METRADO DE CARGA NORMA DE CARGA E-020 N° DESCRIPCION UND PESO Nº VECES L A H AREA Peso Kg Peso TN
TERCER NIVEL1 LOSA ALIGERADA TERCER NIVEL 50.48
A Kg/m2 350 1 18.00 6300B Kg/m2 350 1 9.14 3199C Kg/m2 350 1 15.21 5323.5D Kg/m2 350 1 13.57 4749.5E Kg/m2 350 1 10.89 3811.5F Kg/m2 350 1 12.21 4273.5G Kg/m2 350 1 7.31 2558.5H Kg/m2 350 1 14.46 5061I Kg/m2 350 1 14.00 4900J Kg/m2 350 1 7.09 2481.5K Kg/m2 350 1 11.79 4126.5M Kg/m2 350 1 10.55 3692.5
2 COLUMNAC-1 Kg/m3 2400 20 1.25 0.25 0.25 3750 3.75
3 VIGA PRINCIPALEJE 1,2,3, ENTRE A-B Kg/m3 2400 4 3.35 0.25 0.50 4020 16.56
EJE 1,2,3, ENTRE B-C Kg/m3 2400 4 3.75 0.25 0.50 4500EJE 1,2,3, ENTRE C-D Kg/m3 2400 4 2.25 0.25 0.50 2700EJE 1,2,3, ENTRE D-E Kg/m3 2400 4 4.45 0.25 0.50 5340
4 VIGA SECUNDARIA 12.66
EJE A,B,C,D,E, ENTRE 1-2 Kg/m3 2400 5 4.05 0.25 0.40 4860EJE A,B,C,D,E, ENTRE 2-3 Kg/m3 2400 5 3.25 0.25 0.40 3900EJE A,B,C,D,E, ENTRE 3-4 Kg/m3 2400 5 3.25 0.25 0.40 3900
5 MUROS Y TABIQUES Kg/m2 300 10.55 1.25 3956.25 3.96
6 REVOQUES, ENLUCIDOS Y MOLDURAS Kg/m3 1800 10.55 0.015 1.25 356.06 0.36
CARGA MUERTA TOTAL 87.76
SOBRE CARGA CUARTO NIVEL Kg/m2 150 144.22 21633 21.63
CARGA TOTAL 3º NIVEL 109.39
SEGUNDO NIVEL
1 LOSA ALIGERADA SEGUNDO NIVEL 50.48
A Kg/m2 350 1 18.00 6300B Kg/m2 350 1 9.14 3199C Kg/m2 350 1 15.21 5323.5D Kg/m2 350 1 13.57 4749.5E Kg/m2 350 1 10.89 3811.5F Kg/m2 350 1 12.21 4273.5G Kg/m2 350 1 7.31 2558.5H Kg/m2 350 1 14.46 5061I Kg/m2 350 1 14.00 4900J Kg/m2 350 1 7.09 2481.5K Kg/m2 350 1 11.79 4126.5M Kg/m2 350 1 10.55 3692.5
2 COLUMNAC-1 Kg/m3 2400 20 2.5 0.25 0.25 7500 7.50
3 VIGA PRINCIPALEJE 1,2,3, ENTRE A-B Kg/m3 2400 4 3.35 0.25 0.50 4020 16.56
EJE 1,2,3, ENTRE B-C Kg/m3 2400 4 3.75 0.25 0.50 4500EJE 1,2,3, ENTRE C-D Kg/m3 2400 4 2.25 0.25 0.50 2700EJE 1,2,3, ENTRE D-E Kg/m3 2400 4 4.45 0.25 0.50 5340
4 VIGA SECUNDARIA 12.66
EJE A,B,C,D,E, ENTRE 1-2 Kg/m3 2400 5 4.05 0.25 0.40 4860EJE A,B,C,D,E, ENTRE 2-3 Kg/m3 2400 5 3.25 0.25 0.40 3900EJE A,B,C,D,E, ENTRE 3-4 Kg/m3 2400 5 3.25 0.25 0.40 3900
