98489540 project-report-ee-vt

38
TURBOGENERATOR Homework Help https://www.homeworkping.com/ Research Paper help https://www.homeworkping.com/ Online Tutoring https://www.homeworkping.com/ click here for freelancing tutoring sites INTRODUCTION A turbo generator is a turbine directly connected to an electric generator for the generation of electric power. Large steam powered turbo generators (steam turbine generators) provide the majority of the world's electricity and are also used by steam powered turbo-electric ships. Smaller turbo-generators with gas turbines are often used as auxiliary power units. For base loads diesel generators are usually preferred, since they offer much better fuel efficiency and are also more reliable, but on the other hand they are much heavier and need more space. The efficiency of larger gas turbine plants can be enhanced by using a combined cycle, where the hot exhaust gases are used to generate steam which drives another turbo generator. 1

Transcript of 98489540 project-report-ee-vt

Page 1: 98489540 project-report-ee-vt

TURBOGENERATOR

Homework Help httpswwwhomeworkpingcom

Research Paper helphttpswwwhomeworkpingcom

Online Tutoringhttpswwwhomeworkpingcom

click here for freelancing tutoring sites

INTRODUCTION

A turbo generator is a turbine directly connected to an electric generator for the generation of electric power Large steam powered turbo generators (steam turbine generators) provide the majority of the worlds electricity and are also used by steam powered turbo-electric shipsSmaller turbo-generators with gas turbines are often used as auxiliary power units For base loads diesel generators are usually preferred since they offer much better fuel efficiency and are also more reliable but on the other hand they are much heavier and need more spaceThe efficiency of larger gas turbine plants can be enhanced by using a combined cycle where the hot exhaust gases are used to generate steam which drives another turbo generator The Turbo generator was invented by a Hungarian engineer Ottoacute Blaacutethy[citation needed]Turbo generators were also used on steam locomotives as a power source for coach lighting and heating systems since the 1901 invention of the cylindrical rotor ofCharles Brown for a high-speed generator the turbo generator has been the unique solution for converting steam turbine power into electrical power The continuously transposed stator bar invented by Ludwig Roebel in 1912 opened the door for large scale winding application Up to the 1930ies the generators were designed in 2- 4- and even 6-pole in accordance with the speed optimums of the steam turbines in those days The 1920ies ended with impressive power generation plants having generator units in the 100

1

TURBOGENERATOR

MVA range (see Fig1) The stator winding insulation consisted in the beginning of plied-on mica-paper compounded by Shellac varnish later substituted by asphalt Voltages were up to 12 kV In the early 1930ies two European manufacturers were introducing 36 kV stator windings thus eliminating the machine transformer All such designs were suffering of continuous heavy electrical discharges and were soon discontinued After a 60-year time-out a manufacturer surprised the world in 1998 with a cable-based high-voltagegenerator up to 400 kV However again the cable technology was not ready for turbo generator requirements and a breakthrough for commercial application was not achieved In the 1930 US manufacturers were introducing hydrogen as coolant When combined with direct conductor hydrogen cooling in the rotor and later in the stator this allowed aconsiderable increase in specific utilization and efficiency By early 1960 the unit ratings were achieving 500 MVA At that time deionized water cooling in the stator winding was introduced Around 1960 all major manufacturers changed their insulation system to mica tape with synthetic resin impregnation a technology for thermal qualification at 155degC and which has been lasting into these days By end of the 1960 with the power semiconductors becoming mature the dc machine excitation (Fig2) was superseded by the static excitation and by an ac exciter machine with rotating diodes The 1970ies brought again a tremendous growth in unit ratings going along with the introduction of nuclear power Units of 1200 MVA at 3000 rpm and 1600 MVA at 1500 rpm at up to 27 kV were designed and put in operation The rotor diameters were arriving at their physical limits Water-cooling of the rotor winding was introduced Along with plans for2000 MVA and beyond superconducting rotor windings and stator air-gap windings were studied However in early 1980 the market focus was shifting to gas turbine technology with some 100 MW beginning to grow into the area of large power plants and initiating a new round of up rating the simple and robust air-cooling technology in the 300 MVA range by 1996

2

TURBOGENERATOR

A 500 MW TURBO GENRATOR

The generator has for a long time been developed by repeating the cycle design ndash test ndash adjust design tools ndash extrapolate design A tremendous breakthrough came with the large computers in the 1960ies immediately being used for the key competences such as magnetic field calculations nonlinear coolant flow networks and mechanical turbine generatorshaft calculations Some programs of that area are even in use in the todayrsquos PC environment As an example magnetic equivalent circuits were established to determine excitation currents Once these programs were calibrated on measured data they have been proven very accurate and stilltoday for most applications make obsolete any FEM method The two poles and four poles differ considerably in construction At 50cs the former run at 3000rpm and the latter at 1500The useful range of two pole machines has been extended to 300 MVA and in consequence the four-pole Construction is obsolete

3

TURBOGENERATOR

STATOR OF TURBO GENRATOR

Generally the stator of a turbo generator comprises a cylindrical core which extends along a first longitudinal axis and comprises a plurality of axial cavities and two opposite headers connection terminals of the turbo generator a plurality of electrical windings which are split into groups and which extend along paths defined in part in the axial cavities and in part at the headers the electrical windings of each group being isopotential and connected in parallel between a pair of terminalsA known stator of a three-phase turbo generator comprises six terminals (three of which are connected to earth and three of which are connected to the electrical energy distribution main) nine electrical windings which are split into three groups each comprising three isopotential electrical windings connected in parallel between a pair of terminals seventy-two cavities each of which is occupied at the same time by two different portions of electrical windings The electrical windings have straight segments accommodated in the cavities and connection segments which are arranged at the headers and

4

TURBOGENERATOR

which have the function of connecting together the straight segments arranged in different axial cavities and some straight segments to the terminalsConsidering that according to the wiring diagram of the stator described above each axial cavity is occupied at the same time by two different electrical windings and that each electrical winding presents a path essentially identical to the other electrical windings each electrical winding presents sixteen straight segments which are arranged at corresponding axial cavities and a plurality of connection segments which are adapted to connect the straight segments to each other and to the terminals and are arranged at the headersThe connection segments determine a considerable axial dimension at the header of the stator above all considering that the electrical windings are generally defined by bars which must be maintained spaced apart one from the other Furthermore the axial dimension of the stator is increased by the wiring configuration followed by the electrical windings indeed in an electrical winding it is often necessary to connect together two straight segments arranged in diametrically opposite axial cavitiesThe technical solution of forming isopotential electrical windings between a pair of terminals rather than a single electrical winding between a pair of terminals allows to decrease the current value in the single isopotential electrical windings to increase the cooling surface and to reach higher unitary powers with respect to traditional electrical windings and for a given ventilating gas The currently known solutions envisage the formation of two or three isopotential electrical windings connected in parallel between each pair of terminalsThe stators which adopt this type of solution ie of fractioning the electrical windings of the stator in addition to the aforementioned drawback of the axial dimensions due to the high number of connection segments at the headers present the drawback of overloading with electrical current the connection zones of the electrical windings to the terminal pair to which they lead

