A Operasi TurbinOkkkk
Transcript of A Operasi TurbinOkkkk
-
STEAM TURBINE OPERATIONS
The procedures described here are for a steam turbine geared to a fixed-pitch propeller, but are. Otherwise
general, intended to provide background information only, and are not comprehensive or all-inclusive.
Recommended procedures for specific equipment should be sought out and followed.
10.1 Preparation, raising vacuum, warming the turbine
lf a turbine has been shut down for an extended period, or if the casings of the turbines or reduction gear have
been opened, verification should be sought that all foreign objects, including tools and rags' were removed
before the casings were closed. All hatches and inspection openings should be closed and sealed.
Rotor axial-position indicators should be checked.
Lubricating oil (LC) should be at a temperature of at least 90oF (about 39oC), clean, and in acceptable
condition. The oil should be circulated through the purifier for about twelve hours prior to its use to ensure
that it is clean, free of water, and to bring it up to minimum temperature, Oil filters should be cleaned. lf there
is any doubt about the quality of the oil, a sample should be taken for testing, and if necessary, the oil should
be transferred to the LO setting tank, and the system should be drained, flushed and refilled
The LO pump is started. When the gravity tank is filled to its normal level, the sump level is checked and
corrected. Oil flow to all bearings and gear meshes is verified Casing and throttle drains are opened.
Permission to rotate the propeller using the turning gear must be obtained from the bridge. The turning gear
is engaged and started. A round is made, listening for unusual noises.
The circulating water pump is lined up and started, using the high sea suction if in port or in shallow water .
Flow through the condenser and LO cooler is verified.
The condensate - recirculation valve is opened, and the condensate pump is started. With the turbine rotors
rotating on the turning gear, steam is admitted to the gland seals..The gland exhaust fan or ejector is started.
The air ejector is started: lf a steam-jet air ejector is-fitted, only the second stage is started at this point, to
raise vacuum to about 15 inches of mercury (about 0.5 bar).
The main steam stop valves are checked to see that they are closed, and then the ahead and astern throttle
valves are opened fully, then closed, to check their operation. steam is then brought up to the throttle valves
with the lines drained and the drains closed. The astern steam guarding valve is opened. Permission to rotate
the propeller with steam must be obtained from the bridge, The. turning gear is disengaged, and immediately
the astern throttle is opened enough to start the rotors turning, then throttled down to keep the shaft turning
at about five rpm, for about fifteen seconds. The ahead throttle is then opened, wide enough to start the rotors
spinning, then throttled down to a shaft speed of about five rpm, and closed after about fifteen seconds, This
alternating rotation is continued for about fifteen minutes. Rounds should be made while the rotor are
spinning to listen for unusual noises. Turbine alarms and trips are tested.
After fifteen minutes of continuously spinning the rotors alternately ahead and astern, the throttles may be left
closed for three to five minutes at i time, then spun briefly in each direction. when machinery is arranged for
bridge control, an automatic rotor-spinning program is included, and the turbines can therefore be placed on
bridge control at this point. In any case, this procedure is continued until maneuvering is begun .
Just prior to the start of the maneuvering period condenser vacuum is brought up to normal
10.2 Maneuvering
Throughout the maneuvering period, the astern guarding valve is open, the throttle and casing drains are open,
and the extraction valves are closed. lf the feed-pump recalculating valve is manually controlled, it is kept
open throughout. The condensate-recirculation valve must be adjusted to keep a level in the drain well at all
times. Both of these recirculation functions are automated for bridge control. Orr ships with scoop injection, the
circulating pump is run throughout the maneuvering period. In some plants, steam pressure and superheat
temperature are reduced for maneuvering.
-
During the maneuvering period, the ahead and astern throttle valves are used to meet commands, either by
direct manual control, or under remote control from the engine control station or from the bridge. The throttles
are never open simultaneously: whichever throttle is opened must be closed completely before opening the
other. When changing speed, a throttle is opened or closed further than necessary to quickly achieve the
required rpm, then adjusted to maintain the rpm. Under manual control, ahead throttle settings are
simplified by using the first-stage exhaust pressure, which correlates consistently with rpm.
lf there is a critical-speed range, it is passed through quickly.
When slowing down, if the way on tire ship turns the propeller at a higher speed than ordered, astern steam
is used to correct the rpm while moving ahead, and ahead steam is used when moving astern. Such correction
is especially required when a stop is ordered, to keep the propeller from turning. During an extended stop, the
rotors are periodically spun ahead and astern. These procedures are automated for bridge control.
During the maneuvering period, instrumentation is monitored, manually or automatically. The boilers, in
particular, are watched closely as they respond to changes in steam demand. Depending on the extent and
condition of automation present, it may be necessary to make adjustments to keep temperatures, pressures,
and levels within bounds. A common precaution is to keep the standby feed pump ready, warmed, and with
only its steam stop valve closed.
To help ensure continuity of electric supply, it is a common practice to keep an additional ship's-service
generator on the line. Where motor driven thrusters are fitted, the bus may be divided to isolate the thrusters
from other services.
At the end of a departure maneuvering period, throttle and casing drains are closed, and the astern guarding
valve is closed. The correct number of ahead nozzles for the required speed are opened, and the ahead throttle
is gradually opened fully. lf steam pressure and/or temperature were reduced for the maneuvering period,
normal values are gradually restored. Feed-pump and condensate-recirculation valves are closed.
Extraction valves are opened. Live steam to the gland-seal system is secured. if water depth permits, the
circulating pump is switched to the low sea suction. On ships with scoop injection, the scoop valve is opened
and the circulating pump is stopped. Additional generators are secured. At the boilers, atomizer-tip sizes and
the number of burners in use are adjusted to match the steam demand .
10.3 Routine operation
While under way at steady power, all instrumentation is monitored, manually or automatically, and
adjustments are made as required. Even in plants with extensive automation, engineers make regular rounds,
listening for unusual noises, looking for leaks and sources of unusual vibration, and checking sight glasses
and fluid levels: Trends are noted for their value in planning maintenance and in avoiding unexpected failure.
When a speed reduction is ordered, the throttle valve may be used for an immediate response, but a longer-
term adjustment is made by adjusting the number of nozzles, then opening the throttle again. Nozzle groups .
in use should always be adjacent to each other.
