Clean Water Facility
60% Estimate Review
City Council Special Workshop 2
• Project Team• City of Oak Harbor• Carollo Engineers• Hoffman Construction• KBA Construction Management• OAC – Project Advisor• HDR – Rates• PFM – Funding Advisor
Introductions
9/30/2015
City Council Special Workshop 3
• 60% Design Cost Estimate• Bio-solids Alternatives• Community Room Options• Funding and Rates
Agenda
9/30/2015
City Council Special Workshop 4
60% Cost Estimate
9/30/2015
City Council Special Workshop 5
• 2008 Sewer Comp Plan – Anaerobic Cell at Lagoons• 2010 Facilities Plan – Site and process selection• 2013 Selected Windjammer Park• 2014 Selected and Purchased former WIB property• 2014 Selected GC/CM Process and Hoffman
Background
9/30/2015
City Council Special Workshop 6
• 60% Engineers estimate provides a probable range of cost • -5% to +15%
• GC/CM provide opinion of cost for a Guaranteed Maximum Price. • Conservative escalation factors, allowances and contingencies
“Budget Number”• Think of these numbers as the “Bookends” of potential
construction costs• Estimate is not a bid!
GC/CM “Opinion of Cost” vs. “Engineers Estimate”
9/30/2015
City Council Special Workshop 7
• Incorporated Cost Savings from 30% review• Reduced Deep Excavation Footprint• Headworks / MBR Common Wall• Electrical, Instrumentation and Controls
30% 60%What’s Changed?
9/30/2015
City Council Special Workshop 8
• Greater Detail in Drawings• More Advanced Vendor Quotes• Site Prep A – Better Understanding of Site Risks• Confirmed Depth to Glacial Till• Some Systems Showed an Increase in Cost• Others Systems Showed a Decrease in Cost
30% 60%What’s Changed?
9/30/2015
City Council Special Workshop 9
• Everything inside the box to the right
• Architectural Concept A• Construction Only!• Does not include splash park
What’s included in the Opinion of Cost?
9/30/2015
City Council Special Workshop 10
• Bio-solids Dryer• Community Room• Rebuilding City Beach Street• Southern Access Road• Architectural Concept A
What’s Included
9/30/2015
City Council Special Workshop 11
• Demolition of former bank building• North parking lot• Southern parking lot• Mitigation• Property / Easements / Right of Way• Engineering / Construction Management /
Archaeology
What isn’t included
9/30/2015
City Council Special Workshop 12
60% Cost Estimate
Carollo Hoffman$60M
$70M
$80M
$90M
$100M
$110M
$120M
$98M
$113M
$91M
$109M
30% 30%60% 60%
9/30/2015
City Council Special Workshop 13
Area 30% 60% Delta % DeltaAdmin/Maintenance $6,576,485 $5,957,850 ($618,635) -9.4%
Community Center $1,670,560 $2,372,686 $702,126 42.0%
Landscaping $766,966 $2,446,105 $1,679,139 218.9%Civil Sitework $17,522,245 $17,869,334 $347,089 -2.0%Headworks $13,225,668 $13,226,368 $700 0.0%Secondary Building $28,521,730 $26,447,663 ($2,074,06
7) -7.3%
AB WAS Storage $13,272,552 $13,022,498 ($250,054) -1.9%Blower Building $2,009,339 $2,657,458 $648,119 32.3%
Biosolids Facility $17,827,572 $14,615,311 ($3,295,443) -18.5%
Odor Treatment $4,036,544 $4,820,893 $784,349 19.4%
Electrical Building $7,873,971 $5,543,733 ($2,330,238) -29.6%
Total $113,303,660 $108,896,717
($4,406,943) -3.9%
Hoffman 30% vs. 60%
We will discuss these two later
in the presentation
We will discuss these two later
in the presentation
9/30/2015
City Council Special Workshop 14
Description CostsDirect Costs $9,046,471Escalation Allowance $550,046Market Conditions Allowance $136,241Design Contingency $622,807Subcontractor Bonding $47,819Negotiated Support Services $644,488GMP Contingency $386,676SUBTOTAL, GMP $11,434,547GC/CM Specified General Conditions $243,826
GC/CM Fee $489,399Sales Tax $1,058,596Total Construction Costs $13,226,368
Headworks Breakdown
9/30/2015
City Council Special Workshop 15
• Mechanical• Concrete• Contingency Factors• Construction Indirect Costs• Explore Options to Increase Value and
Reduce Cost
Cost Savings Moving Forward
9/30/2015
City Council Special Workshop 16
Questions?
9/30/2015
City Council Special Workshop 17
Bio-solids
9/30/2015
City Council Special Workshop 18
Background: “Biosolids 101”• What are biosolids?
“Sewage sludge” are the solids that settle out in the wastewater treatment process. “Biosolids” are produced by treating sewage sludge to meet standards that allow for beneficial use.