5

TURBOGENERATOR

GENERATOR STATOR

STATOR CORE

The active part of the stator consists of segmental lamination of low loss alloy steel the slots ventilation holes and dovetail keyholes are punched out in one operation the stampings are rather complicated on account of the number of holes and slots that have to be produced The use of cold-rolled grain-oriented steel sheet has possibilities in machines as well as in transformers most particularly in two pole machines where the major loss occurs in the annular part of the core external to the slotting Hear the flux direction is manly

6

TURBOGENERATOR

Circumferential and by cutting the core-plate sectors in such a way that the preferred flux direction is at right angles to their central radial axis substantial reduction in core-loss can be securedIt is of great important that the assembled stator laminations are uniformly compressed during and after building and that slot are accurately located The core plates are assembled between end plates with fingers projecting between the slots to support the flanks of the teeth The end plates are almost invariably of non-magnetic material for this stepped reduces stray load loss The end packets of core plates may be stepped to a larger bore for the same reason

STATOR WINDING

The windings of two pole machines are comparatively straightforward The number of slots must be a multiple of 3(or 6 if two parallel circuits are required )single layer concentric or two-layer short-pitched windings may be used The single layer concentric winding is readily clamped in the overhang but causes a higher load loss because the end connections run parallel to the stator end plates chording is not possible so that flux harmonics have full effect The two layer winding is more common chorded to about 56 pitch which practically eliminates 5th and 7th harmonics from the open circuit emf wave The end windings are packed and clamped or tied with glass cord

7

TURBOGENERATOR

It is invariable practice with two layer windings to make the coils as half turns and to joint the ends The conductors must always be transposed to reduce eddy-current losses The conductors are insulated in many cases with bitumen-bonded micanite wrapped on as tape vaccume driedthen impregnated with bitumen under pressure and compressed size The process is illustrated in pictureeach copper bar A forming part of a conductor is insulated with mica tape B and C A set of bars forming one conductor is assembled and pressedDthe conductor is insulated with layers of mica tapeEthen the conductors are assembled to form a slot barFand pressed to the required dimensionssynthetic resinsbhave now replaced bitumen Within the slotsthe outer surface of the conductor insulation is at earth potential in the overhang it will approach more nearly to the potential of the enclosed copper Surface discharge will take place if the potential gradient at the transition from slot to overhang is excessive and it is usually necessary to introduce voltage grading by means of a semi conducting (eggraphitic) surface layer extending a short distance outward from the slot ends The slot inductance is increased by setting the winding more deeply in to the slots This has the incidental advantage of spacing the overhang farther away from the rotor end-rings

8

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 2: 98489540 project-report-ee-vt

TURBOGENERATOR

MVA range (see Fig1) The stator winding insulation consisted in the beginning of plied-on mica-paper compounded by Shellac varnish later substituted by asphalt Voltages were up to 12 kV In the early 1930ies two European manufacturers were introducing 36 kV stator windings thus eliminating the machine transformer All such designs were suffering of continuous heavy electrical discharges and were soon discontinued After a 60-year time-out a manufacturer surprised the world in 1998 with a cable-based high-voltagegenerator up to 400 kV However again the cable technology was not ready for turbo generator requirements and a breakthrough for commercial application was not achieved In the 1930 US manufacturers were introducing hydrogen as coolant When combined with direct conductor hydrogen cooling in the rotor and later in the stator this allowed aconsiderable increase in specific utilization and efficiency By early 1960 the unit ratings were achieving 500 MVA At that time deionized water cooling in the stator winding was introduced Around 1960 all major manufacturers changed their insulation system to mica tape with synthetic resin impregnation a technology for thermal qualification at 155degC and which has been lasting into these days By end of the 1960 with the power semiconductors becoming mature the dc machine excitation (Fig2) was superseded by the static excitation and by an ac exciter machine with rotating diodes The 1970ies brought again a tremendous growth in unit ratings going along with the introduction of nuclear power Units of 1200 MVA at 3000 rpm and 1600 MVA at 1500 rpm at up to 27 kV were designed and put in operation The rotor diameters were arriving at their physical limits Water-cooling of the rotor winding was introduced Along with plans for2000 MVA and beyond superconducting rotor windings and stator air-gap windings were studied However in early 1980 the market focus was shifting to gas turbine technology with some 100 MW beginning to grow into the area of large power plants and initiating a new round of up rating the simple and robust air-cooling technology in the 300 MVA range by 1996

2

TURBOGENERATOR

A 500 MW TURBO GENRATOR

The generator has for a long time been developed by repeating the cycle design ndash test ndash adjust design tools ndash extrapolate design A tremendous breakthrough came with the large computers in the 1960ies immediately being used for the key competences such as magnetic field calculations nonlinear coolant flow networks and mechanical turbine generatorshaft calculations Some programs of that area are even in use in the todayrsquos PC environment As an example magnetic equivalent circuits were established to determine excitation currents Once these programs were calibrated on measured data they have been proven very accurate and stilltoday for most applications make obsolete any FEM method The two poles and four poles differ considerably in construction At 50cs the former run at 3000rpm and the latter at 1500The useful range of two pole machines has been extended to 300 MVA and in consequence the four-pole Construction is obsolete

3

TURBOGENERATOR

STATOR OF TURBO GENRATOR

Generally the stator of a turbo generator comprises a cylindrical core which extends along a first longitudinal axis and comprises a plurality of axial cavities and two opposite headers connection terminals of the turbo generator a plurality of electrical windings which are split into groups and which extend along paths defined in part in the axial cavities and in part at the headers the electrical windings of each group being isopotential and connected in parallel between a pair of terminalsA known stator of a three-phase turbo generator comprises six terminals (three of which are connected to earth and three of which are connected to the electrical energy distribution main) nine electrical windings which are split into three groups each comprising three isopotential electrical windings connected in parallel between a pair of terminals seventy-two cavities each of which is occupied at the same time by two different portions of electrical windings The electrical windings have straight segments accommodated in the cavities and connection segments which are arranged at the headers and

4

TURBOGENERATOR

which have the function of connecting together the straight segments arranged in different axial cavities and some straight segments to the terminalsConsidering that according to the wiring diagram of the stator described above each axial cavity is occupied at the same time by two different electrical windings and that each electrical winding presents a path essentially identical to the other electrical windings each electrical winding presents sixteen straight segments which are arranged at corresponding axial cavities and a plurality of connection segments which are adapted to connect the straight segments to each other and to the terminals and are arranged at the headersThe connection segments determine a considerable axial dimension at the header of the stator above all considering that the electrical windings are generally defined by bars which must be maintained spaced apart one from the other Furthermore the axial dimension of the stator is increased by the wiring configuration followed by the electrical windings indeed in an electrical winding it is often necessary to connect together two straight segments arranged in diametrically opposite axial cavitiesThe technical solution of forming isopotential electrical windings between a pair of terminals rather than a single electrical winding between a pair of terminals allows to decrease the current value in the single isopotential electrical windings to increase the cooling surface and to reach higher unitary powers with respect to traditional electrical windings and for a given ventilating gas The currently known solutions envisage the formation of two or three isopotential electrical windings connected in parallel between each pair of terminalsThe stators which adopt this type of solution ie of fractioning the electrical windings of the stator in addition to the aforementioned drawback of the axial dimensions due to the high number of connection segments at the headers present the drawback of overloading with electrical current the connection zones of the electrical windings to the terminal pair to which they lead

