A321 C-Check's Turnaround Time Reduction

12
C-Check downtime reduction by 50% Hatim NAITLHO March 2007

Transcript of A321 C-Check's Turnaround Time Reduction

Page 1: A321 C-Check's Turnaround Time Reduction

C-Check downtime reduction by 50%Hatim NAITLHOMarch 2007

Page 2: A321 C-Check's Turnaround Time Reduction

Context

• RAM had scheduled the C-checks of CN-RNX and CN-RNY in Air France industries Toulouse.

• The work package was discussed on Sep. 2006. • The best TAT proposed was 6.5 days.• Due to operational constraints, RAM decided to

perform these C-Checks in it’s facilities on January 2007

Page 3: A321 C-Check's Turnaround Time Reduction

Project Scope

• Fleet: A321 family• Organization: Royal Air Maroc Maintenance & Engineering

Center – Casablanca• Maintenance visite: C2-check

Page 4: A321 C-Check's Turnaround Time Reduction

Project goals

• Execution of C2-Checks of CN-RNX and CN-RNY in RAM facilities

• Reduction of the turnaround time of C-check• Minimization of man-hours in the C-check• Reduction of C-check cost

Page 5: A321 C-Check's Turnaround Time Reduction

Project team

• Project management: – Hatim NAITLHO, Aircraft Maintenance Senior Manager– Mustapha ELGHAZI: Base maintenance senior manager

• Project members : – Lhoussaine ELASLI: team supervisor – Mostafa ELASRI, Hassan ELHAMDI: B1 engineers– Hassan MESSOUDI, Abdelilah BALMANE: B2 engineers

Page 6: A321 C-Check's Turnaround Time Reduction

Conceptual Framework

A new conceptual framework was elaborated to achieve a breakthrough of performance and achieve the ambitious goals of the project:

PlanningC-check managementMan-hours allocation

Bottleneck management

Page 7: A321 C-Check's Turnaround Time Reduction

Conceptual Framework

The new conceptual framework: – MECE breakdown– TOC based planning– Lean management– Kaizen blitz event– Process mapping & redesign

Page 8: A321 C-Check's Turnaround Time Reduction

TOC based planning

The Theory of Constraints (TOC) is a philosophy of management and continuous improvement originally developed by E. Goldratt:

TOC allowed us to manage the C-check bottlenecks and subordinate resources to them:

• Optimized allocation of resources

Page 9: A321 C-Check's Turnaround Time Reduction

Results

• Reduction of Turnaround Time of C2 check of CN-RNX from 6.5 to 3.5 days

• Reduction of Turnaround Time of C2 check of CN-RNY from 6.5 to 3.2 days

• Decreased cost by $50k per check

Page 10: A321 C-Check's Turnaround Time Reduction

Achievement celebration

This exceptional achievement had been praised by the chairman and CEO of Royal Air Maroc Mr. Driss BENHIMA

Page 11: A321 C-Check's Turnaround Time Reduction

Achievement celebration

This exceptional achievement had been praised by the chairman and CEO of Royal Air Maroc Mr. Driss BENHIMA

Page 12: A321 C-Check's Turnaround Time Reduction

Conclusion

• The reduction of Turnaround Time of A321 C-Check was a result of three main factors:– Strong leadership and teamwork– Strong commitment of the players involved in the C-

check– Solid conceptual framework