AAVS0 & AAVS0.5: System Design and Test Plan

26
AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy AAVS0 & AAVS0.5: System Design and Test Plan Nima Razavi-Ghods Eloy de Lera Acedo Andrew Faulkner Jan Geralt bij de Vaate Laurens Bakker Peter Hall Adrian Sutinjo Mark Waterson

description

AAVS0 & AAVS0.5: System Design and Test Plan. Nima Razavi-Ghods Eloy de Lera Acedo Andrew Faulkner Jan Geralt b ij de Vaate Laurens Bakker Peter Hall Adrian Sutinjo Mark Waterson. Overview. AAVS0 (& AAVS0.5): System Architecture Objectives System design - PowerPoint PPT Presentation

Transcript of AAVS0 & AAVS0.5: System Design and Test Plan

Page 1: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

AAVS0 & AAVS0.5: System Design and Test Plan

Nima Razavi-GhodsEloy de Lera Acedo

Andrew FaulknerJan Geralt bij de Vaate

Laurens BakkerPeter Hall

Adrian SutinjoMark Waterson

Page 2: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Overview• AAVS0 (& AAVS0.5): System Architecture

– Objectives– System design– Test RF front-end developments (Pre-ADU)– UniBoard digital back-end requirements– Receiver housing options– Control software development

• Test Plan (Cambridge, Medicina and Murchison)– Testing already carried out on AAVS0 (Cambridge)– Intermediate testing without a full receiver– Extended testing with a full receiver (AAVS0.5)– A plan for the future…

Page 3: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Objectives (AAVS0 & 0.5)

• Deploy a 16 element dual-polarised low frequency AA (SKALA) with a full receiver at Lords Bridge (Cambridge) and then at the Murchison Site, WA

• Continue from AAVS0 by testing the Antenna + LNA in a potential low RFI SKA environment and prototype technologies suitable for future AA-low developments

• As well as performing coupling and pattern measurements, there should be an aim to measure system temperature as well as assess beamformer and correlator platforms.

• Gain understanding of practical aspects of deployment at site.• Understand some of the impact on “Calibration and Science”• Our aim is therefore a potential “Testing Platform” for AAVS1

Page 4: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

AAVS0 & 0.5: System ArchitectureArm 1 (1-pol)

Arm 2 (1-pol)

MGA-16516

LNA Board: ~40dB gain

HDF400 cable(20m = 2dB loss

@ 450 MHz)

Phase Switch

Gain (15dB to 46dB)

Pre-ADU (x32 Boards)

Balun

PC

ADU - 8 RF inputs per board

Filters Pre-whitening

VLNA

32

8-bit, 1Gsps

8

8-bit, 1Gsps

8

8-bit, 1Gsps

8

8-bit, 1Gsps

8

UNIBOARD 1

UNIBOARD 2

4.2dBm for full scale digitisation (2.6mW, 360mV)

32

half of UNIBOARD sub-rack

Control

MGA-62563

To work in both low and high RFI environment

Page 5: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Active SKALA SpecificationsParameters Frequency Typical Units

Antenna Directivity 70 MHz100 MHz300 MHz450 MHz

7.58

7.47.6

dBi

LNA module Gain(noise matched)

70 MHz100 MHz300 MHz450 MHz

37404340

dB

LNA module Noise Figure(noise matched)

70 MHz100 MHz300 MHz450 MHz

1.180.510.470.44

dB

LNA module supple current (per board)

- 155 mA

LNA module power dissipation (per board)

- 750 mW

LNA module input IP2 70-450 MHz -23 (worst case) dBm

LNA module input IP3 70-450 MHz -18 (worst case) dBm

Page 6: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Our Environment (SKALA)

• Using the Active SKALA element at the Murchison site

Page 7: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

The worst case RFI (Cambridge)

Page 8: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Front-end (Pre-ADU)

HPF

VLNA (+5V)

LPF

2dB

FM Notch

0dB

0°180°

Att.

