60% Design and Cost Estimate

52
Clean Water Facility 60% Estimate Review

Transcript of 60% Design and Cost Estimate

Page 1: 60% Design and Cost Estimate

Clean Water Facility

60% Estimate Review

Page 2: 60% Design and Cost Estimate

City Council Special Workshop 2

• Project Team• City of Oak Harbor• Carollo Engineers• Hoffman Construction• KBA Construction Management• OAC – Project Advisor• HDR – Rates• PFM – Funding Advisor

Introductions

9/30/2015

Page 3: 60% Design and Cost Estimate

City Council Special Workshop 3

• 60% Design Cost Estimate• Bio-solids Alternatives• Community Room Options• Funding and Rates

Agenda

9/30/2015

Page 4: 60% Design and Cost Estimate

City Council Special Workshop 4

60% Cost Estimate

9/30/2015

Page 5: 60% Design and Cost Estimate

City Council Special Workshop 5

• 2008 Sewer Comp Plan – Anaerobic Cell at Lagoons• 2010 Facilities Plan – Site and process selection• 2013 Selected Windjammer Park• 2014 Selected and Purchased former WIB property• 2014 Selected GC/CM Process and Hoffman

Background

9/30/2015

Page 6: 60% Design and Cost Estimate

City Council Special Workshop 6

• 60% Engineers estimate provides a probable range of cost • -5% to +15%

• GC/CM provide opinion of cost for a Guaranteed Maximum Price. • Conservative escalation factors, allowances and contingencies

“Budget Number”• Think of these numbers as the “Bookends” of potential

construction costs• Estimate is not a bid!

GC/CM “Opinion of Cost” vs. “Engineers Estimate”

9/30/2015

Page 7: 60% Design and Cost Estimate

City Council Special Workshop 7

• Incorporated Cost Savings from 30% review• Reduced Deep Excavation Footprint• Headworks / MBR Common Wall• Electrical, Instrumentation and Controls

30% 60%What’s Changed?

9/30/2015

Page 8: 60% Design and Cost Estimate

City Council Special Workshop 8

• Greater Detail in Drawings• More Advanced Vendor Quotes• Site Prep A – Better Understanding of Site Risks• Confirmed Depth to Glacial Till• Some Systems Showed an Increase in Cost• Others Systems Showed a Decrease in Cost

30% 60%What’s Changed?

9/30/2015

Page 9: 60% Design and Cost Estimate

City Council Special Workshop 9

• Everything inside the box to the right

• Architectural Concept A• Construction Only!• Does not include splash park

What’s included in the Opinion of Cost?

9/30/2015

Page 10: 60% Design and Cost Estimate

City Council Special Workshop 10

• Bio-solids Dryer• Community Room• Rebuilding City Beach Street• Southern Access Road• Architectural Concept A

What’s Included

9/30/2015

Page 11: 60% Design and Cost Estimate

City Council Special Workshop 11

• Demolition of former bank building• North parking lot• Southern parking lot• Mitigation• Property / Easements / Right of Way• Engineering / Construction Management /

Archaeology

What isn’t included

9/30/2015

Page 12: 60% Design and Cost Estimate

City Council Special Workshop 12

60% Cost Estimate

Carollo Hoffman$60M

$70M

$80M

$90M

$100M

$110M

$120M

$98M

$113M

$91M

$109M

30% 30%60% 60%

9/30/2015

Page 13: 60% Design and Cost Estimate

City Council Special Workshop 13

Area 30% 60% Delta % DeltaAdmin/Maintenance $6,576,485 $5,957,850 ($618,635) -9.4%

Community Center $1,670,560 $2,372,686 $702,126 42.0%

Landscaping $766,966 $2,446,105 $1,679,139 218.9%Civil Sitework $17,522,245 $17,869,334 $347,089 -2.0%Headworks $13,225,668 $13,226,368 $700 0.0%Secondary Building $28,521,730 $26,447,663 ($2,074,06

7) -7.3%

AB WAS Storage $13,272,552 $13,022,498 ($250,054) -1.9%Blower Building $2,009,339 $2,657,458 $648,119 32.3%