The LO purifier is kept in continuous bypass. service on the main sump. The purifier and LO filters are
cleaned weekly, or as experience dictates, and accumulations are examined for metallic traces. oil samples
should be withdrawn monthly for an analysis of the physical and chemical properties of the oil, which can
reveal incipient Problems
10.4 Securing
At the end of an arrival maneuvering period the extraction valves are closed, the astern guarding valve is
open, the throttle and casing drain are open,. live-steam supply to the glands is open, the feed-pump
recirculation valve and the condensate-recirculation valve. are open, and the turbines are being spun periodically
with steam. This situation is maintained until the bridge has given and confirmed the order, finished with
-
engines The main steam stop valves are then closed, and the throttle valves are used to dump any steam"
remaining in the tines. me throttle valves are then closed tightly, and immediately, the turning gear is engaged
and started'
Air ejectors are secured, but gland-sealing seal is maintained, so that vacuum breaks though the air-ejector
vent, rather than through the packing glands. when the condenser reaches atmospheric pressure, gland sealing
steam supply is closed, and gland exhaust fan or ejector is stopped. when the condenser drain well level is
normal, the condensate pump and circulating pump are stopped.
After several hours, when the turbine rotors have cooled to ambient temperatures, the turning gear is
stopped (but not disengaged) and the LO pump is stopped.
Every other day at idle, a LO pump is started, and when oil flow is confirmed at the bearings and gears, the
turning gear is started and run for about fifteen minutes, taking care to stop the shaft in a different position
each time. At the same time, the air ejector is run to draw fresh air through the turbines' with steam-jet air
ejectors, the second stage is sufficient for this purpose. lf portable, the LO purifier should be run
continuously on the main sump, with steam to the heater, to prevent condensation within the gear case.
10.5 Emergency operation
cross-compound turbines are required to be fitted with arrangements for bypassing either turbine, in case of a
problem with the turbine or its gear train. generally, with one turbine, less than half of the rated power can be
achieved because of torque limits on shafts and gear. A typical arrangement involves blanked flanges at the
throttle, crossover, and condensers inlet, the necessary sections of connecting piping, and orifices to limit
steam flow. lf the high-pressure turbine is to be bypass, the ahead throttle is connected directly to the
crossover by the prefabricated emergency pipe section, with an orifice inserted after the throttle valve' and a
blank is inserted in the high-pressure exhaust flange. The high-pressure turbine is disconnected from the
gearing. in service, the ahead throttle is used to control steam pressure, up to a maximum set by the orifice.
It may be necessary to reduce the steam temperature, as well. if the astern turbine is on the low-pressure rotor,
it remains available.
If the low-pressure turbine is bypassed, the crossover is connected directly to the condenser inlet, and a blank
is inserted at the low-pressure turbine inlet. An orifice is inserted after the ahead throttle valve. The bypassed
low-pressure turbine is disconnected from the gearing. In operation, the ahead throttle valve is then used to
control steam pressure, up to the limit set by the orifice. lf the astern turbine is on the low-pressure rotor, no
astern power is available. In fact, the astern steam line should be blanked off, or the astern valves wired
closed as a safety precaution.
lf, after a prolonged stop, a rotor vibrates or squeals as the throttle is opened, it my be because the rotor is
warped from uneven heating. The problem can often be solved with minimal damage by spinning the rotor at
low speed for several minutes to heat it evenly.
lf lubricating oil pressure fails while the shaft is turning, the throttle will close automatically. However,
with way on the ship, the shaft will continue to be turned by the propeller. Consequently, the shift must be
stopped, and held at a stop, using steam, although permission to do so must be o5iained from the bridge. The
emergency supply of lubricating oil in the gravity tanks will not be sufficient for more than a few minutes of
operation- lf permission cannot be granted, for example, during an emergency full astern, it is because the
risk of bearing and gear damage is an acceptable trade-off against greater danger to the ship or to personnel.
10.6 Starting auxiliary turbines
A generalized procedure is described here. The steps actually required depend on the particular installation
and application.
The unit is first inspected to ensure that it is closed up and ready for service. A small unit might be turned
over by hand while the operator listens for any scraping noise or any sign of resistance. oil levels are checked.
-
lf there is a pressure-fed lubrication system the priming pump is operated. Availability of cooling water, if
required, is verified. Linkages for governor valves or manual trips are inspected for: freedom of operation.
Steam drains are opened.
It is necessary to have the rotor spinning soon after steam is admitted so that it warms evenly. A no condensing
turbine is started by opening the exhaust valve fully, then opening the steam inlet valve
sufficiently to start the turbine turning. For a condensing turbine exhausting to an independent condenser,
the circulating water flow is established, then the steam inlet valve is opened sufficiently to start the turbine
turning; if there is a gland-seal steam supply it is then opened, and vacuum is raised. For a turbine
exhausting to a condenser already under a vacuum, the exhaust valve is opened slightly, then the steam inlet
valve is opened sufficiently to start the turbine turning; if there is a gland-seal steam supply it is then opened,
and then the exhaust valve is opened completely. Once the turbine is turning and the exhaust is established,
the drain valves are closed and the steam inlet valve is opened until the governor or other .control device
takes charge.
It is important to periodically test the safety devices, especially the over speed trip, and it is common to do this
when starting the turbine, but before placing it under load. After the devices are proven, they are reset the
steam inlet valve is again opened until the governor or other control device takes charge. At that point the
turbine is ready for load
OPERASI TURBIN UAP
Prosedur yang mendeskripsikan sini adalah untuk satu turbin uap mencocokkan ke satu baling alunan tetap, tapi
adalah. Umum jika tidak, dimaksud untuk menyediakan keterangan latar belakang hanyalah, dan tidak
menyeluruh atau semua termasuk.
Merekomendasikan prosedur untuk alat-alat perlengkapan spesifik harus dicari-cari dan ikuti.
10. 1 Persiapan, menaikkan ruang hampa, menghangat turbin
lf satu turbin telah ditutup untuk satu periode berkelanjutan, atau kalau selubung dari turbin atau perangkat
reduksi telah dibuka, pembuktian harus dicari bahwa semua objek asing, meliputi alat dan goda disingkirkan
sebelum selubung ditutup. Semua penetasan dan pembukaan inspeksi harus menjadi tertutup dan tersegel.
Indikator posisi di sekitar axis baling-baling harus dicek.
