Activity List
description
Transcript of Activity List
![Page 1: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/1.jpg)
Activity List
AIT Waste Water Treatment System
![Page 2: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/2.jpg)
AIT Waste Water Treatment Facility: Activity List
i
Document History
Version
Number
Description Date Author Checked
1 Original 11/03/13 TS, NMcH,
SP, LM
LM
2 Updated following sequencing of
activities
25/03/13 TS LM
![Page 3: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/3.jpg)
AIT Waste Water Treatment Facility: Activity List
ii
Table of Contents Document History ............................................................................................................................... i
1.0 Activity List ............................................................................................................................ 1
Sponsor Acceptance ......................................................................................................................... 17
![Page 4: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/4.jpg)
AIT Waste Water Treatment Facility: Activity List
1
1.0 Activity List
The Following table outlines the Activity list for the project. This document provides a
comprehensive list of all activities on the project. This list includes a scope of work description for
each activity, with sufficient detail for a clear understanding of what is required to be carried out.
Project Name: AIT Waste Water Treatment System Date: 11/03/13
Activity ID # Activity Description of work Responsible party
1000 Obtain Project Funding Funding for the completion of the project must be sourced.
AIT
1001 Appoint Consulting Engineer For this activity a consulting engineer with proven experience of similar projects must be sourced and appointed.
TNLS
1002 Complete Survey For this activity a topographical survey of the site must be completed, including; spot levels of roads, ground, corners of structures and location of services
Consulting Engineer
1003 Complete Preliminary Design As part of this activity an initial outline design of the treatment system and auxiliary works must be completed
Consulting Engineer
1004 Prepare Project Drawings This activity includes the preparation of plans, sections, elevations, site location map and other necessary project drawings and maps for the planning application
Consulting Engineer
![Page 5: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/5.jpg)
AIT Waste Water Treatment Facility: Activity List
2
1005 Prepare Newspaper Add and Site Notice
This activity includes preparing and putting in place a suitable newspaper add and site notice describing the works
Consulting Engineer
1006 Prepare and Submit Planning Application
This activity consists of completion and submission of a planning application for the project to Westmeath Co. Co. , including all relevant attachments and payments
Consulting Engineer/TNLS
1007 Prepare Drawings for Discharge Licence
For this activity a drawing of the location of the connection to the municipal sewer must be prepared, also a plan drawing of the premises drainage system must be prepared.
Consulting Engineer
1008 Estimate Discharge Effluent Characteristics
This activity includes the preparation of an effluent Characteristic and Discharge table. This will involve estimating such characteristics as Average Flow, BOD,Temperature,COD, Max/day, Max/hr.
Consulting Engineer
1009 Prepare and Submit Discharge Licence Application
This activity will involve preparing and submitting an application to Westmeath Co. Co. for a discharge licence, including all relevant attachments and payments.
Consulting Engineer/TNLS
![Page 6: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/6.jpg)
AIT Waste Water Treatment Facility: Activity List
3
1010 Prepare location map for road opening licence
This activity involves preparing a location map for road excavations for the purpose of connecting to the municipal sewer.
Consulting Engineer
1011 Prepare and Submit Road Opening Licence Application
This activity consists of completion and submission of a road opening licence application for the project to Westmeath Co. Co. , including all relevant attachments and payments
Consulting Engineer/TNLS
1012 Prepare Preliminary Health and Safety Plan
For this activity a preliminary Health and Safety Plan must be prepared in accordance with Regulation 12 of S.I. No. 504 of 2006 Safety, Health and Welfare at Work (Construction) Regulations, 2006.
PSDP
1013 Develop the Health and Safety Plan for the Project
This activity requires that the Health and safety Plan be developed for the Construction Stage in compliance with the above regulations. This involves the implementation of the Health and Safety Plan, and any amendments required.
PSCS
1014 Prepare Work Activity Method Statements
This activity involves the preparation of all method statements (safe systems of work) throughout the project lifecycle.
PSDP/PSCS
![Page 7: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/7.jpg)
AIT Waste Water Treatment Facility: Activity List
4
1015 Design Sewer Network This activity requires the design of a suitably sized sewer network to transport waste water from the collection point at the rear of the engineering building to the treatment plant and to the discharge point at the eastern entrance to the campus. This will include all piping, connections, pumps etc.
