Act basin priority project
-
Upload
woden-valley-community-council-inc -
Category
Presentations & Public Speaking
-
view
39 -
download
0
Transcript of Act basin priority project
ACT Basin Priority ProjectImproving long term water quality in the ACT and
the Murrumbidgee River System
Briefing to Woden Valley Community Council4 March 2015
Project Background
• WMPA: Basin States to undertake one or more Priority Projects that will:o Substantially contribute to
improved efficiency of rural water use
o The sustainability of water use
o Overall health of the Basin
ACT Basin Priority Project
• February 2014: the ACT Government signed a funding agreement with the Commonwealth of up to $85 million for the ACT Basin Priority Project.
• The Project will Improve the Long Term Water Quality in the ACT and the Murrumbidgee River System
• The Project will be delivered in two phases with a focus on six priority catchments
ACT Basin Priority Project
• Catchments selected to achieve representation of the broad variety of catchment types and land development across the Territoryo Yarralumla Creek –Mature catchment flowing into Molonglo Rivero Lake Tuggeranong – Mature urbanised catchment flowing into Lake
Tuggeranongo Upper Molonglo – Semi-rural catchment flowing into Lake Burley
Griffino Fyshwick – Industrial catchment flowing into Lake Burley Griffin and
Jerrabomberra Wetlandso Lower Molonglo – Developing catchment flowing into Molonglo o Riverview (West Belconnen) – Greenfield development flowing into
Murrumbidgee River
Governance Structure
Joint Commonwealth/ACT Steering Committee
Joint Commonwealth/ACT Steering Committee
BPP Management TeamBPP Management Team
ACT and Region Catchment
Management Coordination
Group
ACT and Region Catchment
Management Coordination
Group
Senior Executive Water Group
(ACT Government)
Senior Executive Water Group
(ACT Government)
Project Advisory Group – Technical
Experts
Project Advisory Group – Technical
Experts
Project Advisory Group –
Community Stakeholders
Project Advisory Group –
Community Stakeholders
Future Delivery TeamDesigners/Construction Contractors
Phase 2
Future Delivery TeamDesigners/Construction Contractors
Phase 2
Phase 1 – to Feb 2016
Pre-feasibility: Gathering data on existing conditions & infrastructure• Audit of WQ Data and establish data
management framework• Water quality monitoring in 6 catchments. • Pre-feasibility identification of options (GHD Synthesis
report)• Audit of existing water quality infrastructure assets
Phase 1
Six catchments project – completed March 2015
Objective:
• Water quality database• Design and implement a water quality
monitoring framework for the six catchments• Preliminary recommendations on
appropriate interventions (GHD Report on six catchments)
Phase 1
ACT wide monitoring project – to June 2015
Framework for surface water and ground water based on water quality objectives for the ACT. Options include:
• Bathymetry • Sediment sampling• Micropollutants
Phase 1
Audit of Infrastructure project – to June 2015Objectives: • Audit a representative selection of existing stormwater assets;• Advise on performance, efficiency and effectiveness,
maintenance and measures to improve performance; • Options for the type and placement infrastructure assets
within the ACT.• Looks at gross pollutant traps, rain gardens, swales, water
quality & settlement ponds and wetlands plus..
Phase 1 – To Feb 2016
Final Options Identification – April to September 2015
• Identification of treatment train options across 6 catchments and in-lakeo Establish key environmental, social, economic criteriao Develop investment framework and MCA tool
• Community engaged in option identification
Phase 1 – to Feb 2016
Business Case
• Ranked options to Cabinet – Sep 15
• Draft business case to Commonwealth – Dec 15
• Final business case to Commonwealth – Feb 16
Phase 2 -To be completed by March 2019.
• Will involve the construction or augmentation of water quality infrastructure.
• Is subject to the Commonwealth Government’s final assessment and agreement.
• A supplementary report to the initial business case utilising information from Phase One will inform Phase Two.
Phase 2- Design and ConstructionMay 2016 to March 2019
• Design of approved treatment train infrastructure • Development application approvals• Construction• Need to manage risk of short timeframe
The Yarralumla Creek system
• Yarralumla Creek the main drainage line
o Length 10 km
o Catchment 30 km2
• Drains from the south to the north, to
the lower Molonglo River
• Tributary Long Gully Creek drains the eastern part of the
catchment
The Yarralumla Creek system
• Established catchment• Intensively urbanised
o 83% of catchment is utilised for ‘urban intensive uses’
• ‘Flashy’ o Increase of 0.9 of a meter within 5
mins at Curtin
The Problem – Yarralumla Creek
• High sediment and nutrient loads entering the Molonglo
• Poor quality into Murrumbidgee River• Steep, flashy system - erosion• High flows and hydraulics limit
options available• New development and shifts in
climate likely to place further pressure on system
Flow Debris Up stream of Cotter Road
21 Feb – 3 monthly rainfall event.
Water level and flow response significant
Organic load
BPP: Holistic Management
• Infrastructure proposals within catchment• Management options in catchment (street sweeping)• Practice change (leaves and clippings in open space)
and domestic)
Composting grass clippings, garden waste and leaves helps keep our waterways cleaner.
Catchment infrastructure options1. Wetlands – low in the system on main drainage line2. Naturalisation/riparian revegetation3. Bio-retention (rain gardens) to remove
contaminants from stormwater runoff4. GPTs – low in the system
Next Steps
Establish Multi-Criteria Investment Framework
End Assignment Catchment Options
Catchment Options to cabinet – End September
Assess and Rank Options across Catchments
March April May June July August September
Catchment Options Analysis & Assessment
Start Assignment Catchment Options
Community expectation
research
Community consultations on
infrastructure options
Comments
Thank you...
Basin Priority Project [email protected]
http://www.environment.act.gov.au/water/act-basin-priority-project
Community Engagement
• Targeted engagement on:– community expectations of water quality and waterways– infrastructure options analysis– design process
• Briefing to catchment and community groups• Open house, factsheets and website• Behaviour change campaign on catchment friendly behaviour• Quarterly meetings of Project Advisory Groups – Community
Stakeholders
Community Engagement – Beyond 2015
• Consultation with community about successful infrastructure proposals
• After construction, opportunity to become part of a supported Parkcare Group assisting in caring for infrastructure
Proposed Infrastructure and Management Options
• rea• et / Management Option
Treatment / Management Options Bio-retention system (aka bio-filtration system or raingarden) Buffer Strips Gross Pollutant Traps Infiltration systems (also including porous pavements) Media Filtration systems Ponds Rainwater tank Sedimentation basins Vegetated swales Wetlands Naturalisation of channel Riparian revegetation Floating wetlands
Evolution of water management
Waste-water
Water supply Drainage
Water-ways
Water cycle
Water sensitive
Drivers
Management responses
Population growth
Public health Population growth and
development
Social amenity; environmental
health
“Limits to growth”
Intergenerational equity, resilience to climate change
Supply hydraulics
Separate sewerage schemes
Drainage/flood
protection
Point source and
stormwater pollution
management
Diverse, fit-for-purpose water supplies linked with waterway
protection
Adaptive and multi-functional
infrastructure and landscapes
Based on T. Wong and R. R. Brown 2009 The Water Sensitive City: Principles for Practice. Water Science and Technology 60(3):673-682
Liveable
Quality of urban
environment
Integrated solutions, built
in to urban form