5

TURBOGENERATOR

GENERATOR STATOR

STATOR CORE

The active part of the stator consists of segmental lamination of low loss alloy steel the slots ventilation holes and dovetail keyholes are punched out in one operation the stampings are rather complicated on account of the number of holes and slots that have to be produced The use of cold-rolled grain-oriented steel sheet has possibilities in machines as well as in transformers most particularly in two pole machines where the major loss occurs in the annular part of the core external to the slotting Hear the flux direction is manly

6

TURBOGENERATOR

Circumferential and by cutting the core-plate sectors in such a way that the preferred flux direction is at right angles to their central radial axis substantial reduction in core-loss can be securedIt is of great important that the assembled stator laminations are uniformly compressed during and after building and that slot are accurately located The core plates are assembled between end plates with fingers projecting between the slots to support the flanks of the teeth The end plates are almost invariably of non-magnetic material for this stepped reduces stray load loss The end packets of core plates may be stepped to a larger bore for the same reason

STATOR WINDING

The windings of two pole machines are comparatively straightforward The number of slots must be a multiple of 3(or 6 if two parallel circuits are required )single layer concentric or two-layer short-pitched windings may be used The single layer concentric winding is readily clamped in the overhang but causes a higher load loss because the end connections run parallel to the stator end plates chording is not possible so that flux harmonics have full effect The two layer winding is more common chorded to about 56 pitch which practically eliminates 5th and 7th harmonics from the open circuit emf wave The end windings are packed and clamped or tied with glass cord

7

TURBOGENERATOR

It is invariable practice with two layer windings to make the coils as half turns and to joint the ends The conductors must always be transposed to reduce eddy-current losses The conductors are insulated in many cases with bitumen-bonded micanite wrapped on as tape vaccume driedthen impregnated with bitumen under pressure and compressed size The process is illustrated in pictureeach copper bar A forming part of a conductor is insulated with mica tape B and C A set of bars forming one conductor is assembled and pressedDthe conductor is insulated with layers of mica tapeEthen the conductors are assembled to form a slot barFand pressed to the required dimensionssynthetic resinsbhave now replaced bitumen Within the slotsthe outer surface of the conductor insulation is at earth potential in the overhang it will approach more nearly to the potential of the enclosed copper Surface discharge will take place if the potential gradient at the transition from slot to overhang is excessive and it is usually necessary to introduce voltage grading by means of a semi conducting (eggraphitic) surface layer extending a short distance outward from the slot ends The slot inductance is increased by setting the winding more deeply in to the slots This has the incidental advantage of spacing the overhang farther away from the rotor end-rings

8

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 3: 98489540 project-report-ee-vt

TURBOGENERATOR

A 500 MW TURBO GENRATOR

The generator has for a long time been developed by repeating the cycle design ndash test ndash adjust design tools ndash extrapolate design A tremendous breakthrough came with the large computers in the 1960ies immediately being used for the key competences such as magnetic field calculations nonlinear coolant flow networks and mechanical turbine generatorshaft calculations Some programs of that area are even in use in the todayrsquos PC environment As an example magnetic equivalent circuits were established to determine excitation currents Once these programs were calibrated on measured data they have been proven very accurate and stilltoday for most applications make obsolete any FEM method The two poles and four poles differ considerably in construction At 50cs the former run at 3000rpm and the latter at 1500The useful range of two pole machines has been extended to 300 MVA and in consequence the four-pole Construction is obsolete

3

TURBOGENERATOR

STATOR OF TURBO GENRATOR

Generally the stator of a turbo generator comprises a cylindrical core which extends along a first longitudinal axis and comprises a plurality of axial cavities and two opposite headers connection terminals of the turbo generator a plurality of electrical windings which are split into groups and which extend along paths defined in part in the axial cavities and in part at the headers the electrical windings of each group being isopotential and connected in parallel between a pair of terminalsA known stator of a three-phase turbo generator comprises six terminals (three of which are connected to earth and three of which are connected to the electrical energy distribution main) nine electrical windings which are split into three groups each comprising three isopotential electrical windings connected in parallel between a pair of terminals seventy-two cavities each of which is occupied at the same time by two different portions of electrical windings The electrical windings have straight segments accommodated in the cavities and connection segments which are arranged at the headers and

4

TURBOGENERATOR

which have the function of connecting together the straight segments arranged in different axial cavities and some straight segments to the terminalsConsidering that according to the wiring diagram of the stator described above each axial cavity is occupied at the same time by two different electrical windings and that each electrical winding presents a path essentially identical to the other electrical windings each electrical winding presents sixteen straight segments which are arranged at corresponding axial cavities and a plurality of connection segments which are adapted to connect the straight segments to each other and to the terminals and are arranged at the headersThe connection segments determine a considerable axial dimension at the header of the stator above all considering that the electrical windings are generally defined by bars which must be maintained spaced apart one from the other Furthermore the axial dimension of the stator is increased by the wiring configuration followed by the electrical windings indeed in an electrical winding it is often necessary to connect together two straight segments arranged in diametrically opposite axial cavitiesThe technical solution of forming isopotential electrical windings between a pair of terminals rather than a single electrical winding between a pair of terminals allows to decrease the current value in the single isopotential electrical windings to increase the cooling surface and to reach higher unitary powers with respect to traditional electrical windings and for a given ventilating gas The currently known solutions envisage the formation of two or three isopotential electrical windings connected in parallel between each pair of terminalsThe stators which adopt this type of solution ie of fractioning the electrical windings of the stator in addition to the aforementioned drawback of the axial dimensions due to the high number of connection segments at the headers present the drawback of overloading with electrical current the connection zones of the electrical windings to the terminal pair to which they lead

5

TURBOGENERATOR

GENERATOR STATOR

STATOR CORE

The active part of the stator consists of segmental lamination of low loss alloy steel the slots ventilation holes and dovetail keyholes are punched out in one operation the stampings are rather complicated on account of the number of holes and slots that have to be produced The use of cold-rolled grain-oriented steel sheet has possibilities in machines as well as in transformers most particularly in two pole machines where the major loss occurs in the annular part of the core external to the slotting Hear the flux direction is manly

6

TURBOGENERATOR

Circumferential and by cutting the core-plate sectors in such a way that the preferred flux direction is at right angles to their central radial axis substantial reduction in core-loss can be securedIt is of great important that the assembled stator laminations are uniformly compressed during and after building and that slot are accurately located The core plates are assembled between end plates with fingers projecting between the slots to support the flanks of the teeth The end plates are almost invariably of non-magnetic material for this stepped reduces stray load loss The end packets of core plates may be stepped to a larger bore for the same reason

STATOR WINDING

The windings of two pole machines are comparatively straightforward The number of slots must be a multiple of 3(or 6 if two parallel circuits are required )single layer concentric or two-layer short-pitched windings may be used The single layer concentric winding is readily clamped in the overhang but causes a higher load loss because the end connections run parallel to the stator end plates chording is not possible so that flux harmonics have full effect The two layer winding is more common chorded to about 56 pitch which practically eliminates 5th and 7th harmonics from the open circuit emf wave The end windings are packed and clamped or tied with glass cord

