A Robust SRU Waste Heat Boiler Design - Brimstone …€¦ · 2012 Brimstone Conference • Limits...
Transcript of A Robust SRU Waste Heat Boiler Design - Brimstone …€¦ · 2012 Brimstone Conference • Limits...
A Robust SRU Waste Heat Boiler Design
Sean M. McGuffie, P.E. Porter McGuffie, Inc. Lawrence, KS, USA [email protected]
Dennis H. Martens, P.E. Porter McGuffie, Inc. Lawrence, KS, USA [email protected]
Michael J. Demskie Flint Hills Resources Pine Bend, MN, USA [email protected]
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Michael J. Demskie – Flint Hills Resources - Reliability group
• Sean M. McGuffie – Porter McGuffie Inc. – Senior Engineer
• Dennis H. Martens – Porter McGuffie Inc. - Consultant and Technical
Advisor
Introduction of Authors
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Flint Hills Resources SRU # 5 WHB application – Pine Bend, Minnesota - 320,000 BPD Refinery
• An SRU WHB that was not reliable and the replacement with a reliable WHB
• What made the replacement WHB robust? – CFD analysis results for the replacement WHB
• State-of-the-art CFD analysis information
Introduction
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• 525 LTPD SRU #5 initial startup in June 1993 – 2 pass in single shell kettle type – 600 psi sat steam – refractory and ferrule system
• May 1994 unplanned shutdown – tube leaks – Root cause – Burner vibration with refractory and
ferrule system failure – Replaced 73 of the 400 first pass tubes – refractory and ferrule system
WHB Chronological History
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• May 1999 first planned shutdown – tube leaks – Root cause – refractory and ferrule system separation
from tubesheet face • Anchors burned up • chicken and the egg – cause and effect • Did the separation happen before or after the first tube leak?
– Replaced all 400 tubes in first pass – refractory and ferrule
Original WHB History
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Authors’ experience is for a >2500 °F operating temperature, the SS including 310 SS, anchors for a refractory and ferrule system always “burn off” to close to the tubesheet face or the face of the insulation for the tubesheet as the refractory temperature is above the ~ 2500 °F melting point for the SS anchors and sulfidation metal sulfide melting point of ~ 1650 °F.
Original WHB History
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• July 2002 unplanned shutdown – tube leaks – Root cause – undetermined - lack of consensus – Major corrosion on face of tube sheet (see picture) – Repair weld buildup on tube sheet – Replaced all 400 tubes in first pass – Significant down time and reduced SRU capacity – Two piece removable ferrules installed
Original WHB History
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Original WHB History 2002
Scale removed Sandblasted
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Original WHB History
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Life: installed in 1993 and replaced 2003 = 10 years • 1994 unplanned shutdown - replaced 73 tubes • 1999 first planned shutdown – replaced 400 tubes • 2002 unplanned shutdown – replaced 400 tubes
– significant shutdown and SRU capacity reduction The original WHB essentially had 3 failures in 9 years
with one failure occurring at a planned shutdown
Original WHB History Summary
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• For Reliability FHR decided to replace Original WHB – Fit in existing plant plot space
• Don’t move furnace or condensers
– More robust design – better service reliability – Single pass kettle type – long tubes – Similar process conditions
• Consideration for O2 enrichment
• Sept 2003 - Second planned shutdown – new WHB
Replacement WHB History