5 MUROS Y TABIQUES Kg/m2 300 10.55 2.5 7912.5 7.91
6 REVOQUES, ENLUCIDOS Y MOLDURAS Kg/m3 1800 10.55 0.025 2.5 1186.88 1.19
CARGA MUERTA TOTAL 96.30
SOBRE CARGA TERCER NIVEL Kg/m2 150 144.22 21633 21.63
CARGA TOTAL 2º NIVEL 117.93
PRIMER NIVEL
1 LOSA ALIGERADA PRIMER NIVEL 50.82
A Kg/m2 350 1 18.12 6342B Kg/m2 350 1 9.17 3209.5C Kg/m2 350 1 15.28 5348D Kg/m2 350 1 13.75 4812.5E Kg/m2 350 1 10.97 3839.5F Kg/m2 350 1 12.19 4266.5G Kg/m2 350 1 7.35 2572.5H Kg/m2 350 1 14.57 5099.5I Kg/m2 350 1 14.17 4959.5J Kg/m2 350 1 7.14 2499K Kg/m2 350 1 11.82 4137M Kg/m2 350 1 10.68 3738
2 COLUMNAC-1 Kg/m3 2400 20 2.75 0.3 0.3 11880 11.88
3 VIGA PRINCIPALEJE 1,2,3, ENTRE A-B Kg/m3 2400 4 3.3 0.25 0.50 3960 16.32
EJE 1,2,3, ENTRE B-C Kg/m3 2400 4 3.7 0.25 0.50 4440EJE 1,2,3, ENTRE C-D Kg/m3 2400 4 2.2 0.25 0.50 2640EJE 1,2,3, ENTRE D-E Kg/m3 2400 4 4.4 0.25 0.50 5280
4 VIGA SECUNDARIA 12.48
EJE A,B,C,D,E, ENTRE 1-2 Kg/m3 2400 5 4.00 0.25 0.40 4800EJE A,B,C,D,E, ENTRE 2-3 Kg/m3 2400 5 3.20 0.25 0.40 3840EJE A,B,C,D,E, ENTRE 3-4 Kg/m3 2400 5 3.20 0.25 0.40 3840
5 MUROS Y TABIQUES Kg/m2 300 10.4 1.5 4680 4.68
6 REVOQUES, ENLUCIDOS Y MOLDURAS Kg/m3 1800 10.4 0.015 1.5 421.20 0.42
CARGA MUERTA TOTAL 96.60
SOBRE CARGA SEGUNDO NIVEL Kg/m2 200 145.21 29042 29.04
CARGA TOTAL 1º NIVEL 125.65
METRADO DE CARGAS DE PORTICOS X ML.TERCER NIVEL PORTICO 1ELEMENTO PESO (TN) A H CARGA (TN/M) ATViga Principal 2.40 0.25 0.5 0.30Losa Aligerada 0.30 2.15 0.64 2.15Acabados 0.12 2.15 0.26Tabiqueria 0.15 2.15 0.32
3.6 4 2.5 4.7
C.M. 1.53
SOBRE CARGA0.3 2.15 0.64
C.V. 0.64
CARGA MAYORADA
Wu=1.4CM+1.7CV 3.23 TN/ML.
TERCER NIVEL PORTICO 2ELEMENTO PESO (TN) A H CARGA (TN/M) ATViga Principal 2.40 0.25 0.5 0.30Losa Aligerada 0.30 3.90 1.17 1.75Acabados 0.12 3.90 0.47Tabiqueria 0.15 3.90 0.59
3.6 4 2.5 4.7
C.M. 2.52 2.15
SOBRE CARGA0.3 3.90 1.17
C.V. 1.17
CARGA MAYORADA
Wu=1.4CM+1.7CV 5.52 TN/ML.
