A Robust SRU Waste Heat Boiler Design - Brimstone …€¦ · 2012 Brimstone Conference • Limits...

62
A Robust SRU Waste Heat Boiler Design Sean M. McGuffie, P.E. Porter McGuffie, Inc. Lawrence, KS, USA [email protected] Dennis H. Martens, P.E. Porter McGuffie, Inc. Lawrence, KS, USA [email protected] Michael J. Demskie Flint Hills Resources Pine Bend, MN, USA [email protected]

Transcript of A Robust SRU Waste Heat Boiler Design - Brimstone …€¦ · 2012 Brimstone Conference • Limits...

A Robust SRU Waste Heat Boiler Design

Sean M. McGuffie, P.E. Porter McGuffie, Inc. Lawrence, KS, USA [email protected]

Dennis H. Martens, P.E. Porter McGuffie, Inc. Lawrence, KS, USA [email protected]

Michael J. Demskie Flint Hills Resources Pine Bend, MN, USA [email protected]

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Michael J. Demskie – Flint Hills Resources - Reliability group

• Sean M. McGuffie – Porter McGuffie Inc. – Senior Engineer

• Dennis H. Martens – Porter McGuffie Inc. - Consultant and Technical

Advisor

Introduction of Authors

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Flint Hills Resources SRU # 5 WHB application – Pine Bend, Minnesota - 320,000 BPD Refinery

• An SRU WHB that was not reliable and the replacement with a reliable WHB

• What made the replacement WHB robust? – CFD analysis results for the replacement WHB

• State-of-the-art CFD analysis information

Introduction

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• 525 LTPD SRU #5 initial startup in June 1993 – 2 pass in single shell kettle type – 600 psi sat steam – refractory and ferrule system

• May 1994 unplanned shutdown – tube leaks – Root cause – Burner vibration with refractory and

ferrule system failure – Replaced 73 of the 400 first pass tubes – refractory and ferrule system

WHB Chronological History

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• May 1999 first planned shutdown – tube leaks – Root cause – refractory and ferrule system separation

from tubesheet face • Anchors burned up • chicken and the egg – cause and effect • Did the separation happen before or after the first tube leak?

– Replaced all 400 tubes in first pass – refractory and ferrule

Original WHB History

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Authors’ experience is for a >2500 °F operating temperature, the SS including 310 SS, anchors for a refractory and ferrule system always “burn off” to close to the tubesheet face or the face of the insulation for the tubesheet as the refractory temperature is above the ~ 2500 °F melting point for the SS anchors and sulfidation metal sulfide melting point of ~ 1650 °F.

Original WHB History

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• July 2002 unplanned shutdown – tube leaks – Root cause – undetermined - lack of consensus – Major corrosion on face of tube sheet (see picture) – Repair weld buildup on tube sheet – Replaced all 400 tubes in first pass – Significant down time and reduced SRU capacity – Two piece removable ferrules installed

Original WHB History

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Original WHB History 2002

Scale removed Sandblasted

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Original WHB History

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Life: installed in 1993 and replaced 2003 = 10 years • 1994 unplanned shutdown - replaced 73 tubes • 1999 first planned shutdown – replaced 400 tubes • 2002 unplanned shutdown – replaced 400 tubes

– significant shutdown and SRU capacity reduction The original WHB essentially had 3 failures in 9 years

with one failure occurring at a planned shutdown

Original WHB History Summary

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• For Reliability FHR decided to replace Original WHB – Fit in existing plant plot space

• Don’t move furnace or condensers

– More robust design – better service reliability – Single pass kettle type – long tubes – Similar process conditions

• Consideration for O2 enrichment

• Sept 2003 - Second planned shutdown – new WHB

Replacement WHB History

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• October 2006 - Unplanned shutdown due to furnace refractory problem - hot spot – Inspected WHB – removed some ferrules – Ferrules in good condition – No corrosion noted – SO FAR SO GOOD – 3 years of operation

