A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

download A PRACTICAL GUIDE FOR  ENVIRONMENTAL PROTECTION &   ENHANCEMENT WORKS

of 136

description

Flow chart for Environmental Impact Assessment / Preliminary Environmental Impact Assessment Report.

Transcript of A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    1/136

    Arahan Teknik (Jalan) 16/03; (Pindaan 2008)

    JKR 21300-0002-09

    JABATAN KERJA RAYA

    Cawangan Kejuruteraan Jalan & Geoteknik

    Ibu Pejabat JKR Malaysia

    Peti Surat 18 & 19, Menara Tun Razak

    Jalan Raja Laut50350 Kuala Lumpur

    A PRACTICAL GUIDE FOR

    ENVIRONMENTAL PROTECTION &ENHANCEMENT WORKS

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    2/136

    i

    GREEN MISSION

    Being the key implementing agency for governmentsprojects, Jabatan Kerja Raya (JKR)

    is committed and dedicated to steer the organization and safeguard the environment by

    adopting the following principles:-

    Natural resources protection and enhancement

    Resource efficiency

    Sustainable consumption

    Sustainable construction

    Adherence to relevant laws and regulations

    In doing so, Jabatan Kerja Raya (JKR) is guided by their environmental management

    system (ISO 14001 EMS) particularly during the construction stage to minimize and

    mitigate impacts to the environment through controlled site clearing, protection andmaintenance of slopes, waste minimization and management and compliance to legal

    requirements.

    In moving forward, JKR is committed in ensuring that all projects are developed in a

    sustainable manner, focus shall be given at planning stage in order to take into account the

    need to identify and mitigate environmental impacts for developments in Environmentally

    Sensitive Areas (ESAs) or within its vicinity. Protection of ESA is one of the key steps

    towards protecting our countrys natural resources.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    3/136

    ii

    PREFACE

    In line with the MS: ISO 14001 requirement, a continual improvement of the system must

    be done to ensure success and effectiveness of environmentally sustainable approach in

    construction. To produce a clear and comprehensive tender document, revision of JKRTender Documents on environment protection and enhancements has been done by

    itemising the environmental works into the Bill of Quantities to allow contractors to tender

    a realistic price. Arahan Teknik (Jalan) 16/03, produced in 2004, provided changes to the

    items in the Tender Document with regards to the Condition of Contracts, Instruction to

    Tenderers, Specification to Environmental Protection and Enhancements, Preamble to Bill

    of Quantities, Need Statement, Bill of Quantities and Drawings.

    In 2006, a committee comprising multi-disciplinary personnel was set up to revise the

    Arahan Teknik (Jalan) 16/03. Changes have been made in accordance to problems

    encountered and inadequacies of the previous Arahan Teknik. The overall improvement is

    aimed to ensure contractors understand the application of the environment protection

    works that they have tendered in the Bill of Quantities. Notwithstanding the importance of

    other technical agencies requirements to protect the environment, some parts have been

    added such as the preparation of Erosion and Sediment Control Plan (ESCP) and

    management of disposal site for surplus material as part of the latest EIA requirements.

    Drawings of mitigation works have been revised and amended. The revised Arahan

    Teknik (Jalan) 16/03 is made applicable, not only to road projects, but to all projects in

    JKR. It is important that all parties involved in the construction industry, be made aware of

    the latest government requirements in environment protection to ensure our nation has the

    capacity to be sustainable in the long term future.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    4/136

    iii

    ACKNOWLEDGEMENT

    This revised Arahan Teknik (Jalan) 16/03 was prepared by a sub-committee comprising

    thirty-seven (37) multi-disciplinary personnel as listed below:-

    (1) Ir. Cheong Pui Keng Pengarah, JKR Cawangan Alam

    Sekitar dan Tenaga (CAST)

    (2) DatoIr. Dr. Hj. Roslan bin Md Taha Pengarah, JKR Negeri Sembilan

    (3) Ir. Hj. Abu Harith bin Shamsuddin KPPK, JKR Cawangan

    Kejuruteraan Senggara

    (4) Ar. Cik Lee Bee Chew Retired, (formerly Pengarah, JKR

    Cawangan Alam Sekitar dan

    Tenaga.

    (5) En. Meor Mohamed Haris bin Meor Hussein KPP, JKR Perak (Jalan).

    (6) En. Muhamad Rahimi b Abdullah KPPK, Cawangan Kej. Jalan &

    Geoteknik

    (7) Pn. Hjh. Sujatiah binti Tamrin PPK, Cawangan Jalan

    (8) Pn. Hjh. Faridah binti Abdul Rashid KPP, Kementerian Kewangan

    (formerly JKR Cawangan Kontrak

    dan Ukur Bahan)

    (9) Tn. Hj. Abdul Rahman bin Idris KPP, JKR WPKL

    (10) Pn. Nor Shahrene binti Mohd Ibrahim KPP (Arkitek). JKR Cawangan

    Pengurusan Korporat

    (11) En. Amran bin Majid Juruukur Bahan, Cawangan

    Kejuruteraan Ukur Bahan

    (12) Pn Emmy Sherina binti Ismail Hashim Jurutera Senggara, JKR DaerahKuala Terengganu

    (13) En. Nasrollah bin Mohamad PP, (ECER)

    (14) En. Hamizan bin Husain PP, Cawangan Kej Mekanikal

    (15) En. Mohd Nor Rashidi bin Abd Jalil PP, Cawangan Pengurusan

    Korporat

    (16) En. Mohd Aznan Shukri b Mohamed Safian Jurutera Bangunan, JKR Hilir

    Perak

    (17) Pn. Nurazaini binti Mokhtar PPK, Jabatan Pengairan dan

    Saliran

    (18) YM Raja Nur Ashikin binti Raja Zainal ERE Consulting Group Sdn. Bhd.

    (19) Pn. Geetha P. Kumaran Europasia Eng. Services Sdn.Bhd. & ENSEARCH

    (20) En. Romzi bin Mat Zainul ATZ Consult Sdn. Bhd. (formerly

    HSSI S/B)

    (21) En. Shamsul Azhar bin Ismail Wiranda (M) Sdn. Bhd.

    (22) En. Mohd Zikri bin Azmi Wiranda (M) Sdn. Bhd.

    (23) En. Mohd. Khusairi b. Mohd. Isa KPP, CAST

    (24) Cik Siti Nor bt. Othman PP, CAST

    (25) Pn. Siti Noor Aiza bt. Abd. Aziz PP, CAST

    (26) Cik Nurazura bt. Ali PP, CAST

    (27) En. Azizul b. Hashim PP, CAST

    (28) Pn. Hawa Liza bt. Zahari PP, CAST(29) En. Khairol Nazri b. Abdul Khaiyom PP, CAST

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    5/136

    iv

    (30) En. Mohd. Fauzie b. Ismail PP, CAST

    (31) Cik Aida Elyana bt. Jamil PP, CAST

    (32) En. Khairul Amir b. Isahak PP, CAST

    (33) En. Mohd. Amir b. Hashim PP, CAST

    (34) Pn. Noor Azizah bt. Majid PP, CAST

    (35) En. Mohd. Eikmal b. Ahmad PP, CAST(36) Pn. Zuraiha bt. Zainuddin@Abd Aziz PP, CAST

    (37) Pn. Izmazurin bt. Ramli PP, CAST

    Finally, the publisher wishes to express its gratitude to the above committee members for

    their valuable contributions and preparation of this guide.

    Published by:-

    Unit Standard & SpesifikasiBahagian Penyelarasan & Khidmat Sokongan

    Cawangan Kejuruteraan Jalan & Geoteknik

    Ibu Pejabat JKR Malaysia

    Tingkat 14, Menara Tun Razak

    Jalan Raja Laut

    50350 Kuala Lumpur

    Reproduction of any part from this publication may be made subject to due

    acknowledgement of the source. However, the publisher does not accept any responsibility

    for any consequences arising from the use of the information within this guide.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    6/136

    v

    A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION &

    ENHANCEMENT WORKS

    CONTENTS PAGE

    CHAPTERS

    1.0 Introduction 1

    2.0 Environmental Requirements 5

    3.0

    Contractual Requirements 14

    4.0 Specifications 16

    5.0 Method of Measurement 35

    6.0 Bill of Quantities 71

    7.0 Best Management Practices 82

    8.0 Standard Drawings and Figures 91

    REFERENCES 104

    APPENDIX 1 105

    Standard Specifications for Building Works (2005 Edition):-

    SECTION A: PRELIMINARIES AND GENERAL CONDITIONS

    AND SECTION C: EXCAVATIONS AND EARTHWORKS

    APPENDIX 2: Government Requirements (Need Statement) 111

    (Term of Reference) (For Design and Build Projects Only)

    APPENDIX 3: Standard Report Format for :- 120

    (i) Environment Management Plan (EMP)

    (ii) Environment Quality Report (EQR)

    (iii)

    Environment Management Audit Report (EMAR)

    (iv) Closure Audit Report (CAR)

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    7/136

    1

    CHAPTER 1

    INTRODUCTION

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    8/136

    2

    CHAPTER 1.0: INTRODUCTION

    1.0 Introduction

    Environmental protection and conservation is gaining more significance in the long termnational development plan. In this regards, Malaysia as a country, has reaffirmed its

    commitments towards the protection and conservation of its environment as stated in the

    National Policy on Environment, National Physical Plan (NPP) and prevailing

    Malaysia Plans.

