A SURVEYONTHE EFFECTIVENESS AND IMPACT OF...
Transcript of A SURVEYONTHE EFFECTIVENESS AND IMPACT OF...
1
)
EXECUTIVE SUMMARY
(FINAL REPORT)
A Study by IBS Centre, Construction Industry Development Board Malaysia (CIDB)
A SURVEY ON THE EFFECTIVENESS AND IMPACT
OF INDUSTRIALISED BUILDING SYSTEM (IBS)
TRAINING ON CONTRACTORS
SULIT
2
EXECUTIVE SUMMARY From the perspective of Industrialised Building System (IBS), there is a general
consensus that contractors among the wide range of industry stakeholders
hold a very important position to ensure the success of IBS application.
Despite acknowledging its benefits, contractors are still not rapidly
embracing IBS. For contractors, the construction industry is an established
industry with many deep-seated and culturally-embedded practices, so the
introduction of anything perceived as new or different faces barriers. To deal
with this matter and to produce contractors which capable to undertake IBS
projects under SPP 7: 2008, the Construction Industry Development Board
(CIDB) has organise training for contractors to be vendor of specialist
contractors (installer) for IBS. Nonetheless the effectiveness and the impact
of this training have never been measured and the current state of
contractors is not known. The primary aim of this study is to determine the
effectiveness and impact of IBS training to contractors in the Malaysian
construction industry. The secondary aim is to identify the success factors for
contractor to implement IBS. The majority of respondents had undergone IBS
training courses but not all contractors have implemented IBS project after
completion of training. A challenge to be faced by the contractors is the
lack of suitable and sustainable opportunities in IBS. Most respondents
agreed that the position and financial strength is an important aspect
contributing to the success of contractors. Thus, measures deemed
appropriate by the CIDB in attracting contractors to enter the field of IBS is to
provide better incentives. Collaboration in the form of partnering is the best
way to develop a contractor in the field of IBS. In addition, knowledge of the
financial aspects should be emphasised to the contractor to enter the field
of IBS. At the end of the report recommendations and transformation
framework for contractors are presented.
SULIT
3
TABLE OF CONTENTS
No. Content Page
Executive Summary 2
Key Findings 6
1.0 Introduction 8
2.0 The Role of Contractor in IBS 9
3.0 Problem Statement 11
4.0 Training and Education 8
5.0 The Survey 13
6.0 Survey Data and Analysis 15
7.0 Conclusions 30
8.0 Recommendations 31
9.0 Transformation Framework for Contractor to Adopt IBS
32
10.0 Build offsite Accreditation Scheme 37
SULIT
4
LIST OF FIGURES
No. Figure Page
1 Respondent registration under CIDB 16
2 Respondent's professional background 17
3 Respondent's Working Experience 21
4 The percentage of contractors involved in IBS tender 19
5 Type of IBS Project 20
6 Type of system used in IBS project 21
7 Type of future training preferred by contractors 23
8 Contractors involved in the manufacturing component of IBS 26
9 Contractors have to be a specialist contractor in the IBS 27
10 Transformation Firework 33
SULIT
5
LIST OF TABLES
No. Table Page
1 Respondent registration under CIDB 15
2 Respondent professional background 16
3 Respondent’s Working Experience 17
4 Number of IBS Project Undertaken by the Company 19
5 Total Value of IBS Project 19
6 Type of project 20
7 Training Effectiveness of IBS Centre 21
8 Training Effectiveness of IBS Centre 22
9 Perspective of contractors on the implementation of IBS in government building
23
10 Challenges faced by Contractors in Carrying out IBS Projects 24
11 Factors that Contribute to the Success of IBS Contractor 25
12 Contractors Involved in the Manufacturing Component of IBS 26
13 Contractors have to be a Specialist Contractor in the IBS 27
14 Improving measures to be taken by the CIDB 28
15 Action to be taken by Contractor to Involve in IBS 29
16 Ranking of factors that are important to contractors in IBS 30
SULIT
6
KEY FINDINGS
• The primary aim of this study is to determine the effectiveness and
impact of IBS training to contractors in the Malaysian construction
industry. The secondary aim is to identify the success factors for
contractor to adopt IBS from current conventional practices
• More than half of the contractor is G1. G1 represent 55.9% of total
respondents, while the remaining 44.1% represent G2, G3, G4, G5
and G7. Most likely the survey represents the perspective of small
and medium sized contractors.
• Most of the respondents (87.9%) agree that IBS contractor’s training is
effective.
• 22.6% of the respondents who have completed the training involved
in IBS tender
• Only 9% of the respondent has been awarded contracts that
involved IBS elements. Most of them involved in IBS projects tendered
by the government. Most of the IBS projects conducted by these
contractors are school with 42.9% followed by Government Office
Building with 28.6% and the least type of project is hospital with 14.3%.