• No O2 enrichment operation at this point • O2 operation begins July 2008

Replacement WHB History

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• September 2008 - First planned shutdown – Inspected WHB – removed all ferrules – Ferrules in good condition – No significant corrosion noted (see picture) – Two piece removable ferrules – same design – SO FAR SO GOOD – 5 years of operation

• O2 operation began July 2008 (2 months)

Replacement WHB History

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Replacement WHB 2008

5 years operation

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• September 2012 status – 9 years service – No unplanned WHB shutdowns to date – SO FAR SO GOOD – Significant O2 enrichment service time to date – Next inspection plan is to remove all ferrules and

inspect • Tubesheet - tube ends – length of tube

Replacement WHB

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Installed 2003 and currently in operation 2012 • 2006 Inspection, unit down for furnace repair

– No corrosion or leaks found – no repairs • 2008 first scheduled turnaround - inspection

– No corrosion or leaks found – no repairs The replacement WHB had no unscheduled shut downs

or repairs in 9 years – SIGNIFICANT IMPROVEMENT COMPARED TO ORIGINAL WHB (3/9)

Replacement WHB History Summary

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Please raise your hand if you have one or more SRU WHB’s in your custody

and care

POP Survey of Audience

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Keep your hand raised if you have a WHB that has operated 5 years

without any corrosion or unscheduled shutdowns due to tube leaks

(not just fouling)

POP Survey of Audience

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Keep your hand raised if you have a WHB that has operated 10 years

without any corrosion and unscheduled shutdowns due to tube leaks

(not just fouling)

POP Survey of Audience

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Reoccurring issue of tubesheet and tube end corrosion–leaking tubes – Temperatures > 600 °F for corrosion to occur

• July 2002 failure had severe ferrule ID deposits that reduced flow path to pencil size

• High pressure drop – hot gas bypassing – heating tubesheet • Observed average localized corrosion rate from1999 – 2002

(3 years) was in excess of 50 mil/yr indicating > 850 °F metal temperatures (see corrosion graph)

Original WHB Design/Failure Review

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Original WHB Design/Failure Review

0.001

0.01

0.1

1

10

500 600 700 800 900 1000 1100

Temperature (F)

Mol

% H

2S

1 mil/year2 mils/year3 mils/year5 mils/year10 mils/year15 mils/year20 mils/year25 mils/year30 mils/year40 mils/year50 mils/year

No Corrosion

f

@ 4% H2S 50 mil/yr 850 °F

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Why the high temp at the tubesheet and tube ends? – Refractory and ferrule system possible issues:

• Improper design -heat flux – thickness of refractory • Improper installation – QC - materials and workmanship • Improper dryout procedures • Burner vibration damage to refractory and ferrules • Inadequate operational parameter control • Chicken and the Egg – tube leak or refractory/ferrule • 2002 FHR Root cause – undetermined - lack of consensus

Original WHB Design/Failure Review

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Tubesheet-to-tube inlet end joint possible issues: – 2” thick tubesheet with two grooves – rolled - seal weld

• concern for high tube compression/tension loads on joint?

– Chicken and the Egg – tube leak or refractory/ferrule • Obviously there are a number of possible issues any

one of which could initiate the problem and result in high corrosion rates and leaking tubes

Original WHB Design/Failure Review

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• 5 year turnaround intervals • 20 year life • Avoid unplanned shutdowns due to WHB by:

– Avoiding high temperatures at tubesheet (corrosion) – Avoiding tube-to-tubesheet joint leakage – Avoiding tube damage downstream of ferrules

• Not a significant problem for the original WHB

Robust Replacement WHB Criteria

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Item Original WHB - First Pass Replacement WHB Type 2 Pass - 1 shell - kettle 1 Pass - 1 shell - kettle

Diameter of tubes 2 ¼” OD 2.03” ID 3” NPD pipe 2.9” ID

Number of tubes 400 479 Tube length 15’ – 0” 36” – 0”

Tube specification SA 213-T11 - 12 BWG A 106B Sch 80 Mass flux lb/sec-ft2 4.4 1.75