Minyak pelumas (LC) harus ada di satu suhu dari paling tidak 90oF (kesana-sini 39oC), suci, dan pada kondisi
bisa diterima. Minyak harus beredar melalui bahan pembersih untuk tentang duabelas utama jam untuk
penggunaannya untuk memastikan bahwa ini adalah bersih, bebas dari air, dan untuk membawakan ini sampai
minimum suhu, Saringan minyak harus dibersihkan. lf di situ adalah apapun ragukan sekitar mutu dari minyak,
satu contoh harus dikira menguji, dan kalau perlu, minyak harus dikirim ke LO menyetel mobil tempur, dan
sistem harus dialirkan, dibilas dan isi kembali
Pompa LO diawali. Ketika mobil tempur daya berat diisi ke taraf normal ini, taraf air bah adalah diperiksa dan
terkoreksi. Meminyaki aliran terhadap semuanya melahirkan dan mencocokkan rajut diverifikasi alir Selubung
dan tingkap pemadam dibuka. Ijin untuk berputar baling mempergunakan gir pemutaran harus diperoleh dari
anjungan. Gir pemutaran berhubungan dengan dan awali. Satu ronde dibuat, mendengarkan untuk bising tidak
biasa.
Pompa air beredar diluruskan dan awali, mempergunakan hisapan laut tinggi kalau di bandar atau di air dangkal.
Alir melalui kondensator dan LO lebih dingin diverifikasi.
-
Kondensasi katup edaran ulang dibuka, dan pompa kondensasi diawali. Dengan baling-baling turbin berputar
pada gir pemutaran, uap air diakui ke anjing laut kelenjar.. Kipas pembuangan udara kelenjar atau ejector
diawali.
Alat pembuang udara diawali: lf satu alat pembuang udara pancaran uap air dicocokkan, hanyalah langkah
kedua diawali dalam posisi ini, untuk mengacungkan ruang hampa untuk sekitar 15 inci air raksa (kesana-sini
0.5 batang).
Uap air utama menghadang katup dicek untuk melihat bahwa mereka ditutup, kemudian di depan dan gas katup
buritan kapal dibuka sepenuhnya, kemudian tertutup, untuk mencek operasi mereka. uap air kemudian adalah
membesarkan ke gas katup dengan baris alir dan alir tertutup. Jaga uap air buritan kapal katup dibuka. Ijin untuk
berputar baling dengan uap air harus diperoleh dari anjungan, . mengarahkan gir dilepaskan, dan dengan
seketika tingkap pemadam buritan kapal dibuka cukup untuk mengawali pemutaran baling-baling, kemudian
mencekik bawah untuk mempertahankan pemutaran batang pada tentang lima rpm, untuk tentang lima belas
detik. Tingkap pemadam di depan kemudian adalah terbuka, cukup lebar untuk mengawali pemintalan baling-
baling, kemudian mencekik bawah ke satu kecepatan batang dari sekitar lima rpm, dan tertutup setelah tentang
lima belas detik, Gantian bertukar-tukar ini berlanjut untuk tentang lima belas menit. Ronde harus dibuat
sementara baling-baling sedang memutar untuk mendengarkan untuk bising tidak biasa. Turbin memperingatkan
dan perjalanan diuji.
Setelah lima belas menit dari secara terus-menerus pemutar baling-baling secara berurutan di depan dan buritan
kapal, tingkap pemadam mungkin sebelah kiri tertutup untuk tiga ke lima menit di waktu aku, kemudian putar
dengan singkat di masing-masing arah. ketika permesinan disusun untuk menjembatani kontrol, satu pemintalan
baling-baling otomatis program diliputi, dan turbin dapat oleh karenanya jadi ditempatkan pada kontrol
anjungan dalam posisi ini. Setidak-tidaknya, prosedur ini berlanjut hingga mengatur siasat dimulai.
Tepat sebelum awal dari mengatur siasat ruang hampa kondensator periode dibesarkan ke normal
10. 2 Mengatur Siasat
Sepanjang mengatur siasat periode, katup jaga buritan kapal adalah buka, alir tingkap pemadam dan selubung
adalah buka, dan katup ekstraksi ditutup. lf merekalkulasi pompa pembayaran katup secara manual terkontrol,
ini biarkan tetap terbuka sepanjang. Kondensasi katup edaran ulang harus disesuaikan untuk mempertahankan
taraf suatu pada alir baik terus menerus. Kedua ini fungsi edaran ulang diotomatiskan untuk menjembatani
kontrol. Kapal Orr dengan suntikan sekop, pompa edar dioperasikan sepanjang mengatur siasat periode. Di
beberapa pabrik, kukus desakan dan suhu superheat dikurangi untuk mengatur siasat.
Selama mengatur siasat periode, di depan dan gas katup buritan kapal biasanya perintah pertemuan, yang
manapun oleh mengarahkan kontrol manual, atau di bawah pengendali jarak jauh dari stasiun kontrol mesin atau
dari anjungan. Tingkap pemadam jangan buka secara serempak: manapun tingkap pemadam dibuka harus
ditutup habis-habisan sebelum membuka yang lain. Ketika mengubah kecepatan, satu tingkap pemadam adalah
terbuka atau selanjutnya yang tertutup dibandingkan perlu untuk dengan cepat mencapai rpm diperlukan,
kemudian penyesuaian untuk memelihara rpm. Di bawah kontrol manual, setelan tingkap pemadam di depan
disederhanakan oleh penggunaan yang pertama langkah melelahkan desakan, yang hubungan secara konsisten
dengan rpm.
lf terdapat sebuah kecepatan kritis tempat latihan, ini dilalui dengan cepat.
Ketika melambatkan, kalau jalannya pada kapal ban mengarahkan baling pada satu kecepatan lebih tinggi
dibandingkan diorder, uap air buritan kapal biasanya benar rpm saat menggerakkan di depan, dan di depan uap
air dipergunakan ketika menggerakkan buritan kapal. Koreksi demikian adalah terutama diperlukan ketika satu
berhenti diorder, untuk mempertahankan baling dari mengarahkan. Selama satu berhenti berkelanjutan, baling-
baling pada waktu tertentu diputar di depan dan buritan kapal. Prosedur ini diotomatiskan untuk menjembatani
kontrol.
Selama mengatur siasat periode, instrumentasi dimonitor, secara manual atau secara otomatis. Dandang,
khususnya, ditonton lekat saat mereka menjawab untuk berganti di permintaan uap air. Bergantung kepada luas
-
dan kondisi otomasi tayang, ini mungkin perlu untuk membuat penyesuaian untuk mempertahankan suhu,
desakan, dan tingkat diantara batas. Satu jaga-jaga umum adalah untuk mempertahankan pembayaran penolong
memompa siap, dihangat, dan dengan hanya katup berhenti uap airnya tertutup.
