A Presentation on ARR & Tariff Proposal of WESCO for FY 2007-08 Broad Suggestions/Objections

36
1 A A Presentation Presentation on on ARR & Tariff Proposal of ARR & Tariff Proposal of WESCO for FY 2007-08 WESCO for FY 2007-08 Broad Broad Suggestions/Objections Suggestions/Objections Feburary 13, 2007 Feburary 13, 2007 ether, let us light up our lives. ORISSA ELECTRICITY REGULATORY COMMISSION ORISSA ELECTRICITY REGULATORY COMMISSION

description

ORISSA ELECTRICITY REGULATORY COMMISSION. Together, let us light up our lives. A Presentation on ARR & Tariff Proposal of WESCO for FY 2007-08 Broad Suggestions/Objections Feburary 13, 2007. - PowerPoint PPT Presentation

Transcript of A Presentation on ARR & Tariff Proposal of WESCO for FY 2007-08 Broad Suggestions/Objections

Page 1: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

1

A A Presentation Presentation

on on ARR & Tariff Proposal of ARR & Tariff Proposal of WESCO for FY 2007-08WESCO for FY 2007-08

BroadBroad Suggestions/ObjectionsSuggestions/Objections

Feburary 13, 2007Feburary 13, 2007

Together, let us light up our lives.

ORISSA ELECTRICITY REGULATORY COMMISSIONORISSA ELECTRICITY REGULATORY COMMISSION

Page 2: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

2

TARIFF FILING BEFORE THE COMMISSION (FY 2007-08)

ITEMS WESCO

Rev. Req. (Rs.Cr.) ( Including Reasonable Return & excluding Previous Losses) 1266.13

Power Purchase (MU) 6000

Anticipated Sale (MU) 4140.00

LT 890.00

HT 1560.00

EHT 1690.00

Distribution Loss (%) 31.00%

Collection Efficiency (%) 95.00%

AT&C LOSS (%) 34.45%

Exp. Rev.at Exist. Tariff (Net) (Rs.Cr.) 1224.85

(Exp. Rev+Misc.Rev.) at Exist. Tariff (Net) (Rs.Cr.) 1227.85

Revenue Gap ( +/- ) (Rs. Cr. ) -38.2800

Previous Losses (Rs. Cr. ) -202.37

Revenue Gap ( +/- ) (Rs. Cr. ) including past losses at Existing Tariff -240.65

Exist.Overall Average Tariff (Net) (p/u) 298.00

Exist.LT Average Tariff (Net) (p/u) 232.00

Exist.HT Average Tariff (Net) (p/u) 318.00

Exist.EHT Average Tariff (Net) (p/u) 314

NOTE: WESCO has not proposed any change in RST but to bridge the Revenue Gap through increase in tariff, reduction in BST, Govt. subsidy etc.

Page 3: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

3

Data SourcesData Sources

• As stated by WESCO :

– The Accounts up to September 2005 have been audited as

per Companies Act

– The accounts up to March 2006 have been audited as per

Income Tax Rules

– It has relied upon the audited accounts upto September

2005 as per Companies Act and accounts upto March 2006

as per Tax Audit for preparation of ARR

Page 4: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

4

Category FY 2005-06 FY 2006-

07(April-Sept)FY 2006-07(Prop)

Growth (%)FY 2007-08(Prop)

Growth (%) Remarks(Basis)

LT 693.760 374.380 786.000 13.300 890.000 13.230

Domestic 468.554 256.569 529.600 13.030 611.100 15.390 Impact of electrification under RE programme

Irrigation 47.201 21.340 60.000 27.120 70.000 16.670 Metering of Irrigation consumers

HT 1,033.120 598.707 1,234.000 19.440 1,560.000 26.420 Trend of FY 05-06& growth

from existing and new consumers

Large Ind. 641.689 378.389 787.000 22.650 1,046.600 32.990 Growth from existing and 13

new1MVA consumers

Power Int. 43.416 26.700 56.000 28.980 88.000 57.140 Addition of 1 new consumer

&enhancement of load

Mini Steel 214.781 119.429 238.000 10.810 265.000 11.340 Addition of 1 new consumer

