Accelerated Construction Technology Transfer (ACTT) - A...

15
1 Chris Schneider FHWA Office of Asset Management August 5, 2008 Accelerated Construction Accelerated Construction Technology Transfer (ACTT) Technology Transfer (ACTT) - - A Program Update A Program Update - - 2008 Annual Meeting San Antonio, Texas AASHTO Highway Subcommittee on Construction

Transcript of Accelerated Construction Technology Transfer (ACTT) - A...

Page 1: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

1

Chris SchneiderFHWA Office of Asset ManagementAugust 5, 2008

Accelerated Construction Accelerated Construction Technology Transfer (ACTT)Technology Transfer (ACTT)

-- A Program Update A Program Update --

2008 Annual MeetingSan Antonio, Texas

AASHTO HighwaySubcommittee on Construction

Page 2: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

2

What is ACTT?“ACTT is a strategic process, which uses

various technologies and techniquesto reduce overall project durationreduce overall project duration while

enhancing safety and quality.”

(Faster, Safer, Better)

What is ACTT?“ACTT is a strategic process, which uses

various technologies and techniquesto reduce construction time while

enhancing safety and quality.”

(Faster, Safer, Better)

Page 3: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

3

ACTT Basicso A structured 3-day workshop is the centerpiece

of the processo Utilizes skill sets from a national resource poolo National experts teamed with local counterpartso Recommendations are documented in a report

ACTT vs VE

Page 4: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

4

ACTT Skill Setso Construction

o Environmental

o Geotechnical & Materialso Innovative Contracting/

Financing

o Pavement/ Maintenance

o Public Relationso RW/ Utilities/ RR

Coordinationo Roadway Design/

Geometrics

o Structures

o Traffic Safety/ ITSo Worker Health and

Safety

Page 5: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

5

How ACTT Workso Initiate ACTT Model early (planning process)o Set measurablemeasurable goals for project (traffic, time, cost)o Identify needed SKILL SETS (project focus)o National & local Transportation Professionals brainstormo Develop & consider all SKILL SET strategiesoo NetworkNetwork with other affected SKILL SETSo Develop SKILL SET prioritieso Develop workshop report (address recommendations)(address recommendations)o Agency makes appropriate changes to the projecto Ideally, the agency adopts the ACTT mindset

and process for future projects

Page 6: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

6

o TRB Special Report 249 (1996)- Recommended strategic forum

o TRB Task Force A5T60 “Accelerating Innovation in Transportation” (1999)- Remove barriers to innovation- Advocates continuous quality improvement- Foster strategies for beneficial change

o Sponsored by AASHTO TIG & FHWA until 2005

History of ACTT

Page 7: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

7

Held an ACTT workshop

Scheduled an ACTTworkshop

City of Baltimore, MD

Considering an ACTTworkshop

2

2

2

Status of ACTT to Date

22

Page 8: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

8

ACTT Experiences andLessons Learned

o Feedback received from 6 States that used an ACTT workshop in the project development process

o The scope of the 6 projects varies greatlyo All 6 States report significant savings or vital

lessons learned as a result of the ACTT process

Page 9: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

9

Oklahoma ACTT

o ODOT has realized an estimated $15.8 million in savings for the $360M I-40 Crosstown project- Completed early geotech investigations- Eliminated cast-in-place wall designs- Use of better traffic control schemes/ detours- Utilizing pre-established borrow sites

Page 10: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

10

Louisiana ACTT

o LaDOTD reduced the construction timeframe from 225 proposed to 125 actual days for its I-20 project- Utilized very early strength latex modified concrete- Hyroblasted and overlaid 1½” without impacting

expansion joints- Used innovation in its TCP and detours- Incorporated innovative contract methods

and optimized the letting date

Page 11: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

11

“It was a very useful workshop” … “The results benefited the project as well as practices across the State. However, the workshop was late in the design process so wasn’t as effective as it had the potential to be.”

Montana ACTT

Page 12: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

12

New Hampshire ACTTo For its I-93 Project, NHDOT incorporated a host

of ACTT recommendations. A few include:- Prefabrication option for bridge elements and retaining walls- Use of Smart Work Zones – all construction contracts- Implemented a utility impact and relocation plan, and

advance SUE plans for the entire corridor

o Organizational changes:- CPM scheduling now specified on all projects- Improved communications among counterparts

Page 13: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

13

WARNINGINNOVATION

AHEAD

Why ACTT in Your State?oo ADDRESS CUSTOMER NEEDS!!ADDRESS CUSTOMER NEEDS!!o Apply National Expertiseo Improve Roadway Performanceo Improve Safetyo Reduce Construction Timeo Minimize Worker Exposureo Minimize Traffic Congestion

Page 14: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

14

Visit FHWA’s website at:www.fhwa.dot.gov/construction/accelerated/

Page 15: Accelerated Construction Technology Transfer (ACTT) - A ...sp.construction.transportation.org/Documents/Schneider...o Sponsored by AASHTO TIG & FHWA until 2005 History of ACTT 7 Held

15

Thank You

QUESTIONS?****

Chris SchneiderFHWA Office of Asset [email protected]