Consulting Engineer
1016 Design influent screens for the system
This activity includes the sizing and design of mechanical influent screens for the removal of large solids and grit from the influent.
Consulting Engineer
1017 Design of Influent Equalisation System
For this activity a number of elements must be designed; including, flow inlet, pre-cast concrete holding tank and outflow pumping system.
Consulting Engineer
1018 Design Treatment Basins This activity involves the design of two No. pre-cast concrete treatment basins to allow for redundancy, maintenance, high flows, and seasonal variations.
Consulting Engineer
1019 Design Operation System This activity requires the design of a flow based batch operation system for the treatment facility.
Consulting Engineer
![Page 8: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/8.jpg)
AIT Waste Water Treatment Facility: Activity List
5
1020 Design Aeration System This activity requires the design an air blower system for the treatment basins, designed to incorporate several air blower, versus a single unit. The design should allow units to be taken off line when maximum aeration is not required.
Consulting Engineer
1021 Design Post Basin Flow Equalisation For this activity an effluent equalisation system must be designed to smooth out flow variations prior to downstream processes. This will require the design of a pre-cast concrete holding tank and discharge system.
Consulting Engineer
1022 Prepare Project Decommissioning Plan
This activity explains how to decommission the Waste Water Treatment Plant (WWTP) at the end of its lifecycle
Consulting Engineer/TNLS
1023 Prepare Tender Documents This activity includes the preparation of documents required to be included as part of the project tender packages
Consulting Engineer/TNLS
1024 Prepare Project Drawings for Tender Process
This activity consists of preparing drawings and specifications for the project. They are required to be such a standard to allow tenders to accurately complete estimates.
Consulting Engineer
![Page 9: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/9.jpg)
AIT Waste Water Treatment Facility: Activity List
6
1025 Assess Tender Submissions and Shortlisting of Tenderers
This activity consists of assessing submitted tenders on the basis of most economically advantageous tender and creating a shortlist of the five most viable tenders
TNLS
1026 Completing Interviews of Shortlisted Tenderers
This activity consists of preparation and completion of interviews of shortlisted contractors. The interviews should aim to exhibit the contractor’s qualification, and experience on similar projects before.
TNLS
1027 Appoint Contractor to the Project This activity includes the approval of the client of the recommended tenderer, and the completion of a formal letter to the tenderer appointing them as contractor for the project
AIT/ TNLS
1028 Traffic Management Plan Within this Risk Management traffic control measures have to be put in place for the area.
Consulting Engineer/ Contractor
1029 Construction of the Project The activity includes the completion of the Sewerage Treatment Works and all auxiliary works associated with the construction of the Wastewater Treatment Plant
Contractor
1030 Appoint Project Manager for the Project
This activity involves the project sponsor ensuring a person’s eligibility and experience for the
AIT
![Page 10: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/10.jpg)
AIT Waste Water Treatment Facility: Activity List
7
position.
1031 Prepare a Business Case This activity involves the identification of project deliverables, evaluation of possible project locations, and evaluation and estimated costing of possible treatment system options.
TNLS
1032 Prepare Project Charter This activity requires the preparation of a document to formally authorise the project and document initial requirements that satisfy the stakeholders' needs and expectations
TNLS
1033 Prepare Stakeholder Register This activity involves the preparation of a comprehensive list of all the stakeholders, and their importance to the project is stated. Also, their expectations for the project are identified
TNLS
1034 Prepare Stakeholder Management Strategy
This activity involves the determination of how groups of stakeholders and/or individual stakeholders incorporated in the project.
TNLS
![Page 11: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/11.jpg)
AIT Waste Water Treatment Facility: Activity List
8
1035 Develop Project Management Plan Within this, a lot of plans have to be set up, these involve: Change Management Plan, Communications Management Plan, Cost Management Plan, Procurement Management Plan, Project Scope Management Plan, Schedule Management Plan, Quality Management Plan, Staffing Management Plan and a Risk Management Plan. The project Scope, Project Charter, a Milestone List, the Risk Register, a resource calendar, cost and project baseline all have to be set up and identified.
