be ANSI 864, 9th Edition Listed. Systems listed to ANSI 864, 8th

edition (or previous revisions) shall not be accepted.

C. Local and State Building Codes.

D. All requirements of the Authority Having Jurisdiction (AHJ).

1.7 APPROVALS

Each system must have proper listing and/or approval from the following:

1. Authority Having Jurisdiction 2. State Fire Marshal 3. UL Underwriters Laboratories Inc. 4. FM Factory Mutual

Page 30: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 4 of 13

PART 2 - PRODUCTS

2.1 EQUIPMENT AND MATERIAL, GENERAL

A. All equipment and components shall be new, and the manufacturer's model. The materials, appliances, equipment and devices shall be tested and listed by a nationally recognized approvals agency for as part of a fire protective signaling system, meeting the National Fire Alarm Code.

B. All equipment and components shall be installed in strict compliance manufacturers' recommendations. Consult the manufacturer's manuals for all wiring diagrams, schematics, physical equipment sizes, etc., before beginning system installation.

C. All equipment shall be attached to walls and ceiling/floor assemblies and shall be held firmly in place (e.g., detectors shall not be supported solely by suspended ceilings). Fasteners and supports shall be adequate to support the required load.

D. All equipment must be available "over the counter" through the Equipment Distributor (SED) market and can be installed by independent of the manufacturer.

2.2 CONDUIT AND WIRE

A. Conduit: 1. Conduit shall be in accordance with The National Electrical Code (NEC), local and state

requirements. 2. Where required, all wiring shall be installed in conduit or raceway. Conduit fill shall not

exceed 40 percent of interior cross sectional area where three or more cables are contained within a single conduit.

3. Cable must be separated from any open conductors of power, or Class 1 circuits, and shall not be placed in any conduit, junction box or raceway containing these conductors, per NEC Article 760-29.

4. With the exception of telephone connections, wiring for 24 volt DC, alarm notification,

emergency communication and similar power-limited auxiliary functions may be run in the same conduit as initiating and signaling line circuits. All circuits shall be provided with transient suppression devices and the system shall be to permit simultaneous operation of all circuits without or loss of signals.

5. Conduit shall not enter the fire alarm control panel, or any other remotely mounted control panel equipment or backboxes, except where conduit entry is specified by the FACU manufacturer.

B. Wire: 1. All fire alarm system wiring shall be new.

2. Wiring shall be in accordance with local, state and national codes (e.g., NEC Article

760) and as recommended by the manufacturer of The fire alarm system. Number and size of conductors shall be as recommended by the fire alarm system manufacturer, but not less than 18 AWG (1.02 mm) for Initiating Device Circuits and 14 AWG (1.63 mm) Notification Appliance Circuits.

Page 31: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 5 of 13

3. All wire and cable shall be listed and/or approved by a recognized agency for use with a protective signaling system.

4. Wire and cable not installed in conduit shall have a fire resistance rating suitable for the installation as indicated in NEC 760 e.g., FPLR).

5. All field wiring (with exception of external communications Ethernet) shall be electrically supervised for open circuit and ground fault.

C. Terminal Boxes, Junction Boxes and Cabinets: 1. All boxes and cabinets shall be UL listed for their use and purpose.

D. The fire alarm control panel shall be connected to a separate dedicated circuit, maximum 20 amperes. This circuit shall be labeled at the main power distribution panel as FIRE ALARM. Fire alarm control panel primary power wiring shall be 12 AWG. The control panel cabinet shall be grounded securely to either a cold water pipe or grounding rod. The control panel enclosure shall feature a quick removal chassis to facilitate rapid replacement of the FACU electronics.

2.3 CONTROL PANEL

A. The FACU shall be a Fire-Lite Model MS-5UD-7, or equal, and shall communicate with and control the following types of equipment used to up the system: smoke and thermal (heat) detectors, manual stations, alarm notification appliances, printer, annunciators, Digital Dialer and Ethernet Communicators and other system controlled devices. Ethernet communications shall be via a Fire-Lite Model IPDACT, or equal. Central station supervisory equipment shall be a Teldat Corporation Visoralarm- Plus listed to UL-864 standards.