TERCER NIVEL PORTICO 3ELEMENTO PESO (TN) A H CARGA (TN/M) ATViga Principal 2.40 0.25 0.5 0.30Losa Aligerada 0.30 3.45 1.04 1.7Acabados 0.12 3.45 0.41Tabiqueria 0.15 3.45 0.52
3.6 4 2.5 4.7
C.M. 2.27 1.75
SOBRE CARGA0.3 3.45 1.04
C.V. 1.04
CARGA MAYORADA
Wu=1.4CM+1.7CV 4.93 TN/ML.
TERCER NIVEL PORTICO 4ELEMENTO PESO (TN) A H CARGA (TN/M)Viga Principal 2.40 0.25 0.5 0.30Losa Aligerada 0.30 1.7 0.51Acabados 0.12 1.7 0.20 ATTabiqueria 0.15 1.7 0.26
3.6 4 2.5 4.7
C.M. 1.27 1.7
SOBRE CARGA0.3 1.7 0.51
C.V. 0.51
CARGA MAYORADA
Wu=1.4CM+1.7CV 2.64 TN/ML.
AT
2.15
AT
1.75
2.15
AT
1.7
1.75
AT
1.7
METRADO DE CARGAS DE PORTICOS X ML.TERCER NIVEL PORTICO AELEMENTO PESO (TN) A H CARGA (TN/M)Viga Secundaria 2.40 0.25 0.40 0.24Losa Aligerada 0.30 1.8 0.54Acabados 0.12 1.8 0.22Tabiqueria 0.15 1.8 0.27
C.M. 1.27
SOBRE CARGA0.3 1.8 0.54
C.V. 0.54
CARGA MAYORADA
Wu=1.4CM+1.7CV 2.69 TN/ML.
TERCER NIVEL PORTICO BELEMENTO PESO (TN) A H CARGA (TN/M)Viga Principal 2.40 0.25 0.40 0.24Losa Aligerada 0.30 3.80 1.14Acabados 0.12 3.80 0.46Tabiqueria 0.15 3.80 0.57
C.M. 2.41
SOBRE CARGA0.3 3.80 1.14
C.V. 1.14
CARGA MAYORADA
Wu=1.4CM+1.7CV 5.31 TN/ML.
TERCER NIVEL PORTICO CELEMENTO PESO (TN) A H CARGA (TN/M)Viga Principal 2.40 0.25 0.40 0.24Losa Aligerada 0.30 3.25 0.98Acabados 0.12 3.25 0.39Tabiqueria 0.15 3.25 0.49
C.M. 2.09
SOBRE CARGA0.3 3.25 0.98
C.V. 0.98
CARGA MAYORADA
Wu=1.4CM+1.7CV 4.59 TN/ML.
TERCER NIVEL PORTICO DELEMENTO PESO (TN) A H CARGA (TN/M)Viga Principal 2.40 0.25 0.40 0.24Losa Aligerada 0.30 3.60 1.08Acabados 0.12 3.60 0.43Tabiqueria 0.15 3.60 0.54
C.M. 2.29
SOBRE CARGA0.3 3.60 1.08
C.V. 1.08
CARGA MAYORADA
Wu=1.4CM+1.7CV 5.04 TN/ML.
TERCER NIVEL PORTICO EELEMENTO PESO (TN) A H CARGA (TN/M)Viga Principal 2.40 0.25 0.40 0.24Losa Aligerada 0.30 2.35 0.71Acabados 0.12 2.35 0.28Tabiqueria 0.15 2.35 0.35
C.M. 1.58
SOBRE CARGA0.3 2.35 0.71
C.V. 0.71
CARGA MAYORADA
Wu=1.4CM+1.7CV 3.41 TN/ML.
AT AT
1.8 1.8
3.4 3.5 4.3
AT AT
1.8 1.8
3.4 3.5 4.3
2 2
AT AT
2 2
3.4 3.5 4.3
1.25 1.25
AT AT
1.25 1.25
3.4 3.5 4.3
2.35 2.35
AT AT
2.35 2.353.4 3.5 4.3
DIRECCION X
3.60 4.00 2.50 4.70
3.60 4.00 2.50 4.70
3.60 4.00 2.50 4.70