EHT 878.394 474.145 980.000 11.570 1,690.000 72.450 Trend of FY 05-06& growth

from existing and new consumers

Large Ind. 454.233 133.141 285.000 (37.260) 350.000 22.810 Increase in contract

demand

Heavy Ind. 132.567 243.043 495.000 273.400 1,124.000 127.070 Adddition of 2 new

consumers

Power Int. 20.838 3.486 8.000 (61.610) 18.000 125.000

Spl. Tar. 93.181 - (100.000) (79.060) - -

Total Sale(MU) 2,606.276 1,447.232 3,000.000 15.150 4,140.000 38.000

Power Purchase(MU)

4,188.510 2,263.710 4,600.000 9.824 6,000.000 30.435

Energy input has beenestimated based on theestimated consumption of4140 MU and distribution lossof 31%.

Dist. Loss (%) 37.800 34.780 31.000

Growth(%) in Sale(MU) as proposed by WESCO

Page 5: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

5

Tariff StructureTariff Structure

• WESCO has proposed –

• No change in tariff structure

• No special tariff should be allowed to the industries having own CPPs

• Demand charge of Rs 200/- per KVA to be applicable for consumers having contract demand 70 KVA and above under HT Industrial (M) and GP category.

• The provisions of tariff applicable to large industries should be made applicable to above consumers.

• Fixed charges for LT Industrial(S), LT Industrial(M) & PWW to be levied on KVA in place of KW.

• Demand charges @ 120% of demand charges to be made applicable on MD recorded along with applicable energy charges for CPPs

Page 6: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

6

Tariff Structure .. Contd..Tariff Structure .. Contd..

• The minimum demand charges concept i.e. 80 % of CD should not be made applicable to CPPs

• The over drawl energy should be considered in cumulative basis for all DISTCOs together instead of considering DISTCO wise over drawl till to Intra-State ABT is implemented.

• Rebate @ 2% for payment of BST bills within three working days from the date of presentation of bill.

• Approved the annual revenue requirement for FY 07-08 including amortisation of regulatory assets and tring of uncovered gap for FY 06-07.

• Bridge the Revenue Gap through combination of increase in Retail Supply Tariff, Reduction in Bulk supply Tariff, Government Subsidy etc.

Page 7: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

7

BROAD TARIFF BROAD TARIFF RELATED ISSUES RELATED ISSUES

RAISED BY OBJECTORS RAISED BY OBJECTORS ( To be addressed by the ( To be addressed by the

Licensees )Licensees )

Page 8: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

8

Legal Issues• The ARR application filed by the licensee is not tenable under

law due to the following defects:– The licensees account has not been audited for FY 2004-05

and 2005-06. – The licensee has filed the application to confuse the

consumer public without disclosing the purpose for such filing.

– The interested persons are being kept in dark and not able to file effective objection and as such the purpose of such exercise has been frustrated and contrary to law and principle of natural justice.

– The procedure/method so adopted by the Commission be made simple and inexpensive.

– The licensee has failed to provide details as required under regulations to the Commission for consideration of his application as such the application may be rejected.

Page 9: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

9

Issues raised by Objectors

• Distribution Loss:

– The licensee has miserably failed to arrest high Distribution loss on

account of unauthorized use of power.

– Distribution loss should be calculated by taking ratio of units lost in

distribution system excluding EHT sale.

– Since, a large chunk of consumers are still unmetered and having

defective meters, the declared loss by the licensee is unrealistic.

• Collection Efficiency:

– The consumers are not to be burdened for in-efficiency of licensees

to collect their energy dues from consumers every year.

Page 10: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

10

Issues raised by Objectors.. Contd..

• AT&C Loss– AT&C concept should not be implemented as it hides the inefficiency

of the Licensee. • Power Factor Incentive/ Power Factor Penalty

– Power Factor incentive has to be calculated upto two decimal fraction – Power factor penalty is levied for power factor less than 90% &

power factor incentive should be given for power factors above 90% at the same rate.

– Power factor penalty for the small and medium industry consumer may be introduced.

• Cross Subsidy– Bench Marks for gradual reduction of cross subsidy may be fixed

from this year to achieve Zero level by 2009-10.

Page 11: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

11

Issues raised by Objectors.. Contd..