1. The control panel shall be a UL listed and FM approved microprocessor controlled

Conventional Control Panel. 2. Function: The control panel shall perform the following functions:

a. Supervise and monitor all initiating device circuits and alarm notification circuits for trouble and alarm conditions.

b. Detect the operation of any initiating device circuit and the location of the alarm condition. Operate all notification appliances devices as designed.

c. Visually and audibly annunciate any trouble, supervisory or alarm condition on panel display.

B. System Capacity The Control Panel shall include five programmable initiating device circuits, four programmable output circuits, three programmable Form-C relays, digital communicator, integral power supply and 80 character LCD. 1. The IDCs (Initiating Device Circuits) shall be individually programmable as conventional

two-wire smoke detector circuits, as well as any dry contact input device. Examples of dry contact input devices include four-wire smoke detectors, manual pull stations, detectors, pressure switches, and waterflow switches. The IDCs shall support Style D (Class A) operation by adding an expansion board. The IDCs shall support conventional two-wire smoke detectors well as conventional smoke detectors capable of generating a maintenance signal when the detector becomes dirty and a separate supervisory ‘freeze’ signal when ambient temperature falls below the detector rating of approximately 45 degrees F.

Page 32: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 6 of 13

2. The four programmable outputs shall be individually programmable as conventional supervised NACs (Notification Appliance Circuits). Each NAC may be individually programmed as any of the following: Silence Inhibit, Auto-Silence, Strobe Synchronization, Selective Silence (horn-strobe mute), Temporal or Steady Signal, Silenceable or Non-silenceable.

3. The FACU shall be capable of coding Notification Appliance Circuits in March Time Code (120 PPM), Temporal (NFPA 72), and California Code. Main panel notification circuits (NACs 1, 2, 3 & 4) shall also automatically synchronize any of the following manufacturer’s notification appliances connected to them: System Sensor, Wheelock, Gentex, Faraday and Amseco, with no need for additional synchronization modules.

4. The three programmable relays shall be individually programmable as Alarm, Trouble and Supervisory. When programmed as a Trouble relay, the relay shall be fail-safe.

5. The on board power supply shall be capable of 7.0 Amps(MS-10UD-7, or equal,) of regulated, filtered power.

C. System Display

The system shall have five LED indicators as well as an 80 character LCD (Liquid Crystal Display). The LCD shall be capable of displaying a custom description for each input and output circuit. The system LEDs shall indicate the status of the following system parameters: AC POWER Green LED FIRE ALARM Red LED SUPERVISORY Yellow LED TROUBLE Yellow LED ALARM SILENCED Yellow LED

1. The main system display shall be an integral, eighty characters LCD with a keypad. The

keypad shall have full programming capability without requiring the use of a laptop computer.

2. The FACU shall include a history log with 256 event storage. The history shall be accessible from the main system display.

3. The system shall include a real-time clock/calendar with daylight savings time control.

D. System Control Switch Operation 1. ACK/Step Silence Switch:

a. Activation of the control panel tone silence switch in response to alarms troubles and supervisory conditions shall silence the local panel piezo electric signal and change the LED from flashing mode to steady-ON mode. Occurrence of any new conditions in the system shall cause the control panel to resound the Local Piezo sounder and repeat the alarm, trouble, or supervisory sequences.

b. Depression of the Acknowledge switch shall also silence all remote annunciator piezo sounders.

2. Alarm Silence Switch: Activation of the alarm signal silence switch shall cause all alarm notification appliances to return to the normal condition after an alarm condition.

3. System Reset Switch: Activation of the System Reset Switch shall cause all electronically-latched initiating devices, as well as all associated output devices and circuits, to return to their normal condition. Holding system reset switch down shall perform a LAMP TEST function and will activate the piezo sounder.

Page 33: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 7 of 13

4. Alarm Activate (Drill): Switch The Alarm Activate switch shall activate all notification appliance circuits. The drill function shall latch until the panel is silenced or reset.

5. Lamp Test: The System RESET switch shall also function as a Lamp Test switch and shall activate all system LEDs and light each segment of the liquid crystal display.

E. System Operation 1. Zone Status LEDs: The alarm, supervisory, or trouble LED(s) shall flash until event(s)

have been acknowledged LED(s) shall then illuminate steady. Any subsequent alarm, supervisory or trouble will flash the new event only.

