Transcript of AC24 installation using CASIM
E x p e c t M o o r f r o m a L e a d e r .
Suction Pile & Manifold InstallationAC 24
Suction Pile & Manifold InstallationAC 24
OverviewOverview
• Field Architecture• Mobilization• Installation• Lessons Learned
Field LocationField Location
• Alaminos Canyon Block 24– 160 miles south of Galveston– 120 miles offshore– 4851 ft WD
Field ArchitectureField Architecture
• 2 existing subsea wells– A 4,356 ft WD– B 4,851 ft WD
• Spar– 18’ gas & oil export lines
Mobilization 3/11-3/12Mobilization 3/11-3/12
InterMoor Fourchon Dock• 2 CASIM units (50t capacity)• Offshore basket
– 7 ROV Shackles• 2 x 85t• 3 x 55t• 2 x 35t
– 11 Green Pin Shackles (85t)– 2 ROV Hooks (100t)– 1 Miller Swivel (75t)
• Compressed Nitrogen Bottles and rack• Offshore toolbox
– Compressed gas booster pump– Soft slings– Misc other tools and hardware (chain for sea fastening)
Mobilization 3/12Mobilization 3/12
InterMoor Fourchon Dock• 35’ suction pile
– Steel chocks– Chain
• Subsea Manifold– Stands
Mobilization 3/12Mobilization 3/12
• Video link here• Video link here• Weight of Suction Pile ~ 36 tons• 13.5’ diameter• 35’ pile, 42’ overall length
Transit 3/12-3/14Transit 3/12-3/14
3/12 2300—Depart InterMoor Dock3/13 1515—Stop in Vermillion 395-ROV Trial3/13 1600—Underway3/14 0815—Arrive on location AC24
Installation – Survey 3/14-3/15Installation – Survey 3/14-3/15
3/14/09 – 1005 Load Subsea Basket (SSB)– 1301 SSB in water– 1440 Basket touchdown at seabed– 1530 Buckets placed– 1600 Boxing in beacons & PLEMs
3/15/09 – 0800 Finished box in
Installation – Suction Pile 3/15-3/16Installation – Suction Pile 3/15-3/16
3/15/09 – 1000 Adjust CASIM Pressures
• 2315psi top, 2165 bottom– 1239 CASIM rigging underway– 1510 Suction pile overboarded– 1600 Pre-lift safety meeting and JSA– 1804 Pile vertical– 2048 Transfer to tower crane complete– 2230 Suction pile at 100’ above seabed– 2351 Touchdown on seabed <1° from vert
3/16/09 – 0012 Self weight penetration 24.5’– 0200 Vacuum pumped to 32.5’ penetration – 0238 Suction pile disconnected from rigging– 0710 Rigging recovered on deck
Installation – Suction Pile photosInstallation – Suction Pile photos
Pressure adjustment
Deck layout pre-deployment
Moving CASIM for rigging
Overboarding
Installation – Deploying CASIMInstallation – Deploying CASIM
• Video link here and here• Weight of assembly – 7 tons• Length of assembly ~ 60’ (fully extended)
Installation – Suction Pile photosInstallation – Suction Pile photos
Pile 248’ below waterline Pile 239’ below waterline
Top of pile 70’ above seabedRighting pile at 250’ WD
Installation – Suction Pile photosInstallation – Suction Pile photos
Zeroing in on target-3’ to goZeroing in on target-6’ to go
Zeroing in on target-inches left TOUCHDOWN
Installation – Suction Pile as builtInstallation – Suction Pile as built
Target Location
Actual Location
Installation – Manifold 3/16Installation – Manifold 3/16
3/16/09– 0738 CASIM lowered on deck– 0740 Adjust CASIMs pressure
• 2165-1114 psi lower and 2351-1265 psi upper– 1000 Pre-lift safety meeting and JSA– 1334.40 Lift manifold– 1335 Manifold in water, lower to 250’ WD for transfer– 1450 Lowering to 100’ above seabed– 1549 Moving vessel to suction pile location– 1656 Manifold landed on Suction Pile
Installation – Manifold transferInstallation – Manifold transfer
• Video link here• Weight of Manifold 11 tons• Dimensions ~ 10’ x 10’ x 15’
Installation – Manifold PhotosInstallation – Manifold Photos
Attaching Rigging
Swapping lifting bridle Rigging Manifold
Installation – Manifold transferInstallation – Manifold transfer
Manifold subsea—241’ Lowering CASIM from Tower
Grabbing rigging; transfer to tower Removing sling from ROV hook
Installation – Manifold transferInstallation – Manifold transfer
Transferring load from crane to tower Freeing ROV hook—take 1
Freeing ROV hook—take 2 Manifold prior to lowering
Installation – Landing ManifoldInstallation – Landing Manifold
Lowering on suction pile—3’ to goLowering manifold—274’ to go
Lowering suction pile—1’ to go TOUCHDOWN
Installation – Manifold disconnectInstallation – Manifold disconnect
Inclination check--<1° off vertical Locking down
Removing ROV Shackle pins Lifting Rigging
Lessons LearnedLessons Learned
• Clear communication is the key to success• When transferring load from one crane to
another, add a few extra feet to the sling• Slow steady crane movements• Plan for the unexpected• Practice preparing and conducting a JSA• Measure twice cut once—Manifold slings• Bleeding pressure for CASIMs happens at about
38psi/min
E x p e c t M o r e . . . G e t M o o r .
Project TeamProject Team
Oil Company E• Project Manager• Subsea Systems Engineer
InterMoor• Offshore Project Manager• Offshore Construction Manager
DMT Emerald• Ship’s Captains• Vessel Superintendant
UTec• Project Chief• Surveying Engineer
Huisman/Intrepid• Project Manager
• Independent Consultant Subsea Systems• Safety Superintendant
• Field Engineer• Field Engineer
• Deck Foreman• Crew
• Surveying Engineer