Tube sheet thick 2” 1 ¼ “ Tube sheet material SA 516-70 SA 516-70

Inlet TS joint Roll and seal weld Full penetration weld Tube projection 7/16” No projection

Original and Replacement WHBs

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Avoiding high temp corrosion – tubesheet/tubes – Used FHR two piece removable ferrule experience

• Installation, inspection and maintenance procedures

– Limit mass flux – limited ferrule inlet pressure loss – Establish/manage max process temperature and flow

• Startup and shutdown considerations

– No tube projection past face of tubesheet – Minimize tubesheet thickness

Robust Replacement WHB Criteria

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Avoiding tube-to-tubesheet joint leakage – Utilized full penetration tube-to-tubesheet weld – Minimized tubesheet thickness – Used thick wall pipe - accommodates FP weld – No tube projection past face of tubesheet – Startup and shutdown considerations (tube stress)

• Rigid tube sheet considerations (tube-to-shell temperatures)

Robust Replacement WHB Criteria

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Avoiding tube damage downstream of ferrules – Limited mass flux

• Limiting turbulence at ferrule outlet • Limiting max heat flux

– Establish/manage max process temperature and flow • Startup and shutdown considerations

Robust Replacement WHB Criteria

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• The operational history of the replacement WHB indicates a robust design was achieved

• FHR decision to analyze the robust design – Determine how design features affect performance

• Maximum heat flux • Tube/Tubesheet operating temperatures • Pressure drop in ferrule assembly

CFD Analysis of Robust WHB

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• To establish the necessary process input, PMI partnered with KPS Technology & Engineering to: – Data mine 6 years of DCS data to determine periods of

interest and maximum WHB duty – Process combustion calculations using Sulsim 7 for

the periods of interest and development of gas composition data

• Consensus selection of representative process conditions for CFD analysis

CFD Analysis of Robust WHB

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Develop process-side model • Fully coupled heat transfer problem

– Requires the inclusion of all assembly geometry

CFD Analysis of Robust WHB

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Initially developed 3 process conditions of interest, based on DCS data

CFD Analysis of Robust WHB

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Velocity results were typical – Recirculation occurs downstream of ferrule – Increased turbulence at this location increases

maximum heat transfer • Primary use of CFD is to estimate the flux multiplier at

this location

CFD Analysis of Robust WHB

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Analyses indicated large margin to established limits – Maximum heat flux was below 50,000 BTU/hr-ft2

– Maximum tubesheet temperature was below sulfidation limit

– Pressure drops were acceptable

CFD Analysis of Robust WHB

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Abandoned remaining cases from DCS data • Performed analyses at maximum established firing

temperature (refractory limit) • Performed analyses at greater mass flows than

recorded in operation • Used results to provide guidance for future operation

CFD Analysis of Robust WHB

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Limits must be based on measurable process parameters – Zone 1 and 2 temperatures – Mass / Volume flow

• Process parameters are used to develop pseudo-duty (product of mass flow and Zone 2 temperature) for each case analyzed

Determining Operational Limits

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Perform curve fit for pseudo-duty versus maximum flux

Determining Operational Limits

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Relate pseudo-duty to operational limits – Maximum flux – Maximum metal temperature

• Algebraically solve for allowable mass flow at a given temperature

• Derate curve based on process measurement limits and unknowns with CFD model

Determining Operational Limits

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Determining Operational Limits

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• CFD is a method of solving the Navier-Stokes Equations

• Equations are nonlinear and require a numerical procedure to solve all but the most trivial problems

Unknowns in CFD

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Due to computing requirements, techniques have only been in use recently – Limits for physics models implemented – Limits on applicability based on experience – Primary simplifying assumption

Unknowns in CFD

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Consideration of turbulence requires grids with a large number of cells with transient integration

• Not suited to engineering applications, only for laboratory environments

• Steady-state solutions incorporate turbulence models – Methods to account for the transient nature of the flow