Untuk menolong memastikan kelangsungan elektris barang persediaan, ini adalah satu praktek umum untuk
mempertahankan satu kapal tambahan generator jasa dengan segera. Dimana digerakkan mesin pendorong
dicocokkan, bis mungkin dibagi untuk mengisolasikan pendorong dari jasa lain.
Pada akhir dari satu periode mengatur siasat keberangkatan, alir tingkap pemadam dan selubung ditutup, dan
katup jaga buritan kapal ditutup. Angka benar dari di depan alat pemercik untuk kecepatan diperlukan dibuka,
dan tingkap pemadam di depan secara berangsur-angsur terbuka sepenuhnya. lf mengukus desakan dan / atau
suhu dikurangi untuk mengatur siasat periode, nilai normal secara berangsur-angsur tersimpan ulang. Beri
makan pompa dan kondensasi katup edaran ulang ditutup.
Katup ekstraksi dibuka. Uap air tinggal ke sistem anjing laut kelenjar diamankan. kalau menyiram permisi
kedalaman, pompa edar ditukarkan ke laut rendah hisap. Pada kapal dengan suntikan sekop, katup sekop dibuka
dan pompa edar dihadang. Generator tambahan diamankan. Pada dandang, alat penyemprot memasang ujung
ukuran dan angka dari pembakar di penggunaan disesuaikan untuk mencocokan permintaan uap air.
10. 3 operasi Rutin
Sementara dalam perjalanan di kekuatan mantap, semua instrumentasi dimonitor, secara manual atau secara
otomatis, dan penyesuaian dibuat seperti yang diperlukan. Bahkan di pabrik dengan otomasi luas, merekayasa
tetap perbuatan membulatkan, mendengarkan untuk bising tidak biasa, mencari bocor dan sumber dengan
getaran tidak biasa, dan gelas pandangan mata pengecekan dan taraf zalir: Kecenderungan adalah terkenal akan
nilai mereka di pemeliharaan perencanaan dan di dalam menghindari kegagalan tak diduga.
Ketika satu pengurangan kecepatan diorder, gas katup mungkin dipergunakan untuk satu tanggapan langsung,
tapi satu penyesuaian masa lebih panjang dibuat dengan menyesuaikan angka dari alat pemercik, kemudian
pembukaan tingkap pemadam lagi. Group alat pemercik. di penggunaan harus selalu menjadi berdekatan untuk
satu sama lain.
Bahan pembersih LO disimpan jalan pintas berkepanjangan. layanan pada air bah utama. Bahan pembersih dan
saring LO adalah
membersihkan mingguan, atau saat pengalaman dikte, dan akumulasi diuji untuk jejak metalik. meminyaki
contoh harus ditarik bulanan untuk satu analisa dari fisik dan kimia sifat dari minyak, yang yang dapat
mengungkapkan Masalah masih dalam permulaan
10. 4 Mengamankan
Pada akhir dari satu periode mengatur siasat kedatangan katup ekstraksi ditutup, katup jaga buritan kapal adalah
buka, alir tingkap pemadam dan selubung adalah buka,. uap air tinggal menyediakan ke kelenjar adalah buka,
pompa pembayaran
katup edaran ulang dan kondensasi katup edaran ulang. adalah buka, dan turbin diputar pada waktu tertentu
dengan uap air. Keadaan ini dipelihara hingga anjungan yang punya tertentu dan terkonfirmasi order,
diselesaikan dengan mesin uap air utama menghadang katup kemudian adalah tertutup, dan gas katup biasanya
tempat pembuangan sampah apapun uap air" sisa pada gerigi garpu. gas katup aku kemudian adalah tertutup
dengan ketat, dan dengan seketika, gir pemutaran berhubungan dengan dan awali '
Alat pembuang udara diamankan, tapi anjing laut segel kelenjar dipelihara, sehingga ruang hampa itu pecah
meskipun demikian lubang angin alat pembuang udara, rada dibandingkan melalui kelenjar alat pembungkus.
ketika tekanan atmosfer jangkauan kondensator, uap air segel kelenjar barang persediaan ditutup, dan kipas
pembuangan udara kelenjar atau ejector dihadang. ketika sumur alir kondensator taraf adalah normal, pompa
kondensasi dan pompa edar dihadang.
Setelah beberapa jam, ketika baling-baling turbin telah menyejukkan ke suhu ambient, gir pemutaran adalah
dihadang (tetapi bukan lepaskan) dan pompa LO dihadang.
-
Berselang sehari pada kosong, satu pompa LO diawali, dan ketika meminyaki aliran dikonfirmasikan pada
dukung dan gigi persneling, gir pemutaran diawali dan menjalankan untuk tentang lima belas menit,
memperhatikan untuk menghadang batang pada satu posisi berbeda setiap kali. Pada waktu yang sama, alat
pembuang udara lari menuju gambar udara terbuka melalui turbin dengan alat pembuang udara pancaran uap air,
langkah kedua adalah cukup untuk penggunaan ini. lf portabel, bahan pembersih LO harus dioperasikan secara
terus-menerus pada air bah utama, dengan uap air ke alat pemanas, untuk mencegah kondensasi pada kasus
mencocokkan.
10. 5 operasi Darurat
seberangi turbin senyawa diperlukan dicocokkan dengan pengaturan untuk membypass yang manapun turbin,
jika satu masalah dengan turbin atau ini mencocokkan kereta api. umumnya, dengan satu turbin, kurang dari
setengah dari kekuatan bertingkat dapat dicapai karena akibat tenaga putaran batasi pada batang dan gir. Satu
pengaturan khas melibatkan blanked flens pada tingkap pemadam, penyeberangan jalan, dan anak teluk
kondensator, bagian perlu dengan salurkan lewat pipa penghubung, dan mulut untuk membatasi aliran uap air.
lf turbin tekanan tinggi adalah jalan pintas, tingkap pemadam di depan dihubungkan secara langsung ke
penyeberangan jalan oleh darurat dirakit setengah jadi menyalurkan lewat pipa bagian, dengan satu mulut
memasukkan setelah gas katup kosong ' dan satu dimasukkan pada lelah tekanan tinggi flens. Turbin tekanan
tinggi diputuskan dari cocok. di jasa, tingkap pemadam di depan biasanya mengontrol desakan uap air, sampai
maksimum simpan mulut.