• Quality of Services:

– The industries are put to financial burden for being unable to

achieve 80% Load Factor due to the inability of the licensee to

supply proper quality power.

– Due to slow up gradation of the system and sub-station, the new

industries are finding difficult to get power connection.

– Voltage/frequency fluctuation –The accountability should be fixed

with the License in terms of financial compensation for the

fluctuation beyond standard norms.

Page 12: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

12

Issues raised by Objectors.. Contd..

• Consumer Classification

– Electricity tariff for poultry may be at par with agriculture.

• The State Government has decided to classify poultry as agriculture

– Reliance Telecom Ltd. and Reliance Infocomm Ltd. - Electricity energy may be charged at Industrial Rates instead of General Purpose rates to the IT & ITES Industries operating in the State

– BSNL Orissa Circle, Bhubaneswar• BSNL may be treated as an industrial undertaking as power is substantially

utilized as motive force for Industrial purpose and without supply of power it is not possible to run the Telecom services.

• The BSNL is coming under the purview of industry as per the verdict of the Hon’ble Supreme Court in several cases.

• So also as per the finance Act, 2002 w.e.f. 01.4.03, the business of providing Telecommunication Services has been declared as industrial undertaking.

Page 13: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

13

Issues raised by Objectors.. Contd..

• Financial Issues

– In absence of the audited balance sheet and report of the auditors it is not possible for the objector to make proper observation on financial matters.

– WESCO even could not infuse working capital fund either from their own resources or from their Banker as a result of which WESCO is funded through GRIDCO dues bearing interest/DPS @24% per annum. Such higher cost is being borne by the consumer ultimately.

• Interests attributable to bonds

– The interest attributed to bonds against arrear of power purchases cost and capital value of bonds are not payable by consumers.

Page 14: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

14

Issues raised by Objectors.. Contd..

• Interests towards securitization – The interest towards securitization as well as capital of securitization

should not be passed on to the revenue requirement for tariff proposes.– Infusing additional funds - The licensee may be directed to infuse

additional funds as may be required to turn around the sector.– Regulatory assets - Any losses that the distribution licensee likes to incur

after complying with the orders of the Commission, can only be considered for the purpose of computing the Regulatory Assets.

– Employees cost - It is suggested that an increase of about 6% over last year’s provision may be allowed while fixing the employees cost for the FY 2007-08.

– Past Losses - Past losses should be paid through tariff by consumers only if these losses have been incurred due to reasons beyond the control of licensee and in spite of licensee having performed as per bench marks fixed by OERC.

Page 15: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

15

Issues raised by Objectors.. Contd..• Computation of Load Factor

– Load factor or consumption ratio to be determined on the basis of Maximum Demand recorded in the meter in accordance with Regulation 2(y) of the OERC Distribution (Conditions of Supply) Code, 2004.

– It will be just and proper to calculate the load factor on the basis of Maximum Demand or 80% of the Contract Demand whichever is higher.

– A lower load factor upto 50% may be prescribed for the period of annual maintenance, which will be jointly decided by the licensee and the consumer.

– The guaranteed load factor of 80% should be determined on an annual basis.

– Load factor may be computed separately for peak and off peak hours and the overall load factor be computed by integrating the above data.

– The LF be calculated based on the actual period of availability of unrestricted power supply during the month.

– The MD during the off peak hours should not be considered for computing the LF.

– Any consumer availing LF incentive is higher remunerative in the interest of financial viability of WESCO and should not be penalized for over drawl.

Page 16: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

16

Issues raised by Objectors.. Contd..

• Tariff Issues

– The gap of electricity charges between high consumption and low consumption should be reduced to minimum level, which will discourage theft of energy.

• Contract Demand

– Time frame for reducing the contract demand may not be imposed.

• Provision for Rebate

– Seven clear days may be given from the receipt of the bill to get the rebate on prompt payment.

• Emergency Supply to CPPs

– The proposal of demand charges for emergency drawal to CPPs should be rejected.

– Emergency power requirement for CPP/Generating stations are very low and for short duration only, it is not at all justified to propose demand charges for emergency power to CPP’s.

Page 17: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

17

Issues raised by Objectors.. Contd..

• General Issues– The additional costs actual or estimated on account of the

inefficiency/inability of licensee should not be passed on to the consumers through the tariff, either as a direct cost or a so called Regulatory Asset.