2. Supervisory: A short circuit on this zone shall cause the supervisory LED and zone yellow LED to flash, and shall activate the supervisory notification circuit. An open circuit shall report as a zone trouble.

3. Zone Disable: Disable/Enable shall be accomplished in programming mode. If a zone has been disabled, the control panel LCD will display the zone which has been disabled and FACU will turn on the Trouble LED.

F. Programming and System Commissioning 1. The FACU shall have a configuration option which allows the user to program the

FACU.

G. The control panel shall support the following modules: 1. 80 character Remote LCD Annunciator which mimics the FACU main display. 2. I/O LED Driver which provides LED outputs for connection to a custom graphics

annunciator. 3. Printer Module which provides a serial/parallel output for connection to a UL listed event

printer. 4. Relay Module which provides 10 form C relays. 5. LED Annunciator Module which mounts on the FACU door and provides three LEDs for

each zone: Alarm, Trouble and Supervisory. 6. Built in Digital Communicator (complies with NFPA 72). 7. Optional transmitter module which complies with NFPA-72 Auxiliary and Remote

Station Protective Signaling systems. 8. Optional Class A Converter Module

H. The control panel shall also include the following functions: 1. Battery/Earth fault supervision shall be provided. 2. 7 AH to 26 AH battery options shall be available, providing up to 90 hours standby. 3. Remote Synchronization Output shall be provided. 4. Programmable Make/Break ratio shall be provided. 5. Watchdog timer to supervise microprocessor shall be provided.

I. Remote Field Charging Power Supply 1. The remote field charging power supply shall be a FCPS-24FS6 or FCPS-24FS8, or

equal. The FCPS-24FS6/8 shall be used to provide power to audio visual devices or any other device on the system whenever the power requirements exceed those provided by the FACU.

2. The FCPS-24FS6 shall offer up to 6.0 amps continuous current of regulated, filtered, 24 volt power. It shall include an integral charger designed to charge 7.0 to 18.0 amp hour batteries and to support 60 hour standby.

Page 34: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 8 of 13

3. The FCPS-24FS8 shall offer up to 8.0 amps continuous current of regulated, filtered, 24 volt power. It shall include an integral charger designed to charge 7.0 to 18.0 amp hour batteries and to support 60 hour standby.

4. The Field Charging Power Supply shall provide regulated and filtered 24 VDC power to four notification appliance circuits configured as either four Class B (Style Y) or Class A (Style Z, with ZNAC-4 option module). Alternately, the four outputs may be configured as all non-resettable, all resettable, or two non-resettable and two resettable.

5. The Field Charging Power Supply shall include an attractive surface mount backbox. 6. The Field Charging Power Supply shall include the ability to delay the AC fail delay per

NFPA requirements. 7. The Field Charging Power Supply shall include power limited circuitry, per UL

standards. 8. The Field Charging Power Supply shall provide UL-Listed NAC synchronization using

System Sensor, Wheelock, or Gentex “Commander²” appliances.

J. Digital Alarm Communicator Transmitter (DACT) and Internet Protocol Digital Alarm Communicator Transmitter (IPDACT). The DACT is an interface for communicating digital information between a fire alarm control panel and a UL-Listed central station. When the optional IPDACT Ethernet module is connected to the on board DACT, the system shall be capable of transmitting contact ID formatted alarms to a central station equipped with a compatible IP receiver via Ethernet over a private or public WAN/LAN, Intranet or Ethernet.

1. The IPDACT shall be an integral module component of the fire alarm control panel

enclosure. 2. The IPDACT shall include connections to the alarm panel’s phone outputs and shall

convert the contact ID protocol in DTMF form into UDP Ethernet Packets. It shall include the ability for simultaneous reporting of panel events up to three different IP addresses.

3. The IPDACT shall be completely field-programmable locally from a PC via a serial port or via Ethernet and Telnet.

4. The IPDACT shall be capable of transmitting events in contact ID Format. 5. Communication shall include vital system status such as:

a. Independent Zone (Alarm, supervisory, trouble, non-alarm) b. AC (Mains) Power Loss c. Low Battery and Earth Fault d. System Off Normal e. 12 and 24 Hour Test Signal f. Abnormal Test Signal (per UL requirements) g. IP Line Failure

6. The IPDACT shall support independent zone/point reporting via the Contact ID format.

This format shall enable the central station to have exact details concerning the location of the fire for emergency response. The IPDACT shall be capable of providing simulated phone lines to the FACU and panel communication over IP shall be transparent to the panels normal operation over phone lines.