• About 86.2% of the respondents feel that the training conducted
by CIDB assisting respondent in carrying out projects of IBS.13.8% of
the respondent does not agree because of lack of practical training
and inadequate training period.
SULIT
7
• Majority of the respondent (30.3%) agree that roof truss installation is
the training that must be conducted by the CIDB in future for the
contractors.
• Most of the respondents with mean score 4.46 strongly agree that
knowledge about IBS is the main factor that contributes to the
success of IBS contractor.
• 82.9% of the respondent agrees that IBS implementation
of government projects under SPP 7: 2008 do give some benefit to
contractors such as financial gain, time reduction, quality and safety.
• As strategic measure, most of the respondents (88.6%) agree that
contractors should be involved in the manufacturing of IBS
components with some financial aid and incentives from
government.
• Despite the implementation of IBS in public project under SPP 7: 2008,
lack of suitable projects is the main challenge faced by the
contractors results the contractors is not keen to participate into IBS
project tender. Besides that, relying much on the manufacturer is also
the main challenge faced by the contractor in carrying out IBS
projects.
• Partnering and vendor system is the effective method to increase the
capability of contractor on IBS. Further, positioning and financial
strength is the most important aspect to the contractor in order to
implement the IBS project.
SULIT
8
1.0 Introduction to IBS
1.1 Industrialised Building System (IBS) is the term coined by the industry
and government in Malaysia to represent the adoption of
construction industrialisation and the use of prefabrication of
components in building construction. IBS is defined as a construction
technique in which components are manufactured in a controlled
environment (on or off site), transported, positioned and assembled
into a structure with minimal additional site work.
1.2 IBS consists of precast component systems, fabricated steel
structures, innovative mound systems, modular block systems and
prefabricated timber structures as construction components. Parts of
the building that are repetitive but difficult – and too time consuming
and labour intensive to be casted onsite – are designed and
detailed as standardised components at the factory and are then
brought to the site to be assembled. The onsite casting activities in
IBS utilise innovative and clean mound technologies.
1.3 The construction industry has started to embrace IBS as a method of
attaining better construction quality and productivity, reducing risks
related to occupational safety and health, alleviating issues for skilled
workers and dependency on manual foreign labour, and achieving
the ultimate goal of reducing the overall cost of construction. Apart
from this, it offers minimal wastage, fewer site materials, a cleaner
and neater environment, controlled quality, and lower total
construction costs.
SULIT
9
2.0 The Role of Contractor in IBS
2.1 Contractors are the stakeholders dealing with project management
and solving issues in construction on a day-to-day basis. They are
responsible for the means and methods to be used in the
construction execution of the project, in accordance with the
contract documents, and for the supplying of all materials, labour,
equipment (engineering vehicles and tools) and services necessary
for the construction of the project. In many cases, the main
contractors will delegate portions of the contract work to
subcontractors.
2.2 As in a common rule, contractors will provide direct labour for civil
aspects of a construction project, such as placement of concrete
and carpentry with specialty areas, such as mechanical and
electrical construction furnished by specialty subcontractors.
2.3 From the perspective of IBS, there is a general consensus that
contractors among the wide range of industry stakeholders hold a
very important position to ensure the success of IBS application.
2.4 Despite acknowledging its benefits, contractors are still not rapidly
embracing IBS. The construction industry is an established industry
with many deep-seated and culturally-embedded practices, so the
introduction of anything perceived as new or different faces barriers.
The barriers to adopting the IBS method in construction are:
2.4.1 IBS requires radical and substantial change from a
traditional building process towards a manufacturing
process. It was highlighted that the idealism, processes,
SULIT
10
management and skill sets behind IBS method are
different from those in the conventional method.
2.4.2 In contrast to the traditional method, the design,
manufacturer, assembly and other related processes
require a more coherent structure of process planning
and control in order to reduce defects and errors.
2.4.3 A strong constraint in the industry is a lack of adequate
knowledge of the IBS method. There is limited expertise in
the marketplace among designers and constructors
regarding the IBS method. Approaches to design are still
largely based on traditional methods that are unsuited to
IBS.
2.4.4 Although IBS is used to address the skill shortage in the
construction industry, some evidence suggests that a
skilled workforce in specific skill areas like integration,
coordination and assembly are becoming more
important to IBS due to different roles and project
methods that are undertaken.
2.4.5 IBS adoption requires a new business approach,
investment and financial planning including an effective
combination of cost control and selection of projects that
give enough volume to justify the investment.
2.4.6 IBS adoption requires an improvement in conventional
procurement and management of the supply chain. The
IBS building procurement is slightly different from
conventional methods which include purchasing of
materials in advance before the actual site progresses.
