A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING...
Transcript of A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING...
![Page 1: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/1.jpg)
A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT
• Diana Salhab
Ph.D. Student, Department of Civil and Environmental Engineering, University of Alberta (U of A), [email protected]
• Karim Noueihed
M.Sc. Student, Department of Civil and Environmental Engineering, U of A, [email protected]
• Ahed Fayek
M.Eng. Student, Department of Civil and Environmental Engineering, U of A, [email protected]
• Farook Hamzeh
Associate Professor, Department of Civil and Environmental Engineering, U of A, [email protected]
• Ritu Ahuja
Lean Integration Leader, Kinetic Construction Ltd., [email protected]
![Page 2: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/2.jpg)
AGENDA
Conclusion
Application of
Framework Results
Suggested Framework
MethodologyLiterature
ReviewIntroduction
![Page 3: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/3.jpg)
Presentación
INTRODUCTION
LPS aims at reducing variability
in construction works (Hamzeh et
al. 2012)
COVID-19 wasn't accounted for in any production
system
Restrictions issued such as limited
person to person contact (Parr et al.
2021)
Shift to online communication
platforms
![Page 4: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/4.jpg)
Presentación
INTRODUCTION
01
02
Adapting to new work conditions
Current LPS practices yet to beexplored
Framework: reintroducing different aspects of lean philosophy to pave the way for successful implementation of LPS in a virtual environment
Questionnaire: assessing the enablers and challenges currently faced
Problem statement
Study contribution
![Page 5: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/5.jpg)
LITERATURE REVIEW
Researcher Challenges to LPS Implementation
Viana et al. (2010)
Difficulty in adapting to the new culture
Incompatible personnel qualifications
Long time spent on planning issues
Ballard et al. (2007)
Strong resistance to change
Lack of leadership
Lack of commitment from upper management
Hamzeh et al. (2016)Different levels of understanding of Lean Construction
philosophy
Non-collaborative development of the master schedule
Porwal et al. (2010)
Lack of training
Lack of leadership
Failure of management commitment/organizational climate
Organizational inertia & resistance to change
Table 1. Literature Review on Challenges to LPS Implementation
![Page 6: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/6.jpg)
Design Science Research (DSR)
Presentación
METHODOLOGY
1.Problem identification: implementing LPS in a
virtual environment
2.Solution design: framework that targets these
challenges
3.
Evaluation: expert panel questionnaire of practitioners applying LPS in the current situation
![Page 7: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/7.jpg)
SUGGESTED FRAMEWORK
Framework: reintroduces different aspects of lean philosophy to pave the way for successful implementation of LPS
Figure 1. Flowchart of the Framework
![Page 8: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/8.jpg)
APPLICATION OF FRAMEWORK RESULTS
12- How can you improve the LPS implementation and increase trust and transparency in your opinion in a virtual environment?-More practice, Training
13- What do you think can be done to get culture lean in a virtual environment?-Proper Training
14- What is the main challenge you are facing in implementing LPS in the virtual environment?-Having a positive buy-in, absence of face-to-face interaction
Figure 2. Questionnaire
![Page 9: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/9.jpg)
APPLICATION OF FRAMEWORK RESULTS: SENIOR MANAGER INTERVIEW
1
Extremely important
Face to face interaction
Major issue
Lack of physical interaction
Major challengeBody language and tactile factor:prerequisite for buy in
Keeping trades engagedand winning their buy-in
Very effective but softwarecannot be used to manage allaspects of a project
Using software:
![Page 10: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/10.jpg)
Presentación
DISCUSSION
Questionnaire findings:Embracement of LPS practices
Encouragement to work on LPS software
More effective to complete meetings online
Drawbacks:
Spending time adapting to new technologies -> fast learning curve
Passiveness and less engagement in online meetings
Framework:
Spreading a culture of learning and cooperation
Providing various types of training
Maintaining physical separation
Visual control over commitment fulfillments -> enforces commitment
![Page 11: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/11.jpg)
CONCLUSIONS
LPS implementation holds the potential of new challenges after the restrictions. Framework: providing a lean culture, providing various types of training…
Virtual environment embraces this framework and LPS implementation Practitioners are introduced to advantages of lean
Limitation: only five practitioners are interviewedRecommendation: interview further practitioners and explore additional aspects of the virtual implementation
![Page 12: A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER … · 2021. 7. 16. · A FRAMEWORK FOR IMPLEMENTING THE LAST PLANNER SYSTEM IN A VIRTUAL ENVIRONMENT • Diana Salhab Ph.D. Student,](https://reader035.fdocuments.net/reader035/viewer/2022071523/613ce4ad4c23507cb635ac4e/html5/thumbnails/12.jpg)
THANK YOU!Questions?