720MW Karot Hydropower Project Pakistan
Environmental and Social Impact AssessmentVolume I - Non-Technical Summary
July 2015
ss SS SS ss ss
MM
26 June 2015
720MW Karot Hydropower Project Pakistan
Environmental and Social Impact Assessment Volume I - Non-Technical S
720MW Karot Hydropower Project Pakistan
Environmental and Social Impact Assessment Volume I - Non-Technical Summary
July 2015
Mott MacDonald, Victory House, Trafalgar Place, Brighton BN1 4FY, United Kingdom
T +44 (0)1273 365 000 F +44(0) 1273 365 100 W www.mottmac.com
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
Revision Date Originator Checker Approver Description
A 3 July 2015 K. Murnane M. Maxwell I. Scott Draft
B 31 July 2015 M Maxwell I Scott I Scott Final
Issue and revision record
Information class: Standard
This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.
This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
Chapter Title Page
1 Introduction 1
1.1 Overview _________________________________________________________________________ 1
2 The Project 3
2.1 Why is the Project needed? ___________________________________________________________ 3
3 Managing environmental and social impacts 12
3.1 How was the Project assessed? _______________________________________________________ 12 3.2 How will people and the environment be affected? ________________________________________ 12 3.3 Cumulative impacts ________________________________________________________________ 15
Contents
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
1
1.1 Overview
This Non-Technical Summary presents the main findings and conclusions of the Environmental and Social
Impact Assessment (ESIA) completed for the proposed 720MW Karot Hydropower Project (HPP) (“the
Project”).
The ESIA has been prepared in accordance with national legislation, the International Finance
Corporation’s Environmental and Social Performance Standards (IFC PS) 2012 and the World Bank’s
Environmental, Health and Safety (EHS) Guidelines (2007). The ESIA has also been undertaken in
accordance with the requirements of the Pakistan Environmental Protection Act (1997). These international
standards and guidelines place emphasis on meeting good international industry practice with more focus
on social and health impacts, human and labour rights and stakeholder engagement than the national
process might require.
The ESIA takes into account the Updated ESIA prepared by Pakistan Environmental Services (Private)
Limited (PES) for national permitting purposes that was submitted to the relevant Pakistan Environmental
Protection Agencies in January 2015 (PES Updated ESIA 2015), as well as the Environmental Impact
Assessment prepared by SMEC in 2009 for the initial Project design.
1.2 What is the Project?
The Project will be a 720MW run-of-river hydropower scheme constructed on the Jhelum River that will
generate electricity to be fed into Pakistan’s State Grid.
The primary components of the Project are:
� A 95.5m high dam at the Karot village on the Jhelum River
� A Powerhouse with four turbines
� A Spillway separate from the dam
� A reservoir, created by the dam, extending approximately 27km upstream of the dam wall
The Project will employ 3,500 people, of which approximately 3,000 will be Pakistani many of whom will be
local to the area.
Karot and Azad Pattan road bridges will be replaced as a result of the Project; Karot due to the closeness
of the main construction site and Azad Pattan as a result of flooding from the reservoir. In addition the
footbridge at Ain Pana will be submerged as well as sections of the Kahuta-Azad Pattan Road, along the
right and left bank of the reservoir, and these will be reconstructed.
An overhead transmission line for export of power to a 500kV transmission line will be built by the Pakistan
Government (independently of this Project).
1.3 Who is developing the Project?
Karot Power Company (Private) Limited (KPCL) is the Project Proponent and is a wholly owned subsidiary
of China Three Gorges South Asia Investment Limited (CSAIL). CSAIL is an investment holding company
1 Introduction
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
2
formed in September 2011 to acquire, develop, build, own and operate renewable power generation
projects in Pakistan. . CSAIL is a wholly owned subsidiary of CWE Investment Corporation (CWEI) who is
a wholly owned subsidiary of the state owned China Three Gorges Corporation (CTGC) and serve as its
dedicated overseas investment platform.
The Project’s design has been developed by an established Project Design Company. The Engineering,
Procurement and Construction (EPC) Contract has been awarded to a consortium comprising Yangtze
Three Gorges Technology and Economy Development Co., Ltd (TGDC – engineering and construction)
and China Machinery Engineering Corporation (CMEC - procurement) (EPC contractor) at the beginning of
2015, who will produce the detailed Project design and construct the Project. The EPC contractor is wholly
owned by CTGC.
