Accelerated Artificial Corrosion Monitoring of … with Purpose Accelerated Artificial Corrosion...

29
Learning with Purpose Learning with Purpose Accelerated Artificial Corrosion Monitoring of Reinforced Concrete Slabs Using the Half- Cell Potential Method Justin Wilson a and Tzu-Yang Yu b a Master's Student b Assistant Professor, Ph.D. Department of Civil and Environmental Engineering University of Massachusetts Lowell SAGEEP 2013 March 19, 2013 Denver, CO Session 4: Applications of GPR: Civil Infrastructure

Transcript of Accelerated Artificial Corrosion Monitoring of … with Purpose Accelerated Artificial Corrosion...

Learning with PurposeLearning with Purpose

Accelerated Artificial Corrosion Monitoring of Reinforced

Concrete Slabs Using the Half-Cell Potential MethodJustin Wilson a and Tzu-Yang Yu b

a Master's Studentb Assistant Professor, Ph.D.

Department of Civil and Environmental EngineeringUniversity of Massachusetts Lowell

SAGEEP 2013March 19, 2013

Denver, COSession 4: Applications of GPR: Civil Infrastructure

Learning with Purpose 2

Motivation and ObjectiveExperimental Approach• Accelerated corrosion test• Data collection

Results• Data modeling

ConclusionsAcknowledgementsReferences

OverviewOverview

Learning with Purpose 3

• Why Monitor Corrosion?– Corrosion affects the

service life of concrete structures

– Corrosion is inevitable

– Many structures were built with unprotected rebar

• Half-Cell Potential– Standardized test– Proven Reliability

Motivation and ObjectiveMotivation and ObjectiveMotivation and Objective

(Source: www.fhwa.dot.gov)

Learning with Purpose 4

Motivation and ObjectiveMotivation and Objective

Case: MA Route 6A over Scorton CreekSandwich, MA

Spalling of South Exterior BeamCracking to Interior Beam at Midspan

Learning with Purpose 5

Determine how the spatial distribution of half-cell potential (HCP) measurements on Reinforced Concrete (RC) slabs change in timePerform a visual inspection to validate the resultsDevelop parameters for the distribution of HCP in the time domainCompare the HCP data at varying concrete covers to an non-ponded RC slab in the same environment

Motivation and ObjectiveMotivation and ObjectiveGoals

Learning with Purpose 6

Experimental ApproachExperimental Approach

Learning with Purpose 7

Experimental ApproachExperimental Approach

Concrete Laboratory, CEE, UMass Lowell

Learning with Purpose 8

Adapted version of the Modified Southern Exposure Test [2]

Controlled environment• Relative humidity kept to 50%• Temperature 73oF when ponding• Temperature 100oF when drying

Slabs ponded in weekly cycles for 52 weeks• 4 days of ponding• 3 days of drying

Slabs covered with a tarp to keep conditions constant

Experimental ApproachExperimental Approach

Learning with Purpose 9

• Elcometer 3312 Model H

• Ag/AgCl reference electrode

• Readings corrected to Cu/CuSO4 values

• Test specification– ASTM C678 - 09

• Procedure similar to the Modified Southern Exposure Test

Experimental ApproachExperimental ApproachSpecifications Half-Cell System

Elcometer 331² ® Model H & HM Half Cell MeterSource:  www.elcometer.com

Learning with Purpose 10

Concrete Cover• Influences the rate of corrosion

Location of Measurement• Least resistivity when measurements are taken

directly over the barsWater Content• Affects the resistivity of the concrete

Atmospheric Conditions• Affects the water content of the slab

Experimental ApproachExperimental ApproachFactors Affecting HCP Measurement

Learning with Purpose 11

Results - Slab 1Results - Slab 1

Concrete Laboratory, CEE, UMass Lowell(Week 52)

Learning with Purpose 12

Results – Slab 1Results – Slab 1

S1-1

HCP = -530 mVConcrete Laboratory, CEE, UMass Lowell

(Week 52)

Learning with Purpose 13

Results – Slab 1Results – Slab 1

S1-2 S1-3

HCP = -501 mV HCP = -422 mVConcrete Laboratory, CEE, UMass Lowell

(Week 52)

Learning with Purpose 14

HCP Contour MapsHCP Contour Maps

Contour maps were as expected for Slab 1

(Week 52)

Learning with Purpose 15

HCP Contour MapsHCP Contour Maps

(Week 52)

Slab 2 shows lower HCP at the front of the slab–Spatial location of the point of measurement is important

Learning with Purpose 16

HCP Contour MapsHCP Contour Maps

Slab 3 shows more corrosion with areas of less concrete cover

–Variations in concrete cover affect HCP

(Week 52)

Learning with Purpose 17

HCP Contour MapsHCP Contour Maps

The contour map for Slab 4 was as expected–It shows minor variations across the entire slab

(Week 52)

Learning with Purpose 18

Average HCP vs. TimeAverage HCP vs. TimeGraphical Representation

Learning with Purpose 19

All Slabs show an increase until Week 14• Residual pore water

Slab 2 stays fairly constant after Week 28• About (-140 mV)

Slab 3 shows more variability than Slab 2, but stays relatively constant after Week 24• About (-240 mV)

