8. Eaton Elect BOS Presentation for NSC conference, June '14

15
© 2013 Eaton. All Rights Reserved. Electrical BOS solutions for UK grid-connected PV systems Richard Molloy Segment Sales – Renewable Energy 25 th June 2014

description

AC protection and BOS

Transcript of 8. Eaton Elect BOS Presentation for NSC conference, June '14

Page 1: 8. Eaton Elect BOS Presentation for NSC conference, June '14

© 2013 Eaton. All Rights Reserved.

Electrical BOS solutions for UK grid-connected PV systems

Richard Molloy

Segment Sales – Renewable Energy

25th June 2014

Page 2: 8. Eaton Elect BOS Presentation for NSC conference, June '14

2© 2013 Eaton. All Rights Reserved.

Presentation overview

• Introduction• Electrical BOS – a

definition• Component overview –

typical SLD• Design considerations• Examples• G59/3 update• Future trends

Page 3: 8. Eaton Elect BOS Presentation for NSC conference, June '14

3© 2013 Eaton. All Rights Reserved.

Electrical Balance Of System

• The electrical infrastructure required to gather and combine the DC power generated by multiple panels and provide a single AC power feed to the building and/or the grid

Page 4: 8. Eaton Elect BOS Presentation for NSC conference, June '14

4© 2013 Eaton. All Rights Reserved.

Electrical SLD, 1.3MW Eaton Beaver PlantPanels & racking

DC combiners

Inverters

AC Switchgear & transformer

Building / Grid connection & metering

DC cable

AC cable

Page 5: 8. Eaton Elect BOS Presentation for NSC conference, June '14

5© 2013 Eaton. All Rights Reserved.

System design topology

• Decision to be made at early stage of system design between using a few central inverters or multiple string inverters

• Each type has BOS design differences in downstream element but basic premise is the same

Page 6: 8. Eaton Elect BOS Presentation for NSC conference, June '14

6© 2013 Eaton. All Rights Reserved.

Design considerations

• General:• Space / location• Access for installation and maintenance• UV stability• Cable routing• Ongoing production processes• Security

• Electrical:• AC switchgear loading – must use 0% diversity factor• Cable volt drop <1% increases cable size

• Ensure terminal capacities can accept large cables

Page 7: 8. Eaton Elect BOS Presentation for NSC conference, June '14

7© 2013 Eaton. All Rights Reserved.

Design considerations – large sites

• Fault levels can be high• Ensure protective devices have sufficient fault current

breaking capacity• Especially problematic for string-inverter based sites

• Inter-tripping requirements – HV connected sites• The DNO is likely to have specific MV inter-tripping

requirements and this varies by DNO

• Site earthing requirements• Ensure earthing is considered up-front

• Lead times• Many BOS items can be on extended lead times

Page 8: 8. Eaton Elect BOS Presentation for NSC conference, June '14

8© 2013 Eaton. All Rights Reserved.

UK grid integration project locations

Page 9: 8. Eaton Elect BOS Presentation for NSC conference, June '14

9© 2013 Eaton. All Rights Reserved.

Complete containerised solution

Page 10: 8. Eaton Elect BOS Presentation for NSC conference, June '14

10© 2013 Eaton. All Rights Reserved.

1.5MW substation with t/x & POC

Page 11: 8. Eaton Elect BOS Presentation for NSC conference, June '14

11© 2013 Eaton. All Rights Reserved.

PV Distribution Board, 50 to 250kWp +

• Includes lockable rotary isolator, G59 protection relay, contactor, MID certified kWh meter with RS485 comms and commissioning socket

• Available from 50kWp up to 250kWp +

• Options for number / size / type of inverter inputs

Page 12: 8. Eaton Elect BOS Presentation for NSC conference, June '14

12© 2013 Eaton. All Rights Reserved.

160kW PV-DB with 100mA Type A TP RCBOs

Page 13: 8. Eaton Elect BOS Presentation for NSC conference, June '14

13© 2013 Eaton. All Rights Reserved.

EREC G59/3

• Released Sept. ‘13 – mandatory w.e.f. 1st Dec. ’14• Many minor revisions over G59/2 – plus some

substantial ones• New performance requirements for ‘type tested’

generator units (inverters)• Type testing of inverters now accepted for a wider

range of applications (versus requirement for dedicated additional protection and witness testing)

• Changes to testing & commissioning requirements• Section 12 – all very substantially revised and much of this section is new

• Changes to test sheet templates

Page 14: 8. Eaton Elect BOS Presentation for NSC conference, June '14

14© 2013 Eaton. All Rights Reserved.

Future trends

• On-going reductions in cost• Standardisation of site electrical design• Increase in DC voltage• Increase in AC connection voltage• Introduction of grid stability requirements

• Real-time reactive power control• Variable export power limits• Large scale energy storage solutions

Page 15: 8. Eaton Elect BOS Presentation for NSC conference, June '14

15© 2013 Eaton. All Rights Reserved.