    In summary, the National Policy on Environment aims for continuous economic, social

    and cultural progress and enhancement of the quality of life of Malaysians, through

    environmentally sound and sustainable development.

    The main goal of the NPP is to create an efficient, equitable and sustainable national

    framework that will guide future development of the country. It is an important piece ofdocument as it provides the spatial element in development planning as well as spells out

    policies that determine the direction of physical development and conservation areas

    within Peninsular Malaysia. It also identifies areas that need to be conserved and protected

    via a ranking system. These areas are called Environmentally Sensitive Areas (ESA).

    Such identification will greatly assist any project proponent (government or private sector)

    in evaluating and determining the feasibility of some projects at macro or national level.

    In line with the nations aspirations in protecting the environment, JKR has formulated

    and implemented the JKR Green Mission and has an Accredited MS ISO 14001

    since 5thNovember 2002. The main objective of the document is to protect and enhance

    the environment by ensuring that projects are being implemented in a sustainable manner

    and with the least impacts to the environment.

    1.1 Objectives

    This Revised Arahan Teknik shall aim to attain the following objectives:-

    To ensure that the JKR EMS ISO 14001 requirements in terms of environmental

    protection measures are properly incorporated in the preparation of the tender

    documentand subsequently implementedduring the planning, construction andoperational stages of the project.

    To guide users on the requirements pertaining to environmental protection,mitigation and enhancement measures in the preparation of tender document.

    1.2 Method of Procurement

    This document is applicable for both conventional and design and build contracts. A

    typical example of the process flow for both types of contracts can be referred to in the

    JKRs Quality Management System (QMS).

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    9/136

    3

    1.3 Limitation

    This document may have limited use for costing and environmental protection

    measures purposes in the preparation of Bill of Quantities (BQ) for Projects that are

    subjected to the following:

    Detailed Environmental Impact Assessment Study (particularly for projects that

    involve reclamation;

    Marine-related projects such as jetties, marina, coastal protection structures or any

    structure that extends out into the sea; and

    Projects located within areas identified as Environmentally Sensitive Areas (ESAs)such as wildlife sanctuary, wetlands, marine parks and national parks.

    For projects identified above, more specific environmental protection measures may be

    required in order to minimize impacts to the environment.

    1.4 Format of Document

    This Revised Arahan Teknik (Jalan) 16/03 has been divided into eight chapters addressing

    the various components which form part and parcel of the tender document preparation

    process.

    In addition to the introductory material in this section, the document contains:-

    Chapter 2.0 Environmental Requirementsin which environmental requirements

    at various project development stages will be described. Relevantguidelines are also tabulated for reference purposes.

    Chapter 3.0 Contractual Requirements in which environmental requirementspertaining to different methods of procurement will be presented.

    Chapter 4.0 Specifications in which environmental protection works are

    elaborated to assist users in preparing tender document as well as

    ensuring compliance to the relevant legislations and regulations.

    Chapter 5.0 Method of Measurement (MOM) in which elaboration of methods

    of measurement for items stated in the BQ will be measured. Itdescribes the items, unit and measurement for payment.

    Chapter 6.0 Bill of Quantities (BQ) in which environmental protection works

    will be itemized in terms of unit, quantity, rate and cost. It will cover

    both non-physical works and physical works.

    Chapter 7.0 Best Management Practices (BMP)in which samples of mitigating

    measures that have been implemented successfully at site are shown.

    Chapter 8.0 Standard Drawings and Figuresin which preliminary drawings and

    figures of mitigating measures such as silt trap, sediment basins, checkdams and fuel storage skid tanks are shown.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    10/136

    4

    APPENDIX 1

    Standard Specifications For Building Works (2005 Edition):- SECTION A :

    PRELIMINARIES AND GENERAL CONDITIONS AND SECTION C :

    EXCAVATIONS AND EARTHWORKS

    Appendix 2 Government Requirements (Need Statement) (Term of Reference)

    (For Design and Build Projects Only)

    Appendix 3 Standard Report Format for Environmental Management Plan

    (EMP), Environmental Quality Report (EQR), Environmental

    Monitoring and Audit Report (EMAR) and Closure Audit Report

    (CAR)

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    11/136

    5

    CHAPTER 2

    ENVIRONMENTAL REQUIREMENTS

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    12/136

    6

    CHAPTER 2: ENVIRONMENTAL REQUIREMENTS

    The legislation that is related to the prevention, abatement, control of pollution and

    enhancement of the environment in Malaysia is stipulated in the Environmental Quality

    Act 1974 (Amendment) 2007. To date, 40 sets of Regulations and Orders have beenintroduced and enforced. Under this Act, an Environmental Impact Assessment (EIA) is

    required for activities prescribed under the Environmental Quality (Prescribed

    Activities (Environmental Impact Assessment) Order 1987. Those activities that are

    not subject to the mandatory EIA requirement are nevertheless subject to various other

    regulations under the Act. The standard regulations require evaluation for project siting,

    pollution control, monitoring and self regulation via the audit process.

    For the states of Sabah and Sarawak, the environmental requirements are clearly stipulated

    in the Environment Protection (Amendment) Enactment 2004and Natural Resources

    and Environment Ordinance respectively.

    Apart from compliance with the Environmental Quality Act (EQA) 1974 (Act 127) and

    other related environmental legislations, the following Acts are also applicable based on

    its relevancy to the planning, design, construction, equipping and commissioning of any

    project.

    (a)

    National Land Code (Act 56 of 1965)

    (b) Town and Country Planning Act 1976, (Act 172)

    (c)

    Street, Drainage and Building Act, 1974: Act 133 and Amendment, 1978

    (d) Protection of Wildlife Act, 1972 (Act 76)

    (e) Forestry Act 1984 (Act 313)

    (f)

    Land Conservation Act 1960 (Act 385)

    (g) Occupational Safety and Health Act 1994 (Act 514)

    (h) Solid Waste and Public Cleansing Management Act 2007 (Act 672)

    (i) Federal Territory (Planning) Act 1982 (Act 267)

    (j)

    Workers Minimum Amenities Act 1990 (Act 446)

    (k) Local Government Act 1976 (Act 171)

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    13/136

    7

    2.1 Planning/Design Stage

    Environmental requirement during planning or design stage is clear whereby if the said

    project has been classified as a prescribed activity according to the Environmental

    Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987 and

    Section 34A of the Environmental Quality (Prescribed Activities)(EnvironmentalImpact Assessment) Order 1987, an Environmental Impact Assessment (EIA) study

    needs to be carried out and submitted to Department of Environment for approval prior to

    project implementation.

    Under the Act, there are a total of nineteen (19) categoriesof prescribed activities which

    include agriculture, airport, drainage and irrigation, land reclamation, fisheries, forestry,

    housing, industry, railways, transportation, resort and recreation development, waste

    treatment and disposal, and water supply projects. Additionally, a Detailed Environmental

    Impact Assessment (DEIA) study is required for thirteen (13)different types of projects

    which include steel mill, pulp and paper mill, cement plant, coal-fired power plant, dams

    (hydroelectric and water supply), coastal land reclamation, incinerators (scheduled wastesand solid wastes, solid wastes disposal sites, projects involving land clearance where more

    than 50% of the area has slope>250) and logging (>500 hectares). It is to be noted that for

    projects in Sabah and Sarawak, specific local legislations pertaining to EIA requirements

    need to be adhered to.

    For the state of Sabah, lists of prescribed activitiesare contained in First Scheduleand

    Second Scheduleof the Environment Protection (Prescribed Activities) (Environment

    Impact Assessment) Order 2005. For projects in Sabah, an environmental impact

    assessment report is required for any prescribed activities specified in the Second

    Schedule of the Environment Protection (Prescribed Activities) (Environment Impact

    Assessment) Order 2005. In addition, a proposal for mitigation measures is required for

    any prescribed activities specified in the First Schedule.

    For projects in Sarawak, an environmental impact assessment report is required for any

    prescribed activities specified in the First Schedule of the Natural Resources and

    Environment (Prescribed Activities) Order 1994.

    Apart from the legislative requirement, EIA may be prepared taking into consideration the

    sensitivity of the project in terms of its location, site conditions and magnitude of impacts.

    In some cases, preparation of EIA study is required by the local authorities or form part of

    the contractual requirement of a project.

    Findings from the study are intended to provide input in the planning of the Project,

    particularly in minimizing environmental impacts during the construction and operational

    stages. An EIA is considered as a planning tool to assist the Project Initiator in

    anticipating impacts of the development, both beneficial and adverse, with an aim to

    maximize the beneficial impacts and minimize the adverse impacts on the environment.