– Any cost due to additional power purchase, beyond the allowable distribution loss should not be included in the ARR of the licensee.

– A penalty up to a limit of 20% in excess use of the electricity than the contract demand during peak hours may be introduced.

– Increase in the reconnection charge – no justification.• The charges to the consumers should reflect the cost to the licensee.

– DPS for LT consumers – no justification.• A LT consumer loses the rebate of 10 p/kwh in a month. Additional

levy of DPS is thus unnecessary and un reasonable.

Page 18: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

18

Issues raised by Objectors.. Contd..

– The demand charges may be calculated prorate if the total of period of interruption (causing loss of production due to interruptions) and the pre-arranged shut downs availed on intimation, or statutory power cuts, exceeds 60 hours in a moth.

– The street light burning hours should be on actual time i.e. for 10 hours a day.

– The ceiling limit of 10% of total consumption for the colony consumption should be waived

– Electricity charges for the colony consumption should be at per with domestic rate because the electricity used in the colony is never used for any industrial purpose.

– Special tariff for running of FOUNDRY –A special tariff structure @50% of the existing tariff, may be introduced for running of the furnaces.

Page 19: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

19

Issues raised by Objectors.. Contd..

– Revision of ARR/Reduction of Tariff – The tariff revision application

indicates that the petitioner had made a cash profit of about Rs.43.533

crores during the year 2006-07 in spite of having heavy TD losses, high

financial losses and DPS. The petitioner ought to have come up with the

proposal for reduction in tariff.

– Demand charges –

• The demand charges may be calculated on prorate basis for the

actual period of power availability.

• The demand charges may be exempted if there is power interruption

for more than 50 hours in a month.

– To have a uniform tariff for all consumers based on commercial principle

of cost plus benefit basis.

Page 20: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

20

Issues raised by Objectors.. Contd..

– The maximum hydel power is produced in WESCO.

• Hence the consumer of WESCO may be given benefit of the same by a lower tariff.

– Separate Tariff may be introduced for Specified Public Purpose consumers under private sector especially for Educational Institutions.

– Service Connection charges - It is suggested that a realistic amount in place of Rs500/- may be fixed so that the Licensee can procure quality materials in time.

– Uniform rate may be introduced for LT (domestic) without any slab system.

– Tariff Revision - The proposed tariff revision is not at all desirable as there is no improvement in services.

Page 21: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

21

Issues raised by Objectors.. Contd..

• OERC Regulations

– During the initial period of supply, which is prescribed for five years, an Exit Clause should be provided since the consumer has right to choose it’s supplier.

– Customer’s Security Deposit – Consumers may be permitted to furnish bank guarantee or to open revolving letter of credit in favour of licensee in lieu of security deposit as it becomes extremely difficult for small and medium scale industry to invest such huge sum for purchase of power in cash.

– Period of agreement – The validity of power agreement is presently 5 years, should be reduced to 1 year in view of the changing market scenario and fluctuating market demands.

Page 22: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

22

BROAD TARIFF BROAD TARIFF RELATED ISSUESRELATED ISSUES

Page 23: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

23

The Following Areas have not been adequately addressed

• D.T. wise Energy Audit & Consumer Indexing for loss reduction

• Spot Billing & Collection for improvement of Collection Efficiency

• Repair & Maintenance

• Arrear Collection & Liquidation of power purchase dues

• Man power deployment ( Both Executive & Non Executive ) for

reducing AT & C Loss

• Non Investment in system improvement for Quality Supply

Page 24: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

24

2005-06 2006-07 2007-08A. Expenditure Tax Audited Approved Proposed

Cost of Power Purchase 604.55 610.17 948.12Cost of Transmission 101.2Employee costs 77.79 80.16 109.44Repair & Maintenance 10.19 24.25 28.16

Administrative and General Expenses 17.42 15.78 23.77

Provision for Bad & Doubtful Debts 51.71 24.04 61.24Other expenses 23.36Depreciation 17.93 17.02 18.56

Interest Chargeable to Revenue including INT on SD 24.25 31.43 60.04Carrying cost 3.37 9.66Sub-Total 827.2 907.41 1258.99Less: Expenses capitalised 0.97 3.38 2.60Total expenses 826.23 904.03 1256.39