KPCL will operate the Project for 30 years, after which the Project will be transferred to the Government of
Pakistan.
1.4 Is there an opportunity to comment on the Project?
In addition to the consultation activities that have already occurred, community members and other
stakeholders can provide comment on the Project. If you would like to comment on the Project you can
contact the Project Proponent at:
Project Proponent Information
Name of Company Karot Power Company (Private) Ltd
Address House No. 05, Street No. 72, F-8/3, Islamabad, Pakistan
Telephone +92 51 2287088
E-mail Contact via website (‘Contact Us’ page)
Website www.karotpower.com
Further information on the Project can be found on the Project website: www.karotpower.com
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
3
2.1 Why is the Project needed?
The Project is being built in order to increase the supply of electricity being fed into Pakistan’s State Grid.
There is a shortage of electricity supply in Pakistan which leads to frequent power cuts. It is estimated that
there is a shortfall of electricity supply that ranges from 3,300MW in summer to 7,300MW in the winter.
In 2008 Pakistan’s Water and Power Development Authority (WAPDA) launched a National Water
Resource and Hydropower Development Programme called Vision 2025. This policy prioritises
development of hydropower in Pakistan in order to increase energy supply.
Pakistan’s National Power Policy (2013) also outlines the importance of hydropower projects in
overcoming Pakistan’s energy shortages. This policy highlights the desire for Pakistan to be self-sufficient
in energy generation and to move away from oil based energy generation.
The Government of Pakistan sees hydropower as a means of generating affordable electricity for local
people.
2.2 Where will the Project be located?
The Project is proposed to be built on the Jhelum River in Pakistan, in an area characterised by
mountainous terrain and a deep gorge. The Jhelum River forms the boundary between the province of
Punjab in the west and Azad Jammu and Kashmir (AJ&K) in the east. The dam will be located near the
villages of Karot (Punjab) and Hollar (AJ&K) approximately 55km south-east of Islamabad.
The reservoir created by the dam will extend approximately 27km upstream and have a volume of
152million cubic metres (Mm3) at full supply level (FSL) of 461m above sea level. The powerhouse
(housing the four turbines) will be located approximately 650m downstream of the dam crest and 300m
upstream of the Karot Bridge.
The Project location is shown in Figure 2.1.
2 The Project
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
4
Figure 2.1: Project location
Source: Mott MacDonald based on map included in PES Updated ESIA 2015 and SEA 20141
The Punjab province, AJ&K, Rawalpindi District as well as the villages of Karot and Hollar are shown in
Figure 2.2.
Along with other potential hydropower projects on the Jhelum River the Project has been identified as a
potential project for development since the early 1980s that could contribute cost-effective energy to the
national electricity grid in order to secure the long-term energy needs of Pakistan.
1 Annandale, David D. and Hagler Bailly Pakistan (Pvt) Ltd. 2014. Strategic Environmental Assessment of Hydropower Development
in Azad Jammu and Kashmir. Islamabad: IUCN Pakistan
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
5
Figure 2.2: Villages within the Project Area of Influence
Source: Mott MacDonald
2.3 I live near the Project, will I need to relocate?
Approximately 49 households in the village of Karot and 25 households in the village of Hollar will be
relocated because these houses are too close to the construction site and will be affected by construction
of the main Project components as well as construction noise, including blasting and drilling. Filling up the
reservoir will affect approximately 116 further households through loss of income or livelihood. Affected
communities have been involved in the consultation process to date, and the relocation or compensation of
these households will be managed through a Resettlement Action Plan. It is expected that the majority of
the affected households will move to other nearby villages, although a small number could relocate to
Beor, Kahuta and Islamabad. The Project will pay to move the affected households to comparable
properties or provide monetary compensation in order that new houses can be purchased.
The Project will result in 78 commercial business structures along the Jhelum River banks being inundated
by the reservoir so will lose their income generating abilities. Of the 78 business structures affected, 10
shops will be acquired as a result of construction of the dam and 40 shops, nine restaurants and a petrol
pump on right side of the Jhelum River will be affected by the reservoir. Any economic losses will be fully
compensated by the Project.
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
6
2.4 What will the Project look like?
A visual representation of the Project and layout of the dam site is provided in Figure 2.3.