    For better understanding of the EIA process and procedures, an EIA flow chart for both

    Preliminary EIA and Detailed EIA are shown in Figures 1 and 2. Similarly, a simple EIA

    flow chart for Sarawak and Sabah are shown in Figures 3 and 4.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    14/136

    8

    Figure 1: Flowchart for Preliminary EIA Process in Malaysia

    Source: Department of Environment, Malaysia

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    15/136

    9

    Figure 2: Flowchart for Detailed EIA Process in Malaysia

    Source: Department of Environment, Malaysia

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    16/136

    10

    Figure 3: Flowchart for EIA Process in Sarawak

    Source: Natural Resources and Environment Board, Sarawak

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    17/136

    11

    Figure 4: Flowchart for Preliminary EIA Process in Sabah

    Source: Environment Protection Department, Sabah

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    18/136

    12

    2.2 Implementation/ Construction Stage

    In order to monitor Projects compliance with the general requirements of the Clients

    needs and relevant environmental legislation, an Environmental Management Plan

    (EMP)shall be prepared as detailed herein. The EMP shall be prepared in accordance to

    the format or guidelines recommended by the Department of Environment (DOE) and/orother relevant government departments requirements. These guidelines shall provide the

    framework for the preparation of the environmental management and mitigation measures

    to mitigate on-site impacts to acceptable limits as stipulated by the DOE.

    The EMP is not intended as a rigid planning document but an active documentthat shall

    be revised and improved, as and when required, throughout the implementation stage.

    Proper execution of the EMP is expected to result in minimal adverse impacts on the

    surrounding environment and its natural resources.

    The plan shall outline the responsibilitiesof the various parties involved in the Project,

    the environmentalrequirements for the Project and specifies mitigationmeasures andenvironmental monitoring and audit that must be implemented during construction

    stage. The EMP shall be prepared and implemented to ensure compliance to the JKR EMS

    ISO 14001.

    Integral to EMP is the establishment of a monitoring program that serves as a

    quantitative feedback mechanism on the effectiveness of the mitigation measures.

    Essentially, the monitoring program is a set of procedures targeted towards periodical

    measurement of environmental indicators that provides a platform to evaluate

    environmental performance through comparisons against baseline and compliance levels.

    Selection of environmental components to monitor, their locations, parameters and

    frequency of monitoring are governed by the EIA approval conditions or by a Registered

    Environmental Consultant (if no EIA was carried out for the project). As a norm,

    monitoring is centered on the issues of water, noise and air qualities likely to be impacted

    upon by the Project.

    The auditing procedure and schedule shall be detailed out in the EMP. The audit shall

    focus on the implementation of the EMP and/or other environmental management

    elements. The environmental auditor shall have the necessary expertise and experience to

    execute the tasks diligently and professionally in accordance with the requirements of JKR

    EMS: MS ISO 14001 and shall undertake the following tasks:-

    (a) To carry out environmental compliance audits quarterly and closure audit on

    completion of the project;

    (b) To evaluate monitoring data for water, air, noise qualities and if applicable

    vibration qualities;

    (c)

    To verify implementation of corrective and preventive action findings on adequacy

    of compliance to the EMP and/or JKR EMS ISO 14001;

    (d) To prepare a comprehensive environmental auditing report in compliance to

    elements as stated in the EMP and/or JKR EMS ISO 14001;

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    19/136

    13

    2.3 Operational/Post Construction Stage

    Upon submission and acceptance of the closing audit at the end of the construction period,

    monitoring of operational activities in compliance to the necessary laws and regulations is

    encouraged to be continued during the post constructionstage in order to ensure that the

    operational stage of the project does not cause any environmental damage. The impact ofgenerated wastewater has been deemed to be the more significant residual impact that

    requires further monitoring. The quality of any wastewater discharged must comply with

    the limits as stipulated by the Environmental Quality (Sewage) Regulations 2009.

    2.4 Applicable Guidelines

    The use of the relevant Guidelinesin the planning/design stage of the project is deemed

    necessary in order to ensure the project activities do not violate any applicable laws and

    regulations. The guidelines need to be used in respect to the project site specific

    conditions.

    The General guidelines applicable are as follows:-

    Area to be developedApplicable Guidelines

    General Sites

    Guidelines for the Environmental Impact Assessment

    of Highway/Road Projects, JKR Malaysia

    Environmental Impact Assessment Guidelines for

    Housing and New Township Development Project,

    DOE 2003 Urban Storm Water Management Manual for Malaysia

    (Manual Saliran Mesra Alam Malaysia), JPS 2000

    Guidelines for Prevention and Control of Soil Erosionand Siltation in Malaysia, DOE 1996

    Environmental Audit Guidance Manual, DOE 2009

    Submission checklist for stormwater management in

    Malaysia, DID 2008

    Hill slope and Sensitive

    Sites

    Cabinet Committee Guidelines on Hill slope

    development;

    KPKT Guidelines for Development of Hilly Areas,

    JPBD 2009;

    JKR Manual on Slope Maintenance

    Coastal Sites

    JPS Guidelines 1/97 Erosion Control for Coastal

    Development Area, 1997;

    Planning Standards for Coastal Areas, JPBD

    Planning Standards for the Physical Development of

    Islands, JPBD

    Note: The above guidelines are not exhaustive.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    20/136

    14

    CHAPTER 3

    CONTRACTUAL REQUIREMENTS

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    21/136

    15

    CHAPTER 3: CONTRACTUAL REQUIREMENTS

    Environmental protection and enhancement works for conventional contract projects are to

    be specified in the Instructions to Tenderer (ITT)and Conditions of Contracts. These

    shall form part of the pre bid document to be prepared for Conventional Contract projects.

    3.1 Instructions to Tenderer (ITT)

    As stated in the Contract Specification issued by JKR on behalf of the Government of

    Malaysia, the Contractor shall comply with all legal duties and obligations regarding the

    protection of the environment as laid down in the Environmental Quality Act 1974 (Act

    127). Before the commencement of works Contractor shall submit to the Superintendent

    Officer (S.O.), an Environmental Management Plan (EMP), detailing the Contractors

    proposed arrangement for the abatement and mitigation measures for environmental

    protection, environmental monitoring, testing programmed and reporting, and hisorganisation chart.

    3.2 Conditions of Contract

    Within forty-five (45) days from the Letter of Acceptance, the successful tendered shall

    submit for the S.O.s approval an Environmental Management Plan (EMP) as specified. In

    the event if the contractor fail to submit such plan, then the government deserves the right

    to prepare such plan and the cost incurred shall be deducted from the contract sum. The

    cost of preparing the EMP shall include the cost involved in obtaining the services of a

    Registered Environmental Consultant and is deemed to be borne by the Contractor.

    The Environmental Impact Assessment (EIA) report and the Conditions of Approval given

    by the Department of Environment (DOE), where possible, will be made available by the

    Government to assist the Contractor and the environmental consultant in preparing the

    EMP.

    3.3 Design and Build Contract

    For design and build contract, reference shall be made to the need statement pertaining toenvironmental protection and enhancement requirements. The need statement is as

    appended in appendix 2 of this document.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    22/136

    16

    CHAPTER 4

    SPECIFICATIONS

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    23/136

    17

    CHAPTER 4: SPECIFICATIONS

    This section contains the specification relating to environmental matters in the execution

    of JKR projects in line with JKR EMS: MS ISO 14001and shall be read in conjunction

    with the Standard Specification for Buildings, Road Works and JKR Green Mission.

    However where these matters appear also in other sections of the Contract Document, thisspecification shall take precedence.

    4.1 Legislation and Regulations

    The Contractor shall at all times adhere to all existing statutesregarding the protection

    of the Environment.

    Prior to the execution of the project, the Contractor shall comply with the Environmental

    Quality Act (EQA) 1974 (Act 127) and other related environmental legislation including,

    but not limited to:

    (a) National Land Code (Act 56 of 1965)

    (b)

    Town and Country Planning Act 1976, (Act 172)

    (c) Street, Drainage and Building Act, 1974: Act 133 and Amendment, 1978

    (d)

    Protection of Wildlife Act, 1972 (Act 76)

    (e) Forestry Act 1984 (Act 313)

    (f)

    Land Conservation Act 1960 (Act 385)

    (g) Occupational Safety and Health Act 1994 (Act 514)

    (h) Solid Waste and Public Cleansing Management Act 2007 (Act 672)

    (i)

    Federal Territory (Planning) Act 1982 (Act 267)

    (j) Workers Minimum Amenities Act 1990 (Act 446)

    (k) Local Government Act 1976 (Act 171)

    The Contractor shall be liable for and shall indemnify the Government against any

    damages, expenses, liability, losses, claims, prosecution, proceedings, fines and penalties

    caused by any non-compliances or contraventions of the above legislation and regulations.