7. The IPDACT shall utilize a supervisory heart beat signal of no less than once every 90 seconds insuring multiplexed level line supervision. Loss of Internet or Intranet connectivity shall be reported in no more than 200 seconds. Alarm events shall be

Page 35: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 9 of 13

transmitted to a central station within 90 seconds from time of initiation to time of notification.

8. The supervising station shall consist of a Teldat Corporation Visoralarm-Plus receiver. Said receiver shall contain a smart card for backup of all account data. Backup smart card shall initiate a new receiver with all account information in less than 60 seconds from powerup.

K. Power Supply 1. The power supply for the MS-5UD-7 panel shall be integral to the control panel itself,

and shall provide all control panel and peripheral device power needs. 2. Input power shall be 120 VAC, 60 HZ. The power supply shall provide an integral

battery charger for use with batteries up to 26 AH for the MS-10UD-7. 3. The MS-5UD-7 shall provide 7.0 amperes of regulated 24 VDC power for notification

devices, Four-Wire smoke detector power 24 VDC up to 500 mA, non resettable power 24 VDC up to 500 mA.

4. The power supply shall be designed to meet UL and NFPA requirements for power-limited operation on all notification and initiating circuits.

5. Positive-temperature-coefficient thermistors, circuit breakers, fuses, or other over-current protection shall be provided on all power outputs.

L. Mechanical Design The control panel shall be housed in a cabinet designed for mounting directly to a wall or vertical surface. The back box and door shall be constructed of 0.060 steel with provisions for electrical conduit connections into the sides and top. The door shall provide a key lock and shall include a glass or other transparent opening for viewing of all indicators. The cabinet shall be approximately 5.21 inches (13.23 cm) deep and 16.8 inches (42.73 cm) wide. Height shall be approximately 19.26 inches (48.92 cm). An optional trim ring shall be used for flush mounting of cabinet. Space shall be provided in the cabinet for 7 AH or 18 AH batteries. If 26 AH batteries are used, a separate battery enclosure shall be available from the same manufacturer.

2.4 BATTERIES

A. Shall be 12 volt, Gell-Cell type (2 required).

B. Battery shall have sufficient capacity to power the fire alarm system for not less than 24 hours plus 5 minutes of alarm upon a normal AC power failure.

C. The batteries are to be completely maintenance free. No liquids are required. Fluid level checks refilling, spills and leakage shall not be required.

2.5 SYSTEM COMPONENTS

A. Horns, Strobes, and Horn/Strobes 1. General:

All horns, strobes and horn/strobes shall be System Sensor SpectrAlert Advance series, or equal. Horns, strobes and horn/strobes shall mount to a standard 4 × 4 × 1½-inch back box, 4-inch octagon back box or double-gang back box. Two-wire products shall also mount to a single-gang 2 × 4 × 1.875-inch back box. A universal mounting plate shall be used for mounting ceiling and wall products. The notification appliance circuit wiring

Page 36: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 10 of 13

shall terminate at the universal mounting plate. Indoor SpectrAlert Advance products shall operate between 32 and 120 degrees Fahrenheit from a regulated DC, or full-wave rectified, unfiltered power supply. Strobes and horn/strobes shall have field-selectable candela settings including 15, 15/75, 30, 75, 95, 110, 115, 135, 150, 177, 185.

2. Strobes: The strobe shall be a System Sensor SpectrAlert Advance Model SR, or equal, listed to UL 1971 and shall be approved for fire protective service. The strobe shall be wired as a primary-signaling notification appliance and comply with the Americans with Disabilities Act requirements for visible signaling appliances, flashing at 1Hz over the strobe’s entire operating voltage range. The strobe light shall consist of a xenon flash tube and associated lens/reflector system.