Biosolids Facility $17,827,572 $14,615,311 ($3,295,443) -18.5%

Odor Treatment $4,036,544 $4,820,893 $784,349 19.4%

Electrical Building $7,873,971 $5,543,733 ($2,330,238) -29.6%

Total $113,303,660 $108,896,717

($4,406,943) -3.9%

Hoffman 30% vs. 60%

We will discuss these two later

in the presentation

We will discuss these two later

in the presentation

9/30/2015

Page 14: 60% Design and Cost Estimate

City Council Special Workshop 14

Description CostsDirect Costs $9,046,471Escalation Allowance $550,046Market Conditions Allowance $136,241Design Contingency $622,807Subcontractor Bonding $47,819Negotiated Support Services $644,488GMP Contingency $386,676SUBTOTAL, GMP $11,434,547GC/CM Specified General Conditions $243,826

GC/CM Fee $489,399Sales Tax $1,058,596Total Construction Costs $13,226,368

Headworks Breakdown

9/30/2015

Page 15: 60% Design and Cost Estimate

City Council Special Workshop 15

• Mechanical• Concrete• Contingency Factors• Construction Indirect Costs• Explore Options to Increase Value and

Reduce Cost

Cost Savings Moving Forward

9/30/2015

Page 16: 60% Design and Cost Estimate

City Council Special Workshop 16

Questions?

9/30/2015

Page 17: 60% Design and Cost Estimate

City Council Special Workshop 17

Bio-solids

9/30/2015

Page 18: 60% Design and Cost Estimate

City Council Special Workshop 18

Background: “Biosolids 101”• What are biosolids?

“Sewage sludge” are the solids that settle out in the wastewater treatment process. “Biosolids” are produced by treating sewage sludge to meet standards that allow for beneficial use.

• How can biosolids be used?Biosolids can be used in different ways, depending on their classification. “Class B” biosolids must be land applied in bulk at a permitted site. “Class A” biosolids can also be land applied in bulk, and may even be bagged and sold if they are high enough quality.

9/30/2015

Page 19: 60% Design and Cost Estimate

City Council Special Workshop 19

Biosolids Reuse in Washington

Covered dump truck

Dewatered biosolids

King County’s “Loop” Trucks

Land application in Eastern WA

SoundGRO Fertilizer

Pierce Co, WA

Dried Biosolids Loading

Alderwood, WA

9/30/2015

Page 20: 60% Design and Cost Estimate

City Council Special Workshop 20

Background: Oak Harbor’s Plan

• Several alternatives evaluated in Facilities Plan, including:­ Beneficial reuse of dried Class A biosolids­ Beneficial reuse of lime-stabilized Class B biosolids­ Landfilling dewatered untreated solids that do not meet reuse standards

• Dryer for Class A biosolids preferred long-term solution­ Most flexibility for local reuse (Potential revenue source to reduce annual O&M cost)­ Reduced truck traffic­ “Manageable” odor and aesthetic risk

• Lime-stabilization for Class B proposed for Phase 1­ Lower initial capital cost, but higher cost for hauling to Eastern WA­ Provides time to develop and implement Class A beneficial reuse program

9/30/2015

Page 21: 60% Design and Cost Estimate

City Council Special Workshop 21

What has changed since planning?• Lime stabilization not recommended at Windjammer Vicinity

­ Potential for odor, mess­ Large footprint required to store treated biosolids­ Truck traffic (lime deliveries; Class B biosolids off-haul)

• Cost of Class A dryer has increased between planning and 60%­ More proven technology (that is also larger, more expensive) selected

to reduce risk and increase operator safety• Estimated total WWTP construction cost at 60% motivates

review of solids treatment alternatives to reduce impact to rate payers

9/30/2015

Page 22: 60% Design and Cost Estimate

City Council Special Workshop 22

What alternatives are currently being considered?

• “Base Case”: Beneficial Reuse of Class A Biosolids­ Construct on-site dewatering and thermal drying to Class A­ Beneficial reuse of biosolids on Whidbey Island­ NOTE: Basis of current 60% cost estimate

• Alternative 1: Beneficial Reuse of Class B Biosolids­ Construct on-site dewatering­ Construct off-site treatment with lime stabilization to Class B­ Haul lime-stabilized biosolids for beneficial reuse in Eastern Washington