Slab 4 is more noisy than the minimum values

Average HCP vs. TimeAverage HCP vs. TimeObservations

Learning with Purpose 20

Parameter Slab 1 Slab 2 Slab 3 Slab 4

P1 3.399e‐4 ‐3.614e‐5 ‐4.226e‐5 ‐3.736e‐4

P2 ‐3.102e‐2 4.985e‐3 1.138e‐2 4.444e‐2

P3 0.6127 ‐0.2572 ‐0.8518 ‐1.725

P4 2.375 7.219 24.43 25.23

P5 ‐280.2 ‐247.3 ‐485.4 ‐263

R2 0.98 0.91 0.66 0.56

Average HCP vs. TimeAverage HCP vs. TimeModel Parameters

Learning with Purpose 21

Minimum HCP vs. TimeMinimum HCP vs. TimeGraphical Representation

Learning with Purpose 22

Slab 1 shows an expected, decreasing trendSlab 2 stays fairly constant throughout the entire experiment (-180 mV)Slab 3 dips sharply at the start, but remains constant afterward (-550 mV)• Possible excess mix water trapped in slab

Slab 4 stays constant throughout the first 30 weeks, but rises afterwards (-120 mV)• Possible indicator of background noise

Minimum HCP vs. TimeMinimum HCP vs. TimeObservations

Learning with Purpose 23

Parameter Slab 1 Slab 2 Slab 3 Slab 4

P1 ‐3.722e‐4 1.575e‐5 1.860e‐5 ‐5.037e‐4

P2 6.16e‐2 9.032e‐4 ‐2.116e‐3 5.574e‐2

P3 ‐3.21 ‐0.1928 0.1145 ‐1.988

P4 49.05 6.771 ‐4.405 26.21

P5 ‐377.8 ‐234.4 ‐451.9 ‐261.5

R2 0.97 0.46 0.31 0.51

Minimum HCP vs. TimeMinimum HCP vs. TimeModel Parameters

Learning with Purpose 24

Effect of Concrete CoverEffect of Concrete Cover1.5” Concrete Cover

Slab 1 (Week 52) Slab 4 (Week 52)

47.1% Decrease in Average HCP 53.2% Increase in Average HCP

Learning with Purpose 25

Effect of Concrete CoverEffect of Concrete Cover2” Concrete Cover

Slab 2 (Week 52) Slab 4 (Week 52)

41.1% Increase in Average HCP 50.2% Increase in Average HCP

Learning with Purpose 26

Concrete cover is the most important factor determining the rate of corrosionVisual inspection validates the experimental results• Corrosion observed at the points of lowest HCPData collected on Slab 4 can be used to determine the level of noise in HCP measurements• Further analysis required to denoise the data

ConclusionsConclusions

Learning with Purpose 27

Financial Support from National Institute of Standards and Technology (NIST) Technology Innovation Program (TIP) and Prof. Ming Wang from Northeastern University through the Vehicle Onboard Traffic Embedded Roaming Sensors Project (VOTERS)The authors would also like to thank Carlos Jaquez, Hao Liu, and Ross Gladstone of UMass Lowell for their help in collecting HCP data

AcknowledgementsAcknowledgements

Learning with Purpose 28

1. Frolund, T., Klinghoffer, O., Sorensen, H.E. 2003 “Pro’s and Con’s of Half-cell Potentials and Corrosion Rate Measurements.” Structural Faults and Repair Conference, London, UK, July 1-3.2. Darwin, D., Balma, J., Locke, Jr., C.E., Nguyen, T.V. 2001 “Accelerated Testing for Concrete Reinforcing Bar Corrosion Protection Systems.” Long Term Durability of Structural Materials. 97-108.3. Gulikers, J.J.W. 2009. “Application of a Statistical Procedure ti Evaluate the Results from Potential Mapping on a Parking Garage.” Taylor & Francis Group. 267-273.4. Leelalerkeit, V., Kyung, J-W., Ohtsu, M,. Yokota, M. 2004. “Analysis of Half-Cell Potential Measurement for Corrosion of Reinforced Concrete.” Construction and Building Materials. Vol. 18. 155-162.5. Li, C.Q. July-August 2001, “Initiation of Chloride-induced Reinforcement Corrosion in Concrete Structural Members – Experimentation.” ACI Structural Journal. Vol. 98 #4. 502-510.6. Li, C.Q., Melchers R. September-October 2005. “Time-Dependent Risk Assessment of Structural Deterioration Caused by Reinforcement Corrosion.” ACI Structural Journal. Vol. 102 #5. 754-761.7. Otiento, M.B., Alexander, M.G., Beushausen, H.D. September-October 2010. “Suitability of Various Measurement Techniques for Assessing Corrosion in Cracked Concrete.” ACI Structural Journal. Vol. 107 #5. 481-489.8. Poupard, O., L’Hostis, V., Catinaud, S., Petre-Lazar, I. 2006. “Corrosion Diagnosis of a Reinforced Concrete Beam after 40 Years Natural Exposure in Marine Environment.” Cement and Concrete Research. Vol. 36. 504-520.9. Yuan, Y., Yongsheng, J., Shah, S.P. May-June 2007, “Comparison of Two Accelerated Corrosion Techniques for Concrete Structures.” ACI Structural Journal. Vol.104 #3. 344-347.

ReferencesReferences

Learning with PurposeLearning with Purpose

Thank You for your attention

Questions?