Primary Simplifying Assumption

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Turbulence models can be sensitive – Grid topology – Model selected – Flow conditions

• Adverse pressure gradients • Recirculating flow • Detached flow

Primary Simplifying Assumption

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Recirculation occurs downstream from ferrule

• Known problem with turbulence models

Primary Simplifying Assumption

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Consider this graph prepared for ASME Tutorial Primary Simplifying Assumption

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• DNB – Most limits developed by nuclear industry • Sulfidation – Temperatures on Couper-Gorman curves

are estimates • Gas bypass – Bypassing can be highly sensitive to

geometry of assembly as installed

Other Limitations in CFD use for WHBs

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Detached Eddy Simulation (DES) and Large Eddy Simulation (LES) are available

• Reduce computational expense from Direct Numerical Simulation (DNS)

• Transient analysis techniques that avoid some of the major limitations of turbulence models

What if More Accurate Information is Needed?

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Dissimilar time-scales between flow phenomena and thermal time constants require difficult procedure

• Two-models must be used and boundary conditions exchanged

• Statistical analysis of output required • Orders of magnitude greater effort

What if More Accurate Information is Needed?

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

What if More Accurate Information is Needed?

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

DES Analysis of WHB Ferrule

Temperatures with Turbulence Model

Temperatures with DES Model

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

DES Analysis of WHB Ferrule

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Through the use of proper design, successful WHBs are possible – Process design and operating limit parameters must

be considered and evaluated for impact on reliability • Mass flux • Operating temperatures • Maximum heat flux

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Guidance for these parameters is not well addressed in any industry consensus document

• Consideration of parameters is, instead, typically left to the SRU licensor

• Evaluation of capital costs versus reliability – Impacts of unscheduled shutdowns are very significant – Repairs often extend shutdowns

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Three Critical areas to consider for WHB designs

1. Avoid high metal temperatures at the tubesheet

2. Avoid tube-to-tubesheet joint leakage

3. Avoid tube damage downstream of the ferrules

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Seven design guidance features to consider and incorporate to address the 3 critical design areas:

1. Ferrule system design – Limit maximum tube end temperature to not more than 615 °F

2. Mass flux – Limits maximum heat flux at end of ferrule and pressure drop through ferrule. Authors suggest 2.5 lb/sec-ft2 for waste heat boilers at higher operating temperatures

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

3. Establish and limit process temperature – design the WHB accordingly and manage operations consistent with these limits

4. Minimize tube projection past the front face of the tubesheet – flush is best practice - no fin

5. Minimize tubesheet thickness – both conductance through the tube sheet and the heat input through the area of the tube holes are important

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

6. Use full penetration welds - or strength welds and rolling – but do not use seal welds for high pressure steam applications or tube end loads

7. Limit pressure drop through the ferrule – associated with # 2 above. Process gas can be driven through a refractory and ferrule or removable ferrule systems which increases the metal temperature and likelihood of corrosion

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• CFD can be used to qualify designs – Determine operational temperatures and fluxes – Compare to limits

• DNB – 50 – 70 kBTU/hr-ft2 - evaluate turbulence multiplier

• Temperature – 600 °F – avoid corrosion • Pressure drop – 0.15 psi at inlet of ferrules - can be a problem

if a significant gas path through the ferrule system is present

– Limitations of CFD results must be understood

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• Common to evaluate failures to “not make the same mistake again”

• Uncommon to evaluate a WHB to determine why it is reliable

• Incorporating knowledge and experience can help prevent unscheduled shutdowns

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• There is not one set of numerical values that are applicable to all WHB applications – For instance, mass flux for large ID tubes may be

unsuitable for small tubes – Understanding how all design parameters influence

the WHB’s performance is critical for reliable designs

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

• “The height of stupidity is doing the same thing the same way and expecting a different result”

• “The height of good engineering is determining what resulted in high reliability and doing the same thing the same way and expecting the same results.”

Conclusions

A Robust SRU Waste Heat Boiler Design

2012 Brimstone Conference

Thank you for your attention

Questions