Figure 2.3: Project layout
Source: Project Design Company, 2015, Video (2015-04-03) (labels added by Mott MacDonald)
2.5 What are the main Project components?
The key Project components include:
� Reservoir created by the construction of the dam and will stretch 27km upstream of the dam
� Diversion tunnels that will divert the river flow to enable construction of the dam and other Project
elements
� Dam of 95.5m high from foundation level and 460m across
� Cofferdams to divert river flow and enable excavation and construction of structures
� Spillway to allow large flows of water to safely bypass the dam in the event of a flood or during
closure/maintenance of the powerhouse
� Headrace tunnels that take water from the intake area to the turbines in the powerhouse
� Powerhouse that will generate 720MW of electricity
� Tailrace returns the water to the river after it has been through the turbines
These Project components are displayed visually in Figure 2.4.
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
7
Figure 2.4: Project layout (dam site and lower reach of the reservoir behind the dam)
Source: KPCL (labels and contours of the original riverbed added by Mott MacDonald)
In addition to the roads and bridges reconstructed in the reservoir area, a 1.2km long section of an existing
35kV distribution line within the reservoir area also requires reconstruction at a higher elevation. The
towers of this distribution line are expected to be either flooded by the reservoir or located within the
defined 20 year flood return period safety buffer at FSL.
Power will be exported from the Project’s dedicated switchyard (exact location is still to be confirmed but
will be close to the powerhouse) to the national grid. The transmission facilities from the switchyard are
likely to run to major load centres in the western part of Pakistan. The precise route of this transmission
line will be identified by the National Transmission and Despatch Company (NTDC) who are reviewing
power export needs in the area for a number of hydropower projects under construction or development,
and therefore are required to take a strategic approach to planning route options and capacity. If required
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
8
under Pakistan regulation a separate EIA process will be conducted for the transmission line to identify and
manage environmental and social issues.
2.6 Are there other proposed developments in the area?
There are other hydropower schemes existing or planned on the Jhelum River. The Project will be located
upstream of the existing Mangla Dam and downstream of the proposed Azad Pattan HPP, Mahl HPP and
Kohala HPP. Eventually, the Project will be part of a cascade of five large hydropower schemes on the
Jhelum River. Figure 2.5 shows the position of Karot HPP in relation to other hydropower schemes on the
Jhelum River.
Figure 2.5: Proposed hydropower schemes located on the Jhelum River
Source: KPCL
2.7 When will construction start?
It is expected that construction will begin in quarter four of 2015 and will occur over a period of
approximately five years, with the completion date scheduled for quarter four of 2020.
2.8 What will happen during the construction phase?
During construction key activities will include:
� Resettlement and land acquisition
� Site enabling works including the construction of new roads and bridges and storage areas; processing
and batching plants will be brought to the site
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
9
� Development of a construction camp including worker’s quarters, mess facilities, offices, storage areas,
water treatment plant, waste handling area and other required facilities
� Site preparation works including the clearing of both banks of the river
� River diversion works
� Excavations for the dam and other Project components
� Installation of the turbines and generators and associated electrical work
� Completion works including reinstatement of disturbed land
The Project will generate large amounts of earthen material, or “spoil”, from excavating the tunnels, dam
foundations, spillway, powerhouse and road functions. Some of the excavated materials will be reused for
the construction of the dam, coffer dam, powerhouse, spillway and for road widening. The remainder will
be disposed of at four spoil disposal sites which are in near to the Project dam site. It is anticipated that all
spoil will be transferred to the spoil disposal sites by trucks.
There will be a peak construction workforce during 2017 of 3,500 people, approximately 85% of whom will
be Pakistan nationals, with construction expected to occur 24 hours a day, 7 day per week, with three eight
hours shifts for workers. Accommodation for approximately 3,500 workers will be provided, located away
from existing villages; the nearest village being Gorah Rajan.
2.9 How will the site be accessed?
Access roads to support the delivery of equipment and personnel to site will be provided to connect all of
the main Project components to the existing road network. Road and bridge replacements will be required
in the dam area and in the reservoir area. Road widening and strengthening along access routes will be
undertaken by the National Highway Authority of Pakistan. All roads will need to be built to accept heavy
weights and oversized hauls.