7

TURBOGENERATOR

It is invariable practice with two layer windings to make the coils as half turns and to joint the ends The conductors must always be transposed to reduce eddy-current losses The conductors are insulated in many cases with bitumen-bonded micanite wrapped on as tape vaccume driedthen impregnated with bitumen under pressure and compressed size The process is illustrated in pictureeach copper bar A forming part of a conductor is insulated with mica tape B and C A set of bars forming one conductor is assembled and pressedDthe conductor is insulated with layers of mica tapeEthen the conductors are assembled to form a slot barFand pressed to the required dimensionssynthetic resinsbhave now replaced bitumen Within the slotsthe outer surface of the conductor insulation is at earth potential in the overhang it will approach more nearly to the potential of the enclosed copper Surface discharge will take place if the potential gradient at the transition from slot to overhang is excessive and it is usually necessary to introduce voltage grading by means of a semi conducting (eggraphitic) surface layer extending a short distance outward from the slot ends The slot inductance is increased by setting the winding more deeply in to the slots This has the incidental advantage of spacing the overhang farther away from the rotor end-rings

8

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 4: 98489540 project-report-ee-vt

TURBOGENERATOR

STATOR OF TURBO GENRATOR

Generally the stator of a turbo generator comprises a cylindrical core which extends along a first longitudinal axis and comprises a plurality of axial cavities and two opposite headers connection terminals of the turbo generator a plurality of electrical windings which are split into groups and which extend along paths defined in part in the axial cavities and in part at the headers the electrical windings of each group being isopotential and connected in parallel between a pair of terminalsA known stator of a three-phase turbo generator comprises six terminals (three of which are connected to earth and three of which are connected to the electrical energy distribution main) nine electrical windings which are split into three groups each comprising three isopotential electrical windings connected in parallel between a pair of terminals seventy-two cavities each of which is occupied at the same time by two different portions of electrical windings The electrical windings have straight segments accommodated in the cavities and connection segments which are arranged at the headers and

4

TURBOGENERATOR

which have the function of connecting together the straight segments arranged in different axial cavities and some straight segments to the terminalsConsidering that according to the wiring diagram of the stator described above each axial cavity is occupied at the same time by two different electrical windings and that each electrical winding presents a path essentially identical to the other electrical windings each electrical winding presents sixteen straight segments which are arranged at corresponding axial cavities and a plurality of connection segments which are adapted to connect the straight segments to each other and to the terminals and are arranged at the headersThe connection segments determine a considerable axial dimension at the header of the stator above all considering that the electrical windings are generally defined by bars which must be maintained spaced apart one from the other Furthermore the axial dimension of the stator is increased by the wiring configuration followed by the electrical windings indeed in an electrical winding it is often necessary to connect together two straight segments arranged in diametrically opposite axial cavitiesThe technical solution of forming isopotential electrical windings between a pair of terminals rather than a single electrical winding between a pair of terminals allows to decrease the current value in the single isopotential electrical windings to increase the cooling surface and to reach higher unitary powers with respect to traditional electrical windings and for a given ventilating gas The currently known solutions envisage the formation of two or three isopotential electrical windings connected in parallel between each pair of terminalsThe stators which adopt this type of solution ie of fractioning the electrical windings of the stator in addition to the aforementioned drawback of the axial dimensions due to the high number of connection segments at the headers present the drawback of overloading with electrical current the connection zones of the electrical windings to the terminal pair to which they lead

5

TURBOGENERATOR

GENERATOR STATOR

STATOR CORE

The active part of the stator consists of segmental lamination of low loss alloy steel the slots ventilation holes and dovetail keyholes are punched out in one operation the stampings are rather complicated on account of the number of holes and slots that have to be produced The use of cold-rolled grain-oriented steel sheet has possibilities in machines as well as in transformers most particularly in two pole machines where the major loss occurs in the annular part of the core external to the slotting Hear the flux direction is manly

6

TURBOGENERATOR

Circumferential and by cutting the core-plate sectors in such a way that the preferred flux direction is at right angles to their central radial axis substantial reduction in core-loss can be securedIt is of great important that the assembled stator laminations are uniformly compressed during and after building and that slot are accurately located The core plates are assembled between end plates with fingers projecting between the slots to support the flanks of the teeth The end plates are almost invariably of non-magnetic material for this stepped reduces stray load loss The end packets of core plates may be stepped to a larger bore for the same reason

STATOR WINDING

The windings of two pole machines are comparatively straightforward The number of slots must be a multiple of 3(or 6 if two parallel circuits are required )single layer concentric or two-layer short-pitched windings may be used The single layer concentric winding is readily clamped in the overhang but causes a higher load loss because the end connections run parallel to the stator end plates chording is not possible so that flux harmonics have full effect The two layer winding is more common chorded to about 56 pitch which practically eliminates 5th and 7th harmonics from the open circuit emf wave The end windings are packed and clamped or tied with glass cord

7

TURBOGENERATOR

It is invariable practice with two layer windings to make the coils as half turns and to joint the ends The conductors must always be transposed to reduce eddy-current losses The conductors are insulated in many cases with bitumen-bonded micanite wrapped on as tape vaccume driedthen impregnated with bitumen under pressure and compressed size The process is illustrated in pictureeach copper bar A forming part of a conductor is insulated with mica tape B and C A set of bars forming one conductor is assembled and pressedDthe conductor is insulated with layers of mica tapeEthen the conductors are assembled to form a slot barFand pressed to the required dimensionssynthetic resinsbhave now replaced bitumen Within the slotsthe outer surface of the conductor insulation is at earth potential in the overhang it will approach more nearly to the potential of the enclosed copper Surface discharge will take place if the potential gradient at the transition from slot to overhang is excessive and it is usually necessary to introduce voltage grading by means of a semi conducting (eggraphitic) surface layer extending a short distance outward from the slot ends The slot inductance is increased by setting the winding more deeply in to the slots This has the incidental advantage of spacing the overhang farther away from the rotor end-rings

8

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 5: 98489540 project-report-ee-vt

TURBOGENERATOR

which have the function of connecting together the straight segments arranged in different axial cavities and some straight segments to the terminalsConsidering that according to the wiring diagram of the stator described above each axial cavity is occupied at the same time by two different electrical windings and that each electrical winding presents a path essentially identical to the other electrical windings each electrical winding presents sixteen straight segments which are arranged at corresponding axial cavities and a plurality of connection segments which are adapted to connect the straight segments to each other and to the terminals and are arranged at the headersThe connection segments determine a considerable axial dimension at the header of the stator above all considering that the electrical windings are generally defined by bars which must be maintained spaced apart one from the other Furthermore the axial dimension of the stator is increased by the wiring configuration followed by the electrical windings indeed in an electrical winding it is often necessary to connect together two straight segments arranged in diametrically opposite axial cavitiesThe technical solution of forming isopotential electrical windings between a pair of terminals rather than a single electrical winding between a pair of terminals allows to decrease the current value in the single isopotential electrical windings to increase the cooling surface and to reach higher unitary powers with respect to traditional electrical windings and for a given ventilating gas The currently known solutions envisage the formation of two or three isopotential electrical windings connected in parallel between each pair of terminalsThe stators which adopt this type of solution ie of fractioning the electrical windings of the stator in addition to the aforementioned drawback of the axial dimensions due to the high number of connection segments at the headers present the drawback of overloading with electrical current the connection zones of the electrical windings to the terminal pair to which they lead