• Alternative 2: Landfill Disposal of Unclassified Solids (Interim Only)­ Construct on-site dewatering­ Haul dewatered solids to landfill (extending 2-year period requires Ecology

exemption)9/30/2015

Page 23: 60% Design and Cost Estimate

City Council Special Workshop 23

“Base Case”: Beneficial Reuse of Class A BiosolidsSolids Process Schematic

9/30/2015

Page 24: 60% Design and Cost Estimate

City Council Special Workshop 24

TRUCK LOADING

DEWATERING

DRYING

WAS STORAGE

SOLIDS BUILDING

“Base Case”: Beneficial Reuse of Class A BiosolidsSite Plan & Solids Building at WWTP

9/30/2015

Page 25: 60% Design and Cost Estimate

City Council Special Workshop 25

“Base Case”: Beneficial Reuse of Class A BiosolidsSummary of Estimated Costs

Base Case - Class A Dryer Estimated Cost Notes

Based on 60% design

8,700 sf building with dryer installed

Assumes 1 FTE for solids process

Assumes $0 for hauling/Class A reuse

10-year Annualized Cost (Capital + O&M) $2.2 M Assumes 3% interest

Capital Cost (WWTP)

Annual O&M Cost

$14.5M

$500,000

9/30/2015

Page 26: 60% Design and Cost Estimate

City Council Special Workshop 26

“Base Case”: Beneficial Reuse of Class A BiosolidsAdvantages and Challenges

Advantages• Consolidates solids treatment at

WWTP• Fewest truck trips to/from WWTP• Beneficial reuse consistent with

Ecology requirements• Class A provides flexibility for

reuse options• Potential revenue to offset O&M

cost

Challenges• High Capital Cost• High Operating Cost• Requires development of

Class A Biosolids Program• Additional complexity for

O&M9/30/2015

Page 27: 60% Design and Cost Estimate

City Council Special Workshop 27

Alternative 1: Beneficial Reuse of Class B BiosolidsSolids Process Schematic

9/30/2015

Page 28: 60% Design and Cost Estimate

City Council Special Workshop 28

Alternative 1: Beneficial Reuse of Class B BiosolidsSite Plan at WWTP

WAS STORAGE

SOLIDS BUILDING

TRUCK LOADING

DEWATERING

9/30/2015

Page 29: 60% Design and Cost Estimate

City Council Special Workshop 29

Alternative 1: Beneficial Reuse of Class B BiosolidsSite Plan Off-Site (Lime Stabilization Facility)

Lime Stabilization Facility

Lime Stabilized Biosolids

9/30/2015

Page 30: 60% Design and Cost Estimate

City Council Special Workshop 30

Alt 1 - Class B Lime Stabilization Estimated Cost Notes

Based on 60% design

5,800 sf building, no dryer

Based on preliminary information

Assumes facility at City Shops

Total Capital Cost Range $12.2M - $13.2M

Assumes .5 FTE for solids process

Includes $316,000 hauling to Eastern WA

10-year Annualized Cost (Capital + O&M) $2.1M - $2.2M Assumes 3% interest

Capital Cost (WWTP) $8.2M

Annual O&M Cost $672,000

Capital Cost (Off-Site Lime Facility) $4.0M - $5.0M

Alternative 1: Beneficial Reuse of Class B BiosolidsSummary of Estimated Costs

9/30/2015

Page 31: 60% Design and Cost Estimate

City Council Special Workshop 31

Alternative 1: Beneficial Reuse of Class B BiosolidsAdvantages and Challenges

Advantages• Potentially reduced Capital

Cost• Beneficial reuse consistent

with Ecology requirements

Challenges• High Operating cost• Additional truck trips to/from

WWTP• Limited flexibility for reuse of

Class B biosolids• Separates biosolids handing and

treatment from WWTP• Requires another site• Likely requires amendment to

Facilities Plan and Environmental Documents 9/30/2015

Page 32: 60% Design and Cost Estimate

City Council Special Workshop 32

Alternative 2: Landfill Disposal of Unclassified SolidsSolids Process Schematic

9/30/2015

Page 33: 60% Design and Cost Estimate

City Council Special Workshop 33

WAS STORAGE

SOLIDS BUILDING

DRYING (FUTURE)

Alternative 2: Landfill Disposal of Unclassified SolidsSite Plan at WWTP

TRUCK LOADING

DEWATERING

9/30/2015

Page 34: 60% Design and Cost Estimate

City Council Special Workshop 34

Alternative 2: Landfill Disposal of Unclassified SolidsSummary of Estimated Costs