Ini mungkin perlu untuk mengurangi suhu uap air, juga. kalau turbin buritan kapal berada di atas baling-baling
low-pressure, tersedia sisa ini.
Kalau turbin low-pressure adalah bypassed, penyeberangan jalan dihubungkan secara langsung ke anak teluk
kondensator, dan satu kosong dimasukkan pada turbin low-pressure anak teluk. Satu mulut dimasukkan setelah
gas katup di depan. Turbin low-pressure bypassed diputuskan dari cocok. Di operasi, gas katup di depan
kemudian adalah dipergunakan untuk kontrol mengukus desakan, sampai pembatas menyimpan mulut. lf turbin
buritan kapal berada di atas baling-baling low-pressure, tidak ada buritan kapal mendaya ada tersedia. Pada
kenyataan, pipa uap buritan kapal harus blanked batal, atau katup buritan kapal kawat tertutup sebagai satu jaga-
jaga keselamatan.
lf, setelah satu berhenti berlarut-larut, satu baling-baling bergetar atau memekik sebagai tingkap pemadam
dibuka, iniku menjadi karena baling-baling dilengkungkan dari pemanasan tidak seimbang. Masalah dapat
sering menjadi terpecahkan dengan kerusakan minimal dengan memutar baling-baling di kecepatan rendah untuk
beberapa menit untuk memanaskan ini datar.
lf melumasi tekanan oli menggagal sementara batang sedang mengarahkan, tingkap pemadam akan menutup
secara otomatis. Bagaimanapun, dengan cara pada kapal, batang akan berlanjut diarahkan oleh baling. Alhasil,
pergeseran harus dihadang, dan ada pada satu berhenti, mempergunakan uap air, walau ijin untuk melakukan
harus o5iained dari anjungan. Barang persediaan keadaan darurat dari minyak pelumas pada mobil tempur daya
berat tidak akan cukup untuk lebih dari beberapa menit operasi ijin lf tidak dapat diwariskan, antara lain,
selama satu darurat buritan kapal penuh, ini adalah karena risiko dari kerusakan kaitan dan gir adalah satu jual
bisa diterima melawan bahaya lebih besar ke kapal atau ke personalia.
10. 6 turbin pelengkap Permulaan
Satu prosedur disamaratakan dideskripsikan sini. Tahapan sebenarnya memerlukan bergantung kepada instalasi
tertentu dan aplikasi.
Unit yang pertama memeriksa pastikan bahwa ini ditutup rapat-rapat dan siap untuk layani. Satu unit kekecilan
mungkin diserahkan oleh tangan sementara operator mendengarkan untuk apapun bising garutan atau apapun
tanda daya tahan. meminyaki bertingkat dicek. lf terdapat sebuah paksa memberi makan sistem pemberian
minyak pelumas pompa cat dasar dioperasikan. Availabilitas dari air pendingin, kalau diperlukan, diverifikasi.
Pertalian untuk katup gubernur atau perjalanan manual diperiksa untuk: kebebasan untuk operasi. Mengukus alir
dibuka.
-
Ini perlu untuk mempunyai pemintalan baling-baling segera setelah uap air diakui sangat yang ini menghangat
datar. Satu tidak ada turbin pemadatan diawali dengan membuka katup buang sepenuhnya, kemudian
pembukaan katup anak teluk uap air
cukup untuk mengawali pemutaran turbin. Untuk satu turbin pemadatan melelahkan ke satu kondensator
independen, aliran air sirkulasi didirikan, kemudian katup anak teluk uap air dibuka cukup untuk mengawali
pemutaran turbin; kalau terdapat sebuah kelenjar menyegel barang persediaan uap air ini kemudian adalah
terbuka, dan ruang hampa dinaikkan. Untuk satu turbin melelahkan ke satu kondensator telah pada satu ruang
hampa, katup buang dibuka sedikit, kemudian katup anak teluk uap air dibuka cukup untuk mengawali
pemutaran turbin; kalau terdapat sebuah kelenjar menyegel barang persediaan uap air ini kemudian adalah
terbuka, kemudian katup buang dibuka habis-habisan. Satu kali turbin sedang mengarahkan dan lelah didirikan,
katup alir ditutup dan katup anak teluk uap air dibuka hingga gubernur atau pengambilan lain alat .control beban.
Ini penting untuk pada waktu tertentu menguji alat keselamatan, terutama kecepatan terlalu jalani, dan ini umum
untuk lakukan ini ketika mengawali turbin, tapi sebelum menempatkan ini berbebanarus. Setelah alat
dibuktikan, mereka ditata ulang katup anak teluk uap air adalah lagi terbuka hingga gubernur atau alat kontrol
lain mengambil beban. Di titik itu turbin adalah siap untuk isi
OPERASI Turbin Uap
Prosedur-prosedur menggambarkan di sini adalah untuk suatu turbin uap menghubungkan suatu baling-baling
titi nada/lemparan yang ditetapkan?diperbaiki, tetapi adalah. Jika tidak umum, yang diharapkan untuk
menyediakan informasi latar belakang saja, dan bukanlah semua termasuk atau menyeluruh.
Prosedur-prosedur direkomendasikan untuk peralatan yang spesifik harus dicari-cari dan diikuti.
101 Preparation, ruang hampa peningkatan, hangat turbin
lf suatu turbin mempunyai henti sela untuk satu periode yang diperluas, atau jika selubung-selubung turbin-
turbin atau roda-gigi reduksi telah dibuka, verifikasi harus dicari bahwa semua object yang asing, termasuk
perkakas dan perca dipindahkan sebelum selubung-selubung itu tertutup. Semua pintu bawah dan bukaanperiksa
harus tertutup dan tersegel.
indikator posisi Baling-baling di sekitar axis harus dicek.