5

TURBOGENERATOR

GENERATOR STATOR

STATOR CORE

The active part of the stator consists of segmental lamination of low loss alloy steel the slots ventilation holes and dovetail keyholes are punched out in one operation the stampings are rather complicated on account of the number of holes and slots that have to be produced The use of cold-rolled grain-oriented steel sheet has possibilities in machines as well as in transformers most particularly in two pole machines where the major loss occurs in the annular part of the core external to the slotting Hear the flux direction is manly

6

TURBOGENERATOR

Circumferential and by cutting the core-plate sectors in such a way that the preferred flux direction is at right angles to their central radial axis substantial reduction in core-loss can be securedIt is of great important that the assembled stator laminations are uniformly compressed during and after building and that slot are accurately located The core plates are assembled between end plates with fingers projecting between the slots to support the flanks of the teeth The end plates are almost invariably of non-magnetic material for this stepped reduces stray load loss The end packets of core plates may be stepped to a larger bore for the same reason

STATOR WINDING

The windings of two pole machines are comparatively straightforward The number of slots must be a multiple of 3(or 6 if two parallel circuits are required )single layer concentric or two-layer short-pitched windings may be used The single layer concentric winding is readily clamped in the overhang but causes a higher load loss because the end connections run parallel to the stator end plates chording is not possible so that flux harmonics have full effect The two layer winding is more common chorded to about 56 pitch which practically eliminates 5th and 7th harmonics from the open circuit emf wave The end windings are packed and clamped or tied with glass cord

7

TURBOGENERATOR

It is invariable practice with two layer windings to make the coils as half turns and to joint the ends The conductors must always be transposed to reduce eddy-current losses The conductors are insulated in many cases with bitumen-bonded micanite wrapped on as tape vaccume driedthen impregnated with bitumen under pressure and compressed size The process is illustrated in pictureeach copper bar A forming part of a conductor is insulated with mica tape B and C A set of bars forming one conductor is assembled and pressedDthe conductor is insulated with layers of mica tapeEthen the conductors are assembled to form a slot barFand pressed to the required dimensionssynthetic resinsbhave now replaced bitumen Within the slotsthe outer surface of the conductor insulation is at earth potential in the overhang it will approach more nearly to the potential of the enclosed copper Surface discharge will take place if the potential gradient at the transition from slot to overhang is excessive and it is usually necessary to introduce voltage grading by means of a semi conducting (eggraphitic) surface layer extending a short distance outward from the slot ends The slot inductance is increased by setting the winding more deeply in to the slots This has the incidental advantage of spacing the overhang farther away from the rotor end-rings

8

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 6: 98489540 project-report-ee-vt

TURBOGENERATOR

GENERATOR STATOR

STATOR CORE

The active part of the stator consists of segmental lamination of low loss alloy steel the slots ventilation holes and dovetail keyholes are punched out in one operation the stampings are rather complicated on account of the number of holes and slots that have to be produced The use of cold-rolled grain-oriented steel sheet has possibilities in machines as well as in transformers most particularly in two pole machines where the major loss occurs in the annular part of the core external to the slotting Hear the flux direction is manly

6

TURBOGENERATOR

Circumferential and by cutting the core-plate sectors in such a way that the preferred flux direction is at right angles to their central radial axis substantial reduction in core-loss can be securedIt is of great important that the assembled stator laminations are uniformly compressed during and after building and that slot are accurately located The core plates are assembled between end plates with fingers projecting between the slots to support the flanks of the teeth The end plates are almost invariably of non-magnetic material for this stepped reduces stray load loss The end packets of core plates may be stepped to a larger bore for the same reason

STATOR WINDING

The windings of two pole machines are comparatively straightforward The number of slots must be a multiple of 3(or 6 if two parallel circuits are required )single layer concentric or two-layer short-pitched windings may be used The single layer concentric winding is readily clamped in the overhang but causes a higher load loss because the end connections run parallel to the stator end plates chording is not possible so that flux harmonics have full effect The two layer winding is more common chorded to about 56 pitch which practically eliminates 5th and 7th harmonics from the open circuit emf wave The end windings are packed and clamped or tied with glass cord

7

TURBOGENERATOR

It is invariable practice with two layer windings to make the coils as half turns and to joint the ends The conductors must always be transposed to reduce eddy-current losses The conductors are insulated in many cases with bitumen-bonded micanite wrapped on as tape vaccume driedthen impregnated with bitumen under pressure and compressed size The process is illustrated in pictureeach copper bar A forming part of a conductor is insulated with mica tape B and C A set of bars forming one conductor is assembled and pressedDthe conductor is insulated with layers of mica tapeEthen the conductors are assembled to form a slot barFand pressed to the required dimensionssynthetic resinsbhave now replaced bitumen Within the slotsthe outer surface of the conductor insulation is at earth potential in the overhang it will approach more nearly to the potential of the enclosed copper Surface discharge will take place if the potential gradient at the transition from slot to overhang is excessive and it is usually necessary to introduce voltage grading by means of a semi conducting (eggraphitic) surface layer extending a short distance outward from the slot ends The slot inductance is increased by setting the winding more deeply in to the slots This has the incidental advantage of spacing the overhang farther away from the rotor end-rings

8

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 7: 98489540 project-report-ee-vt

TURBOGENERATOR

Circumferential and by cutting the core-plate sectors in such a way that the preferred flux direction is at right angles to their central radial axis substantial reduction in core-loss can be securedIt is of great important that the assembled stator laminations are uniformly compressed during and after building and that slot are accurately located The core plates are assembled between end plates with fingers projecting between the slots to support the flanks of the teeth The end plates are almost invariably of non-magnetic material for this stepped reduces stray load loss The end packets of core plates may be stepped to a larger bore for the same reason

STATOR WINDING

The windings of two pole machines are comparatively straightforward The number of slots must be a multiple of 3(or 6 if two parallel circuits are required )single layer concentric or two-layer short-pitched windings may be used The single layer concentric winding is readily clamped in the overhang but causes a higher load loss because the end connections run parallel to the stator end plates chording is not possible so that flux harmonics have full effect The two layer winding is more common chorded to about 56 pitch which practically eliminates 5th and 7th harmonics from the open circuit emf wave The end windings are packed and clamped or tied with glass cord

7

TURBOGENERATOR

It is invariable practice with two layer windings to make the coils as half turns and to joint the ends The conductors must always be transposed to reduce eddy-current losses The conductors are insulated in many cases with bitumen-bonded micanite wrapped on as tape vaccume driedthen impregnated with bitumen under pressure and compressed size The process is illustrated in pictureeach copper bar A forming part of a conductor is insulated with mica tape B and C A set of bars forming one conductor is assembled and pressedDthe conductor is insulated with layers of mica tapeEthen the conductors are assembled to form a slot barFand pressed to the required dimensionssynthetic resinsbhave now replaced bitumen Within the slotsthe outer surface of the conductor insulation is at earth potential in the overhang it will approach more nearly to the potential of the enclosed copper Surface discharge will take place if the potential gradient at the transition from slot to overhang is excessive and it is usually necessary to introduce voltage grading by means of a semi conducting (eggraphitic) surface layer extending a short distance outward from the slot ends The slot inductance is increased by setting the winding more deeply in to the slots This has the incidental advantage of spacing the overhang farther away from the rotor end-rings

8

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 8: 98489540 project-report-ee-vt

