A Water Treatment Solution for heavy metals
Transcript of A Water Treatment Solution for heavy metals
-
8/3/2019 A Water Treatment Solution for heavy metals
1/1
An innovative Water Treatment Solution for Heavy Metals
ZwolleThe Netherlands
ResultsThe First lab results showed that the water contained
mainly Crhomium6. The concentrations showed to be
much lower than earlier levels: 25-36.000 g/l. We found
out that a three-staged treatment with chemicals was
needed to get the best results. Phase 1 was a pH
correction. Then the Chromium was precipitated with
iron3chloride and the last step was to ad a polymer for
optimal settlement of the created sediments. In the lab we
could reduce the water concentrations below 100 g/l.
Also visible results where good: a good defined
sedimentation with on top a brightened water.
The lab results where then translated to the full scale
application. In the field the water in the old cellar is been
treated with the same recipe by spraying the different
chemicals over the water surface. Due to the wet autumn
the total amount of water was raised from 600 to 1.500
m and in the end we had to treat the water several
times. Each treatment lasted 1-2 days. But the results
were very good: like in the lab we were able to reduce theChromium6 concentrations below 100 g/l.
Beside the on-site water treatment we also took care of
the discharging of the water in the cellar. Discharging this
water without the sediments was done by floating pumps.
To be sure, we also installed a small water treatment
unit to prevent any sediments from discharging to the
local sewer (sand filtration).
ChallengeIn the Summer of 2011 HMVT was asked to provide a
practical solution for the treatment of 600 m polluted
water in an old cellar in Zwolle, The Netherlands.
On this project old buildings were being demolished and also a
soil remediation was carried out. The location was severelypolluted with Chromium3, Chromium6 and Nickel. As a result
of the very wet Summer the old and still to demolish concrete
cellar stood full of polluted water with Chromium6
concentrations of 400.000 g/l. A temporary water treatment
plant based on ion-exchange was having a lot of problems due
to clogging and was not capable of treating the water to meet
the discharge levels.
SolutionOur solution was based on precipitation of the heavy metals to
the bottom of the cellar and additionally discharging the
cleaned water to the local sewage system. The residual
polluted sediments could then be removed together with the
demolishing of the cellar and the soil excavations and for
treatment transported from the site.
Before executing this plan, we first collected water from the
location and tested this water in our lab facility. The aim was to
find a recipe of needed chemicals which could meet the local
water discharge levels (