Minyak pelumas (LC) harus pada suatu temperatur dari sedikitnya 90oF (tentang 39oC), membersihkan, dan di
dalam kondisi yang bisa diterima. Minyak itu harus diedarkan melalui bahan pembersih untuk sekitar dua belas
jam sebelum penggunaannya untuk memastikan bahwa nya membersihkan, bebas dari air, dan untuk membawa
nya sampai ke temperatur yang minimum, Saringan minyak harus dibersihkan. lf ada setiap keraguan sekitar
mutu minyak, suatu contoh harus dikira menguji, dan jika yang perlu, minyak itu harus ditransfer ke tangki/tank
pengaturan LO, dan sistim itu harus dialirkan, yang dibilas dan diisi kembali
pompa LO dimulai. Ketika tangki gravitasi itu diisi kepada tingkatan nya yang normal, tingkatan air bah dicek
dan dikoreksi. Minyak mengalirkan kepada semua jala-jala kehilangan akal dan roda-gigi dibuktikan Casing dan
tingkap pemadam mengalirkan dibuka. Ijin untuk berputar baling-baling menggunakan roda-gigi yang
pemutaran yang harus diperoleh dari jembatan. Roda-gigi yang pemutaran ditautkan dan dimulai. Suatu putaran
dibuat, mendengarkan karena suara gaduh yang tidak biasa.
Pompa air edar adalah berbaris dan memulai, menggunakan pengisapan laut yang tinggi jika di dalam pelabuhan
atau di dalam air yang dangkal .Mengalir sepanjang pemadat dan LO pendingin dibuktikan.
-
Air kondensasi -klep sirkulasi ulang dibuka, dan pompa kondesat itu dimulai. Dengan baling-baling-baling-
baling turbin yang berputar di roda-gigi yang pemutaran, uap air diakui sebagai kelenjar/penekan seals..The
kipas buang kelenjar/penekan atau ejector dimulai.
Ejector angkasa dimulai: lf suatu alat pembuang udara pancaran-uap adalah, dicoba, hanya langkah?tahap yang
kedua dimulai pada ini, untuk menaikkan ruang hampa kepada sekitar 15 inci dari air raksa (sekitar 05
bar?palang).
Katup penghenti uap air utama dicek untuk lihat bahwa mereka tertutup, dan lalu di depan dan katup gas buritan
kapal dibuka secara penuh, lalu menutup, untuk memeriksa operasi mereka. uap air kemudian adalah yang
dididik kepada katup gas dengan baris mengalirkan dan saluran-saluran dinutup. Klep penjagaan uap air buritan
kapal dibuka. Ijin untuk berputar baling-baling dengan uap air yang harus diperoleh dari jembatan, .roda-gigi
yang pemutaran dilepaskan, dan dengan segera tingkap pemadam buritan kapal dibuka cukup untuk mulai
baling-baling-baling-baling memutar, lalu mencekik hingga [menuju] ke nafkah batang memutar pada sekitar
lima rpm, untuk sekitar lima belas [detik / barang bekas]. Di depan tingkap pemadam kemudian adalah dibuka,
lebar/luas cukup untuk mulai pemintalan baling-baling-baling-baling, lalu mencekik hingga [menuju] ke suatu
kecepatan poros dari sekitar lima rpm, dan menutup setelah sekitar lima belas [detik / barang bekas], Perputaran
bertukar-tukar ini dilanjutkan untuk sekitar lima belas menit. Putaran harus dibuat selagi baling-baling itu sedang
memutar untuk mendengarkan karena suara gaduh yang tidak biasa. Alarm-alarm turbin dan perjalanan-
perjalanan diuji.
Setelah lima belas menit dari secara terus-menerus memutar baling-baling-baling-baling secara berurutan di
depan dan buritan kapal, tingkap pemadam itu bisa ditinggalkan tertutup selama tiga sampai lima menit pada i
waktu, lalu memutar dengan singkat pada setiap arah. ketika permesinan diatur karena kendali jembatan, satu
program pemintalan baling-baling yang otomatis dimasukkan, dan turbin-turbin itu dapat oleh karena itu
ditempatkan di kendali jembatan dalam posisi ini. Setidak-tidaknya, prosedur ini dilanjutkan sampai bermanuver
dimulai .
Tepat sebelum awal dari bermanuver ruang hampa pemadat periode dididik kepada yang normal
102 Maneuvering
Sepanjang bermanuver periode, klep penjagaan buritan kapal bersikap terbuka, tingkap pemadam dan selubung
mengalirkan bersikap terbuka, dan klep-klep [pengambilan/penyaringan] tertutup. lf pompa-pengisian ketel
recalculating klep adalah dengan tangan terkendali, itu dibiarkan terbuka dalam keseluruhannya. Klep sirkulasi
ulang air kondensasi yang harus disesuaikan untuk menyimpan(pelihara suatu tingkatan di dalam sumur kuras
terus menerus. Keduanya sirkulasi ulang ini berfungsi diotomatkan karena kendali jembatan. Orr kirim dengan
suntikan sekop, pompa edar itu menjalankan sepanjang bermanuver periode. Dalam beberapa pabrik-pabrik,
temperatur tekanan uap dan bahang lewat jenuh dikurangi karena bermanuver.
Selama bermanuver periode, di depan dan katup gas buritan kapal digunakan untuk temu perintah-perintah,
yang manapun oleh kontrol manual yang langsung, atau di bawah pengendalian jarakj dari setasiun kendali enjin
atau dari jembatan. Tingkap pemadam itu tidak pernah membuka secara serempak: tingkap pemadam yang mana
saja dibuka harus tertutup dengan sepenuhnya sebelum membuka yang lain. Ketika mengubah kecepatan, suatu
tingkap pemadam dibuka atau tertutup lebih lanjut dibanding perlu dengan cepat mencapai rpm yang diperlukan,
lalu yang disesuaikan untuk memelihara rpm. Di bawah kontrol manual, di depan pengaturan-pengaturan tingkap
pemadam disederhanakan dengan menggunakan tekanan buang langkah yang pertama, yang menghubungkan
secara konsisten dengan rpm.
lf ada suatu cakupan kecepatan kritis, itu dilewati dengan cepat.
Ketika melambatkan, jika cara di atas putaran kapal ban, baling-baling pada suatu kecepatan yang lebih tinggi
dibanding yang diperintah(dipesan, uap air buritan kapal digunakan untuk mengoreksi rpm selagi bergerak di
depan, dan di depan uap air digunakan ketika menggerakkan buritan kapal. Koreksi seperti itu adalah terutama
diperlukan ketika suatu perhentian diperintah(dipesan, untuk menyimpan(pelihara baling-baling dari memutar.
-
Selama satu perhentian yang diperluas, baling-baling-baling-baling itu pada waktu tertentu diputar di depan dan
buritan kapal. Prosedur-prosedur ini diotomatkan karena kendali jembatan.