TURBOGENERATOR

It is invariable practice with two layer windings to make the coils as half turns and to joint the ends The conductors must always be transposed to reduce eddy-current losses The conductors are insulated in many cases with bitumen-bonded micanite wrapped on as tape vaccume driedthen impregnated with bitumen under pressure and compressed size The process is illustrated in pictureeach copper bar A forming part of a conductor is insulated with mica tape B and C A set of bars forming one conductor is assembled and pressedDthe conductor is insulated with layers of mica tapeEthen the conductors are assembled to form a slot barFand pressed to the required dimensionssynthetic resinsbhave now replaced bitumen Within the slotsthe outer surface of the conductor insulation is at earth potential in the overhang it will approach more nearly to the potential of the enclosed copper Surface discharge will take place if the potential gradient at the transition from slot to overhang is excessive and it is usually necessary to introduce voltage grading by means of a semi conducting (eggraphitic) surface layer extending a short distance outward from the slot ends The slot inductance is increased by setting the winding more deeply in to the slots This has the incidental advantage of spacing the overhang farther away from the rotor end-rings

8

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 9: 98489540 project-report-ee-vt

TURBOGENERATOR

Stator winding

VENTILATIONS

9

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 10: 98489540 project-report-ee-vt

TURBOGENERATOR

Forced ventilation and total enclosure are necessary to deal with the large-scale losses and rating per unit volume the primary cooling medium is air or hydrogen which is in turn passed through a water-cooled heat-exchanger

AIR COOLING

The water coolers are normally in two section so that one can be cleared while the machine is operating Fans on the rotoror separate fansmay be employed the latter in large machines where bearing-spacing or limitation of the diameter makes integral fans inadequate With integral fans mounted on the rotor the air is fed to the space surrounding the stator overhangand pipes and channels convey a proportion towards the centre of the stator corethereform it flowes readily inward to the airgapthen axiallynto the end outlet compartments With separate fans howeverair can be fed directly to the middle as well as to the endsAn improvement of the efficiency by reduction of the airflow losses is in continuous progress using as support CFD programs In the last decades the improvement of the cooling such as axial ventilation of the rotor and indirect cooling of the stator winding allowed huge capability enhancement a better utilisation of the materials as well as a better efficiencyThis trend continues especially for the hydrogen and the aircooled generators

HYDROGEN COOLING

10

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 11: 98489540 project-report-ee-vt

TURBOGENERATOR

A hydrogen-cooled turbo generator is a turbo generator with gaseous hydrogen as a coolant Hydrogen-cooled turbo generators are designed to provide a low-drag atmosphere and cooling for single-shaft and combined-cycle applications in combination with steam turbines Because of the high thermal conductivity and other favorable properties of hydrogen gas this is the most common type in its field today Based on the air-cooled turbo generator gaseous hydrogen went into service as a coolant in the rotor and the stator in 1937 at Dayton Ohio in October by the Dayton Power amp Light Co[2] allowing an increase in specific utilization and a 990 efficiency

The use of gaseous hydrogen as a coolant is based on its properties namely low density high specific heat and highest thermal conductivity at 0168 W(mbullK) of all gases it is 7-10 times better coolant than air Other advantage of hydrogen is its easy detection by hydrogen sensors A hydrogen-cooled generator can be significantly smaller and therefore less expensive than an air-cooled one For stator cooling water can be usedHelium with a thermal-conductivity of 0142 W(mbullK) was considered as coolant as well however its high cost hinders its adoption despite its non-flammability[3]Generally three cooling approaches are used For generators up to 300 MW air cooling can be used Between 250-450 MW hydrogen cooling is employed For the highest power generators up to 1800 MW hydrogen and water cooling is used the rotor is hydrogen-cooled the stator windings are made of hollow copper tubes cooled with water circulating through themThe generators produce high voltage the choice of voltage depends on the tradeoff between demands to electrical insulation and demands to handling high electric current For generators up to 40 MVA the voltage is 63 kV large generators with power above 1000 MW generate voltages up to 27 kV voltages between 23-30 kV are used depending on the size of the generator The generated power is left to a nearby station transformer where it is converted to the electric power transmission line voltage (typically between 115 and 1200 kV)To control the centrifugal forces at high rotational speeds the rotor is mounted horizontally and its diameter typically does not exceed 125 meter the required large size of the coils is achieved by their length The generators operate typically at 3000 rpm for 50 Hz and 3600 rpm for 60 Hz systems for two-pole machines half of that for four-pole machinesThe turbogenerator contains also a smaller generator producing direct current excitation power for the rotor coil Older generators used dynamos and slip rings for DC injection to the rotor but the moving mechanical

11

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 12: 98489540 project-report-ee-vt

TURBOGENERATOR

contacts were subject to wear Modern generators have the excitation generator on the same shaft as the turbine and main generator the diodes needed are located directly on the rotor The excitation current on larger generators can reach 10 kA The amount of excitation power ranges between 05-3 of the generator output powerThe rotor usually contains caps or cage made of nonmagnetic material its role is to provide a low-resistance path for eddy currents which occur when the three phases of the generator are unevenly loaded In such cases eddy currents are generated in the rotor and the resulting Joule heating could in extreme cases destroy the generator[4]Hydrogen gas is circulated in a closed loop to remove heat from the active parts then it is cooled by gas-to-water heat exchangers on the stator frame The working pressure is up to 6 barAn on-line thermal conductivity detector (TCD) analyzer is used with three measuring ranges The first range (80-100 H2) to monitor the hydrogen purity during normal operation The second (0-100 H2) and third (0-100 CO2) measuring ranges allow safe opening of the turbines for maintenance[5]Hydrogen has very low viscosity a favorable property for reducing drag losses in the rotor these losses can be significant as the rotors have large diameter and high rotational speed Every reduction in the purity of the hydrogen coolant increases windage losses in the turbine as air is 14 times more dense than hydrogen each 1 of air corresponds to about 14 increase of density of the coolant and the associated increase of viscosity and drag A purity drop from 97 to 95 in a large generator can increase windage losses by 32 this equals to 685 kW for a 907 MW generator[6] The windage losses also increase heat losses of the generator and the associated cooling problems[7]The absence of oxygen in the atmosphere within significantly reduces the damage of the windings insulation by eventual corona discharges these can be problematic as the generators typically operate at high voltage often 20 kV[8]The bearings have to be leak-tight A hermetic seal usually a liquid seal is employed a turbine oil at pressure higher than the hydrogen inside is typically used A metal eg brass ring is pressed by springs onto the generator shaft the oil is forced under pressure between the ring and the shaft part of the oil flows into the hydrogen side of the generator another part to the air side The oil entrains a small amount of air as the oil is recirculated some of the air is carried over into the generator This causes a gradual air contamination buildup and requires maintaining hydrogen purity

12

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 13: 98489540 project-report-ee-vt