TNLS
1036 Identify Projects Requirements This activity requires the identification and documenting of the requirements of the project in conjunction with all project stakeholders.
TNLS
1037 Prepare Requirements Management Plan
This activity requires the establishment of an effective strategy for the continued management of requirements throughout the project, which should incorporate a traceability matrix.
TNLS
1038 Define the Project Scope This activity involves developing a detailed description of the project based on the project requirements
TNLS
![Page 12: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/12.jpg)
AIT Waste Water Treatment Facility: Activity List
9
1039 Create a Work Breakdown Structure (WBS)
This activity involves the decomposition of project deliverables and project work into smaller, more manageable components. This process will also include the preparation of a WBS dictionary which describes each element in the WBS.
TNLS
1040 Prepare Activity List This activity involves the itemisation of all scheduled activities for the project and provides a detailed description of the work to be performed for each activity.
TNLS
1041 Defining of Activity Attributes This activity requires the identification and documenting of information with regards to each identified activity.
TNLS
1042 Preparation of a Milestone List This activity Identifies all the key milestones in the project. Including the start and end of each life-cycle phase, the completion of key deliverables, passing certain bench marks or tests, or obtaining a sign-off.
TNLS
1043 Sequencing of Project Activities This activity requires the Identification and documentation of relationships among the project activities, by means of a network diagram.
TNLS
![Page 13: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/13.jpg)
AIT Waste Water Treatment Facility: Activity List
10
1044 Estimate Activity Resource Requirements
This activity involves estimating the type and quantities of material, people, equipment and supplies required to perform each activity, and formulating a resource breakdown structure.
TNLS
1045 Estimate Activity Effort This activity requires the estimation of the work hours needed to complete each activity by means of Perth analysis.
TNLS
1046 Estimate Activity Duration The activity requires the approximation of the number of work periods needed to complete individual activities with estimated resources.
TNLS
1047 Perform Critical Path Analysis This activity involves determining the range of times within which the activities can occur. This is done by determining the early start and finish dates for each activity and the late start and finish dates for each activity.
TNLS
1048 Develop Project Schedule This activity requires analysing activity sequences, durations, resource requirements, and schedule constraints to develop a schedule which shows the planned start and end dates for activities
TNLS
1049 Create Schedule Management Plan This activity sets out the criteria and activities for developing and controlling the project schedule.
TNLS
![Page 14: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/14.jpg)
AIT Waste Water Treatment Facility: Activity List
11
1050 Estimate Activity Costs This activity involves the estimation of the most likely cost of each individual activity. Cost estimates should be backed up with documentation that provides the assumptions used and the basis of the estimates.
TNLS
1051 Determine the Project Budget This activity involves aggregating the estimated costs of individual activities to establish an authorised cost baseline.
TNLS
1052 Define Project Funding Requirements
This activity defines the funds needed on a periodical basis which includes funds for the cost performance baseline, plus management reserve.
TNLS
1053 Prepare Quality Management Plan This activity involves documenting the approach for quality assurance, quality control, quality improvement, and process improvement throughout the project.
TNLS
1054 Prepare Human Resource Plan In this activity, roles and responsibilities are defined, project organisational charts are prepared, and a staffing Management Plan is prepared
TNLS
1055 Prepare Communications Management Plan
This activity involves defining a line of communication within the project, and describes who needs what information and when and how it will be
TNLS
![Page 15: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/15.jpg)
AIT Waste Water Treatment Facility: Activity List
12
given to them.
1056 Prepare Risk Management Plan This activity will describe roles and responsibilities, timing and frequency of risk management activities, and the approach to cost and schedule reserves.
TNLS
1057 Identification of Project Risks In this activity all risks are identified, described, categorised and the probability of them occurring are set out by means of a risk register
TNLS
1058 Perform Risk Analysis This activity firstly involves prioritising risks for further analysis by means of qualities analysis, and secondly numerically analysing the effect of identified risks on overall project objectives by means of quantities analysis.
TNLS
1059 Develop Risk Responses This activity involves developing options and actions to enhance opportunities and to reduce threats to project objectives.