At the dam site, a 2.8km section of the Rawalpindi-Kotli Road will be relocated. The new road will run from
the Rawalpindi-Kotli Road through a forest and lead over the Jhelum River to Hollar across the new Karot
Bridge. The Rawalpindi-Kotli Road will be cut off before the spillway but after a shrine and small
community graveyard at Karot which are located adjacent to the Rawalpindi-Kotli Road, approximately
300m before the spillway.
The required road and bridge works in the upper section of the reservoir comprise the following:
� Reconstruction of the Azad Pattan Bridge
� Reconstruction of the suspension bridge in Ain Pana (located approximately 7km downstream of the
Azad Pattan Bridge)
� Relocation of a total of about 6.8km of various sections of the Kahuta-Azad Pattan Road along the right
and left bank of the reservoir, including four concrete bridges with a 20m span and 15 culverts
(structures that allows water to flow under a road) over tributaries of the Jhelum River. These are all
due to higher water levels as a result of inundation by the reservoir
The bridges and road sections will be relocated at higher elevations and be reconnected to the existing
Kahuta-Azad Pattan Road that will remain in situ. Figure 2.6 shows the access routes that will be used to
access the Project site, note that road 5 will not be used.
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
10
For the overall construction period of five years, the Project is expected to generate approximately 720,000
additional vehicle movements over the four external access routes that are likely to be used for the Project.
Of these vehicle movements around 624,000 will be heavy vehicle movements. This additional traffic will
peak during the second year of construction between months 17 and 22 when average daily traffic
movements are expected to be highest on the Beor to Karot option route, with an average of an additional
400 daily traffic movements encountered.
There will also be significant a large number of traffic movements within the Project site boundary
associated with excavation and spoil disposal, which is typical of a construction project of this. These
movements will not use the external access roads and dedicated site access roads will be constructed for
this purpose. Project site traffic movements will not have the same peaks as the external roads as there
will be ongoing excavations and construction for the five year Project construction duration.
A Traffic Management Plan will be included within the ESMP and will address the measures to be applied
to mitigate the impacts from both external and internal construction traffic.
Figure 2.6: Project location and access routes
Source: Mott MacDonald
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
11
2.10 What will happen during operation?
During the operation of the hydropower plant, the water retained in the reservoir behind the dam will flow
through the water intake into the headrace tunnels which will accelerate the speed of the water prior to
entering the powerhouse. At the end of the headrace tunnels the water will flow through the turbines which
will generate electricity, and be discharged back into the Jhelum riverbed through the tailrace channel.
Inflows from the Jhelum River into the reservoir, which exceed the capacity of the turbines, will be
discharged through gates in the spillway.
The Project is expected to generate approximately 3,200GWh of electricity during a year. This is enough
power to provide electricity to approximately 7 million homes. The production of electrical energy will
fluctuate between higher and lower values throughout the year depending on available inflow volumes from
the upstream catchment of the Jhelum River into the reservoir. Inflows are influenced by runoff from
rainfall, snowfall and snowmelt within the catchment area.
During the dry season from October to February (winter), the river inflows are significantly lower and will
need to be stored on a daily basis within the reservoir until sufficient volumes are available for power
generation. During these months, electricity will be produced during peak demand periods only. During the
intermittent months of September and March the ability of the Project to generate electricity at full capacity
will depend on the available flow. The actual electricity output of the Project will be regulated on a daily
basis and determined by NTDC (subject to water availability and permitting requirements). It is expected
that the life of the Project will be around 100 years for all permanent structures.
In the dry season and during times of intermittent flows in the Jhelum River, operations will be limited and
this will result in periods of no flows in the downstream river stretch after the powerhouse outlet. In
addition, the change in the reservoir level of the Mangla Dam means that the length of the river stretch
impacted will change throughout the year and be longer during the dry season than during the wet season.
To maintain aquatic ecosystems downstream of the dam and the human livelihoods which depend on them
at least 15m3 per second (around 10% of the average annual minimum flow) will be released. During
reservoir filling this water will be released through a pipe in one of the diversion tunnels. The exact location
of the release during peaking periods in the operational phase hasn’t been determined; however it is
assumed that it will be released at the powerhouse.