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• October 2006 - Unplanned shutdown due to furnace refractory problem - hot spot – Inspected WHB – removed some ferrules – Ferrules in good condition – No corrosion noted – SO FAR SO GOOD – 3 years of operation
• No O2 enrichment operation at this point • O2 operation begins July 2008
Replacement WHB History
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• September 2008 - First planned shutdown – Inspected WHB – removed all ferrules – Ferrules in good condition – No significant corrosion noted (see picture) – Two piece removable ferrules – same design – SO FAR SO GOOD – 5 years of operation
• O2 operation began July 2008 (2 months)
Replacement WHB History
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Replacement WHB 2008
5 years operation
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• September 2012 status – 9 years service – No unplanned WHB shutdowns to date – SO FAR SO GOOD – Significant O2 enrichment service time to date – Next inspection plan is to remove all ferrules and
inspect • Tubesheet - tube ends – length of tube
Replacement WHB
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Installed 2003 and currently in operation 2012 • 2006 Inspection, unit down for furnace repair
– No corrosion or leaks found – no repairs • 2008 first scheduled turnaround - inspection
– No corrosion or leaks found – no repairs The replacement WHB had no unscheduled shut downs
or repairs in 9 years – SIGNIFICANT IMPROVEMENT COMPARED TO ORIGINAL WHB (3/9)
Replacement WHB History Summary
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Please raise your hand if you have one or more SRU WHB’s in your custody
and care
POP Survey of Audience
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Keep your hand raised if you have a WHB that has operated 5 years
without any corrosion or unscheduled shutdowns due to tube leaks
(not just fouling)
POP Survey of Audience
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Keep your hand raised if you have a WHB that has operated 10 years
without any corrosion and unscheduled shutdowns due to tube leaks
(not just fouling)
POP Survey of Audience
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Reoccurring issue of tubesheet and tube end corrosion–leaking tubes – Temperatures > 600 °F for corrosion to occur
• July 2002 failure had severe ferrule ID deposits that reduced flow path to pencil size
• High pressure drop – hot gas bypassing – heating tubesheet • Observed average localized corrosion rate from1999 – 2002
(3 years) was in excess of 50 mil/yr indicating > 850 °F metal temperatures (see corrosion graph)
Original WHB Design/Failure Review
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Original WHB Design/Failure Review
0.001
0.01
0.1
1
10
500 600 700 800 900 1000 1100
Temperature (F)
Mol
% H
2S
1 mil/year2 mils/year3 mils/year5 mils/year10 mils/year15 mils/year20 mils/year25 mils/year30 mils/year40 mils/year50 mils/year
No Corrosion
f
@ 4% H2S 50 mil/yr 850 °F
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Why the high temp at the tubesheet and tube ends? – Refractory and ferrule system possible issues:
• Improper design -heat flux – thickness of refractory • Improper installation – QC - materials and workmanship • Improper dryout procedures • Burner vibration damage to refractory and ferrules • Inadequate operational parameter control • Chicken and the Egg – tube leak or refractory/ferrule • 2002 FHR Root cause – undetermined - lack of consensus
Original WHB Design/Failure Review
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Tubesheet-to-tube inlet end joint possible issues: – 2” thick tubesheet with two grooves – rolled - seal weld
• concern for high tube compression/tension loads on joint?