2.4.7 Therefore, effort towards total industry adoption to IBS
from conventional methods largely depends on readiness
and maturity of contractors which will coordinate
SULIT
11
processes involved in IBS life cycle. As a consequence,
perspective and the role played by the contractors in IBS
needs to be scrutinised.
3.0 Problem Statement
3.1 However, there were a number of cases where the use of IBS had not
led to total satisfaction and may have actually been less productive
than conventional methods. IBS has been associated in the past with
low-quality buildings, leakages, abandoned projects and other such
drawbacks delivered by contractors.
3.2 There were also cases where building projects were awarded and
constructed by the contractor using IBS but contributed to the
project delays and bad qualities. Contractors also produce poor
workmanship, particularly in applying waterproofing materials and
column and beam alignment.
3.3 Majority of contractor involve in IBS suffered from poor productivity
and financial performance. This is due to the fact that contractors
have to pay the supplier upfront to purchase components. It is a high
capital investment where 30% of the value of the project is to be
paid up front. A delay in the payment means a delay in the
components’ delivery, which eventually affects the productivity of
the projects.
3.4 It is worth noting that in 2008, the Malaysian government made the
use of IBS compulsory in all newly constructed public building. Since
then, the importance of capable contractors to construct public
SULIT
12
building has increased. Nonetheless, there are still limited numbers of
contractors in Malaysia specialising in IBS that can undertake IBS jobs.
3.5 In order to be a specialist in IBS, contractors need to furnish
themselves with the necessary knowledge in implementing IBS. Their
organisations also require some changes with regards to their
process, practices, procedure and administration to embrace IBS.
3.6 Therefore, the role of training and education is important to support
contractors to implement IBS. To deal with this matter and to
produce contractors which capable to undertake IBS projects under
SPP 7: 2008, the Construction Industry Development Board (CIDB) has
organise training for contractors to be vendor of specialist
contractors (installer) for IBS. Nonetheless the effectiveness and the
impact of this training has never been measure and the current state
of contractors is not known.
4.0 Training and Education
4.1 Training and education can be considered as an integral part of an
organisation’s learning and change. Training often embraces
learning and development, experiential learning and cognitive
abilities, and can also considered as a management tool and
instrument for addressing skill deficiencies.
4.2 The primary rationale for training is to adapt employees’
qualifications to job requirements. Although IBS is used to address skill
shortage problems in the construction industry, evidence suggests
that a skilled workforce in specific skill areas such as integration,
coordination and component installation becomes more important
SULIT
13
than in conventional methods due to different undertaken roles and
project methods. Therefore, training is important, especially to
people involved in design, handling, positioning and erecting the
finished product.
4.3 The application of IBS requires a high level of techniques and
precision compared to the conventional method, and therefore
requires continuous trainings. Training labour in innovative method by
ensuring the team received appropriate and thorough training in
new and unfamiliar method in advance of the installation. Whenever
innovative or unfamiliar methods and material is used, operative
should be trained in the application preferably by the supplier or
manufacture before the installation start.
5.0 The Survey
5.1 In 20th July 2011, Construction Research Institute of Malaysia (CREAM)
had received a request from the CIDB to analyse survey of the
effectiveness and impact of IBS training to contractors. The survey
form was developed by CIDB and it includes the process of data
collection, sample proportion and actual data collection as well.
CREAM received the survey forms by stages from 1st August until 5th
August 2011 and completed the final report on 31st August 2011.
5.2 The aim of this study is to determine the effectiveness and impact of
IBS training to contractors in the Malaysian construction industry. To
achieve this aim, the following objectives are being established as
follows:
SULIT
14
5.2.1 To study the number of projects (government / private
sector) that have been implemented by contractors
after attending IBS training by the CIDB
5.2.2 To review the contractor's perspective on the
effectiveness and impact of IBS training
5.2.3 To study the factors that may contribute to the
success of the contractors
5.2.4 To propose recommendations and measures to
improve the quality of training provided by the CIDB
5.2.5 To propose recommendations and measures to
improve quality of training by the CIDB
5.2.6 To propose the way forward for contractors in
adopting IBS
5.3 The data collection used in this research is the quota sampling.
Quota sampling is the numbers probability equivalent of stratified
sampling. Like stratified sampling, the stratums and their proportions
were first identified as they are represented in the population. Then
convenience or judgment sampling is also used to select the
required number of subjects from each stratum. This differs from
stratified sampling, where the stratums are filled by random sampling.
5.4 A total of 35 questionnaires from respondents of all categories of
contractors were obtained from IBS Centre. The information and
data gathered through questionnaire will be compiled and
processed using statistical methods in relation to the objectives of
study. Two statistical methods will be applied, namely descriptive
statistic and inferential statistics. Result from the findings will be
presented in the form of graphs, histogram and pie chart for easier
understanding.