    4.2 Environmental Impact Assessment (EIA)

    In line with EQA 1974, Act 127, Section 34A (1-8), the Contractor shall submit a report

    on projects impact on the environment if the project is listed as prescribed activities in the

    Environmental Quality (Prescribed Activities) (EIA) Order, 1987. The report should be

    prepared in accordance with the requirements as per the latest A Handbook of EIA

    Guidelines by the Department Of Environment.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    24/136

    18

    4.3 Environmental Management Plan (EMP) & Applicable Elements

    4.3.1 Objectives

    The main objective of the Environmental Management Plan (EMP) is to set

    out a comprehensive programmed which will form the basis forimplementing environmental mitigation measures, environmental

    monitoring and environmental auditing of the construction works by the

    Contractor as listed below:-

    (i) To set out various environmental protection / conservation measures

    that conform to the environmental conditions stipulated in the

    Specifications, EIA report and by other relevant authorities (e.g. the

    Department of Environment (DOE);

    (ii) To ensure that the Contractor comply with all applicable

    environmental standards and guidelines, legislative requirements andother relevant conditions related to the environment;

    (iii) To specify a detailed environmental monitoring and auditing

    programmed to ensure that the Contractor and all hisSub-contractors

    comply with all stipulated requirements throughout the duration of the

    project; and

    (iv) To streamline the different functions of various sections and

    authorities related to the environmental matters during construction.

    4.3.2 Preparation of the EMP

    The Contractor shall submit an EMP prepared by a registered

    environmental consultant and approved prior to commencement of any

    works on site. The EMP shall be submitted to the S.O. for endorsement

    within 45 daysfrom the date of Letter of Acceptance in compliance with

    the Conditions of Contract and/or in compliance with the requirements of

    the conditions of approval of the EIA report by the Department of

    Environment. For design and build projects, the need statement shall

    prevail.

    The EMP shall make reference to the following but not limited to:-

    (a) DOE Format for the Preparation of EMPs

    (b) JKR Environmental Management System (EMS)

    (c) The approved EIA report

    (d) EIA Approval Conditions from DOE (attached if any).

    It should be clearly noted the EMP is a document for practical use on site

    by nominated personnel and thus should be concise, up to date and site

    specific.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    25/136

    19

    The execution of the EMP is a joint responsibility of the Contractor,

    consultant and appointed Environmental officer (EO) for the project. The

    EOs primary responsibility is to ensure the implementation of the EMP

    and JKRs EMSand to monitor and report on the site compliance on a daily

    basis.

    4.3.3 Scope of EMP

    Scope of EMP is as per DOE Guidelines on Preparation of EMP.

    4.3.4 Deliverables

    The following documents shall be submitted by the Contractor:-

    Table 1: Deliverables to be submitted by the Contractor to the S.O./P.D.Documents No. of

    Copies

    Reporting Frequency Timing

    Environmental

    Management Plan

    (EMP)

    5 Once only

    (However, EMP should

    be updated when

    necessary)

    Within 45 days from

    the date of the Letter of

    Acceptance and/or as

    compliance to the

    conditions of approval

    of the EIA report

    Environmental Quality

    Report (EQR)

    5 Monthly 4 weeks after

    monitoring

    Environmental

    Monitoring and Audit

    Report (EMAR)

    5 Quarterly 2 weeks after audit

    Closure Audit Report(CAR)

    5 Once Only 2 weeks prior toissuance of Certificate

    of Practical Completion

    (CPC)

    Note: To ensure consistency, a standard reporting format for EMP, EQR, EMAR and CAR

    is provided in Appendix 3.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    26/136

    20

    4.4 Site Office and Facilities

    4.4.1 Site office, workshop, canteen and store

    (a) The Contractor shall provide and maintain on site, suitable and

    sufficient offices for the S.O., his representatives and the Contractorown use.

    (b) The Contractor shall also provide and maintain on site suitable

    workshops and stores with impervious flooring including grease

    traps.

    (c) The Contractor is prohibited from discharging oil and grease to any

    watercourses. Any spilled oil and grease shall be promptly removed

    and this contaminated waste shall be kept in proper containers. Used

    oil and grease shall be kept in separate containers for recycling. All

    containers shall be stored in secured areas prior to disposal by alicensed contractor as per the Environmental Quality (Scheduled

    Wastes) Regulations 2005.

    4.4.2 Accommodation for Workmen

    (a) The Contractor shall provide and maintain on site, suitable and

    sufficient accommodation and camps for his workmen and

    supervisory staff as required in the Contract.

    (b) The location of the workmens accommodation shall be agreed

    beforehand with the S.O. and shall be such as to avoid obstruction

    and nuisance to the Works and public and shall be laid out in an

    approved and orderly manner.

    (c) The construction and habitation of the accommodation shall comply

    with the requirements of all government and local authorities.

    (d) All accommodation for workmen shall be properly ventilated and

    lighted with sufficient toilet and bathing facilities and waste and

    refuse collection bins/disposal. Cooking is prohibited in sleepingquarters.

    (e) The Contractor shall also provide adequate supply of water for

    canteen usage and allowable cooking areas.

    (f) The Contractor shall be wholly responsible for the workmen at the

    accommodation provided. Activities such as hunting/ trapping of

    wildlife should be strictly forbidden and fines/ penalties shall be

    imposed on the Contractor by the relevant Government

    Departments.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    27/136

    21

    4.4.3 Utilities

    (a) Water Supply

    (i) The Contractor shall provide and maintain a potable water

    supply system to all facilities required in the construction area.The supply shall be taken from sources approved by the S.O.

    (ii) The Contractor shall submit his plans for the water supply and

    reticulation system, including filtration, chlorination and other

    proposed treatment where required, to the S.O. for approval, not

    less than thirty (30) days prior to the provision of water supply.

    (iii) Potable water shall comply with the requirements of Ministry of

    Health Standards.

    (b) Sanitation

    (i) The Contractor shall provide and maintain sufficient toilets at

    appropriate locations on site as approved by the S.O. Toilets

    shall be complete with adequate water closets, urinals and hand-

    basins, and proper sanitary system.

    (ii) The Contractor shall maintain all toilets in a clean and sanitary

    condition and shall comply with requirements of the Ministry of

    Health.

    (iii) All wastewater must be treated such that its discharged effluent

    meets the requirements of all existing legislation and

    regulations.

    (c) Solid waste disposal

    (i) The Contractor shall undertake the collection and disposal of

    solid waste such as litter, kitchen and canteen refuse, non-

    hazardous solid waste including office, workshop and

    accommodation waste. Solid waste collection shall be made at

    least twice a week or as and when directed by the S.O.

    (ii) Solid waste shall be stored in proper bins and containers,

    collected and disposed off at designated site(s) approved by the

    S.O. or to a locally available landfill by a licensed contractor.

    (iii) A waste management schedule shall be set up to ensure that

    licensed contractors carry out the collection and disposal of

    waste materials at regular intervals. Proper facilities for the

    temporary collection of solid waste shall be established at the

    site office for construction debris and solid waste.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    28/136

    22

    (iv) The Contractor should adopt ways to minimize waste such as

    reduce, reuse and recycle of waste. Example of waste

    minimizations is to reduce the amount of waste from concrete

    usage, first is by ordering the correct quantity and batch or by

    using concrete panels. Excess concrete can then be recycled as

    concrete blocks and bench or reused as hardcore materials.

    4.5 Site Clearing and Earthworks

    No site clearing and earthworks shall be carried out prior to EMP approval by

    relevant parties/authorities.

    4.5.1 Site Clearing

    (a) Site clearing shall be done in stages and within construction limit. Noburning of cleared vegetation and debris shall be allowed unless prior

    approval has been obtained from the Director General of the

    Department of Environment.

    (b) Erosion mitigating measures shall be installed or constructed before

    commencement of site clearing and earthworks. This includes

    planning for work in stages and also plans for diverting as much as

    possible surface runoff from the work areas.

    (c) For road projects, site clearing should be from the centre of the road

    outwards towards the construction limit to enable escape of wildlife

    into neighbouring jungles.

    (d) Cleared vegetation and debris should be disposed off to approve

    designated spoil tips. The Contractor shall be responsible for

    identifying these disposal areas (unless stated otherwise). The

    approved disposal areas shall be prepared before any site clearing is

    allowed to commence.

    (e) Cleared vegetation, debris and spoils should on no account be

    deposited or pushed into water-courses, streams and rivers.

    (f) Trees and vegetation identified for conservation must be protected by

    the Contractor at all costs.

    (g) Other clearing activities such as access road construction, site office

    and work-camp construction, etc shall be carried out with minimal

    cutting of trees and site clearing. The intended area shall be marked

    out for the S.O.s inspection and approval prior to any site clearing

    works.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    29/136

    23

    (h) Holes and cavities resulting from clearing, grubbing, de-stumping and

    de-rooting shall be backfilled with acceptable materials and

    compacted to approximate densities of adjacent areas.

    (i) The Contractor shall provide all necessary temporary drainage for

    keeping the site and other areas free of standing water. Efforts mustbe made to channel the surface runoff as much as possible away from

    the work areas.

    (j) If due to unforeseen circumstances turfing cannot be carried out

    immediately to the slope exposed areas, temporary protection/cover

    (e.g. plastic sheet or equivalent) shall be applied over exposed

    surfaces by the Contractor at his own cost.

    (k) Should the Contractor fail to ensure compliance with any of the

    above, the S.O. without prejudice to any other rights or remedies

    available to the Government under this Contract may employ and payother persons to execute the work and all costs incurred in connection

    with such employment shall be recoverable from the Contractor as

    stipulated in the Conditions of Contract.

