6.04 Assessing the need for additional surge arresters in ...
Transcript of 6.04 Assessing the need for additional surge arresters in ...
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Assessing the need for additional
surge arresters in an uprated high
voltage substation
Author: Peet Schutte
Co-Author: Chris van der MerweEskom Holdings SOC Ltd
Paper Number 6.04
Session 6
16 November 2017
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Presentation outline
• Introduction
• Back-flashover simulation
• Simulation results
• Conclusion
• Acknowledgements
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Introduction
• When a substation system voltage is uprated, surge arresters with higher protective levels are installed.
• Protective levels of arresters will determine the maximum over-voltages at the arrester terminals.
• Internal and external insulation may possibly be stressed to a point of failure.
• Insulation coordination studies are valuable to determine over-voltage stress on both internal and external insulation.
• In 88 kV substations, phase-to-earth clearance should not be less than 1000 mm and relates to an estimated 530 kV BIL.
• For internal insulation, 132 kV equipment insulation level (BIL) selected 550 kV.
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Insulation types
Non-recoverable or internal insulation
type: Current transformer, power
transformer
Recoverable or external insulation type: Air gap
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
0
60
120
180
240
300
360
420
480
0.0001 0.001 0.01 0.1 1 10 100 1000 10000 100000
Max
imum
Res
idua
l Vol
tage
(kV
peak
)
Resistive current (A peak)
Maximum Current / Voltage characteristic curve 20 °C
Surge arrester characteristic
72 kV rated arrester used in 88 kV substation
108 kV rated arrester used in 132kV substation
10 kA Residual Voltage = 196 kV peak
10 kA Residual Voltage = 294 kV peak
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Surge arrester and separation distance
10 kA Residual Voltage= 196 kVpk
10 kA Residual Voltage= 294 kVpk
Internal insulation 550 kV BIL
External insulation 1 m
phase-to-earth 530 kV BIL
Separation Distance from Arrester
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Fast front transients entering a substation
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Substation single line diagram
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Back-flashover simulation: ATP model
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Back-flashover simulation: Current source
Ramp Type Current Source
Current Peak (kA)
Probability of occurrence (%)
TAN-G Steepness
(kA/µs)
Front Rise Time (µs)
Time to half value
(µs)Source 1 10 95 13.83 0.72 75Source 2 30 52 25.32 1.185 75Source 3 80 7.8 43.42 1.842 75Source 4 160 1.4 63.58 2.5 75
0 10 20 30 40 50 60 700
50
100
150
Source 1 = 10 kA PeakSource 2 = 30 kA PeakSource 3 = 80 kA PeakSource 4= 160 kA Peak
Source 1 = 10 kA PeakSource 2 = 30 kA PeakSource 3 = 80 kA PeakSource 4= 160 kA Peak
Lightning ramp type source currents.
Time (us)
Cur
rent
(kA
)
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Back-flashover simulation: Transient
The steepness of the transient over-voltages were:
• Source 1 (10 kA): Flashover not occurring, no surge on phase conductors.
• Source 2 (30 kA): Peak of 710 kV with a steepness of 1250 kV/µs.
• Source 3 (80 kA): Peak of 1.706 MV with a steepness of 1076 kV/µs.
• Source 4 (160 kA): Peak of 3.022 MV with a steepness of 1205 kV/µs.
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.80
0.5
1
1.5
230 kA Tower Top Voltage30 kA Phase A Voltage80 kA Tower Top Voltage80 kA Phase A Voltage160 kA Tower Top Voltage160 kA Phase A Voltage
30 kA Tower Top Voltage30 kA Phase A Voltage80 kA Tower Top Voltage80 kA Phase A Voltage160 kA Tower Top Voltage160 kA Phase A Voltage
Backflash Voltages
Time (us)
Vol
tage
(M
V)
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Back-flashover simulation: Transient
The steepness of the transient over-voltages were:
• Source 1 (10 kA): Flashover not occurring, no surge on phase conductors.
• Source 2 (30 kA): Peak of 710 kV with a steepness of 1250 kV/µs.
• Source 3 (80 kA): Peak of 1.706 MV with a steepness of 1076 kV/µs.
• Source 4 (160 kA): Peak of 3.022 MV with a steepness of 1205 kV/µs.
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 50
0.5
1
1.5
2
2.5
3
3.530 kA Phase A Voltage80 kA Phase A Voltage160 kA Phase A Voltage
30 kA Phase A Voltage80 kA Phase A Voltage160 kA Phase A Voltage
Backflash Voltages
Time (us)
Vol
tage
(M
V)
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Simulation results: Evaluation of stress
Voltage NodePeak voltage
(kV)Safety margin for LIWL (%)
VLINE 335 64VTRFR1 330 66VBCCB 343 60VTRFR2CB (*CB DIST =60 m)
392 40
Airgap withstand 530kV/m
392 33
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Simulation results: Evaluation of separation distance, stress
and separation distance
CB DIST (m) VTRFR2CB (kV) Safety margin (%)60 392 4080 395 39100 465 18.2120 492 11.7140 550 0
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Simulation results: Surge arrester energy
0 10 20 30 40 50 60 70 80 90 100 110 1200
100
200
300
400
500
600
Line entrance arrester energy without busbar arrestersLine entrance arrester energy with arresters at bus couplerLine entrance arrester energy with busbar arresters on both end551 kJ maximum energy rating
Line entrance arrester energy without busbar arrestersLine entrance arrester energy with arresters at bus couplerLine entrance arrester energy with busbar arresters on both end551 kJ maximum energy rating
Arrester Energy
Time (us)
Ene
rgy
(kJ)
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Conclusion
• Uprating the system voltage in a substation will require higher rated surge arresters.
• With higher protective levels, safety margins between withstand levels of external insulation are reduced.
• The evaluation of over-voltage stress caused by a back-flashover close to the substation results in the following :– Increasing the separation distance to 140 m will result in breaking through
the BIL of both internal and external insulation.
– This scenario is highly unlikely, but additional busbar arresters will improve the safety margins throughout the substation.
– The standard Eskom practice to install MOV arresters at the line entrance and power transformers reduces the probability of large separation distances.
– Optimising the over-voltage protection for non-recoverable insulation will result in decreasing the probability of recoverable insulation failing.
– Busbar arresters are to be installed to increase the safety margins where long conductor distances separate equipment from installed arresters.
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities
Acknowledgements
• Mr. Chris van der Merwe
• Eskom
• CIGRE