Selama bermanuver periode, instrumentasi dimonitor, dengan tangan atau secara otomatis. Ketel uap,
khususnya, diamati lekat ketika mereka bereaksi terhadap perubahan-perubahan di dalam permintaan uap air.
Tergantung pada tingkat dan syarat otomasi menyajikan, mungkin saja perlu membuat penyesuaian-penyesuaian
untuk menyimpan(pelihara temperatur-temperatur, tekanan-tekanan, dan mengukur berbatasan; tidak lewat dari.
Suatu tindakan pencegahan yang umum untuk menyimpan(pelihara pompa umpan standby siap, warmed, dan
dengan hanya katup penghenti uap air nya dinutup.
Untuk membantu memastikan kesinambungan penyediaan yang elektris, [ini] merupakan suatu praktek yang
umum untuk menyimpan(pelihara satu generator layanan tambahan kapal dengan segera. Di mana pendorong-
pendorong yang digerakkan mesin dicoba, bus itu bisa dibagi untuk mengisolasikan pendorong-pendorong dari
jasa lainnya.
Pada akhir suatu keberangkatan yang bermanuver periode, tingkap pemadam dan selubung mengalirkan
tertutup, dan klep penjagaan buritan kapal tertutup. Nomor yang benar di depan alat pemercik untuk kecepatan
yang diperlukan dibuka, dan di depan tingkap pemadam adalah secara berangsur-angsur dibuka secara penuh. lf
tekanan uap dan/atau temperatur dikurangi karena bermanuver periode, nilai-nilai normal secara berangsur-
angsur dipulihkan. klep-klep sirkulasi ulang Pompa-Pengisian Ketel dan air kondensasi tertutup.
Klep-klep [pengambilan/penyaringan] 'dibuka. Uap segar kepada kelenjar/penekan menyegel sistim dijamin
aman. jika kedalaman air mengizinkan, pompa edar itu diswitch kepada pengisapan laut yang rendah. Di atas
kapal-kapal dengan suntikan sekop, klep sekop dibuka dan pompa edar itu dihentikan. Generator-generator
tambahan dijamin aman. Di ketel uap, alat penyemprot memasang ujung ukuran-ukuran dan banyaknya
pembakar-pembakar digunakan disesuaikan untuk memenuhi permintaan uap air .
103 operasi Routine
Sementara yang dalam perjalanan pada kuasa(tenaga yang mantap, semua instrumentasi dimonitor, dengan
tangan atau secara otomatis, dan penyesuaian-penyesuaian dibuat seperti diperlukan. Bahkan di dalam pabrik-
pabrik dengan otomasi yang luas, insinyur-insinyur membuat putaran-putaran reguler, mendengarkan karena
suara gaduh yang tidak biasa, mencari kebocoran-kebocoran dan sumber dari getaran yang tidak biasa, dan
mengecek kacamata penglihatan dan cairan mengukur: Trend bersifat nilai terkenal akan mereka di dalam
merencanakan pemeliharaan dan di dalam menghindari kegagalan tak diduga.
Ketika suatu pengurangan kecepatan diperintah(dipesan, katup gas bisa digunakan untuk satu tanggapan yang
segera, tetapi suatu penyesuaian istilah yang lebih panjang dibuat dengan menyesuaikan banyaknya alat
pemercik, lalu membuka tingkap pemadam lagi; kembali. Alat pemercik menggolongkan .digunakan perlu selalu
adalah damping kepada satu sama lain.
bahan pembersih LO adalah bertahan bypass berkelanjutan. layani di air bah utama. Bahan pembersih dan LO
menyaring adalah
mingguan yang dibersihkan, atau sebagai pengalaman mendikte, dan akumulasi-akumulasi diuji untuk runutan
yang metalik. minyak mencicip harus menarik mundur bulanan untuk satu analisa dari kekayaan kimia dan
secara fisik dari minyak, kaleng yang ungkapkan pemula Problems
104 Securing
Pada akhir satu kedatangan yang bermanuver periode klep-klep [pengambilan/penyaringan] tertutup, klep
penjagaan buritan kapal bersikap terbuka, tingkap pemadam dan selubung mengalirkan bersikap terbuka,.
penyediaan uap segar kepada kelenjar/penekan-kelenjar/penekan bersikap terbuka, pompa-pengisian ketel
-
klep sirkulasi ulang dan klep sirkulasi ulang air kondensasi. bersikap terbuka, dan turbin-turbin itu sedang
diputar pada waktu tertentu dengan uap air. Situasi ini dipelihara; dipertahankan sampai jembatan sudah
memberi dan menetapkan order(pesanan, tidak berhubungan lagi mesin-mesin Katup penghenti uap air utama
kemudian adalah menutup, dan katup gas itu digunakan untuk membuang setiap uap air" menetap di dalam
gerigi garpu. Aku katup gas kemudian adalah menutup dengan ketat, dan dengan segera, roda-gigi yang
pemutaran ditautkan dan dimulai'
Alat pembuang udara dijamin aman, tetapi segel penyegel kelenjar/penekan dipelihara; dipertahankan, sehingga
ruang hampa pecah(rinci meskipun [demikian] lubang angin alat pembuang udara, dibanding melalui parcel.
ketika pemadat menjangkau tekanan udara, pemasukan uap penyegel kelenjar/penekan tertutup, dan kipas buang
kelenjar/penekan atau ejector dihentikan. ketika tingkatan sumur kuras pemadat adalah normal, pompa kondesat
dan pompa edar dihentikan.
Setelah beberapa jam, ketika baling-baling-baling-baling turbin sudah mendinginkan kepada suhu lingkungan,
roda-gigi yang pemutaran adalah
dihentikan (tetapi tidak dilepaskan) dan pompa LO dihentikan.
Berselang sehari pada anggur, suatu pompa LO dimulai, dan ketika minyak mengalirkan ditetapkan di
kehilangan akal dan persneling, roda-gigi yang pemutaran dimulai' dan yang dicalonkan untuk sekitar lima belas
menit, berhati-hati untuk berhenti batang di suatu posisi yang berbeda setiap kali. Pada waktu yang sama, ejector
angkasa mencapai/lari menuju udara terbuka seri melalui dengan alat pembuang udara pancaran-uap turbin itu,
langkah?tahap yang kedua adalah cukup untuk tujuan ini. lf yang jinjing, bahan pembersih LO harus
lari/dijalankan secara terus-menerus di air bah utama, dengan uap air kepada alat pemanas, untuk mencegah
pemadatan di dalam rumah roda-gigi.