    4.5.2 Earthworks

    (a) All silt traps, sedimentation basins, erosion control measures and

    drainage system as shown in drawings must be constructed in stages

    and maintained by the Contractor. The location of these mitigating

    measures shall be detailed and shown on plan in the EMP for the

    approval of the S.O

    (b) The Contractor shall provide all necessary temporary drainage for

    keeping the site and other areas free of standing water before the

    commencement of any earthworks. Effort must be made to channel

    the surface runoff as much as possible away from the work areas.

    (c) All temporary drainage, mitigation measures (e.g. silt traps and silt

    fence) must be constructed before the commencement of any

    earthworks and shall be maintained throughout the construction

    period to ensure their effectiveness.

    (d) Unsuitable materials and surplus earth shall be disposed off in

    designated spoil tips, within the site or off site. Unless otherwise

    stated, the Contractor shall be responsible for identifying these

    disposal areas. The dump site/ disposal areas shall be identified and

    approved by the S.O. before commencement of any earthworks. In

    the event additional disposal areas (spoil tips) are required, the

    Contractor shall also be responsible for identifying these disposal

    areas which shall be approved by the S.O.

    (e) The method of depositing the unsuitable materials and surplus earth tothe spoil tips must be properly engineered designed and must be

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    30/136

    24

    sufficiently graded, leveled, compacted, properly drained, revegetated

    and approved by the S.O. End-tipping shall not be allowed.

    (f) The Contractor shall schedule for earthworks to be carried out as

    much as possible during dry weather periods. This is to ensure that

    the earthwork activities being carried out are done in asystematic/orderly manner in order to minimise earth surfaces from

    being exposed for long periods during wet weather periods. Turfing

    or hydro seeding must be carried out immediately after earthworks

    and before work on other beam/lift commences. If due to unforeseen

    circumstances turfing cannot be carried out immediately, temporary

    protection/cover (e.g. plastic sheets or equivalent) shall be applied to

    the exposed slopes.

    (g) Should the Contractor fail to ensure compliance with any of the

    above, the S.O. without prejudice to any other rights or remedies

    available to the Government under this Contract may employ and payother persons to execute the work and all costs incurred in connection

    with such employment shall be recoverable from the Contractor as

    stipulated in the Conditions of Contract.

    4.6 Access Roads and Existing Road

    (a) All access roads to the site shall be built away from the existing

    watercourses, streams and rivers with proper drainage system and be paved

    for a distance of at least 10 meters from where these access roads join

    existing roads.

    (b) The Contractor shall maintain all access roads including the drainage

    system throughout the construction period to the satisfaction of the S.O.

    (c) Where the Contractor uses existing/private roads as his access, he shall be

    responsible for any damage to the existing roads, bridges, drains, culverts,

    roadside furniture, and all other appurtenances and services on such roads

    caused by any work carried out by him throughout the construction period.

    The Contractor shall repair any damages and reinstate the same to their

    original condition to the satisfaction of the S.O.

    (d) All temporary diversion affecting public/private roads must be approved by

    the Government, private landowner and the S.O. All such diversions must

    be equipped with temporary diversion signs and comply with the

    requirements of Arahan Teknik (Jalan) 2C/85 of JKR. Adequate workmen

    for controlling traffic diversion must be provided.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    31/136

    25

    4.7 Pollution Control

    4.7.1 Water quality

    (a) All silt fence, silt traps, sedimentation basins and other erosion and

    sediment control measures as shown in drawings must beconstructed and maintained by the Contractor.

    (b) Water quality standards and monitoring schedule from the silt traps/

    sedimentation basin/rivers/stream/water bodies shall comply as

    specified in Table 2 or as directed by the S.O. Silt traps and

    sediment basin discharges shall be monitored monthly and shall be

    collected within 30 minutes after a rainfall event of more than

    20mm depth or more.

    (c) The Contractor is prohibited from discharging oil and grease to any

    watercourse. Any spilled oil and grease shall be promptly removedby the Contractor. The Contractor shall collect, keep in proper

    containers, label and store all used oil and grease and other

    scheduled wastes according to Environmental Quality (Scheduled

    Wastes) Regulations, 2005.

    (d) The Contractor shall carry out water quality monitoring at locations

    on existing water bodies as indicated in the EMP. Parameters to be

    tested are as specified in Table 2.

    4.7.2 Noise Control

    (a) All work shall be carried out with least disturbance and noise. The

    Contractor shall ensure all his equipments and machineries are in

    proper working condition so as to minimize the amount of noise

    generated. The S.O. may require the Contractor to replace any

    machinery that to his discretion is emitting excessive noise.

    (b) The Contractor shall comply with the general recommendations set

    out in DOE Interim Planning Guidelines for Construction Noise

    together with any specific requirements described in the Contract.

    (c) The Contractor shall indemnify and keep indemnified the

    Government, S.O. and the S.O.s Representatives against any

    liability for damages on account of noise or other disturbances

    created while or in carrying out of the works and from and against

    all claims, demands, proceedings, damages, costs charges and

    expenses whatever in regard or in relation to such liability.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    32/136

    26

    4.7.3 Air Quality

    (a) Open burning of cleared vegetation, debris and construction waste

    etc, shall not be allowed unless prior approval is obtained from the

    Director General of the Department of Environment.

    (b) The Contractor shall provide suitable spraying equipment for

    regular spraying of water over the existing roads, tracks and access

    roads, near settlements, completed as well as incomplete road and

    other barren areas of the site used by the contractor especially

    during the dry season or as and when directed by the S.O.

    (c) When the Contractors trucks or equipment utilizes public or private

    roadways, all dirt and materials shall be removed from the trucks/

    equipments by hosing, lorry wash-trough, etc. before leaving the

    site.

    (d) The Contractor shall provide for the prompt removal of all dirt and

    other materials spilled from his or his sub-contractors vehicles on

    public or private roadways.

    (e) For Contractors trucks carrying sand, aggregates, earth and other

    loose construction materials liable to spillage, tarpaulin must be

    used to cover such open trucks when passing through villages and

    settlements or on all roadways.

    (f) The Contractor shall also ensure dust control at quarry / batching

    plant (if any) complies with environmental requirement as

    stipulated in the Environmental Quality (Clean Air) Regulations,

    1978.

    4.7.4 Vibration control

    (a) All works shall be carried out with least vibration disturbance. The

    Contractor shall ensure that at any time, the vibration levels

    resulting from his works at or across real property boundary should

    not exceed the Recommended Limit as Specified in Table 2 of thisdocument. No person unless duly authorized by law or carrying our

    legitimate duties shall use explosives or results in explosions which

    create a vibration disturbance across a real property boundary or on

    a public space or right of way.

    (b) The Contractor shall comply with the general recommendations set

    out in DOE Interim Planning Guidelines for Vibration Limits and

    Control in the Environment together with any specific requirements

    described in the Contract.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    33/136

    27

    (c) The Contractor shall indemnify and keep indemnified the

    Government, S.O. and the S.O.s Representatives against any

    liability for damages on account of vibration disturbance created

    while or in carrying out of the works and from and against all

    claims, demands, proceedings, damages, costs charges and expenses

    whatever in regard or in relation to such liability.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    34/136

    28

    Table 2: Environmental Quality Standards to be complied with by the Contractor

    AspectsParameter JKR EMS

    Set Target

    Environment Quality

    (Sewage) Regulations,

    2009

    National Water Quality

    Standards (NWQS)

    StandardA

    Standard B Class IIA Class IIB

    Soil

    Soil loss MinimumearthworkPhaseconstruction

    6berms/bench

    es for slopes

    ( 6m perberm)

    Reusetopsoil

    Water1,2

    Turbidity 200 NTU - - 50 NTU 50 NTU

    Suspended

    Solid 100 mg/l 50 mg/l 100 mg/l 50 mg/l 50 mg/l

    BiochemicalOxygenDemand 5 @

    20C (BOD)5

    50 mg/l 20 mg/l 50 mg/l 3 mg/l 3 mg/l

    ChemicalOxygenDemand(COD)

    100 mg/l 120 mg/l 200 mg/l 25 mg/l 25 mg/l

    pH 5.59 69 5.59 6-9 6-9

    E-Coli 400counts / 100ml

    - - 100 counts/ 100ml

    400counts /100ml

    DissolvedOxygen (DO)

    4 mg/l - - 5-7 mg/l 5-7 mg/l

    Oil andGrease

    10 mg/l 5 mg/l 10 mg/l 40 g/l, N 40 g/l, N

    AmmoniacalNitrogen(river)

    - 10 mg/l 20 mg/l 0.3 mg/l 0.3 mg/l

    Air3

    Total Suspended Particulate(TSP) (24hr)

    Particulate Matter (PM10)(24hr)

    260 g/m /day

    150 g/m3/day

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    35/136

    29

    Reference:

    (1) 2ndSchedule (Regulation 7), Environmental Quality (Sewage) Regulations 2009,

    Environmental Quality Act 1974.