2.11 What will happen at the end of the Project?
The operational phase of the scheme is likely to be 100 years, with the life of installed equipment
estimated to be at least 50 years. During the decommissioning of the Project the impacts would be similar
to that experienced during construction and include impacts associated with:
� Waste disposal
� Removal of steel gates and/or part of the dam and Project components (e.g. powerhouse)
� Impacts related to restoring areas to a natural habitat
� Disposal of hazardous materials
� Retrenchment planning in the unlikely situation that a significant number of jobs are affected
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
12
3.1 How was the Project assessed?
The main stages in the ESIA process are:
� Establishment of the baseline to understand current conditions at and around the proposed Project
sites
� Prediction of impacts of the construction and operational phases
� Identification of mitigation measures to be included in the design and ongoing management
The assessment process was supported by consultation with local people and organisations to ensure that
these views were considered.
A Project Environmental and Social Management Plan (ESMP) has been developed that includes all of the
mitigation measures identified in the ESIA and how these will be implemented. The ESMP includes a
range of underpinning management plans specific to the impacts that have been identified.
The significance of an impact is based on the function of the sensitivity of project affected persons/
environmental receptor and the magnitude of impacts (scale, nature, duration). Where the ESIA found that
the Project could cause significant impacts then actions or procedures (referred to as mitigation measures)
have been developed to avoid, reduce or otherwise mitigate the effects. A great number of potential
impacts can either be avoided or reduced through mitigation; however some impacts may be unavoidable.
A summary of the key findings and the main mitigation measures identified for the social and
environmental impact is set out in this section. The ESIA presents the impacts of the Project in the
following chapters:
� Hydrology and Water Quality
� River Morphology
� Geology, Landslides and Seismicity
� Biodiversity
� Air Quality and Greenhouse Gas Emissions
� Materials and Waste
� Noise
� Landscape and Visual
� Socio-Economics, Community and Culture
� Health and Safety
� Climate Resilience
� Cumulative Impacts
3.2 How will people and the environment be affected?
Whilst environmental and social issues interact, the findings of the ESIA broadly cover the following
themes:
� Effects on people
� Effects on the river and physical features
� Effects on the natural environment and resources
3 Managing environmental and social impacts
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
13
3.2.1 Effects on people
The most significant effect on people is the physical resettlement of 74 households living in the villages of
Karot and Hollar. In addition, the loss of commercial structures on the river banks will affect the ability of
people to run their businesses. A Resettlement Action Plan (RAP) identifies all of the assets and people
affected and sets out the approach to compensating those affected individuals; both in terms of their
homes and their livelihoods. The objective of the RAP is that no people will suffer economic loss or be
provided with housing that is less than they have now.
A number of places of cultural importance will be affected by the Project, including the relocation of four
mosques and four graveyards.
The Project is expected to require 3,500 workers at the peak of the construction phase. The generation of
employment is a beneficial impact of the Project. This provides opportunities for local people to access
jobs and to undertake training to develop new skills.
The construction activities will generate traffic, noise, dust and emissions, and waste. There will be a large
increase in the amount of traffic using particular routes, including heavy goods vehicles. Therefore
measures to manage traffic and prevent accidents will be employed.
In addition to noise from traffic, activities such as blasting, construction of bridges and roads and night-time
construction can create a nuisance. This potential nuisance can be reduced through avoiding traffic routing
through community areas where possible and undertaking construction activities in accordance with best
practice. Separating local villages from the main haul routes by a minimum distance of 30m will also
reduce the impacts of noise. Impacts from dust and emissions will be managed by techniques including
dust suppression by dampening, no burning of waste, speed limits for trucks and vegetating surfaces of
stockpiled materials.
The operation of the hydropower plant will increase the supply of electricity for Pakistan. This will have
national benefits for the economic development of the country.
3.2.2 Effects on the river and physical features
The Jhelum River near the Project site is in a deep narrow V-shaped valley with limited land or floodplain
adjacent to the river as it cuts though the Himalayan Mountain range and Siwalik Hills influenced by local
geology. The flow regime of the Jhelum River is typical of mountainous catchments where runoff is
supplied from both rainfall and snowmelt.
The Project will result in changes to the landscape which will be experienced by local people at various
locations around the Project area who will have views of various project components as well as changes to
the scenic Jhelum River valley caused by spoil deposition.
Mitigation measures to avoid these landscape and visual impacts include minimising vegetation removal,
regeneration of areas at the end of construction, design construction lighting to limit light spill, creating non-
engineered slopes that can be integrated into the natural topography, additional planting in areas identified
by local people to compensate for loss of woodland.