105 operasi Emergency
salib turbin-turbin campuran diwajibkan untuk dicoba dengan pengaturan-pengaturan untuk bypass yang
manapun turbin, dalam hal suatu masalah dengan turbin atau rangkaian roda-gigi nya. secara umum, dengan
turbin nya, kurang dari separuh dari kuasa(tenaga yang dinilai dapat dicapai oleh karena tenaga putaran
membatasi di batang-batang dan roda-gigi. Suatu pengaturan yang khas melibatkan flens,pinggiran roda blanked
di tingkap pemadam, penyeberangan jalan, dan pintu masuk pemadat-pemadat, bagian-bagian yang perlu
menghubungkan memasang pipa, dan mulut-mulut untuk membatasi uap air mengalirkan. lf turbin yang tekanan
tinggi membypass, di depan tingkap pemadam dihubungkan secara langsung kepada penyeberangan jalan oleh
merakit setengah jadi bagian pipa darurat, dengan satu mulut menyisipkan setelah katup gas' dan suatu bahan
tebuk disisipkan di dalam yang tekanan tinggi membuang flens,pinggiran roda. Turbin yang tekanan tinggi
diputus dari perpindahan roda gigi. dalam jabatan, di depan tingkap pemadam digunakan untuk mengendalikan
tekanan uap, sampai ke suatu maksimum menyimpan mulut.
Mungkin saja perlu mengurangi temperatur uap air, juga. jika turbin mundur itu di baling-baling yang tekanan
rendah, itu tetap tersedia.
Jika turbin yang tekanan rendah dibypass, penyeberangan jalan itu dihubungkan secara langsung kepada pintu
masuk pemadat, dan suatu bahan tebuk disisipkan di pintu masuk turbin yang tekanan rendah. Satu mulut
disisipkan setelah di depan katup gas. Turbin tekanan rendah yang dibypass diputus dari perpindahan roda gigi.
Di dalam operasi, di depan katup gas kemudian adalah digunakan untuk mengendalikan tekanan uap, sampai ke
batas menyimpan mulut. lf turbin mundur itu di baling-baling yang tekanan rendah, tanpa daya mundur ada
tersedia. Sebenarnya, garis uap air buritan kapal harus blanked batal, atau klep-klep buritan kapal melengkapi
menutup sebagai suatu tindakan pencegahan.
lf, setelah suatu perhentian yang diperpanjang, suatu baling-baling bergetar atau memekik seperti(ketika tingkap
pemadam itu dibuka, itu ku adalah karena baling-baling itu melengkung dari pemanasan yang tidak seimbang.
Masalah itu dapat sering kali dipecahkan dengan kerusakan minimal dengan pemintalan baling-baling pada
kecepatan rendah untuk beberapa beberapa menit untuk memanaskan nya datar.
-
lf tekanan minyak pelumas gagal selagi batang itu sedang memutar, tingkap pemadam itu akan menutup secara
otomatis. Bagaimanapun, dengan cara di atas kapal, batang itu akan melanjutkan untuk diputar oleh baling-
baling. Sebagai konsekwensi, pergeseran harus dihentikan, dan yang diadakan pada suatu perhentian,
menggunakan uap air, meski ijin untuk melakukannya harus o5iained dari jembatan. Suplai gawat darurat dari
minyak pelumas di dalam tangki gravitasi itu tidak akan menjadi cukup untuk lebih dari (sekedar) beberapa
menit ijin operationlf tidak bisa dihibahkan, sebagai contoh, selama satu buritan kapal darurat penuh, itu adalah
karena resiko dari bantalan dan roda-gigi rusak adalah satu yang bisa diterima menjual melawan terhadap bahaya
yang lebih besar kepada kapal atau kepada personil.
106 turbin bantu Starting
Suatu prosedur yang disamaratakan digambarkan di sini. Langkah-langkah benar-benar memerlukan bergantung
pada instalasi dan aplikasi yang tertentu.
Unit itu adalah pertama diperiksa untuk memastikan bahwa nya ditutup rapat-rapat/dipenuhi dan tersedia bagi
layanan. Suatu unit yang kecil boleh jadi diserahkan dengan tangan selagi operator mendengarkan karena setiap
suara gaduh kikisan atau setiap tanda dari pembalasan. aras minyak dicek. lf ada suatu tekanan memberi makan
sistim pemberian minyak pelumas pompa pemancing itu dioperasikan. Ketersediaan air penyejuk, jika
diperlukan, dibuktikan. Pertalian-pertalian untuk katup governor atau perjalanan-perjalanan manual diperiksa
:kebebasan untuk operasi. Uap air mengalirkan dibuka.
Perlu mempunyai pemintalan baling-baling segera setelah uap air diakui(diijinkan sehingga itu hangatkan datar.
Suatu tidak ada turbin kondensor dimulai dengan pembukaan katup buang secara penuh, lalu membuka katup
masuk uap air
cukup untuk mulai turbin memutar. Karena suatu turbin kondensor yang melelahkan kepada satu pemadat yang
mandiri, air edar mengalirkan dibentuk/mapan, lalu katup masuk uap air dibuka cukup untuk mulai turbin
memutar; jika ada suatu kelenjar/penekan menyegel pemasukan uap yang kemudian adalah dibuka, dan ruang
hampa diangkat. Karena suatu turbin yang melelahkan ke(pada suatu pemadat telah di bawah suatu ruang
hampa, katup buang itu dibuka sedikit, lalu katup masuk uap air dibuka cukup untuk mulai turbin memutar; jika
ada suatu kelenjar/penekan menyegel pemasukan uap yang kemudian adalah dibuka, dan lalu katup buang itu
dibuka dengan sepenuhnya. Begitu turbin itu sedang memutar dan membuang dibentuk/mapan, katup kuras itu
tertutup dan katup masuk uap air dibuka sampai gubernur atau yang lain .alat kendali memegang pimpinan.
Adalah penting untuk pada waktu tertentu menguji alat pengaman, terutama (di) atas perjalanan kecepatan, dan
itu adalah umum untuk lakukan hal ini ketika memulai turbin, tetapi sebelum menempatkan nya yang
berbeban[arus]. Setelah alat-alat terbukti, mereka atur ulang katup masuk uap air adalah lagi; kembali dibuka
sampai gubernur atau alat kendali lain memegang pimpinan. Pada waktu itu turbin itu adalah tersedia bagi beban