8. Eaton Elect BOS Presentation for NSC conference, June '14
-
Upload
bre -
Category
Engineering
-
view
172 -
download
3
description
Transcript of 8. Eaton Elect BOS Presentation for NSC conference, June '14
© 2013 Eaton. All Rights Reserved.
Electrical BOS solutions for UK grid-connected PV systems
Richard Molloy
Segment Sales – Renewable Energy
25th June 2014
2© 2013 Eaton. All Rights Reserved.
Presentation overview
• Introduction• Electrical BOS – a
definition• Component overview –
typical SLD• Design considerations• Examples• G59/3 update• Future trends
3© 2013 Eaton. All Rights Reserved.
Electrical Balance Of System
• The electrical infrastructure required to gather and combine the DC power generated by multiple panels and provide a single AC power feed to the building and/or the grid
4© 2013 Eaton. All Rights Reserved.
Electrical SLD, 1.3MW Eaton Beaver PlantPanels & racking
DC combiners
Inverters
AC Switchgear & transformer
Building / Grid connection & metering
DC cable
AC cable
5© 2013 Eaton. All Rights Reserved.
System design topology
• Decision to be made at early stage of system design between using a few central inverters or multiple string inverters
• Each type has BOS design differences in downstream element but basic premise is the same
6© 2013 Eaton. All Rights Reserved.
Design considerations
• General:• Space / location• Access for installation and maintenance• UV stability• Cable routing• Ongoing production processes• Security
• Electrical:• AC switchgear loading – must use 0% diversity factor• Cable volt drop <1% increases cable size
• Ensure terminal capacities can accept large cables
7© 2013 Eaton. All Rights Reserved.
Design considerations – large sites
• Fault levels can be high• Ensure protective devices have sufficient fault current
breaking capacity• Especially problematic for string-inverter based sites
• Inter-tripping requirements – HV connected sites• The DNO is likely to have specific MV inter-tripping
requirements and this varies by DNO
• Site earthing requirements• Ensure earthing is considered up-front
• Lead times• Many BOS items can be on extended lead times
8© 2013 Eaton. All Rights Reserved.
UK grid integration project locations
9© 2013 Eaton. All Rights Reserved.
Complete containerised solution
10© 2013 Eaton. All Rights Reserved.
1.5MW substation with t/x & POC
11© 2013 Eaton. All Rights Reserved.
PV Distribution Board, 50 to 250kWp +
• Includes lockable rotary isolator, G59 protection relay, contactor, MID certified kWh meter with RS485 comms and commissioning socket
• Available from 50kWp up to 250kWp +
• Options for number / size / type of inverter inputs
12© 2013 Eaton. All Rights Reserved.
160kW PV-DB with 100mA Type A TP RCBOs
13© 2013 Eaton. All Rights Reserved.
EREC G59/3
• Released Sept. ‘13 – mandatory w.e.f. 1st Dec. ’14• Many minor revisions over G59/2 – plus some
substantial ones• New performance requirements for ‘type tested’
generator units (inverters)• Type testing of inverters now accepted for a wider
range of applications (versus requirement for dedicated additional protection and witness testing)
• Changes to testing & commissioning requirements• Section 12 – all very substantially revised and much of this section is new
• Changes to test sheet templates
14© 2013 Eaton. All Rights Reserved.
Future trends
• On-going reductions in cost• Standardisation of site electrical design• Increase in DC voltage• Increase in AC connection voltage• Introduction of grid stability requirements
• Real-time reactive power control• Variable export power limits• Large scale energy storage solutions
15© 2013 Eaton. All Rights Reserved.