• How can biosolids be used?Biosolids can be used in different ways, depending on their classification. “Class B” biosolids must be land applied in bulk at a permitted site. “Class A” biosolids can also be land applied in bulk, and may even be bagged and sold if they are high enough quality.
9/30/2015
City Council Special Workshop 19
Biosolids Reuse in Washington
Covered dump truck
Dewatered biosolids
King County’s “Loop” Trucks
Land application in Eastern WA
SoundGRO Fertilizer
Pierce Co, WA
Dried Biosolids Loading
Alderwood, WA
9/30/2015
City Council Special Workshop 20
Background: Oak Harbor’s Plan
• Several alternatives evaluated in Facilities Plan, including: Beneficial reuse of dried Class A biosolids Beneficial reuse of lime-stabilized Class B biosolids Landfilling dewatered untreated solids that do not meet reuse standards
• Dryer for Class A biosolids preferred long-term solution Most flexibility for local reuse (Potential revenue source to reduce annual O&M cost) Reduced truck traffic “Manageable” odor and aesthetic risk
• Lime-stabilization for Class B proposed for Phase 1 Lower initial capital cost, but higher cost for hauling to Eastern WA Provides time to develop and implement Class A beneficial reuse program
9/30/2015
City Council Special Workshop 21
What has changed since planning?• Lime stabilization not recommended at Windjammer Vicinity
Potential for odor, mess Large footprint required to store treated biosolids Truck traffic (lime deliveries; Class B biosolids off-haul)
• Cost of Class A dryer has increased between planning and 60% More proven technology (that is also larger, more expensive) selected
to reduce risk and increase operator safety• Estimated total WWTP construction cost at 60% motivates
review of solids treatment alternatives to reduce impact to rate payers
9/30/2015
City Council Special Workshop 22
What alternatives are currently being considered?
• “Base Case”: Beneficial Reuse of Class A Biosolids Construct on-site dewatering and thermal drying to Class A Beneficial reuse of biosolids on Whidbey Island NOTE: Basis of current 60% cost estimate
• Alternative 1: Beneficial Reuse of Class B Biosolids Construct on-site dewatering Construct off-site treatment with lime stabilization to Class B Haul lime-stabilized biosolids for beneficial reuse in Eastern Washington
• Alternative 2: Landfill Disposal of Unclassified Solids (Interim Only) Construct on-site dewatering Haul dewatered solids to landfill (extending 2-year period requires Ecology
exemption)9/30/2015
City Council Special Workshop 23
“Base Case”: Beneficial Reuse of Class A BiosolidsSolids Process Schematic
9/30/2015
City Council Special Workshop 24
TRUCK LOADING
DEWATERING
DRYING
WAS STORAGE
SOLIDS BUILDING
“Base Case”: Beneficial Reuse of Class A BiosolidsSite Plan & Solids Building at WWTP
9/30/2015
City Council Special Workshop 25
“Base Case”: Beneficial Reuse of Class A BiosolidsSummary of Estimated Costs
Base Case - Class A Dryer Estimated Cost Notes
Based on 60% design
8,700 sf building with dryer installed
Assumes 1 FTE for solids process
Assumes $0 for hauling/Class A reuse
10-year Annualized Cost (Capital + O&M) $2.2 M Assumes 3% interest
Capital Cost (WWTP)
Annual O&M Cost
$14.5M
$500,000
9/30/2015
City Council Special Workshop 26
“Base Case”: Beneficial Reuse of Class A BiosolidsAdvantages and Challenges
Advantages• Consolidates solids treatment at
WWTP• Fewest truck trips to/from WWTP• Beneficial reuse consistent with
Ecology requirements• Class A provides flexibility for
reuse options• Potential revenue to offset O&M
cost
Challenges• High Capital Cost• High Operating Cost• Requires development of
Class A Biosolids Program• Additional complexity for
O&M9/30/2015
City Council Special Workshop 27
Alternative 1: Beneficial Reuse of Class B BiosolidsSolids Process Schematic
9/30/2015
City Council Special Workshop 28
Alternative 1: Beneficial Reuse of Class B BiosolidsSite Plan at WWTP
WAS STORAGE
SOLIDS BUILDING
TRUCK LOADING
DEWATERING
9/30/2015
City Council Special Workshop 29
Alternative 1: Beneficial Reuse of Class B BiosolidsSite Plan Off-Site (Lime Stabilization Facility)
Lime Stabilization Facility
Lime Stabilized Biosolids
9/30/2015
City Council Special Workshop 30
Alt 1 - Class B Lime Stabilization Estimated Cost Notes
Based on 60% design
5,800 sf building, no dryer
Based on preliminary information