Responsible party
1060 Prepare Procurement Management Plan
This activity sets out how procurement will be managed throughout the projects lifecycle.
TNLS
1061 Plan Procurement for the Project This activity involves documenting project purchasing decisions, specifying the approach, and
TNLS
![Page 16: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/16.jpg)
AIT Waste Water Treatment Facility: Activity List
13
identifying potential sellers.
1062 Perform Quality Assurance This activity involves the prevention of defects within the project.
TNLS
1063 Form the Project Team This activity involves the acquisition and assignment of persons required for the completion of the project.
TNLS
1064 Management of the Project Team This activity involves the continued management of the project team throughout the project.
TNLS
1065 Manage Stakeholders expectations This activity involves communicating with stakeholders to ensure the project meets their expectations and, where appropriate prepare change requests to ensure they are met.
TNLS
1066 Monitor and Control Project This activity involves tracking, reviewing and regulating the project progress to meet defined performance objectives.
TNLS
1067 Complete Integrated Change Control
This activity requires the reviewing of all change requests and managing project document updates.
TNLS
1068 Complete Work Performance Measurements
This activity compares the planned versus actual performance in time, cost, quality, human resources, risk
TNLS
![Page 17: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/17.jpg)
AIT Waste Water Treatment Facility: Activity List
14
and procurement
1069 Verify the Project Scope This activity formalises the acceptance of the project deliverables.
TNLS
1070 Manage Project Scope This activity requires the monitoring of the project status and managing changes to the scope baseline.
TNLS
1071 Control the Project Schedule This activity involves monitoring of the project status, updating of the project progress, and managing changes to the schedule baseline.
TNLS
1072 Control the Project Costs This activity involves monitoring of the project status, updating of the project budget, and managing changes to the cost baseline.
TNLS
1073 Complete Quality Control Measurements
This activity will monitor specific project results to see if they comply with relevant quality standards.
TNLS
1074 Manage Quality control This activity will assess performance and identify ways of eliminating unsatisfactory performance.
TNLS
![Page 18: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/18.jpg)
AIT Waste Water Treatment Facility: Activity List
15
1075 Complete Performance Reports This activity involves a progress report, which provides a detailed summary of what project team members have accomplished up to a given point and how they did it. This should include the number of people who actually worked on an activity compared to the number of people who were scheduled to work on it.
TNLS
1076 Monitor and Control Risks This activity requires the implementation of the risk management plan, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
TNLS
1077 Identify Follow Up Actions This activity identifies action which is required to be completed, following substantial completion, to meet the project requirements.
TNLS
1078 Prepare Closing Statement This activity guides the team members and other stakeholders through the project closing process so that the project is completed in an organised and successful manner. All loose ends are addressed and a mechanism for documenting and sharing lessons learned.
TNLS
![Page 19: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/19.jpg)
AIT Waste Water Treatment Facility: Activity List
16
1079 Prepare Final Acceptance Documents
This activity includes the signing of the Final Acceptance form and certifies that the work contained in the contract has been inspected by the parties listed, that all punch list items on the Substantial Completion form have been completed, that the contractor has fulfilled all his contractual obligations, that the warranties have been accepted and the contractor may receive final payment in full, including all retainage.
TNLS
1080 Complete Project Review This activity requires a review of the completed project, the preparation of a summary of the project, documenting of lessons learned.
TNLS
1081 Close the Project This activity finalises all activities across all of the process groups to formally close the project or the project phase
TNLS
1082 Close Project Procurements This activity involves the closing of each project procurement.
TNLS
1083 Publish Tender Notice On E-Tenders This activity involves the publication of a tender notice for the project on the E-Tenders website.
Consulting Engineer
1084 Preparation of Interviews for Tenderers
This Activity will involve the preparation of an interview for the contractor
Consulting Engineer
![Page 20: Activity List](https://reader034.fdocuments.net/reader034/viewer/2022042719/568c33671a28ab02358c9c12/html5/thumbnails/20.jpg)
AIT Waste Water Treatment Facility: Activity List
17
Sponsor Acceptance
Approved by the Project Sponsor:
____________________________________________ Date: _____________________
Project Sponsor: AIT