Alt 2 - Interim Landfill Estimated Cost Notes

Based on 60% design

8,700 sf building, no dryer

Assumes .3 FTE for solids process

Includes $200,000 hauling to landfill

10-year Annualized Cost (Capital + O&M) $1.5M Assumes 3% interest

Annual O&M Cost $440,000

Capital Cost (WWTP) $9.4M

9/30/2015

Page 35: 60% Design and Cost Estimate

City Council Special Workshop 35

Alternative 2: Landfill Disposal of Unclassified SolidsAdvantages and Challenges

Advantages• Reduced Capital Cost• Reduced O&M Cost• Class A facilities can be

phased-in over time

Challenges• Not consistent with Ecology

requirements – requires exemption

• Interim solution• Limited flexibility for

disposal of unclassified solids

• Likely requires amendment to Facilities Plan and Environmental Documents

9/30/2015

Page 36: 60% Design and Cost Estimate

City Council Special Workshop 36

Summary of Solids Alternatives

9/30/2015

Page 37: 60% Design and Cost Estimate

City Council Special Workshop 37

Questions?

9/30/2015

Page 38: 60% Design and Cost Estimate

City Council Special Workshop 38

Community Room

9/30/2015

Page 39: 60% Design and Cost Estimate

City Council Special Workshop 39

• 60% cost estimate based on Concept A

Community Meeting Room

9/30/2015

Page 40: 60% Design and Cost Estimate

City Council Special Workshop

Community Meeting Room

9/30/2015 40

• +/- 146 w/o tables• +/- 102 w/tables

Page 41: 60% Design and Cost Estimate

City Council Special Workshop 41

Description CostsDirect Costs $1,570,687Escalation Allowance $95,501Market Conditions Allowance $23,655Design Contingency $155,468Subcontractor Bonding $20,958Negotiated Support Services $115,615GMP Contingency $69,366SUBTOTAL, GMP $2,051,250GC/CM Specified General Conditions $43,740

GC/CM Fee $87,794Sales Tax $189,902Total Construction Costs $2,372,686

Community Meeting Room

9/30/2015

Page 42: 60% Design and Cost Estimate

City Council Special Workshop 42

Community Meeting Room• Benefits• Construction

Efficiency• Provide greater

integration into park• Economic

development

• Challenges• Business case• Operations• Securing funding

9/30/2015

Page 43: 60% Design and Cost Estimate

City Council Special Workshop 43

Community Meeting Room

9/30/2015

• Cost Estimate for Concept B under development

Page 44: 60% Design and Cost Estimate

City Council Special Workshop 44

Without Community Meeting Room

9/30/2015

• Concept B without Community Meeting Room

Page 45: 60% Design and Cost Estimate

City Council Special Workshop 45

• Sewer Fund shouldn’t bear the entire burden• Approximately half could be paid by Utility

Funds• The other half by the general fund, grants,

etc…

Funding Options

9/30/2015

Page 46: 60% Design and Cost Estimate

City Council Special Workshop 46

Options

9/30/2015

1. Include Community Room 2. Remove Community Room3. Keep Community Room in Design as an

Additive/Alternate bid item

Page 47: 60% Design and Cost Estimate

City Council Special Workshop 47

Questions?

9/30/2015

Page 48: 60% Design and Cost Estimate

City Council Special Workshop 48

Funding & Rates

9/30/2015

Page 49: 60% Design and Cost Estimate

City Council Special Workshop 499/30/2015

Page 50: 60% Design and Cost Estimate

City Council Special Workshop 50

Summary

9/30/2015

Page 51: 60% Design and Cost Estimate

City Council Special Workshop 51

• We have more work to do!• There are more opportunities for cost savings• We have a great team! (City, Carollo, Hoffman,

OAC, KBA, …)• The bid prices are the ultimate determination

of cost!

Summary

9/30/2015

Page 52: 60% Design and Cost Estimate

City Council Special Workshop 52

• October 20 – City Council Meeting• Resolution 15-xx – Community Room• Resolution 15-xx – Bio-solids Handling• GMP #4 – Site Prep Package B• GMP #5 – Bio-Solids Dryer Procurement• Consultant Agreement Amendments

What’s Next

9/30/2015