Assumes facility at City Shops
Total Capital Cost Range $12.2M - $13.2M
Assumes .5 FTE for solids process
Includes $316,000 hauling to Eastern WA
10-year Annualized Cost (Capital + O&M) $2.1M - $2.2M Assumes 3% interest
Capital Cost (WWTP) $8.2M
Annual O&M Cost $672,000
Capital Cost (Off-Site Lime Facility) $4.0M - $5.0M
Alternative 1: Beneficial Reuse of Class B BiosolidsSummary of Estimated Costs
9/30/2015
City Council Special Workshop 31
Alternative 1: Beneficial Reuse of Class B BiosolidsAdvantages and Challenges
Advantages• Potentially reduced Capital
Cost• Beneficial reuse consistent
with Ecology requirements
Challenges• High Operating cost• Additional truck trips to/from
WWTP• Limited flexibility for reuse of
Class B biosolids• Separates biosolids handing and
treatment from WWTP• Requires another site• Likely requires amendment to
Facilities Plan and Environmental Documents 9/30/2015
City Council Special Workshop 32
Alternative 2: Landfill Disposal of Unclassified SolidsSolids Process Schematic
9/30/2015
City Council Special Workshop 33
WAS STORAGE
SOLIDS BUILDING
DRYING (FUTURE)
Alternative 2: Landfill Disposal of Unclassified SolidsSite Plan at WWTP
TRUCK LOADING
DEWATERING
9/30/2015
City Council Special Workshop 34
Alternative 2: Landfill Disposal of Unclassified SolidsSummary of Estimated Costs
Alt 2 - Interim Landfill Estimated Cost Notes
Based on 60% design
8,700 sf building, no dryer
Assumes .3 FTE for solids process
Includes $200,000 hauling to landfill
10-year Annualized Cost (Capital + O&M) $1.5M Assumes 3% interest
Annual O&M Cost $440,000
Capital Cost (WWTP) $9.4M
9/30/2015
City Council Special Workshop 35
Alternative 2: Landfill Disposal of Unclassified SolidsAdvantages and Challenges
Advantages• Reduced Capital Cost• Reduced O&M Cost• Class A facilities can be
phased-in over time
Challenges• Not consistent with Ecology
requirements – requires exemption
• Interim solution• Limited flexibility for
disposal of unclassified solids
• Likely requires amendment to Facilities Plan and Environmental Documents
9/30/2015
City Council Special Workshop 36
Summary of Solids Alternatives
9/30/2015
City Council Special Workshop 37
Questions?
9/30/2015
City Council Special Workshop 38
Community Room
9/30/2015
City Council Special Workshop 39
• 60% cost estimate based on Concept A
Community Meeting Room
9/30/2015
City Council Special Workshop
Community Meeting Room
9/30/2015 40
• +/- 146 w/o tables• +/- 102 w/tables
City Council Special Workshop 41
Description CostsDirect Costs $1,570,687Escalation Allowance $95,501Market Conditions Allowance $23,655Design Contingency $155,468Subcontractor Bonding $20,958Negotiated Support Services $115,615GMP Contingency $69,366SUBTOTAL, GMP $2,051,250GC/CM Specified General Conditions $43,740
GC/CM Fee $87,794Sales Tax $189,902Total Construction Costs $2,372,686
Community Meeting Room
9/30/2015
City Council Special Workshop 42
Community Meeting Room• Benefits• Construction
Efficiency• Provide greater
integration into park• Economic
development
• Challenges• Business case• Operations• Securing funding
9/30/2015
City Council Special Workshop 43
Community Meeting Room
9/30/2015
• Cost Estimate for Concept B under development
City Council Special Workshop 44
Without Community Meeting Room
9/30/2015
• Concept B without Community Meeting Room
City Council Special Workshop 45
• Sewer Fund shouldn’t bear the entire burden• Approximately half could be paid by Utility
Funds• The other half by the general fund, grants,
etc…
Funding Options
9/30/2015
City Council Special Workshop 46
Options
9/30/2015
1. Include Community Room 2. Remove Community Room3. Keep Community Room in Design as an
Additive/Alternate bid item
City Council Special Workshop 47
Questions?
9/30/2015
City Council Special Workshop 48
Funding & Rates
9/30/2015
City Council Special Workshop 499/30/2015
City Council Special Workshop 50
Summary
9/30/2015
City Council Special Workshop 51
• We have more work to do!• There are more opportunities for cost savings• We have a great team! (City, Carollo, Hoffman,
OAC, KBA, …)• The bid prices are the ultimate determination
of cost!
Summary
9/30/2015
City Council Special Workshop 52
• October 20 – City Council Meeting• Resolution 15-xx – Community Room• Resolution 15-xx – Bio-solids Handling• GMP #4 – Site Prep Package B• GMP #5 – Bio-Solids Dryer Procurement• Consultant Agreement Amendments
What’s Next