SULIT
15
5.5 As research goes, this study has its own limitation that affected the
results of the findings. The number of cases (35 questionnaires) is too
limited for broad generalisations to the population. Regarding to the
data limitations, the study should not be taken as completely
accurate or representative of the study.
6.0 Survey Data and Analysis
6.1 This section presents the analysis and the results of the research
survey form. The data and the results were analysed and presented
to conform the objectives at the beginning of the report.
The Table 1 and Figure 1 above show the respondents’ registration grade
under CIDB. Most of the respondents are G1 contractors with 55.9%, follows
by G2 contractors with 14.7%. The minority is from G3, G4, and G5 which are
5.9% each while G7 contractors represent 11.8% of the sampling.
Table 1: Respondent registration under CIDB
Type of Contractor's Registration Frequency Percentage (%) G1 19 55.9 G2 5 14.7 G3 2 5.9 G4 2 5.9 G5 2 5.9 G7 4 11.8 Total 34 100.0
SULIT
16
Figure 1: Respondent registration under CIDB
Table 2 and Figure 2 above depicted the information on respondents’
background. 77.1% of respondents are owner or managing director of the
company, 11.4% are project managers, 5.7% are technical assistants and
2.9% are project engineers. This statistic shows that the relevant professionals
respondent to their survey, thus increase the validity of the results.
Table 2: Respondents’ professional background
Position Frequency Percentage (%)
Company Owner 27 77.1 Project Engineer 1 2.9 Technical Assistant 2 5.7 Project Manager 4 11.4 Other 1 2.9 Total 35 100.0
SULIT
17
Figure 2: Respondents’ professional background
Referring to Table 3 and Figure 3, 19 respondents that are working in the
construction industry for between 5 and 10 years and 8 out of total
respondents have had 11-15 years working experience. Since most of the
respondents have more than 4 years working experience and this represents
that the data acquired is quite reliable and accurate.
Table 3: Respondents’ Working Experience
Working Experience Frequency Percentage (%)
0-4 years 2 5.7
5-10 years 19 54.3
11-15 years 8 22.9
More than 15 years 6 17.1
Total 35 100.0
SULIT
18
Figure 3: Respondents’ Working Experience
From the table above, it shows that only seven respondents which are 22.6%
of the total respondents that have implemented IBS project after complete
the training. The highest percentage whereby the number of projects
implements IBS is no project which consists of 91.4% of the total respondents.
Next it is followed by less than 5 projects that number
of IBS projects undertaken by the company with 5.7%. Lastly there are only
2.9% of the respondents that have undertaken of IBS project into their 5-15
projects. From the analysis above, it can be summarized that the number of
IBS projects undertaken by the company is still very low. There are only three
numbers of projects that has been done for public sector and no project for
private sector. Two companies have total value of RM 15-30 million and only
one company have total value of RM 5-15 million.
SULIT
19
Figure 4: The percentage of contractors involved in IBS tender
Table 4: Number of IBS Project Undertaken by the Company
Number of Project Frequency Percentage (%)
No project 32 91.4
5-15 project 1 2.9 Less than 5 project 2 5.7 Total 35 100.0
Table 5: Total value of IBS project
Total value of IBS project Frequency Percentage (%) No value 32 91.4 RM 5-15 million 1 2.9 RM 15-30 million 2 5.7 Total 35 100.0
SULIT
20
From the table above, it shows that only seven respondents which are 22.6%
of the total respondents that have implemented IBS project after complete
the training. Most of the IBS projects conducted by these contractors are
school with 42.9% followed by Government Office Building with 28.6% and
the least type of project is hospital with 14.3%.
Table 6: Type of project IBS project types Frequency Percentage (%) School 3 42.9 Government Office Building 2 28.6 Hospital 1 14.3 Other 1 14.3 Total 7 100.0
Figure 5: Type of IBS Project
SULIT
21
The contractor prefer large panel system with 25% followed by metal or steel
formwork system with 18.8% and the least used IBS system is block works
system with 12.5%. It worth knowing, 43.8% prefer other system most probably
precast structure or timber.
Figure 6: Type of system used in IBS project
Based on the results obtained from the questionnaire, it can be summarized
that generally all the respondents moderately agree with the effectiveness
of IBS training. It can be concluded that most of the respondents satisfied
with the content of the IBS training course. Most respondent agree that the
method of teaching is very important with a mean score of 4.35. This is
because the method of teaching makes the respondents easy to
understand the topic. Next is followed by professionalism of trainers with 4.29.
However, most of the respondents felt that the training did not provide an
adequate training period and sufficient practical training into the course.