– Chicken and the Egg – tube leak or refractory/ferrule • Obviously there are a number of possible issues any
one of which could initiate the problem and result in high corrosion rates and leaking tubes
Original WHB Design/Failure Review
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• 5 year turnaround intervals • 20 year life • Avoid unplanned shutdowns due to WHB by:
– Avoiding high temperatures at tubesheet (corrosion) – Avoiding tube-to-tubesheet joint leakage – Avoiding tube damage downstream of ferrules
• Not a significant problem for the original WHB
Robust Replacement WHB Criteria
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Item Original WHB - First Pass Replacement WHB Type 2 Pass - 1 shell - kettle 1 Pass - 1 shell - kettle
Diameter of tubes 2 ¼” OD 2.03” ID 3” NPD pipe 2.9” ID
Number of tubes 400 479 Tube length 15’ – 0” 36” – 0”
Tube specification SA 213-T11 - 12 BWG A 106B Sch 80 Mass flux lb/sec-ft2 4.4 1.75
Tube sheet thick 2” 1 ¼ “ Tube sheet material SA 516-70 SA 516-70
Inlet TS joint Roll and seal weld Full penetration weld Tube projection 7/16” No projection
Original and Replacement WHBs
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Avoiding high temp corrosion – tubesheet/tubes – Used FHR two piece removable ferrule experience
• Installation, inspection and maintenance procedures
– Limit mass flux – limited ferrule inlet pressure loss – Establish/manage max process temperature and flow
• Startup and shutdown considerations
– No tube projection past face of tubesheet – Minimize tubesheet thickness
Robust Replacement WHB Criteria
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Avoiding tube-to-tubesheet joint leakage – Utilized full penetration tube-to-tubesheet weld – Minimized tubesheet thickness – Used thick wall pipe - accommodates FP weld – No tube projection past face of tubesheet – Startup and shutdown considerations (tube stress)
• Rigid tube sheet considerations (tube-to-shell temperatures)
Robust Replacement WHB Criteria
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Avoiding tube damage downstream of ferrules – Limited mass flux
• Limiting turbulence at ferrule outlet • Limiting max heat flux
– Establish/manage max process temperature and flow • Startup and shutdown considerations
Robust Replacement WHB Criteria
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• The operational history of the replacement WHB indicates a robust design was achieved
• FHR decision to analyze the robust design – Determine how design features affect performance
• Maximum heat flux • Tube/Tubesheet operating temperatures • Pressure drop in ferrule assembly
CFD Analysis of Robust WHB
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• To establish the necessary process input, PMI partnered with KPS Technology & Engineering to: – Data mine 6 years of DCS data to determine periods of
interest and maximum WHB duty – Process combustion calculations using Sulsim 7 for
the periods of interest and development of gas composition data
• Consensus selection of representative process conditions for CFD analysis
CFD Analysis of Robust WHB
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Develop process-side model • Fully coupled heat transfer problem
– Requires the inclusion of all assembly geometry
CFD Analysis of Robust WHB
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Initially developed 3 process conditions of interest, based on DCS data
CFD Analysis of Robust WHB
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Velocity results were typical – Recirculation occurs downstream of ferrule – Increased turbulence at this location increases
maximum heat transfer • Primary use of CFD is to estimate the flux multiplier at
this location
CFD Analysis of Robust WHB
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Analyses indicated large margin to established limits – Maximum heat flux was below 50,000 BTU/hr-ft2
– Maximum tubesheet temperature was below sulfidation limit
– Pressure drops were acceptable
CFD Analysis of Robust WHB
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Abandoned remaining cases from DCS data • Performed analyses at maximum established firing
temperature (refractory limit) • Performed analyses at greater mass flows than
recorded in operation • Used results to provide guidance for future operation
CFD Analysis of Robust WHB
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Limits must be based on measurable process parameters – Zone 1 and 2 temperatures – Mass / Volume flow
• Process parameters are used to develop pseudo-duty (product of mass flow and Zone 2 temperature) for each case analyzed
Determining Operational Limits
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Perform curve fit for pseudo-duty versus maximum flux
Determining Operational Limits
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Relate pseudo-duty to operational limits – Maximum flux – Maximum metal temperature
• Algebraically solve for allowable mass flow at a given temperature
• Derate curve based on process measurement limits and unknowns with CFD model
Determining Operational Limits
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Determining Operational Limits
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• CFD is a method of solving the Navier-Stokes Equations
• Equations are nonlinear and require a numerical procedure to solve all but the most trivial problems
Unknowns in CFD
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Due to computing requirements, techniques have only been in use recently – Limits for physics models implemented – Limits on applicability based on experience – Primary simplifying assumption
Unknowns in CFD
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Consideration of turbulence requires grids with a large number of cells with transient integration
• Not suited to engineering applications, only for laboratory environments
• Steady-state solutions incorporate turbulence models – Methods to account for the transient nature of the flow
Primary Simplifying Assumption
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Turbulence models can be sensitive – Grid topology – Model selected – Flow conditions
• Adverse pressure gradients • Recirculating flow • Detached flow
Primary Simplifying Assumption
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Recirculation occurs downstream from ferrule
• Known problem with turbulence models
Primary Simplifying Assumption
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Consider this graph prepared for ASME Tutorial Primary Simplifying Assumption
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• DNB – Most limits developed by nuclear industry • Sulfidation – Temperatures on Couper-Gorman curves
are estimates • Gas bypass – Bypassing can be highly sensitive to
geometry of assembly as installed
Other Limitations in CFD use for WHBs
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Detached Eddy Simulation (DES) and Large Eddy Simulation (LES) are available
• Reduce computational expense from Direct Numerical Simulation (DNS)
• Transient analysis techniques that avoid some of the major limitations of turbulence models
What if More Accurate Information is Needed?