TURBOGENERATOR

Scavenging systems are used for this purpose gas (mixture of entrained air and hydrogen released from the oil) is collected in the holding tank for the sealing oil and released into the atmosphere the hydrogen losses have to be replenished either from gas cylinders or from on-site hydrogen generators Degradation of bearings leads to higher oil leaks which increases the amount of air transferred into the generator increased oil consumption can be detected by a flow meter associated to each bearing[9]Presence of water in hydrogen has to be avoided as it causes deterioration to hydrogen cooling properties corrosion of the generator parts arcing in the high voltage windings and reduces the lifetime of the generator A desiccant-based dryer is usually included in the gas circulation loop typically with a moisture probe in the dryers outlet sometimes also in its inlet Presence of moisture is also an indirect evidence for air leaking into the generator compartment[10] Another option is optimizing the hydrogen scavenging so the dew point is kept within the generator manufacturer specifications The water is usually introduced into the generator atmosphere as an impurity in the turbine oil another route is via leaks in water cooling systems[11]The flammability limits (4-75 of hydrogen in air at normal temperature wider at high temperatures[12]) its autoignition temperature at 571degC its very low minimum ignition energy and its tendency to form explosive mixtures with air require provisions to be made for maintaining the hydrogen content within the generator above the upper or below the flammability limit at all times and other hydrogen safety measures When filled with hydrogen overpressure has to be maintained as inlet of air into the generator could cause a dangerous explosion in confined space The generator enclosure is purged before opening it for maintenance and before refilling the generator with hydrogen During shutdown hydrogen is purged by an inert gas then the inert gas is replaced by air the opposite sequence is used before startup Carbon dioxide or nitrogen can be used for this purpose as they do not form combustible mixtures with hydrogen and are inexpensive Gas purity sensors are used to indicate the end of the purging cycle which shortens the startup and shutdown times and reduces consumption of the purging gas Carbon dioxide is favored as due to very high density difference it is easily displaced by hydrogenHydrogen is often produced on-site in electrolyzers as this reduces the need for stored amount of compressed hydrogen and allows storage in lower pressure tanks with associated safety benefits and lower costs Some gaseous hydrogen has to be kept for refilling the generator but it can be also generated on-site

13

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 14: 98489540 project-report-ee-vt

TURBOGENERATOR

As technology evolves no materials susceptible to hydrogen embrittlement are used in the generator design Not adhering to this can lead to equipment failure

STATOR OF A HYDROGEN COOLED TURBOGENERATOR

DIRECT COOLING

14

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 15: 98489540 project-report-ee-vt

TURBOGENERATOR

Direct cooling of stator winding is applied at ratings rather higher than that which makes the method necessary for rotors tubular conductors can be used or thin walled metal ducts lightly insulated from normal stator conductors A similar design serves for water cooling a stator Here arrangements are required in the overhang for the parallel flow of coolant as well as for the series connection of successive coil-sides Insulating tubes convey the liquid to and from the water ldquoheadersrdquo and the water itself must have adequate resistivity to limit conduction loss Water cooling has obvious disadvantages for rotors

ROTOR OF TURBOGENERATOR

15

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 16: 98489540 project-report-ee-vt

TURBOGENERATOR

The rotor accommodates the field winding whose poles are made of steel laminations A squirrel cage winding for absorbing purposes compensates for parallel services and abnormal load operation The rotor is dynamically balanced and designed to withstand to the electrical and mechanical effects of overspeed as required by the applicable standard and of the triggering according to the design Manufactured with non-salient poles the rotor has a constant air gap along the whole iron core periphery The rotor has a cylindrical shape in whose periphery slots is inserted the excitation winding The field coils are made of bars wires or copper laminations insulated with a class-H insulating material The non-salient pole rotor of the turbogenerator is practically a monobloc with no overhangs or recesses Asa result it becomes sturdier and more resistant to overspeed and coil triggeringGenerator rotor including an inner and an outer concentric rotor part having a non-drive side and enclosing a high vacuum space a first and a second bearing disposed on the non-drive side a hollow shaft end of the outer rotor part being supported in the first bearing a journal of the inner rotor part being extended through the hollow shaft end and separately supported in the second bearing a high-vacuum contact less liquid seal disposed between the hollow shaft end and the journal and having a sealing gap formed there between a co-rotating sealing-liquid reservoir connected to the liquid seal and magnetic field means for holding magnetic sealing liquid in the sealing gap

Rotors are most generally made from solid forgings must be homogeneous and flawless Test pieces are cut from the circumference and the ends to provide information about the mechanical qualities and the micro structure of the material A chemical analysis of the test pieces is subsequently made One of the most important examinations is the ultrasonic test which will discover internal faults such as crackes and fissures This will usually render the older practice of trepanning along the axis necessary

The rotor forging is planed and milled to form the teeth About two-thirds of the rotor pole-pitch is slotted leaving one-third unslotted for the pole centre

16

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 17: 98489540 project-report-ee-vt

TURBOGENERATOR

ROTOR OF A TURBOGENERATOR

17

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 18: 98489540 project-report-ee-vt

TURBOGENERATOR

ROTOR WINDING

The normal rotor winding is of silver-bearing copper The heat developed in the conductors causes them to expands while the centrifugal force presses them heavily against the slot wedges imposing a strong frictional resistance to expension Ordinary copper soften when hot and may be subject to plastic deformation As a result when the machine is stopped and the copper coolsit contracts to a shorter length than originally The phenomenan of copper-shortening can be overcome by preheating the rotor before starting up with new machines the use of silver-bearing copper having a much higher yield pointmitigates the troubleConcentric multi-turn coils accommodated in a slot number that is a multiple of four are usedthe slot-pitch being chosen to avoid undesirable harmonics in the waveform of the gap density The slots are radial and the coils formed of flat strip with seprators between turnsthe coils may be performed The insulation is usually micanitebut bonded asbestos and glass fabric have both been usedAs much copper as possible is accommodated in the rotor slotsthe depth and width of the slots being limited by the stresses at the roots of the teethand by the hoop stresses in the end in retaining rings The allowable current depends on cooling and expension Comparatively high temperature-rises are allowedthe hot spot temperature may reach 140 degree centigrade

18

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 19: 98489540 project-report-ee-vt

TURBOGENERATOR

EXCITER

Installed at the non-drive end side of the generator the exciter is formed by fixed poles that accommodate the excitation field coils the armature and the rotating rectifier bridge Its purpose is to supply direct voltage to exciter rotor It supplies direct current controlled by the voltage regulator according to the load requirements thus maintaining constant voltage for the main generator

Exciter Stator The poles accommodate the field coils which are series connected their ends being connected to the terminal block (I(+) and K(-)) Its purpose is to supply the flux to the exciter rotor It is supplied with a direct current controlled by the voltage regulator according to the load requirements thus keeping the main generator voltage constant

Exciter Rotor The exciter rotor is mounted on the main shaft of themachine The rotor is formed by laminations with slots that accommodate a star-connected three-phase winding The phases are connected to the rotating rectifying diode set

exciter

19

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 20: 98489540 project-report-ee-vt

TURBOGENERATOR

SLIP RINGS

Slip rings are required for conveying the exciting current to and from the rotor winding Rings of steel shrunk over micanite may be placed one at each end of the rotoror both at one end inside or outside the bearing

20

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 21: 98489540 project-report-ee-vt