SULIT
22
Table 7: Training Effectiveness of IBS Centre
Training Effectiveness of IBS Centre Frequency
Score 1 2 3 4 5 Mean Score Position Indicator
Manner of service of teaching is good 0 0 2 16 13 4.35 1 Agree The top and professional trainers 0 1 1 17 12 4.29 2 Agree Training centres with good facilities 0 1 3 16 11 4.19 3 Agree Conducted appropriate syllabus 0 0 2 22 7 4.16 4 Agree Skills learned help you 0 1 3 20 7 4.06 5 Agree Adequate theoretical training 0 1 1 25 4 4.03 6 Agree Adequate training term 0 0 5 21 5 4.00 7 Agree Adequate training period 0 0 7 20 4 3.90 8 Agree Sufficient practical training 1 1 6 20 3 3.74 9 Agree
In Table 8, most of respondents agree that the training conducted by CIDB
assisting respondent in carrying out project of IBS with 86.2%.
Table 8: The effectiveness of IBS training for contractor
Respondent's answer Frequency Percentage (%)
Yes 25 86.2 No 4 13.8 Total 29 100.0
The Figure 7 shows the types of training that shall be conducted by the CIDB
in the future according to contractors. 30.3% of respondents agree that
training on installation roof trust must be conducted by the CIDB in the future
for contractors. It followed by project management with 24.2% and
entrepreneurship with 21.2%.
SULIT
23
Figure 7: Types of future training preferred by contractors
Most of the respondents agree that implementation of government projects
under SPP 7: 2008 gives benefit to contractors (Table 9):
Table 9: Perspective of contractors on the implementation of IBS in government building
Benefit to the contractor Frequency Percentage (%) Yes 29 82.9 No 6 17.1
Total 35 100.0
SULIT
24
Based on the results obtained from the questionnaire, it can be summarized
that generally all the respondents agree with the challenges faced by
contractors in carrying out project IBS. Most noted challenges that
contribute to the success of IBS contractor is the main challenge to be
involved in IBS is no IBS project at the mean score of 4.26. It follows by high
dependency on the manufacturer with 4.40 mean score. There are two
sections which get the mean score less than 4.00 which indicated that the
least score in the challenges faced by contractors in carrying out of project.
Most of the respondents are not agreeing that IBS reduce company profits
because IBS is actually can increase the profit of the company.
Table 10: Challenges faced by Contractors in Carrying out IBS Projects
Challenges Faced By Contractors in Carrying Out Projects IBS Frequency
Score 1 2 3 4 5
Mean Score Position Indicator
No IBS project 1 2 18 14 4.26 1 Agree Too dependent on the manufacturer 5 16 14 4.26 2 Agree
Less incentive implement IBS 2 2 19 12 4.17 3 Agree No capital 1 6 16 12 4.11 4 Agree political contact and position 1 8 14 12 4.06 5 Agree risk in the project IBS 1 5 22 7 4.00 6 Agree No skills 5 25 5 4.00 7 Agree No IT skills 1 6 22 6 3.91 8 Agree
IBS reduce company profits 2 2 11 13 7 3.60 9 Less agree
SULIT
25
Based on the results obtained from the questionnaire, it can be summarized
that generally all the respondents agree with the factors that contribute to
the success of IBS contractor listed in the question. The most important factor
that contributes to the success of IBS contractor is knowledge on IBS which
stands at the mean score of 4.46. This is because the contractor feels that
knowledge is very important to the success. Next is followed by positioning
and financial strength with 4.40. There are three sections which get the
mean score less than 4.00 which indicated that the least score in the factors
that contribute to the success of IBS contractors. Most of the respondents are
less agree that use of IT, Investment and political contact and position is
important factors that contribute to the success of IBS contractors.
Table 11: Factors that Contribute to the Success of IBS Contractor
Factors That Contribute To the Success of IBS Contractor Frequency
Score 1 2 3 4 5
Mean Score Position Indicator
Knowledge about IBS 1 17 17 4.46 1 Strongly agree Positioning and financial strength 1 2 14 18 4.4 2 Agree
Skilled workers 22 13 4.37 3 Agree Technology 1 2 21 11 4.20 4 Agree Supply chain net 2 3 18 12 4.14 5 Agree Business strategy 6 21 8 4.06 6 Agree Use of IT 1 5 23 6 3.97 7 Agree Investment 2 7 19 7 3.89 8 Agree Political contact and position 2 11 16 6 3.69 9 Agree
The Table 12 and Figure 8 above show the respondent’s answer whether
contractors should be involved in the manufacturing component of IBS
SULIT
26
component. Most of the respondents agree that contractor should be
involved in the manufacturing of IBS component. Only 11.4% does not agree
that contractor should be involved in the manufacturing activities.