    Standard A: For location with downstream water intake

    Standard B: For location with no downstream water intake

    (2) National Water Quality Standards for Malaysia

    Class IIA: Water Supply IIconventional treatment required

    Fishery IIsensitive aquatic species

    Class IIB: Recreational use with body contact

    (3) Recommended Malaysian Guidelines on Ambient Air Quality

    (4) Schedule 1 & Schedule 6, Planning Guidelines for Environmental Noise Limits &

    Control, (Department of Environment, 2004)

    (5) Planning Guidelines for Vibration Limits and Control of the Environment

    (Department of Environment, 2004)

    Note: N No visible floatable materials or debris or no objectionable odour, or no

    objectionable taste.

    Noise4

    Equivalent Noise Level

    (Leq), L10, L90

    Receiving Land Use (residential)

    Day time (7.00 am7.00 pm )L90 60 dBA; L1075 dBA; Lmax 90 dBA;

    Evening (7.00 pm10.00 pm)L90 55 dBA; L1070 dBA; Lmax 85 dBA;

    Night time (10.00 pm7.00 am)Noise Sensitive Areas : LAeq 40 dBASuburban Areas : LAeq 45 dBAUrban Areas : LAeq 50 dBA

    Vibration5

    Vertical Vibration PeakVelocity (mm/s)

    Not more than 3 mm/s at receiver location or across realproperty boundary.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    36/136

    30

    4.8 Preservation of Flora and Fauna

    4.8.1 Flora

    (a) Prior to site clearing, the forester and/or botanist engaged by JKR or

    Contractor shall assist the surveyor to identify any trees of rare,endemic or endangered species which need to be conserved or

    relocated. Trees which are classified as rare, endemic and

    endangered shall be conserved and marked (crossed) red. Similarly,

    trees having girth of 800mm and above shall be conserved and

    marked (crossed) red. Trees which are rare, endemic or endangered

    and required to be relocated shall be marked (crossed) white.

    Should relocation be required, trees shall have girth of 300mm and

    below.

    (b) The Contractor shall beresponsible for the transportation of trees to

    nearby sites, arboretum or other alternatives, as advised by theforester. The Contractor shall ensure all relocated trees are well

    kept.

    (c) The botanist/ forester shall produce a report on the effectiveness of

    the tree conservation, preservation and action plan as proposed in

    the EMP as directed by the S.O. The report shall also cover aspects

    of new findings not covered during the earlier investigation and

    proposal of any rectification plan required.

    (d) The felling of trees shall be confined within the construction limit.

    (e) The Contractor shall prohibit all his and his sub-contractors

    employees from destroying, removing or clearing trees, timber,

    shrub and other flora to any extent greater than that approved by the

    S.O. as being necessary for the execution of the contract.

    (f) The Contractor is prohibited from disposing waste materials

    amongst vegetation within or outside the work site.

    4.8.2 Fauna (Wildlife)

    (a) The Contractor and his employees are prohibited from thefollowing:-

    (i) Hunting, disturbing, capturing, endangering or destroying

    such wildlife by any means (e.g. poison, baits, bird line or

    net) as may be protected by relevant statutes including

    removing or damaging bird nests and eggs.

    (ii) Housing, confining or breeding any wildlife

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    37/136

    31

    4.9 Requirements In Relation To Waterways

    (a) The Contractor and/or JKR shall seek approval from Jabatan Pengaliran &

    Saliran (JPS) for any works related to natural waterways including

    diversions, modifications replacements and/or relocation of rivers,

    watercourses and related structures during execution of the works.

    (b) The Contractor shall coordinate all operations and make adjustments to his

    programmed resulting from JPS requirements pertaining to changes made

    to the natural waterways.

    (c) The Contractor shall ensure that temporary diversions of rivers and/or

    waterways shall be capable of sustaining flows throughout the year as

    specified by the JPS.

    4.10 Erosion and Sediment Control (Temporary works)

    4.10.1 Erosion Control

    (a) Natural

    (I). Bioengineering

    Vetiver

    The plant, Vetiver Zizanioodes (Rumput Wangi) shall be

    non-seeding types tillers derived from tissue culture or

    micro propagation method. The plantlets to be supplied shall

    be at least an aggregate of 5 plantlets with roots at least 3 cm

    long.

    The Contractor shall plant Vetiver Zizanioodes in rows as

    specified in the drawings or as directed by the S.O. In

    difficult soil types, borrowed topsoil may be required to

    refill trenches for planting the vetiver. The Contractor shall

    ensure and maintain the growth of the vetiver.

    Creepers

    The Contractor shall plant creepers either through seeds or

    saplings. Commonly used creepers are of the species

    Centrusemo pubscens, Ficus pumila and Parthenocissus

    himalayana. Ficus pumila and Parthenocissus himalayana

    are suitable on concrete/gunited slopes and rock surfaces.

    Creepers shall be planted into a planter bed previously

    prepared with drainage layer/weep holes and topsoil.

    Creepers should be planted individually immediately at thetoe of wall/slopes at approximately 0.3m centre to centre.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    38/136

    32

    (II) Mulching

    Mulch is a protective cover placed over the soil to protect

    soil from rain, preserve moisture and slows runoff velocity.

    A variety of materials can be used as mulch such as grass

    clippings, leaves, hay, straw, shredded bark, sawdust, woodchips, shredded newspaper, cardboard and wool.

    (b) Proprietary products

    The Contractor may also use proprietary or any man-made products

    available in the market to control erosion on slopes, subject to

    JKRs approval. The suitability of the products used shall follow the

    manufacturers specifications including method of installation and

    maintenance. Examples of propriety products are geotubes, ENKA

    mat, geocells/geoweb, fibromat and coir logs.

    4.10.2 Sediment Control

    The specification as described under this Section shall be read together with

    other related sections of the Standard Specification for Road Works or

    Standard Specification for Buildings and the drawings shall refer to the

    Chapter 8 - Standard Drawings of this document.

    (a) Silt Fence

    Silt fence shall consist of geotextile supported by poles at regular

    interval. The geotextile shall be made of non-woven material with

    minimum properties of 200 g/m or tensile strength 15 kN/m. shall

    be constructed as close as possible, parallel to the contours of the

    site with a setback of at least 0.9 m (3 ft0 from the toe of the slope.

    The silt fence

    The fence shall be inspected after every rain. The silt accumulated

    behind the fence shall be removed when it has reached 2/3 of the

    fence filter height and disposed at designated site. The geotextileshall be checked for rips, tears and other types of deterioration and

    replaced as needed.

    (b) Silt Trap/Sediment Basin

    Silt trap/sediment basin comprises rocks in gabions, shall be

    constructed in respective catchment area to collect and store

    sediment prior to entering natural waterways.

    The silt traps/sediment basins shall be inspected regularly especially

    after heavy rain and any damages shall be rectified. The sediment

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    39/136

    33

    accumulated in the silt traps/sediment basins shall be removed when

    it has reached 2/3 of its depth and disposed at designated site.

    (c) Gabion Wall

    A gabion wall which comprises rocks in gabions but of smallernature compared to silt trap, shall be constructed in difficult terrains

    such as on slopes and narrow valleys for the purpose of collecting

    and storing sediment prior to entering natural waterways.

    (d) Check Dam

    A check dam which is a small, temporary or permanent dam shall

    be constructed across a drainage ditch, swale or channel for the

    purpose of lowering the speed of concentrated flows.

    The check dams shall be inspected regularly especially after heavyrain and any damages shall be rectified. The sediment accumulated

    behind the check dams shall be removed when it has reached 2/3 of

    its height and disposed at designated site. The height of the check

    dam shall be maintained to be the same at all time.

    (e) Silt Curtain

    Silt curtain shall be used to mitigate sediments by confining

    sediments and prevent dispersal and contamination of the water

    body especially in lakes and riverbanks. Silt curtain shall also be

    used as a divider to prevent sediment laden-water from migrating to

    the rest of the water body.

    Silt curtain shall be checked for rips, tears and other types of

    deterioration and replaced as needed. The suspended sediments

    trapped behind silt curtain shall be allowed to settle for a minimum

    of 24 hours, prior to removal of the silt curtain.

    (f) Sand bag barrier

    A sandbag barrier is a series of sand-filled bags placed on a levelcontour to intercept sheet flows. Sandbag barriers pond sheet flow

    runoff, allowing sediment to settle out.

    Sandbag barriers are suitable as a linear sediment control measure

    which includes below the toe of slopes and erodible slopes, as

    sediment traps at culvert/pipe outlets, down slope of exposed soil

    areas, around temporary stockpiles and spoil areas, as check dams

    across mildly sloped construction roads and parallel to a roadway to

    keep sediment off paved areas.

    Sand bag barrier shall be checked daily before and after rain events,In addition, sandbags exposed to sunlight will cause degradation

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    40/136

    34

    and need to be replaced immediately. Sediment should be removed

    when the sediment accumulation reaches one-third of the barrier

    height and disposed at designated site.

    NOTES: Other items not specified above shall be referred to

    the Standard Specification for Road WorksJKR/SPJ/1988 of Section 1 General, Section 2

    Earthworks and Section 3Drainage Works

    REFER TO APPENDIX 1 : Standard Specifications

    For Building Works (2005 Edition):- SECTION A :

    PRELIMINARIES AND GENERAL CONDITIONS

    AND SECTION C : EXCAVATIONS AND

    EARTHWORKS

    4.11 Permanent Works

    4.11.1 Noise Barrier

    (a) Noise barrier shall be provided in sensitive areas such as housing,

    schools and hospitals situated beside busy roads or highways.