B. Special appropriation

Amortisation of Regulatory Asset 141.2Truing up of Revenue gap for FY 2006-07 61.17Contingency reserve 0.42 1.96Total 0.42 204.33

C Return on equity 7.78 7.78TOTAL(A+B+C) 826.65 911.81 1468.5

D. Less Miscellaneous Receipt 31.58 17.19 3.00E. Total Revenue Requirement 795.07 894.62 1465.50F. Expected Revenue(Full year ) 786.65 961.51 1224.86G. GAP(+/-) -8.42 66.89 -240.64

REVENUE REQUIREMENT OF WESCO FOR 2007-08 ( Rs in Crore )

Page 25: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

25

Revenue Requirement for 2007-08 ..Contd..

• Bifurcation of the amount towards cost of power purchase and cost of transmission for FY 2007-08 has not been furnished. The same may be submitted.

• Actual expenditure against the above heads of expenditure for first six months of FY 2006-07 has not been provided by the licensee. The same may be submitted.

• The reason for making higher provision in employee cost of Rs.109.44 crore proposed for FY 2007-08 as against the approved amount of Rs.80.16 crore for FY 2006-07 and Rs.77.79 crore appeared in the tax audit report needs to be justified.

• The proposed rise in A&G expenses for an amount of Rs 23.77 crore for FY 2007-08 as against the approved amount of Rs 15.78 crore for FY 2006-07 and Rs. 17.42 crore for the FY 2005-06 based on Tax Audit reports needs to be explained.

Similarly, the quantum proposed for interest amounting Rs.60.04 crore for FY 2007-08 is nearly Rs.29 crore more than the approved amount of Rs.31.43 crore for FY 2006-07 and nearly Rs. 36 crore more than the tax audited figure for the FY 2005-06. This needs to be explained.

• It may be justified as to why the amortization of regulatory asset and truing up of revenue gap for the FY 2006-07 be allowed and if so how far it is reasonable.

Page 26: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

26

Approved ActualFY 1999-00 14.43 15.90FY 2000-01 14.43 10.25FY 2001-02 13.62 10.12FY 2002-03 15.33 8.04FY 2003-04 16.89 16.27FY 2004-05 17.28 12.85FY 2005-06 21.30 10.19

FY 2006-07 24.25

24.25 (Estimate)

FY 2007-08 28.16 (Prop)

R&M Expenses (Rs. Cr.)

Note: (i) Cause of declining expenditure in R&M ??

(ii) Non utilisation of the approved amount towards R&M is affecting Quality of Supply & increasing interruption.

Page 27: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

27

Fixed Assets addition during the Financial Years

Approved (Rs. in Cr.) Actual(Rs. in Cr.)

FY 2001-02 37.04 18.24

FY 2002-03 55.26 21.32

FY 2003-04 35.43 35.12

FY 2004-05 74.48 71.74

FY 2005-06 85.4117.71

(Tax audit)

FY 2006-07 (Proposed)

68.0631.90 (Revised

Estt.)

FY 2007-08 (Proposed)

87.08 

Note: Why the Gap Between the approved and actual figures of various heads of expenditures have not been adjusted in the Revenue Requirement filing ?

Page 28: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

28

Provision for Bad & Doubtful Debt in Rs. Cr.

  Approved Actual

1999-00 10.60 48

2000-01 12.65 57.1

2001-02 13.73 75.84

2002-03 15.42 78.85

2003-04 17.96 102

2004-05 18.50 50.56

2005-06 21.18 51.71 (Tax Audit)

2006-07 24.04 53.88 (Est.)

2007-08 61.24 (Prop.)

NB : In the audited A/C upto FY 2005-06, the licensee has made huge amount of provision towards Bad & doubtful debt as against the normative level of 2.5% on sale revenue approved by the Commission . This results an inflated loss for the year. The reason of higher provision has neither been explained nor supplied by audited data.

Page 29: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

29

Miscellaneous Income & SMD

• Miscellaneous Income– At the time of determination of RST for 2006-07 for the purpose of

computation of misc. income the latest available audited data for FY 2003-04 was taken into consideration. Now, that audited accounts for FY 2004-05 and accounts upto March 2006 as per tax audit are available and even after deduction of DPS from the misc. income for FY 2004-05 as per audited account is much higher than what has been approved for 2006-07.