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Dissimilar time-scales between flow phenomena and thermal time constants require difficult procedure
• Two-models must be used and boundary conditions exchanged
• Statistical analysis of output required • Orders of magnitude greater effort
What if More Accurate Information is Needed?
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
What if More Accurate Information is Needed?
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
DES Analysis of WHB Ferrule
Temperatures with Turbulence Model
Temperatures with DES Model
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
DES Analysis of WHB Ferrule
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Through the use of proper design, successful WHBs are possible – Process design and operating limit parameters must
be considered and evaluated for impact on reliability • Mass flux • Operating temperatures • Maximum heat flux
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Guidance for these parameters is not well addressed in any industry consensus document
• Consideration of parameters is, instead, typically left to the SRU licensor
• Evaluation of capital costs versus reliability – Impacts of unscheduled shutdowns are very significant – Repairs often extend shutdowns
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Three Critical areas to consider for WHB designs
1. Avoid high metal temperatures at the tubesheet
2. Avoid tube-to-tubesheet joint leakage
3. Avoid tube damage downstream of the ferrules
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Seven design guidance features to consider and incorporate to address the 3 critical design areas:
1. Ferrule system design – Limit maximum tube end temperature to not more than 615 °F
2. Mass flux – Limits maximum heat flux at end of ferrule and pressure drop through ferrule. Authors suggest 2.5 lb/sec-ft2 for waste heat boilers at higher operating temperatures
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
3. Establish and limit process temperature – design the WHB accordingly and manage operations consistent with these limits
4. Minimize tube projection past the front face of the tubesheet – flush is best practice - no fin
5. Minimize tubesheet thickness – both conductance through the tube sheet and the heat input through the area of the tube holes are important
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
6. Use full penetration welds - or strength welds and rolling – but do not use seal welds for high pressure steam applications or tube end loads
7. Limit pressure drop through the ferrule – associated with # 2 above. Process gas can be driven through a refractory and ferrule or removable ferrule systems which increases the metal temperature and likelihood of corrosion
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• CFD can be used to qualify designs – Determine operational temperatures and fluxes – Compare to limits
• DNB – 50 – 70 kBTU/hr-ft2 - evaluate turbulence multiplier
• Temperature – 600 °F – avoid corrosion • Pressure drop – 0.15 psi at inlet of ferrules - can be a problem
if a significant gas path through the ferrule system is present
– Limitations of CFD results must be understood
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• Common to evaluate failures to “not make the same mistake again”
• Uncommon to evaluate a WHB to determine why it is reliable
• Incorporating knowledge and experience can help prevent unscheduled shutdowns
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• There is not one set of numerical values that are applicable to all WHB applications – For instance, mass flux for large ID tubes may be
unsuitable for small tubes – Understanding how all design parameters influence
the WHB’s performance is critical for reliable designs
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
• “The height of stupidity is doing the same thing the same way and expecting a different result”
• “The height of good engineering is determining what resulted in high reliability and doing the same thing the same way and expecting the same results.”
Conclusions
A Robust SRU Waste Heat Boiler Design
2012 Brimstone Conference
Thank you for your attention
Questions