Table 12: Contractors Involved in the Manufacturing Component of IBS
Respondent's answer Frequency Percentage (%) Yes 31 88.6 No 4 11.4
Total 35 100.0
Figure 8: Contractors Involved in the Manufacturing Component of IBS
From Table 13 and figure 9 above show the respondent’s answer whether
the contractors have to be a specialist in the IBS. Most of the respondents
agree that the contractor have to be a specialist in the IBS with 88.6% and
only 11.4% does not agree that the contractor have to be a specialist in the
IBS.
SULIT
27
Table 13: Contractors have to be a Specialist Contractor in the IBS
Respondent's answer Frequency Percentage (%)
Yes 31 88.6 No 4 11.4
Total 35 100.0
Figure 9: Contractors have to be a specialist contractor in the IBS
Based on the results obtained from the questionnaire, it can be summarised
that generally all the respondents agree with the measures to be taken by
the CIDB. Most of the respondents strongly agree that contractor should get
better incentives at the mean score of 4.51 followed by assist in the IBS
component manufacturers and assist in the supervision of capital with each
have mean score of 4.46. Since all the mean score is more than 4.00, it can
SULIT
28
be concluded that all measures that need to be taken by the CIDB are
important.
Table 14: Improving measures to be taken by the CIDB
Measures To Be Taken By the CIDB Frequency Score 1 2 3 4 5
Mean Score Position Indicator
Better incentives 1 15 19 4.51 1 Strongly Agree
Assist in the IBS component manufacturers 2 15 18 4.46 2 Agree
Assist in the supervision of capital 1 17 17 4.46 3 Agree Better training modules 1 20 14 4.37 4 Agree Assist in the preparation of business plans 2 19 14 4.34 5 Agree
IBS contractor documenting good practices 1 21 13 4.34 6 Agree
awareness programs 1 21 13 4.34 7 Agree establish IBS "standards and guideline" 2 21 12 4.29 8 Agree
Online training modules 1 7 17 10 4.03 9 Agree
Based on the results obtained from the questionnaire that action to be taken
by contractor to involve in IBS, it can be summarised that generally all the
respondents agree. Most of the respondents strongly agree that partnering is
the most important aspect to promote the contractor at the mean score of
4.57 followed by creating cluster of IBS with mean score of 4.40. All the
measure is greater than 4.00 except for looking opportunities abroad. The
contractor felt that century abroad is risky and involve capital investment.
SULIT
29
Table 15: Action to be taken by contractor to involve in IBS
Measures To Promote the Contractor in the Field Of IBS Frequency
Score 1 2 3 4 5
Mean Score Position Indicator
Partnering 15 20 4.57 1 Strongly Agree Create a cluster of IBS 21 14 4.40 2 Agree Improve skills 22 13 4.37 3 Agree Be a specialist contractor 2 20 13 4.31 4 Agree Be the IBS manufacturer 4 18 13 4.26 5 Agree Increasing use of IT 1 24 10 4.26 6 Agree R & D and innovation 2 23 10 4.23 7 Agree Looking for opportunities abroad 13 13 9 3.89 8 Agree
The most important factor to the contractor that has been recognized by
the respondents is the financial strength and knowledge about IBS.
Partnering and technology is also score fairly high in the level of importance.
Factor such as contacts and looking for opportunities abroad are consider
less important by contractors.
SULIT
30
Table 16: Ranking of factors that are important to contractors in IBS
Importance Factor Mean score Ranking Position and financial strength 1.8 1 Knowledge about IBS 1.86 2 Partnering 1.94 3 Technology 2 4 Improve skills 2.11 5 Skilled workers 2.2 6 "Investment" 2.2 7 Business strategy 2.26 8 Supply chain network 2.37 9 R&D and Innovation 2.37 10 IT usage 2.4 11 Create a cluster of IBS 2.49 12 Contacts and political position 2.49 13 Looking for opportunities abroad 2.83 14
7.0 Conclusion
7.1 The research reveals that the main attribute to the lack of
contractors embracing IBS are rarely purely technical in origin. They
are more related to the organisational strategy and soft issues which
underpin the capability of organisation to successfully implement IBS.
This led to the identification that IBS is best handled as a holistic
process and it requires a total synchronisation on construction,
manufacturing and design processes. An improved approach to
project management, procurement, rationalisation, standardisation,
repetition, collaboration, integration, supply chain partnering,
planning, skills and training was proposed.
SULIT
31
7.2 IBS knowledge is still very much needed to improve in IBS field. The
contractor should know well about IBS before plunge in IBS sector.
7.3 Position and financial strength is very important aspect that
contributes to the IBS contractor. The high cost is believed to be due
to lack of economy of scale in IBS projects and business monopoly by
the small number of IBS producers in Malaysia
7.4 Contractors need to be involved in small scale production for them
to reduce dependency on manufacture.