• Determination of Simultaneous Maximum Demand (SMD)– Whether increase/decrease in energy consumption has got direct

link with SMD. • Comments on the above subjects are invited for determination of tariff.

Page 30: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

30

Business Plan VRS. ARR

• A comparison of figures in Business Plan

and ARR from FY 2004-05 to 2007-08 with

regard to Distribution Loss, Collection

Efficiency and AT&C Loss, present two

different sets of figures with wide margins as

follows :

Page 31: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

31

WESCO ARR FILING VRS BUSINESS PLAN

 Dist. Loss (%) Col. Efficiency (%) AT&C Loss (%)

FY 2004-05 (ARR) 36.38 92.06 41.43

FY 2004-05 (B.Plan) 34 90 40.6

FY 2005-06 (Prop) 36.32 92.4 41.16

FY 2005-06 (B.Plan) 31 92 36.52

FY 2006-07 (Prop) 33 94 37.02

FY 2006-07 (B.Plan) 28 94 32.32

FY2007-08 (Prop) 31 95 34.45

FY2007-08 (B.Plan) 25 96 28

Page 32: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

32

Finance related issues

• Investment details have not been specified.

• Capital Works In Progress - capability of huge investment

proposal has not been justified.

• Action plan for settlement and collection of arrears

outstanding with the consumers have not been spelt out.

• No Action Plan for establishment of Special Police Station &

Special Court has been given.

Page 33: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

33

Issue of Regulatory Assets • National Tariff Policy on Regulatory Assets stipulates

– Pass through of past losses or profits should be allowed to the extent caused by uncontrollable factors.

– The facility of a regulatory asset should be done only as exception, and subject to the following guidelines.

– should only include natural causes or force majeure conditions – Carrying cost of Regulatory Asset should be allowed to the utilities – Recovery of Regulatory Asset should be time-bound and within a

period not exceeding three years at the most and preferably within control period.

– The use of the facility of Regulatory asset should not be repetitive.• Does the claim of Licensee conform to the National Tariff Policy?• Whether the past losses be treated as regulatory asset and allowed in

tariff along with carrying charges?• Whether the interest cost an account of the regulatory asset should be

allowed to be recovered as a pass through.

Page 34: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

34

Average Revenue Billed (P/U) Vrs Actual as filed by WESCO in ARR filings

Voltage Category

2002-03 2003-04 2004-05

2005-06 (April’05 - Dec, 05) Actual

2005-06 (April’05-March’06) (Actual)

2006 - 07 (April -

Sept,06) (Actual)

2007-08 (Licensee’s Estt.)

LT 242 243 248 248.5 233 224 232

HT 383 367 338 328 321 329 318

EHT 318 277 270 350.5 328 342 314

Overall 299 281 282 305.8 300 306 29834

Note: What is the cause for reduction of LT/HT/EHT average between (April'05-March'06) & (April'05-Dec,05) ? Financial Impact on account of reduced unit rate at LT, HT & EHT works out to Rs. 13.6, 7.23 Cr. and 19.76 cr. respectively. This needs to be clarified by the Licensee.

Page 35: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

35

Power Purchase Cost and Revenue billed in Rs.cr

 FY 2002-03

FY 2003-04

Difference w.r.t previous FY

FY 2004-05

Difference w.r.t previous FY

FY 2005-06

Difference w.r.t previous FY

Cumulative Difference

BST bill (Rs cr.) 452.26 509.97 57.71 543.39 33.42 569.69 26.3 117.43

EHT/HT billing 438.38 470.26 31.88 570.71 100.45 618.78 48.07 180.4

LT billing 187.88 188.37 0.49 166.54 -21.83 176.84 10.3 -11.04

NOTE : The above table indicates that the billing in HT/EHT is much higher through the years than the rise in BST bill whereas, the growth in LT is negative which indicates incremental Distribution loss and poor collection efficiency at LT.

Page 36: A  Presentation  on  ARR & Tariff Proposal of  WESCO for FY 2007-08 Broad Suggestions/Objections

36