    (b) The type of noise barrier used shall be either absorptive, reflective,

    dispersive or mixed depending upon the noise level survey

    conducted or recommendations made by the relevant Consultant.

    (c) The Contractor shall supply and install noise barrier including

    maintenance until the expiry of the defects liability period.

    (d) For concrete noise barrier, creepers shall be planted and maintained

    to cover the said noise barrier until the expiry of the defects liability

    period.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    41/136

    35

    CHAPTER 5

    METHOD OF MEASUREMENT

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    42/136

    36

    CHAPTER 5: METHOD OF MEASUREMENT

    Non-Physical Work

    5.1 Environmental Impact Assessment (EIA) (If Applicable)

    5.1.1 EIA Report

    Unit

    The unit of measurement for preparation of EIA Report shall be Lump Sum

    (sum).

    Measurement

    The measurement for payment shall be the preparation and approval of theEIA report in accordance to the format in the Guidelines for EIA of

    Highway/Road Projects and A Handbook of EIA Guidelines prepared by

    Department of Environment (DOE).

    Pricing Factors

    The item for preparation of the EIA Report shall be in accordance with the

    Preambles to Bill of Quantities:-

    (a) Cost of any study required, literatures, references, consultation in

    the production of the EIA Report;

    (b) Cost for the engagement of a registered environmental consultant

    required for carrying out the respective study and preparation of the

    said report;

    (c) Submission of twenty one (21) hard copies and one (1) digital copy

    of the approved and accepted report to S.O. The copyright of the

    said documents shall be transferred and become the absolute

    property of the Government.

    5.2 Environmental Management Plan (EMP)

    5.2.1 Preparation and acceptance of EMP

    Unit

    The unit of measurement for preparation and acceptance of EMP shall be

    Lump Sum (sum) and include:

    (a) Erosion and Sediment Control Plan (ESCP)

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    43/136

    37

    Pricing Factor

    The item for preparation of ESCP shall be in accordance with the

    Preambles to Bill of Quantities:-

    (a)

    all cost associated in the preparation of a complete report ondrainage system, erosion control plan and course of action to be

    taken;

    (b)

    additional cost for the engagement of a professional engineer

    required for the preparation of the ESCP;

    (c) Submission of five (5) copies of ESCP for endorsement by the S.O.

    (d) Flora Management Plan for tree conservation including method of

    preservation and course of action to be taken

    (e) Wildlife Management Plan for translocation animal to approved

    location by Jabatan Perhilitan.

    Measurement

    The measurement for payment shall be made upon submission and

    acceptance of the EMP prepared in accordance to the format as stipulated

    in the DOE General Checklist for Preparing EMP as follows:-

    (a) 60% upon submission of draft EMP to S.O.;

    (b) 40% upon approval of EMP by DOE/JKR

    Pricing Factor

    The item for preparation of EMP including updating and revision shall be

    in accordance with the Preambles to Bill of Quantities:-

    (a) Cost of literatures, references, consultation and all that is required

    and specified for the production of the EMP;

    (b) cost for the engagement of the registered environmental consultant

    required for the preparation of the EMP including its updating and

    revision;

    (c) Submission of five (5) copies and one (1) digital copy of the

    approved and accepted EMP for endorsement by the S.O. The

    copyright of the said documents shall be transferred and become the

    absolute property of the Government.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    44/136

    38

    5.3 Environmental Officer (E.O.)

    5.3.1 Environmental Officer

    Unit

    The unit of measurement for provision of E.O. shall be Lump Sum (sum).

    Measurement

    The measurement for payment shall be made in each interim payment in

    proportion of the total period lapsed to the Contract Period (excluding

    Defects Liability Period).

    The measurement for payment shall be the man-month basis throughout the

    contract period (excluding Defects Liability Period).

    Pricing Factors

    The item for provision of E.O., assigned to be responsible for

    environmental management works only, shall be in accordance with the

    Preambles to Bill of Quantities:-

    (a) The wages and other emoluments paid to the E.O.;

    (b) Working outside the Contractors normal working hours if so

    required by the S.O.;

    (c) The Contractor, with the approval of the S.O., shall employ a

    competent E.O. (A Graduate in science and/or engineering field

    with a minimum of one year experience in the environmental

    sector);

    (d) Costs and expenses incurred consequent upon the employment or

    hiring of a competent full time E.O. throughout the contract period

    including payment of Employee Provident Fund, insurance, medical

    and hospitalization;

    (e) Costs and expenses incurred for the training/awareness briefing by

    the E.O. to site personnel whose activities have impact on the

    environment;

    (f) Replacement of incompetent E.O. to the equivalent level or higher

    to the approval of the S.O.;

    (g) Any substitution when the appointed E.O. is absent or on leave for

    more than three (3) consecutive days.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    45/136

    39

    5.4 Environmental Monitoring, Audit And Training

    5.4.1 Environmental Monitoring

    5.4.1 (i) Water Quality Monitoring

    5.4.1 (ii) Air Quality Monitoring5.4.1 (iii) Noise Monitoring

    5.4.1 (iv) Vibration Monitoring

    Unit

    The unit for measurement to conduct the above monitoring shall be

    Lump Sum (sum) for the whole duration of the contract.

    Measurement

    The measurement for payment shall be the number of samples takenfor monitoring, tested and accepted by the S.O.

    Pricing Factor

    The item to conduct environmental monitoring (water, air, noise and

    vibration) shall be in accordance with the Preambles to Bill of

    Quantities:-

    (a) Provision of all necessary equipments as specified;

    (b) Carrying out calibration of all necessary equipments prior to

    use;

    (c) Taking samples according to the intervals, parameters and

    for the duration specified at approved sampling locations by

    trained laboratory personnel;

    (d) Recording and noting of specified data;

    (e) Sending samples collected, testing and analysis at approved

    independent accredited laboratory. The analysis report shallbe signed by a registered chemist;

    (f) Submission of analysed results for purpose of reporting

    (preparation of monitoring report is measured separately).

    5.4.1 (v) Environmental Quality Report

    Unit

    The unit of measurement for the preparation of submission of the

    Environmental Quality Report shall be Lump Sum (sum) for thewhole duration of the contract.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    46/136

    40

    Measurement

    The measurement for payment shall be the number of reports

    prepared based on monitoring carried out and accepted by the S.O.

    Pricing Factor

    The item for preparation of the monitoring report shall be in

    accordance with the Preambles to Bill of Quantities:-

    (a) Cost associated in the preparation of a comprehensive

    report;

    (b) Submission of five (5) copies of report to S.O.

    5.4.2 Environmental Audit and Closure Audit

    Unit

    The unit of measurement to conduct environmental audit and preparation of

    environmental monitoring and audit report shall be Lump Sum (sum) for

    the whole duration of the contract.

    Measurement

    The measurement for payment shall be the number of reports prepared

    based on audits carried out and accepted by the S.O.

    Pricing Factor

    The item to conduct environmental audit and preparation of report

    including the Closure Audit Report shall be in accordance with the

    Preambles to Bill of Quantities:-

    (a) Cost and expenses incurred consequent upon the engagement of a

    competent, independent environmental auditor, registered with

    DOE and/or have attended courses on ISO 14001 auditing with a

    minimum of auditing experience for at least 3 sites;

    (b) Cost of carrying out quarterly audits or at any other intervals

    deemed necessary due to the nature of works on site, evaluation of

    monitoring data and verifying implementation of corrective and

    preventive actions;

    (c) Cost associated in the preparation of a comprehensive report

    including recommendations for improvement in accordance with the

    Standard Report Format as specified in Appendix 2 of this

    Document;

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    47/136

    41

    (d) Submission of five (5) copies of report (per audit) with colour

    photographs to S.O.

    5.4.3 Training

    Unit

    The unit of measurement for training shall be in number (no).

    Measurement

    The measurement for payment shall be the number of training sessions

    carried out for the duration of the contract.

    Pricing Factor

    The item for training JKR personnel shall be in accordance with the

    Preambles to Bill of Quantities:-

    (a) Cost associated in organizing and conducting training of JKR

    personnel locally pertaining to Environmental Management, EIA,

    Safety and Health, Environmental related legal and other

    requirements.

    Physical Work

    5.5 Dust and Mud Control

    5.5.1 Water Bowser Truck

    Unit

    The unit of measurement for provision, operation and maintenance of water

    bowser truck shall be in number (no).

    Measurement

    The measurement for payment shall be the number of water bowser truck

    provided on site and shall be made as follows:-

    (a) 60% on complete provision of vehicle and equipment to the

    satisfaction of the S.O.;

    (b) 40% for operation and maintenance which shall be made in each

    interim payment in proportion of the total period lapsed to the

    Contract Period (excluding Defects Liability Period).