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
14
The potential impact of water pollution incidents during the construction period can be managed through
standard procedures to avoid spills of oils and other pollutants, including the control of erosion and
treatment of contaminated water that could affect the river.
A dedicated waste water treatment plant will be constructed to treat all sanitary wastes from the
construction workers camp prior to discharge into the Jhelum River.
The creation of the dam is expected to change the average water flow volume and patterns of water flow
through this part of the gorge. Measures to release water to maintain a minimum level of downstream flow
will be implemented and monitoring of river flows and water quality will be undertaken.
Sediment is produced by erosion, seismic activity and from the tributaries to the Jhelum River. Sediment
can reduce the storage capacity of the reservoir and the downstream river. The Project will reduce the
amount of sediment from moving downstream and this is not considered to be a significant impact in
isolation. However, further analysis is required to establish if the reduction in sediment load downstream of
the Project combined with the proposed hydropower schemes upstream would cause significant adverse
impacts downstream.
The assessment found that there are no significant adverse impacts predicted following the application of
the mitigation measures which include development of a sedimentation and erosion control plan,
installation of slope supports, the avoidance of blasting (where possible), designing cut slopes for seismic
actions, planting vegetation in areas subject to erosion, conducting a landslide risk assessment and
monitoring increase in seismicity due to reservoir activities.
3.2.3 Effects on the natural environment and resources
The Project is expected to generate some adverse impacts on the local natural environment. During the
construction phase adverse impacts are expected on terrestrial habitats and flora due to the loss and
degradation of terrestrial and riparian habitat and the introduction or spread of non-native species. In
aquatic habitats there will be a change in water quality from an increase in turbidity, permanent loss of
habitat and obstruction to fish movement and changes in flow patterns of the Jhelum River.
During operation terrestrial and riparian fauna will experience adverse residual impacts due to permanent
habitat fragmentation, increased disturbance of noise and dust, an increase risk of road kills and changes
in environmental flows. Aquatic habitats and species will be impacted by the creation of the reservoir, the
physical barrier created by the dam, changes in water quality (temperature, sediments and chemical
composition) and changes in water flow.
The golden mahasheer (Tor putitora) fish is found in the Jhelum River and is globally endangered. The
golden mahasheer is known to live in reservoirs (such as the Mangla Reservoir) but will need to migrate to
upstream sections of the river where spawning habitat is available. Mitigation measures will be
implemented to allow fish movements upstream and downstream of the Jhelum River to re-establish
connectivity to spawning habitats.
Mitigation measures also include development of a Biodiversity Management and Action Plan, a
Catchment Management Plan, education and awareness raising for local communities, a Habitat Removal
720MW Karot Hydropower Project Pakistan ESIA Volume I - NTS
15
and Restoration Plan, providing support to the nearby Murree-Kotli Sattian-Kahuta National Park,
eradication of invasive species, on-site restoration of areas where possible, off-site habitat creation or
enhancement, a ban on hunting native species, implementing speed limits where appropriate and reducing
artificial lighting and noise emissions.
There will be large volumes of spoil generated from the excavation works during construction. The spoil
material that cannot be reused in construction activity will be distributed to four disposal sites; three located
on the left of the river bank (when looking downstream) and disposal site #2 is in the river channel,
crossing both sides. It may be possible to engineer the spoil disposal sites to provide cultivatable land for
the local community. Where other wastes are produced, these will be also be re-used or recycled
whenever possible.
In considering the impacts on greenhouse gases, the construction of the Project is predicted to generate
approximately 830,000 (tCO2e) of carbon emissions. The operation of the project will provide a beneficial
effect, by avoiding around 1.6 million tonnes of CO2 each year, by using hydropower to generate electricity
compared to fossil fuel sources of power production.
3.3 Cumulative impacts
The ESIA considers cumulative impacts. The Project is only one of a number of hydropower projects that
are under development in the river basin, and one of five projects in the Jhelum River cascade. Cumulative
impacts are predicted to occur as a result of extended employment for construction workers (as they gain
skills and move from one project to the next), but this does come with a potential downside of crowding
caused by in-migration.
Benefits from the increase in capacity and reliability of electricity supply in the region are expected.
Measures to develop a basin level biodiversity action plan are already underway to address cumulative
impacts on the Jhelum River Basin. In addition, measures to manage sediment flushing are needed to
avoid loss of reservoir storage downstream and to enhance the form of the Jhelum River and habitats
downstream.