7.5 Lack of knowledge is still the main barrier for bold adoption.
8.0 Recommendation
8.1 From the survey done, the skill gap exists are identified in IBS sector. In
order to create a comprehensive and systematic training
programme, the government should conduct comprehensive
preliminary study. The preliminary study will ensure that the training
fits the needs of IBS organisations and accommodates current skill
shortages in the market, particularly specialist skills such as design
and installation, based on information from real practice.
8.2 Contractors need a strategy for a better project approach and for
the sustainability of their business.
SULIT
32
8.2.1 G1-G3: Specialist installer (installation)
8.2.2 G4-G5: IBS production and installation
8.2.3 G7: Complete all the IBS system (design and
installation)
8.3 Position and financial strength is very important factor to the
contractor to implement IBS. Financial aspect such as loan facilities
and the payback system that can be implemented in the current
banking system. Most of the financial institution reluctant to provide
loan/finance to IBS manufacturer.
8.4 Give better incentives (tax relieve, duty free on imported machinery,
soft loan/interest free (SME) from government financial) to the
contractor is the measure that need to be taken into account in
order to attract contractor to implement the IBS.
8.5 CIDB should conduct more seminar and workshop or training course
to increase the knowledge of contractor about IBS. Knowledge is
very important in order to make contractor interest to involve in the
IBS project. More workers should be trained of IBS knowledge.
8.5.1 G1-G3: installation
8.5.2 G4-G5: small to medium technology, flat, culvert
8.5.3 G7 : High Rise building/ green technology
9.0 Transformation Framework for Contractor to Adopt IBS
9.1 In general, a strategic framework to transform traditional contractor
to IBS is based on nine critical success factors and two important
enabling factors which have been identified in the literatures and in
SULIT
33
the case studies. The critical success factors have been categorised
into four elements. The elements are:
• Strategy (corporate leadership and business strategy)
• People (skills, training and education)
• Process (procurement and contract, project management,
technology selection, design management and integration, and
management of the supply chain)
• Enabler (IT tools and continues improvement)
The framework is depicted in Figure 10:
Figure 10: Transformation Framework
STRATEGY
PEOPLE
PROCESS
ENABLER
• Information Technology
• Improvement
• Corporate
Leadership • Business
Strategy
• Skills • Training &
Education
Procurement & Contract
Project Managemen
Design Management
and Inte
Capability Loop
gration
Technology Selection
Management of supply chain
SULIT
34
9.2 In general, the main causes of the lack of contractors embracing IBS
are rarely purely technical in origin. They are more related to the
organisational strategy and soft issues which underpin the capability
of the organisation to successfully implement IBS. The prerequisite of
success depends to a large extent on the establishment of strategy,
meetings of human capability and capacity and finally the
processes.
9.3 First, contractors need to obtain full support from the top
management and align the business strategy, vision and mission with
IBS, and these elements in return are important to convince the
decision makers, clients and their own organisation structure to use
the IBS method. This support and commitment shall drive the
company forward in terms of investment and resources allocation.
Contractors need to develop and adopt a specific model in their
business and to position themselves in the market. This model includes
diversifying of business, setting up a specific division to deal with IBS
and offering a wide range of services in IBS.
9.4 The second element is the development of people capacity. People
can be considered as core drivers to business. As a collective force
they can add value to organisation. People development is the most
important aspect in the organisations. However, they must be in
place to understand organisational processes, implement change
when necessary, and the use of technology to accelerate their
efforts. Migration from the conventional to IBS requires new skills sets
such as integration, design, planning and supply chain which relate
to IBS implementation. It is imperative for the contractor to employ
appropriately skilled operators at site or enable a range of tasks to
be undertaken by fewer but multi-skilled operators. People must
SULIT
35
however be led, the importance of leadership stems from its role in
providing a clear vision of the future and communicating the vision. It
is therefore essential to obtain optimal human capital and skills,
which in turn is represented through the selecting right people for the
right jobs which could improve innovation and creativity. If the
company has the right people, the problem of how to motivate and
manage people largely goes away. On the other hand, if the
company has the wrong people, it does not matter whether or not
they discover the right direction – it is still difficult for the company to
embrace change. Great vision without great people is irrelevant.
Training can be considered as an integral part of organisation
change. The workers need to be trained in IBS skill sets.
9.5 The third element is development in process. Contractors need to
enhance their processes in procurement, project management,
technology selection, design integration and supply chain. Selection
of contract enables them to effectively select and implement
technology and facilitate better design integration. The
improvement in project management means adopting a better
supply chain strategy and enables design integration to take place.
9.6 The final element in the transformation from a conventional method
to IBS is the role of enablers such as Information Technology (IT) and
continuous improvement. IT can play an integral part in many IBS
processes and would be a reliable support tool for design and
project management. Continuous improvement is also critical in
embracing the IBS method. The repetitive process each time the
project is implemented in IBS allows continuous improvement to take
place for better project performance. Both IT and continuous
improvement are important enablers and support tools in the
SULIT
36
development of strategy, people and process for IBS companies, as
depicted in the framework.