3. Horn/Strobe Combination:

The horn/strobe shall be a System Sensor SpectrAlert Advance Model P2R, or equal, listed to UL 1971 and UL 464 and shall be approved for fire protective service. The horn/strobe shall be wired as a primary- signaling notification appliance and comply with the Americans with Disabilities Act requirements for visible signaling appliances, flashing at 1Hz over the strobe’s entire operating voltage range. The strobe light shall consist of a xenon flash tube and associated lens/reflector system. The horn shall have three audibility options and an option to switch between a temporal three-pattern and a non-temporal (continuous) pattern. These options are set by a multiple position switch. On four-wire products, the strobe shall be powered independently of the sounder. The horn on horn/strobe models shall operate on a coded or non-coded power supply.

4. Outdoor Horns, Strobes, and Horn/Strobes:

SpectrAlert, or equal, Advance outdoor horns, strobes and horn/strobes shall be listed for outdoor use by UL and shall operate between minus 40 degrees and 151 degrees Fahrenheit. The products shall be listed for use with a System Sensor outdoor/weatherproof back box with half inch and three-fourths inch conduit entries.

5. Synchronization Requirements:

All Horns, Strobes, and Horn/Strobes shall be synchronized without the need for additional synchronization hardware or modules. Synchronization shall be provided by the MS-5UD-3/MS-10UD-7, or equal, power supply or from an additional field power supply. All Horns, Strobes, and Horn/Strobes shall be Synchronized at 1Hz and horns at temporal three. Also, while operating the strobes, the FACU shall silence the horns on horn/strobe models over a single pair of wires.

B. Manual Fire Alarm Stations 1. Manual Fire Alarm Stations shall be File-lite BG-12 Series, or equal, and be non-code,

with a key- or hex-operated reset lock in order that they may be tested, and so designed that after actual Emergency Operation, they cannot be restored to normal except by use of a key or hex. An operated station shall automatically condition itself so as to be visually detected as activated.

2. Manual stations shall be constructed of red colored LEXAN (or polycarbonate equivalent) with clearly visible operating instructions provided on the cover. The word FIRE shall appear on the front of the stations in white letters, 1.00 inches (2.54 cm) or larger.

3. Stations shall be suitable for surface mounting on matching backbox SB-10 or SB-I/O; or semi-flush mounting on a standard single-gang, double-gang, or 4" (10.16 cm) square

Page 37: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 11 of 13

electrical box, and shall be installed within the limits defined by the Americans with Disabilities Act (ADA) or per national/local requirements. Manual Stations shall be Underwriters Laboratories listed.

C. Conventional Photoelectric Area Smoke Detectors 1. Smoke detector shall be a System Sensor i3 Series, or equal, and conventional

photoelectric smoke detector, listed to Underwriters Laboratories UL 268 for Fire Protection Signaling Systems. The detector shall be a photoelectric type (Model 2W-B, 4W-B, or equal,) or a combination photoelectric/thermal (Model 2WT-B, 4WT-B) with thermal sensor rated at 135°F (57.2°C).

2. The detector shall include a mounting base for mounting to 3½-inch and 4-inch octagonal, single gang, and 4-inch square back boxes with a plaster ring. Wiring connections shall be made by means of SEMS screws. The detector shall allow pre-wiring of the base and the head shall be a plug-in type.

3. The detector shall have a nominal sensitivity of 2.5 percent-per- foot nominal as measured in the UL smoke box. The detector shall be capable of automatically adjusting its sensitivity by means of drift compensation and smoothing algorithms. The detector shall provide dual color LED indication which blinks to indicate power up, normal standby, out of sensitivity, alarm, and freeze trouble (Model 2WT-B, 4WT-B) conditions.

4. Two-wire models shall include a maintenance signal to indicate the need for maintenance at the alarm control panel, and shall provide a loop testing capability to verify the circuit without testing each detector individually.

D. Conventional Ionization Type Area Smoke Detectors

1. Smoke detector shall be a System Sensor 1451, or equal, conventional ionization smoke detector, listed to Underwriters Laboratories UL 268 for Fire Protection Signaling Systems.