VDD (+12V)

2dB

6-bitAtten.0.5dB

to31.5dB

VDD (+12V)

Pre-White

0dB

2dB

VDD (+12V)

2dB

RFIN_1

RFIN_2

RFOUT

SPDT

Control 1 Control 2 Control 3

Controls 4-9

Control 10

23dB

23dB23dB

10-bitLatch

From Arduino (bits 0-9)

LEControl Enable

Control lines

EQ. Network

PWR < 3W per pol

Page 9: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Arduino for Front-end Control

Page 10: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Previous Design (AAVS0)…

Page 11: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

UniBoard Digital Back-end

• The aim is to use half of the standard UniBoard sub-rack as a beamformer & correlator backend.

• In full mode the UniBoard hardware can produce 384 sub-bands x 42 beams (39 bits) through its 10 GbE interfaces.

• Through its 1GbE interface (assuming 80% efficiency of UDP), it can produce 50 MHz of beam data which assuming 1GSamples/s clock corresponds to 100 sub-bands (split between frequency bands and FoV in anyway desired).

Page 12: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

UniBoard

ADC Interface

Page 13: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Adapting UniBoard to AA-low• The ADU hardware needs to be changed to include new filters and

a PLL clock at 1 GHz instead of 800 MHz.• The firmware (VHDL) needs to be adapted for this new sampling

frequency and this requires development time. • There are no “top” level python scripts as of yet which set the

weights for a sub-band and specific antenna. This requires time in dealing with coefficient register mapping but does not present a major challenge.

• There are many python scripts already available which can be used with little or no changes for controlling UniBoard hardware (e.g. quick power spectrum, temperature and other utility functions) .

• There is no “triggered weight update” mechanism but this does not present a significant challenge.

• Data capture is also a viable option for offline correlations.

Page 14: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Receiver Housing Options

• Option 1 (recommended): A screened room in a container within 30-40m of the array (typical price: £20k for a 2.5m x 2.5m x 2.5m 100dB screened room)

• Option 2: Use high spec RF over fibre devices to transmit 32 signals over single mode fibre. A small MWA receiver container (19 inch, 15U) can be used to house Pre-ADU cards and RFoF links. Links with very high dynamic range from OpticalZonu (Z450) cost ~£800 a link. A USB to fibre module is also required here (for Arduino control).

Page 15: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Receiver Housing

Page 16: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Control Software: What should it do?

• Control of the Front-end (Pre-ADU): Set gain, filter switch, phase switch

• Communicate with mid to high level python scripts which control UniBoard

• Set observing mode: Stationary beams, tracking beams and testing mode

• Use and test simple calibration routines and upload complex weights accordingly

• Monitor power spectrum, system temperature and other utility functions including physical temperature

Page 17: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Test Plan…

Page 18: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

AAVS0 Testing so far

• Impedance and Coupling measurements (Cambridge, ASTRON, Stellenbosch)

• Pattern measurements (Cambridge, QinetiQ)• Near-field pattern measurements (Cambridge,

Université catholique de Louvain)• LNA measurements: Gain, NF, IP3 (Cambridge,

NPL, ASTRON)• 4 reports available on these measurements

Page 19: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

AAV0 Testing to do soon

• Further near-field measurements and comparison with simulations (Cambridge, Université catholique de Louvain)

• Far-field pattern measurements (Paardefontein)• Far-field pattern measurements using 2-element

correlator (Cambridge)

Page 20: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Original Test Plan:

Page 21: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

2-element correlator measurements

Feed box 1

Feed and control box 2

Front-end

8-bit ADC Roach PC100 150 200 250 300 350 400 450

20

30

40

50

60

70

80

90

100

Frequency (MHz)

SN

R

Signal to Noise for CAS-A (SKALA+LNA), 200kHz BW, 60s integration

Page 22: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

2-element correlator update

• Alt-Az mount: mechanical design 90% completed. Limit switches and weather proofing to do.

• Control software - completed• Feed box 1 and 2 - completed• Front-end boards in a rack – completed• Roach correlator - completed

Page 23: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

2-element correlator update

Page 24: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Next level testing

Page 25: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

A plan for the future (by July 2012)

• Complete testing of AAVS0 in all aspects previously described and fully characterise the Antenna + LNA.

• Validate measurements against simulations• Continue intermediate testing using strong northern

sources to measure antenna pattern• Develop front-end boards and test in Cambridge• Employ a UniBoard back-end and test in Cambridge• Develop Control software

Page 26: AAVS0 & AAVS0.5:  System Design and Test Plan

AA-Low Technical Progress Meeting, 22-24 October 2012, Medicina, Italy

Thank you.