TURBOGENERATOR

INSULATION

Since its introduction at the end of the 1950ies the synthetic resin mica tape insulation technology has been in use Over the past years a worldwide re-evaluation of insulation technologies has been observed On the far horizon polymer insulations might become an option However when benchmarking with mica tape insulation the required tight quality control for the application in manufacturing and the non-existent inherent fault tolerance for inner discharges become obstacles Therefore it looks that small steps intodayrsquos proven insulation technology will be realized earlier Such novelties close to introduction are - Improved tape now commercially available highthermal conductivity using fillers (HTC) higher mica content by denser roving carrier Both technologies are in verification tests The maximum achievable thermal conductivity is at 05 WmK - Improving the insulation system to a higher thermal class (class 180) Such a technology is in final verification and will soon be available - Increasing the electrical field stress to a higher value a 15 gain seems achievable This allows a better heat transfer and more copper in the slot As specified by standards insulation verification tests are commonly based on comparative tests in specificcharacteristics Any modified insulation system must be at least as good in these characteristics as the established technology Other criteria are sensitivity to manufacturing variances throughput time environmental compliance and second source availability for the components All these improvements for the stator winding insulation look likely to shift the bottleneck into the rotor Fortunately the rotor material technology brings along all prerequisites to be upgraded into class 180 technology This is due to the fact that many components are inherently class 180 and simply need a tighter specification to become qualified In the case of class 180 allowing class 155 operation and probably in a later stage class 180 peaking it is of utmost importance that both stator and rotor winding designs can accommodate their elongation due to thermal expansion A set of design measures has been worked out to provide this safety The materials used in laminates can be the same or different An example of the type of laminate using different materials would be the application of a layer of plastic film mdash the laminate mdash on either side of a sheet of glass mdash the laminated subject Vehicle windshields are commonly made by laminating a tough plastic film between two layers of glass Plywood is a common example of a laminate using the same material in each layer Glued and laminated dimensioned timber is used in the construction industry to make wooden

21

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 22: 98489540 project-report-ee-vt

TURBOGENERATOR

beams Glulam with sizes larger and stronger than can be obtained from single pieces of wood Another reason to laminate wooden strips into beams is quality control as with this method each and every strip can be inspected before it becomes part of a highly stressed component such as an aircraft undercarriageExamples of laminate materials include Formica and plywood Formica and similar plastic laminates (such as Pionite Wilsonart Lamin-Art or Centuryply Mica) are often referred to as High Pressure Decorative Laminate (HPDL) as they are created with heat and pressure of more than 5 psi (34 kPa) A new type of HPDL is produced using real wood veneer or multilaminar veneer as top surface Alpikord produced by Alpi spa and Veneer-Art produced by Lamin-Art are examples of these types of laminateLaminating paper such as photographs can prevent it from becoming creased sun damaged wrinkled stained smudged abraded andor marked by grease fingerprints and environmental concerns Photo identification cards and credit cards are almost always laminated with plastic film Boxes and other containers are also laminated using a UV coating Lamination is also used in sculpture using wood or resin An example of an artist who used lamination in his work is the American Floyd ShamanFurther laminates can be used to add properties to a surface usually printed paper that would not have them otherwise Sheets of vinyl impregnated with ferro-magnetic material can allow portable printed images to bond to magnets such as for a custom bulletin board or a visual presentation Specially surfaced plastic sheets can be laminated over a printed image to allow them to be safely written upon such as with dry erase markers or chalk Multiple translucent printed images may be laminated in layers to achieve certain visual effects or to hold holographic images Many printing businesses that do commercial lamination keep a variety of laminates on hand as the process for bonding many types is generally similar when working with arbitrarily thin material

INSULATION RESISTANCE

When the generator is commissioned immediately after receipt it should be protected against moisture high temperature and dirt thus preventing damages on the insulation resistance The winding insulation resistance must be measured before the generator operation If the ambient is very wet the winding resistance must be measured from time to time during the storage period It is difficult to prescribe fixed rules for the machine insulation resistance values since they change according to the environment conditions

22

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 23: 98489540 project-report-ee-vt

TURBOGENERATOR

(temperature moisture) machinecleaning conditions (dust oil grease and dirt) quality and conditions of the used insulating material A considerabledose of common sense resulted from experience must be applied to conclude when a machine is or is not suitable for service Periodic records are useful for this conclusion

BEARINGS

The bearings are mounted at the frame ends and their purpose is to support the rotor mass and allow it to turn Sleeve bearings are lubricated with oil and the rolling bearings can be lubricated with grease or oil Correct storage operation and maintenance procedures are determinant for their performance and useful life

Oil-lubricated bearing

1048707 Depending on its mounting position the generator can be transported with or without oil in the bearings1048707 The generator must be stored in its mounting position with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication condition1048707 After 6 months of storage and before starting the operation the bearings should be relubricated If the generator is stored for more than 2 years thebearings must be washed inspected and relubricated

Grease-lubricated bearing

1048707 The bearings are factory lubricated for the performance of the generator tests1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft turned manually to keep the bearing in good lubrication conditions1048707 After 6 months of storage and before starting the operation the bearings should be relubricated1048707 If the generator is stored for more than 2 years the bearings must be washed inspected and lubricated again

23

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 24: 98489540 project-report-ee-vt

TURBOGENERATOR

Sleeve Bearing

1048707 Depending on the mounting position the generator can be transported with our without oil in the bearings and must be stored in its mounting with oil in the bearings1048707 The oil level must be respected remaining in the sight glass half1048707 During the storage period at every two months the shaft-locking device must be removed and the shaft rotated at 30 rpm to circulate the oil and keep the sleeve bearing in good lubrication condition

Sealing

After bearing maintenance both halves of seal labyrinth should be fixed together by a circlip ring They must be inserted into the ring seat so the locking pin is fitted into the undercut of the upper half part of housing Poor installation damages the sealing Before seal assembling clean carefully the contact surfaces of the ring and seating and coat the contact area with soft sealing compound Drain holes at bottom half of the ring should be cleaned and cleared When installing this halve of the sealing ring press it slightly against bottom shaft side

24

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 25: 98489540 project-report-ee-vt

TURBOGENERATOR

CONCLUSION

Since more than 100 years turbogenerators have been in use for steam turbine and gas turbine applications of any size The technical evolution has not stopped new market requirements and new material technologies ask for adaptations in design The future market will be characterized by a revitalized need for very large turbogenerators both two-pole and 4-pole The future will also be characterized by an exciting competition between well-established conventional solutions and new ldquohigh techrdquo solutions In any case highly skilled engineers paired with the best available design tools will be required

25

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 26: 98489540 project-report-ee-vt

TURBOGENERATOR

REFERENCES

[1] R Joho C Picech K Mayor ldquoLarge air-cooled turbogenerators -extending the boundariesrdquo CIGRE Session 2006 paper A1-106

[2] C Ginet B Zimmerli A Ziegler W Shugui Ten years of operationalexperience with ALSTOMrsquos air-cooled TOPAIR turbogenerator in the300 MVA class and above Power-Gen Asia 2006 Hong Kong China

[3] J Haldemann ldquoTranspositions in stator bars of large turbogeneratorsrdquoIEEE Trans on EC vol 19 no 3 Sept 2004

[4] Turbo generator by MG SAY

Homework Help httpswwwhomeworkpingcom Math homework helphttpswwwhomeworkpingcom Research Paper helphttpswwwhomeworkpingcom Algebra Helphttpswwwhomeworkpingcom Calculus Helphttpswwwhomeworkpingcom Accounting helphttpswwwhomeworkpingcom Paper Helphttpswwwhomeworkpingcom Writing Help

26

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27

Page 27: 98489540 project-report-ee-vt

TURBOGENERATOR

httpswwwhomeworkpingcom Online Tutorhttpswwwhomeworkpingcom Online Tutoringhttpswwwhomeworkpingcom

27