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    48/136

    42

    Pricing Factor

    The item for provision, operation and maintenance of bowsertruck shall be

    in accordance with the Preambles to Bill of Quantities:-

    (a) All cost associated with the provision and operation of trucksincluding operators, water supply, pumping of water, water tank and

    all other necessary equipments needed to carryout water spraying;

    (b) Carrying out water spraying minimum 3 times a day along

    haul/access roads, existing road and nearby settlement zone or other

    affected areas or as directed by S.O.;

    (c) Maintenance in a roadworthy condition of trucks and associated

    equipments;

    (d) Provision of suitable replacement including equipment when theregular truck is not available or unserviceable for more than 24

    hours;

    (e) Removal of truck and equipment from site on completion of the

    works.

    5.5.2 Tyre Washing Facilities

    5.5.2 (i) Portable Water Jet

    Unit

    The unit of measurement for provision, operation and maintenance

    of portable water jet shall be in number (no).

    Measurement

    The measurement for payment shall be the number of portable

    water jet provided on site and shall be made as follows:-

    (a) 60% on complete construction of structure, platform,provision and installation of all equipments to the

    satisfaction of the S.O.;

    (b) 40% for operation and maintenance which shall be made in

    each interim payment in proportion of the total period lapsed

    to the Contract Period (excluding Defects Liability Period).

    Pricing Factor

    The item for provision, operation and maintenance of portable water

    jet shall be in accordance with the Preambles to Bill of Quantities:-

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    49/136

    43

    (a) cost of construction and maintenance of the structure for the

    elevated water tank and the supply of the water tank;

    (b) cost for the construction of the tyre washing concrete

    platform;

    (c) provision of portable water jet including operator and

    other necessary equipment deemed required for the

    successful washing operation;

    (d) carrying out cleaning of all vehicle tyres at various exits of

    worksites;

    (e) maintenance of all cleaning facilities and associated

    equipments;

    (f) provision of replacement when the regular equipment is notavailable or unserviceable for more than 24 hours;

    (g) demolition, and disposal of all rubbish, debris and surplus

    material including removal of all equipment from site on

    completion of the works to the satisfaction of the S.O.

    including reinstatement of the site.

    5.5.2 (ii) Wash Trough

    Unit

    The unit of measurement for construction and maintenance of wash

    trough shall be in number (no).

    Measurement

    The measurement for payment shall be the number of wash trough

    constructed on site as shown in Drawing and shall be made as

    follows:-

    (a) 80% on complete construction to the satisfaction of the S.O.;

    (b) 20% for maintenance which shall be made in each interim

    payment in proportion of the total period lapsed to the

    Contract Period (excluding Defects Liability Period).

    Pricing Factor

    The item for construction and maintenance of wash trough shall be

    in accordance with the Preambles to Bill of Quantities:-

    (a) Preparation of site and approaches including excavation anddisposal of surplus excavated material;

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    50/136

    44

    (b) Construction of wash trough including concrete, formwork,

    reinforcement, hardcore complete as shown in Drawing;

    (c) Filling and regular maintaining of water during the course of

    the works;

    (d) Maintenance of wash trough and surrounding areas clean

    including desalting and disposal of material;

    (e) Demolition and disposal of all rubbish, debris and surplus

    material from the site to the satisfaction of the S.O.

    including reinstatement of the site.

    5.5.3 Water Sprinkler

    Unit

    The unit of measurement for provision and maintenance of water sprinkler

    shall be in number (no)

    Measurement

    The measurement for payment shall be the number of water sprinkler

    installed at quarry/batching plant and shall be made as follows:-

    (a) 40% on complete installation;

    (b) 60% for operation and maintenance which shall be made in each

    interim payment in proportion of the total period lapsed to the

    Contract Period (excluding Defects Liability Period).

    Pricing Factor

    The item for provision and maintenance of water sprinkler shall be in

    accordance with the Preambles to Bill of Quantities:-

    (a) Supply and installation of water sprinkler system including all other

    necessary equipments and facilities;

    (b) Maintenance of water sprinkler system and associated equipments;

    (c) Removal of all installation on site to the satisfaction of the S.O.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    51/136

    45

    5.6 Erosion Control

    5.6.1 Creepers

    Unit

    The unit of measurement for planting and maintenance of creepers shall be

    square metre (m).

    Measurement

    The measurement for payment shall be made of the plan area placed to the

    lines, level grades and dimensions shown in Drawing or as directed by the

    S.O.

    Pricing Factor

    The item for planting and maintenance of creepers shall be in accordance

    with the Preambles to Bill of Quantities:-

    (a) Removal of debris from the surfaces of earthwork to be turfed;

    (b) The preparation of the areas to be turfed including if appropriates

    the amount of topsoil to be used and its method of application;

    (c) The details and results of investigations to determine which types of

    grass and legume are compatible with the soil in the areas to be

    turfed;

    (d) The types of grass and legume (if any) and strains of seed to be

    used, and the function, root and growth characteristics of each type;

    (e) The rates of application of the grass and legume seeds;

    (f) The type of mulch to be used and its method and rate of application;

    (g) The amount of lime or other chemicals (if any) to be applied to

    improve the soil before, during and after turfing;

    (h) The equipment and methods to be used in preparing and placing the

    turf mix and other materials;

    (i) The cultivation and after care of the turfed areas, including rates

    and frequencies of watering, fertilising, grass cutting and general

    maintenance for 1 year after turfing;

    (j) An estimate of the time required after turfing for establishment of a

    permanent dense growth of grass which will require minimal

    maintenance.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    52/136

    46

    5.6.2 Artificial Erosion Control Items

    Unit

    The unit of measurement for installation and maintenance of artificial

    erosion control items shall be square metre (m).Measurement

    The measurement for payment shall be made of the plan area placed to the

    lines, level grades and dimensions shown in Drawing or as directed by the

    S.O.

    Pricing Factor

    The item for installation and maintenance of artificial erosion control items

    shall be in accordance with the Preambles to Bill of Quantities:-

    (a) Removal of debris from the surfaces of earthwork to be artificially

    controlled;

    (b) The preparation of the areas to be artificially controlled including (if

    any) the amount of topsoil to be used and its method of application;

    (c) The details and results of investigations to determine which types

    artificial erosion control items used are compatible with the soil in

    the areas to be artificially controlled;

    (d) The types of artificial erosion control items (if any) and strains of

    artificial erosion control items to be used, and the function, root and

    growth characteristics of each type;

    (e) The type of artificial erosion control items to be used and its method

    and rate of application including equipments and maintenance

    required.

    5.7 Sediment Control

    5.7.1 (i) Construction of Silt Fence

    Unit

    The unit of measurement for construction of silt fence shall be

    linear metre (m).

    Measurement

    The measurement for payment shall be the length of complete fence

    constructed as shown in Drawing and shall be made as follows:-

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    53/136

    47

    (a) 80% on complete construction to the satisfaction of the S.O.

    (b) 20% on removal

    Pricing Factor

    The item for construction of silt fence shall be in accordance with

    the Preambles to Bill of Quantities:-

    (a) Clearing of site for base preparation;

    (b) Construction of silt fence complete as shown in drawing;

    (c) Removal and disposal of all rubbish, debris and surplus

    material from the site

    (d) To the satisfaction of the S.O. including reinstatement of the

    site

    5.7.1 (ii) Maintenance of Silt Fence

    Unit

    The unit of measurement for maintenance of silt fence shall be

    linear metre (m).

    Measurement

    The measurement for payment shall be made in each interim

    payment in proportion of the total period lapsed to the Contract

    Period (excluding Defects Liability Period).

    Pricing Factor

    The item for maintenance of silt fence shall be in accordance with

    the Preambles to Bill of Quantities:-

    (a) Inspection at regular interval and after heavy rain of

    geotextile and other components for rips, tears and other

    types of deterioration and replacement if required;

    (b) Removal of silt and sediment accumulated to approximate

    2/3 of filter height including its disposal.

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    54/136

    48

    5.7.2 Sand bag barrier

    5.7.2 (i) Installation of sand bag barrier

    Unit

    The unit of measurement for Installation of sand bag barrier

    shall be in number (no).

    Measurement

    The measurement for payment shall be the number of sand

    bag barrier constructed as shown in Drawing and approved

    by the S.O. and made as follows:-

    (a) 80% on complete construction to the satisfaction ofthe S.O.;

    (b) 20% on removal

    Pricing Factor

    The item for construction of installation of sand bag barrier

    shall be in accordance with the Preambles to Bill of

    Quantities:-

    (a) Labour required for installation purposes;

    5.7.2 (ii) Maintenance of sand bag barrier

    Unit

    The units of measurement for maintenance of sand bag

    barrier shall be in number (no).

    Measurement

    The measurement for payment shall be maintenance of the

    completed sand bag barrier and shall be made in each

    interim payment in proportion of the total period lapsed to

    the Contract Period (excluding Defects Liability Period).

    Pricing Factor

    The item for maintenance of sand bag barrier shall be in

    accordance with the Preambles to Bill of Quantities:-

  • 5/19/2018 A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS

    55/136

    49

    (a) Sand bag barrier shall be checked daily before and

    after rain events, weekly during the rainy season, and

    at two-week intervals during the non-rainy season.

    (b) Sediment should be removed when the sediment

    a