2. Ionization type smoke detectors shall be a two wire, 24 VDC type using a dual unipolar chamber.

3. Each detector shall contain a remote LED output and a built-in test switch. 4. Detector shall be provided on a twist-lock base. 5. It shall be possible to perform a calibration sensitivity and performance test on the

detector without the need for the generation of smoke. 6. A visual indication of an alarm shall be provided by dual latching Light Emitting Diodes

(LEDs) over 360 degrees, on the detector, which may be seen from ground level. This LED shall flash every 10 seconds, indicating that power is applied to the detector.

7. The detector shall not alarm when exposed to air velocities of up to 1,200 feet (365.76 m) per minute. The detector screen and cover assembly shall be easily removable for field cleaning of the detector chamber.

8. All field wire connections shall be made to the base through the use of a clamping plate and screw.

E. Automatic Conventional Heat Detectors 1. Mechanical heat detector shall be a System Sensor 5600 Series, or equal, model, listed to

Underwriters Laboratories UL 521 for Heat Detectors for Fire Protective Signaling Systems.

2. The detector shall be either a single-circuit or a dual-circuit type, normally open. The detector shall be rated for activation at either 135°F (57°C) or 194°F (90°C), and shall activate by means of a fixed temperature thermal sensor, or a combination fixed

Page 38: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 12 of 13

temperature/rate-of-rise thermal sensor. The rate-of-rise element shall be activated by a rapid rise in temperature, approximately 15°F (8.3°C) per minute.

3. The detector shall include a reversible mounting bracket for mounting to 3½-inch and 4-inch octagonal, single gang, and 4-inch square back boxes with a square to round plaster ring. Wiring connections shall be made by means of SEMS screws that shall accommodate 14–22AWG wire.

4. The detector shall contain alphanumeric markings on the exterior of the housing to identify its temperature rating and activation method.

5. The rate-of-rise element of combination fixed temperature/rate-of-rise models shall be restorable, to allow for field-testing. The detectors shall include an external collector that shall drop upon activation to identify the unit in alarm.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Installation shall be in accordance with the NEC, NFPA 72, local and state codes, as shown on the drawings, and as recommended by the major equipment manufacturer.

B. All conduit, junction boxes, conduit supports and hangers shall be concealed in finished areas and may be exposed in unfinished areas. Smoke detectors shall not be installed prior to the system programming and test period. If construction is ongoing during this period, measures shall be taken to protect smoke detectors from contamination and physical damage.

C. All fire detection and alarm system devices, control panels and remote annunciators shall be flush mounted when located in finished areas and may be surface mounted when located in unfinished areas.

D. At the final inspection a factory trained representative of the manufacturer of the major equipment shall perform the tests in Section 3.2 TEST.

3.2 TEST: Provide the service of a competent, factory-trained engineer or technician authorized by the manufacturer of the fire alarm equipment to technically supervise and participate during all of the adjustments and tests for the system.

1. Before energizing the cables and wires, check for correct connections and test for short

circuits, ground faults, continuity, and insulation. 2. Close each sprinkler system flow valve and verify proper supervisory alarm at the FACU. 3. Verify activation of all flow switches. 4. Open initiating device circuits and verify that the trouble signal actuates. 5. Open and short notification appliance circuits and verify that trouble signal actuates. 6. Ground device circuits and verify response of trouble signals. 7. Check presence and audibility of tone at all alarm notification devices. 8. Check installation and supervision of heat detectors to ascertain that they will function as

specified.

Page 39: Addendum 03 Narrative

GRDA MULTIPLE WAREHOUSES DCS#ID12032-5 VEHICLE STORAGE-CUSHING, OK

Addendum 03 283100 08/0\7/2015

Page 13 of 13

9. Conduct tests to verify trouble indications for common mode failures, such as alternating current power failure.

3.3 FINAL INSPECTION: At the final inspection a factory trained representative of the manufacturer of the major equipment shall demonstrate that the systems function properly in every respect.

3.4 INSTRUCTION: Provide instruction as required to the building personnel. "Hands-on" demonstrations of the operation of all system components and the entire system shall be provided.

END OF SECTION 283100

Page 40: Addendum 03 Narrative
Page 41: Addendum 03 Narrative
Page 42: Addendum 03 Narrative
Page 43: Addendum 03 Narrative
Page 44: Addendum 03 Narrative
Page 45: Addendum 03 Narrative
Page 46: Addendum 03 Narrative
Page 47: Addendum 03 Narrative