CONSTRUCTION PROGRESS
AS ON 31st OCT’19
![Page 2: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/2.jpg)
STATUS
• Structure completed• Internal Painting – All floor Internal
Painting work completed.• Floor marble laying work under
progress.• Toilet Tiling work under Progress.• All floor Water Proofing work completed• All floor Plumbing work completed.• All floor Fire Fighting work completed.• Bedroom & Kitchen Tiling work under
Progress.• Electrical work under progress.
A – BLOCK
![Page 3: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/3.jpg)
STATUS
• Structure completed• Internal Painting – All floor internal
painting work completed.• Floor marble laying work under progress.• Bedroom & Kitchen Tiling work under
Progress.• Upto 10th floor Toilet Tiling work
completed.• All floor Fire Fighting work completed.• All floor Water Proofing work completed.• All floor Plumbing work completed.• Window fixing work under Progress.• CP & Sanitary Fittings under progress.• Upto 14th floor Electrical work completed.
B – BLOCK
![Page 4: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/4.jpg)
HALL
![Page 5: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/5.jpg)
DINING & BEDROOM
![Page 6: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/6.jpg)
TOILET
![Page 7: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/7.jpg)
TRANSFORMER LINE-A B C D
![Page 8: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/8.jpg)
STATUS
• Structure completed• Internal Painting – Painting work completed• Floor marble laying work completed • Bedroom & Kitchen Tiling work completed• Toilet Tiling work completed• Fire Fighting work completed• Water Proofing work completed• Plumbing work completed• Window fixing work completed• Door frame fixing work completed• Electrical work completed• CP & Sanitary fittings completed.
C – BLOCK
![Page 9: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/9.jpg)
STATUS
• Structure completed• Internal painting – Painting work completed• Floor marble laying work completed• Bedroom & Kitchen Tiling work completed• Toilet Tiling work completed• Fire fighting work completed• Water proofing work completed• Plumbing work completed• Window fixing work completed• Door frame fixing work completed.• Electrical work completed• CP & Sanitary fittings work completed.
D – BLOCK
![Page 10: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/10.jpg)
N – BLOCK
STATUS
• Structure completed• Internal painting – All floor Internal
Painting work completed.• Floor marble laying work under Progress.• Upto 10th floor Toilet Tiling work
completed.• Fire fighting work completed.• Water proofing work completed.• Upto 18th floor Plumbing work
completed.• Window fixing work Nearing completion.• Electrical work under progress.
![Page 11: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/11.jpg)
HALL & BEDROOM
![Page 12: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/12.jpg)
DINING & POOJA AREA
![Page 13: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/13.jpg)
TOILET
![Page 14: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/14.jpg)
O – BLOCK
STATUS
• Structure Completed• Internal painting – All floor painting
completed.• Floor marble laying work under
progress.• Upto 9th floor Toilet Tiling work
completed.• Fire fighting work Completed.• Water proofing work completed.• Plumbing work completed.• Window fixing work nearing
completion.• Upto 15th Electrical work completed.
![Page 15: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/15.jpg)
HALL
![Page 16: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/16.jpg)
KITCHEN & BEDROOM
![Page 17: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/17.jpg)
DINING & POOJA AREA
![Page 18: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/18.jpg)
DB PANEL
![Page 19: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/19.jpg)
TOILET
![Page 20: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/20.jpg)
JEWEL (Q) - BLOCK
STATUS
• Upto 16th floor slab work Completed.• Terrace Activity under progress.
![Page 21: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/21.jpg)
JEWEL (Q) – BLOCK – MODEL UNIT WORK IN PROGRESS
![Page 22: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/22.jpg)
INFINITY (CLUB HOUSE) – EXTERNAL VIEW
![Page 23: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/23.jpg)
INFINITY (CLUB HOUSE) – ENTRANCE VIEW
![Page 24: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/24.jpg)
INFINITY (CLUB HOUSE) – INTERNAL VIEW
![Page 25: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/25.jpg)
INFINITY (CLUB HOUSE) – BANQUET HALL-1
![Page 26: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/26.jpg)
INFINITY (CLUB HOUSE) – BANQUET HALL - 2
![Page 27: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/27.jpg)
INFINITY (CLUB HOUSE) – BANQUET HALL - 3
![Page 28: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/28.jpg)
INFINITY (CLUB HOUSE)-MINI THEATRE
![Page 29: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/29.jpg)
INFINITY (CLUBHOUSE) – GYM - MEN
![Page 30: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/30.jpg)
INFINITY (CLUBHOUSE) – GYM - WOMEN
![Page 31: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/31.jpg)
INFINITY (CLUBHOUSE) – GYM - WOMEN
![Page 32: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/32.jpg)
INFINITY (CLUB HOUSE) - KIDS PLAY AREA
![Page 33: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/33.jpg)
INFINITY (CLUB HOUSE) – TOP VIEW
![Page 34: Abhinandan - CONSTRUCTION PROGRESS AS ON 31st OCT’19abhinandan.klpprojects.com/PDF/ConstructionProgress... · 2020-01-11 · STATUS • Structure completed • Internal Painting](https://reader033.fdocuments.net/reader033/viewer/2022050215/5f61546e4a44c479a03739f7/html5/thumbnails/34.jpg)