9.7 Successful IBS implementation in Malaysia is due to a strong support,
commitment, awareness, vision, knowledge and leadership and
capability to align IBS implementation with corporate strategy.
Therefore, the prerequisite of success in IBS depends to a large extent
on the establishment of the strategy first, followed by meetings of
human capability and capacity and improvement to the processes
as depicted in the final framework.
9.8 However, implementing this framework is a monumental task for
contractors. Improvements in all of the above four elements are
highly dependent on the capability of the contractors. This is clearly
stressed in the focus group. The focus group highlighted that the
capability and maturity is a major issue for change progress and
ensures IBS success. It was highlighted that the majority of the
contractors in Malaysia are not ready to embrace IBS. If the
contractors do not acquire the capability to change to IBS, they
need to embark on extensive development on people capacity. It
must be recognised in the first place that the transformation from
conventional methods to IBS stems not out of technology but
people. The development of human capital will enhance the overall
organisation’s capability in adopting IBS.
9.9 Once the company has enough capability, supported by highly
knowledgeable IBS personnel, they will start again to realign the
overall company’s strategy to the IBS. This is described in the
framework as the capability loop. It is worth noting that the
transformation to IBS concerns change, and not just a routine
SULIT
37
change but a fundamental change. Furthermore, the change from
a conventional method to IBS is a journey over time. As the
environment changes, these external dynamic must be matched as
far as possible by internal change. There is a need to evolve
constantly. Highlighting a number of critical success factors which
underpin the framework will hopefully help contractors guide their
own organisations towards IBS success without having to learn these
lessons the hard way.
9.10 The readiness model should be developed in future to further
enhance this framework. In this context, an advanced state of
organisation readiness is needed for business to expend domestically
and internationally, to compete readily in the global open market
and optimise the adoption of IBS. It is therefore, imperative that
organisations align their business strategies with IBS strategies. Based
on the readiness model, the level of readiness (both the current and
target) should be clear and indicative of the organisation’s situation
in terms of measurable attributes and maturity levels. By identifying
the current and the required organisation status, the readiness gap
can be determined and the route of transformation progress
becomes visible. Progress can be accomplished when the
organisation moves through the levels in sequential order.
10.0 Buildoffsite Accreditation Scheme
10.1 The scheme has been set up by Buildoffsite, the body that
campaigns for the greater uptake of off-site building solutions,
in association with Lloyds Register EMEA to standardise and
ensure best practice across all aspects of the off-site process,
from the submission of tenders through the awarding of
SULIT
38
contracts to the specification, design, manufacture,
construction, handover and even the ongoing maintenance
of a completed building. It also integrates existing quality
assurance and environmental performance certification
under, for example, ISO 9001 and ISO 14001.
10.2 By choosing a supplier registered under the scheme, client
organisations can be confident of the assured levels of
competence, methodology and safe working from
companies that have standardised best practice for the
delivery of their products and services. It will give clients
greater confidence with regards to a company’s technical
competence, effective methodology and commitment to
safety.
10.3 The Buildoffsite Registration Scheme is operated in
collaboration with other organisations that may be able to
provide specialist focus, such as the British Board of
Agreement. Its operating philosophy is to evaluate the control
measures taken by a service provider to mitigate any risks to
the safe and competent delivery of their products and
services.
10.4 By taking this approach it focuses on the way the products
and services are delivered rather than laying down standards
for the products and services themselves. This provides the
flexibility to cover a wide range of different approaches whilst
still setting a benchmark for best practice
10.5 The benefits of the scheme are:
SULIT
39
10.5.1 It provides client organisations with greater
confidence of delivery to time, cost and quality
through the implementation of risk management best
practice
10.5.2 It provides management and shareholders with the
assurance that their risk management, competency
management and configuration management
systems have been independently validated as
meeting best practice with the attendant likelihood of
costly mistakes minimised
10.5.3 It represents a key element of the Buildoffsite Property
Assurance Scheme and will facilitate a route to
market for the offsite provider with recognition of the
scheme by all major lenders including RBS, Lloyd’s
Bank, Santander and Nationwide, together with RICS
and the valuer community
10.6 Methodology
10.6.1 The company will register under the scheme
10.6.2 The company will be audited by the 5 criteria of the
success factors in offsite
10.6.3 The company will me measure by benchmarking tools
and given the marks based on the control measures
taken by a service provider to mitigate any risks to the
safe and competent delivery of their products and
services.
10.6.4 The successful company that received pass or
excellence marks will be given certification of
SULIT
40
accreditation. The accreditation is recognise by all
major lenders including RBS, Lloyd’s Bank, Santander
and Nationwide, together with RICS and the valuer
community